CN110158807A - A kind of Prefabricated composite assembling steel plate shear wall - Google Patents

A kind of Prefabricated composite assembling steel plate shear wall Download PDF

Info

Publication number
CN110158807A
CN110158807A CN201910453650.4A CN201910453650A CN110158807A CN 110158807 A CN110158807 A CN 110158807A CN 201910453650 A CN201910453650 A CN 201910453650A CN 110158807 A CN110158807 A CN 110158807A
Authority
CN
China
Prior art keywords
wall
rubber
transfer port
insertion pipe
rubber slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910453650.4A
Other languages
Chinese (zh)
Other versions
CN110158807B (en
Inventor
王晓勇
金彬
杨吉华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yongfu Construction Engineering Group Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910453650.4A priority Critical patent/CN110158807B/en
Publication of CN110158807A publication Critical patent/CN110158807A/en
Application granted granted Critical
Publication of CN110158807B publication Critical patent/CN110158807B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members

Abstract

The invention belongs to technical field of structural engineering, specifically a kind of Prefabricated composite assembling steel plate shear wall, including No.1 wall, No. two walls and fixed mechanism;The upper and lower ends of the No.1 wall open up fluted, and fixed mechanism is equipped with inside the both ends of No.1 wall;The upper and lower ends of No. two walls are provided with protrusive board;The protrusive board can be with grafting into groove;The fixed mechanism includes rubber patch, transfer port, mounting groove, insertion pipe, sliding tube, sliding panel, rack and rubber membrane;The rubber patch is fixedly connected on the both ends side surface of protrusive board;The transfer port is in bending, and transfer port is symmetrically provided with inside the upper and lower ends of No.1 wall, and one end perforation of transfer port is located in groove, and the other end of transfer port is connected to mounting groove;The lower end of the mounting groove is equipped with insertion pipe;Present invention is mainly used for solve the problem of that steel plate shear force wall in the prior art assembling complexity needs artificially to apply various gasket coatings to ensure airtightness.

Description

A kind of Prefabricated composite assembling steel plate shear wall
Technical field
The invention belongs to technical field of structural engineering, specifically a kind of Prefabricated composite assembling steel plate shear wall.
Background technique
With the development of building trade, the growth of urban population, urban land resource is increasingly precious, promotes people to height The demand of layer building.Common lateral resistant member is mainly reinforced concrete shear wall in skyscraper at present, but reinforcing bar is mixed The self weight for increasing structure, the relatively early generation crack under geological process that soil shear wall rigidity is excessive, ductility is poor, excessive are coagulated, The disadvantages of more difficulty is repaired after shake limits its application, and steel plate shear force wall is then a kind of novel lateral resistant member, with steel Reinforced concrete shear wall is compared, and is self-possessed smaller, is greatly reduced the geological process of structure;Steel plate shear force wall size is smaller, It arranges more flexible;It is prefabricated that mass production can be shifted to an earlier date additionally, due to steel plate shear force wall, situ wet operation is reduced, greatly improve construction Efficiency shortens the construction period.Steel confining part outside conventional steel plates shear wall, construction is complicated, relatively complicated on design and construction, no Conducive to repairing after daily maintenance and shake, while the assembling of existing steel plate shear force wall is relatively complicated, needs artificially to apply various sealings Coating, to cause built-up time longer.
Summary of the invention
In order to make up for the deficiencies of the prior art, a kind of Prefabricated composite assembling steel plate shear wall proposed by the present invention.This hair It is bright to be mainly used for solving steel plate shear force wall assembling complexity in the prior art, it needs artificially to apply various gasket coatings close to ensure The problem of closing property.
The technical solution adopted by the present invention to solve the technical problems is: a kind of Prefabricated composite assembled of the present invention Steel plate shear force wall, including No.1 wall, No. two walls and fixed mechanism;The upper and lower ends of the No.1 wall open up it is fluted, Fixed mechanism is equipped with inside the both ends of No.1 wall;The upper and lower ends of No. two walls are provided with protrusive board;The protrusive board can be with Grafting is into groove;The fixed mechanism includes rubber patch, transfer port, mounting groove, insertion pipe, sliding tube, sliding panel, rack And rubber membrane;The rubber patch is fixedly connected on the both ends side surface of protrusive board;The transfer port is in bending, and transfer port is symmetrically opened It is located inside the upper and lower ends of No.1 wall, one end perforation of transfer port is located in groove, the other end and mounting groove of transfer port Connection;The lower end of the mounting groove is equipped with insertion pipe;The insertion pipe is fixedly mounted in the upper and lower ends wall of No.1 wall, is inserted No.1 spliced eye is symmetrically offered in the end walls of adapter tube, the internal slide of insertion pipe is connected with sliding tube, the both ends of insertion pipe Lower side external surface is engaged with rack by gear;The inner end of the sliding tube is connected to the interior of mounting groove by spring Portion symmetrically offers No. two spliced eyes in the end walls of sliding tube, and the inner wall of sliding tube is fixedly connected with rubber membrane;The gear Bar upper end is engaged with sliding panel by gear;The sliding panel is slidably mounted in the upper and lower ends wall of No. two walls;When work, If necessary to be assembled to shear wall, No.1 wall can be attached with No. two walls by groove and protrusive board, simultaneously Insertion pipe meeting grafting on No.1 wall is into No. two walls, because the both ends side surface of protrusive board is fixedly connected with rubber patch, so convex Plate can cause the air in groove to be extruded when carrying out grafting with groove, run through because of the inside both ends of groove and be communicated with gas transmission Hole, and the other end of transfer port is connected to mounting groove, so peace can be entered by transfer port when the air in groove is extruded In tankage, because the lower end of mounting groove is connect with insertion pipe, the internal slide of insertion pipe is connected with sliding tube, and the inner end of sliding tube The inside of mounting groove is connected to by spring, the inner wall of sliding tube is fixedly connected with rubber membrane, so entering peace in air The motive force that gradually one can be caused downward rubber membrane when in tankage, and finally drive sliding tube in insertion pipe to downslide It is dynamic, to cause the No.1 spliced eye on insertion pipe to be connected to No. two spliced eyes on sliding tube, when No.1 spliced eye and No. two are inserted When slide downward can not be continued by connecing hole connection completion sliding tube, as the increase rubber membrane of air pressure will continue to expand, and it is final swollen Expansion sliding tube enters in No. two walls, but because under the both ends of insertion pipe side external surface rack, and tooth be engaged with by gear The upper end of wheel bar is engaged with sliding panel by gear, so in insertion pipe into No. two walls, both ends when sliding tube slide downward Sliding panel can gradually slid inward, and eventually pass through No.1 spliced eye and No. two spliced eyes and push up the intermediate position of rubber membrane Firmly, with the gas below this seal rubber film, to make in negative pressure state in mounting groove and appendix, to be generated to protrusive board One adsorption capacity reinforces connectivity, and by the way that No.1 spliced eye is arranged on insertion pipe, No. two spliced eyes are set on sliding tube And sliding panel can be made to carry out grafting and avoid high wind from causing wall to further fix to No.1 wall and No. two walls Body shakes.
The inner end of the sliding panel is fixedly connected with magnet block;When insertion pipe is in the grafting in No. two walls, because of grafting Side external surface is engaged with rack by gear under the both ends of pipe, and rack upper end is engaged with sliding panel by gear, so In insertion pipe and sliding tube, the sliding panel at both ends can be inserted gradually into No.1 spliced eye and No. two in grafting when the grafting in No. two walls Hole is connect, and because the inner end of sliding panel is fixedly connected with magnet block, so can generate when the distance between sliding panel moves closer to One active force mutually adsorbed means the sliding panel inner end phase at both ends when insertion pipe and sliding tube grafting completion It is right, at this time due to may further ensure that rubber membrane is completely sealed there are the adsorption capacity of magnet block, it is ensured that mounting groove and gas transmission Negative pressure state is remained in hole, to guarantee the stability of assembling.
Rubber slab is symmetrically slidably fitted in the end walls of the protrusive board;The upper end width of the rubber slab is than transfer port Diameter is two centimetres long, and the both ends outer surface of rubber slab is fixedly installed with hangnail;When protrusive board grafting in groove, because of protrusive board Rubber slab, and longer than the diameter of transfer port centimetre of the upper end width of rubber slab are symmetrically slidably fitted in end walls, so convex The upper end of rubber slab can be sealed transfer port when plate is plugged into certain distance in groove, and with protrusive board grafting distance Increase can cause the upper end of rubber slab to be extruded and enter in transfer port, and the hangnail being fixedly mounted by its both ends outer surface Engaging is completed, the other end of transfer port is sealed, is further ensured that in negative pressure state in transfer port and mounting groove, thus Further increase sealing effect.
The lower end of the rubber slab can offer No.1 sky with grafting into the inside of No.1 wall inside the upper end of rubber slab Chamber offers No. two cavitys inside the lower end of rubber slab;No. two cavitys are connected to No.1 cavity, and filling in No. two cavitys There is steel ball;When protrusive board grafting in groove, as protrusive board in groove go deep by grafting distance, eventually withstand rubber slab Transfer port, and go deep into the state of grafting because protrusive board is unanimously at this time, so the lower end of rubber slab can first be extruded into No.1 wall In vivo, while as the upper end for continuing deeper into rubber slab of protrusive board is extruded into transfer port, at this time because in the upper end of rubber slab Portion offers No.1 cavity, No. two cavitys is offered inside rubber slab lower end, and No.1 cavity is connected to No. two cavitys, so Gas when rubber slab upper end is extruded in No.1 cavity can be injected into No. two cavitys, so that rubber slab and No.1 wall Connection it is even closer, while because in No. two cavitys be filled with steel ball, so can also make in No. two expandable cavities steel ball rise To certain position-limiting action, so that the lower end of rubber slab and No.1 wall be avoided to be detached from.
Uniform intervals are filled with sealant in the lower end wall of the rubber slab;The sealant is filled in the outer of No. two cavitys Side;When No. two cavitys are inflated, because uniform intervals are filled with sealant in the lower end wall of rubber slab, so swollen in No. two cavitys When swollen, that is, expansion of the lower end of rubber slab, one extruding force is generated to the sealant in it, the effect sealant for being squeezed power is saturating It crosses outflow in the aperture of rubber slab lower end and wraps up its lower surface, to the lower end of rubber slab and No.1 wall are completely fixed, no It only can be further improved sealing effect, while the overall stability of structure can also be improved.
Outer lower face surface is fixedly connected with sheet rubber on the lower end of the rubber slab;The other end of the sheet rubber is fixedly connected In the inside of rubber patch;When the lower end of rubber slab is extruded into No.1 wall, because outer lower face surface is fixedly connected on its lower end There is a sheet rubber, and the other end of sheet rubber is fixedly connected on the inside of rubber patch, so in the lower end of rubber slab toward No.1 wall Will pull when interior mobile sheet rubber extension, it is ensured that the intersection that rubber slab is pasted with rubber because rubber slab motive force caused by gap subtract Weak sealing effect.
Beneficial effects of the present invention are as follows:
1. the present invention can be realized in insertion pipe by the way that fixed mechanism is arranged into No. two walls, when sliding tube slide downward The sliding panel at both ends can gradually slid inward, and eventually pass through No.1 spliced eye and No. two spliced eyes for the intermediate position of rubber membrane It withstands, with the gas below this seal rubber film, to make in negative pressure state in mounting groove and appendix, to be produced to protrusive board One raw adsorption capacity reinforces connectivity, and by the way that No.1 spliced eye is arranged on insertion pipe, No. two grafting are set on sliding tube Hole and sliding panel can be made to carry out grafting avoid high wind from causing to further fix No.1 wall and No. two walls Wall shakes.
2. when insertion pipe is in the grafting in No. two walls, because side external surface is engaged with by gear under the both ends of insertion pipe Rack, and rack upper end is engaged with sliding panel by gear, so the grafting in No. two walls in insertion pipe and sliding tube When both ends sliding panel can gradually grafting be into No.1 spliced eye and No. two spliced eyes, and because the inner end of sliding panel is fixedly connected with magnetic Iron block, so one active force mutually adsorbed can be generated when the distance between sliding panel moves closer to, when insertion pipe and cunning Dynamic pipe grafting means that the sliding panel inner end at both ends is opposite when completion, can be at this time due to there are the adsorption capacity of magnet block It is further ensured that rubber membrane is completely sealed, it is ensured that negative pressure state is remained in mounting groove and transfer port, to guarantee to assemble Stability.
3. the present invention can be realized by installing rubber slab in protrusive board when protrusive board grafting in groove, because of the two of protrusive board Rubber slab, and longer than the diameter of transfer port centimetre of the upper end width of rubber slab are symmetrically slidably fitted in end wall, so in protrusive board The upper end of rubber slab can be sealed transfer port when being plugged into certain distance in groove, and with the increasing of protrusive board grafting distance Add the upper end that can cause rubber slab to be extruded and enter in transfer port, and is complete by the hangnail that its both ends outer surface is fixedly mounted At engaging, the other end of transfer port is sealed, is further ensured that in negative pressure state in transfer port and mounting groove, thus into One step improves sealing effect.
Detailed description of the invention
Fig. 1 is main view of the invention;
Fig. 2 is the partial enlarged view in Fig. 1 of the present invention at A;
Fig. 3 is the partial enlarged view in Fig. 1 of the present invention at B;
Fig. 4 is the partial enlarged view in Fig. 3 of the present invention at C;
Fig. 5 is the partial enlarged view in Fig. 3 of the present invention at D;
In figure: No.1 wall 1, groove 11, No. two walls 2, protrusive board 21, rubber slab 22, hangnail 23, No.1 cavity 24, two Number cavity 25, steel ball 26, sealant 27, sheet rubber 28, fixed mechanism 3, rubber patch 31, transfer port 32, mounting groove 33, insertion pipe 34, No.1 spliced eye 341, sliding tube 35, No. two spliced eyes 351, sliding panel 36, rack 37, rubber membrane 38, magnet block 39.
Specific embodiment
It is said as follows using a kind of Prefabricated composite assembling steel plate shear wall of Fig. 1-Fig. 5 to an embodiment of the present invention It is bright.
As Figure 1-Figure 5, a kind of Prefabricated composite assembling steel plate shear wall of the present invention, including No.1 wall 1, No. two walls 2 and fixed mechanism 3;The upper and lower ends of the No.1 wall 1 open up fluted 11, inside the both ends of No.1 wall 1 Equipped with fixed mechanism 3;The upper and lower ends of No. two walls 2 are provided with protrusive board 21;The protrusive board 21 can be with grafting into groove 11 In;The fixed mechanism 3 includes that rubber pastes 31, transfer port 32, mounting groove 33, insertion pipe 34, sliding tube 35, sliding panel 36, tooth Take turns bar 37 and rubber membrane 38;The rubber patch 31 is fixedly connected on the both ends side surface of protrusive board 21;The transfer port 32 is in bending Shape, transfer port 32 are symmetrically provided with inside the upper and lower ends of No.1 wall 1, and one end perforation of transfer port 32 is located in groove 11, The other end of transfer port 32 is connected to mounting groove 33;The lower end of the mounting groove 33 is equipped with insertion pipe 34;The insertion pipe 34 is solid Dingan County symmetrically offers No.1 spliced eye 341 in the upper and lower ends wall of No.1 wall 1 in the end walls of insertion pipe 34, insert The internal slide of adapter tube 34 is connected with sliding tube 35, and side external surface is engaged with rack by gear under the both ends of insertion pipe 34 37;The inner end of the sliding tube 35 is connected to the inside of mounting groove 33 by spring, symmetrical in the end walls of sliding tube 35 No. two spliced eyes 351 are offered, the inner wall of sliding tube 35 is fixedly connected with rubber membrane 38;37 upper end of rack passes through gear It is engaged with sliding panel 36;The sliding panel 36 is slidably mounted in the upper and lower ends wall of No. two walls 2;When work, if necessary Shear wall is assembled, No.1 wall 1 can be attached with No. two walls 2 by groove 11 and protrusive board 21, while one Insertion pipe 34 on number wall 1 can grafting into No. two walls 2, because the both ends side surface of protrusive board 21 is fixedly connected with rubber patch 31, So protrusive board 21 can cause the air in groove 11 to be extruded when carrying out grafting with groove 11, because the inside both ends of groove 11 are passed through It wears and is communicated with transfer port 32, and the other end of transfer port 32 is connected to mounting groove 33, so the air in groove 11 is extruded When can by transfer port 32 enter mounting groove 33 in, because the lower end of mounting groove 33 is connect with insertion pipe 34, the inside of insertion pipe 34 Sliding tube 35 is slidably connected, and the inner end of sliding tube 35 is connected to the inside of mounting groove 33, sliding tube 35 by spring Inner wall be fixedly connected with rubber membrane 38, so when air enters in mounting groove 33 can gradually to rubber membrane 38 cause one to Under motive force, and finally drive the slide downward in insertion pipe 34 of sliding tube 35, to cause the No.1 grafting on insertion pipe 34 Hole 341 is connected to No. two spliced eyes 351 on sliding tube 35, is slided when No.1 spliced eye 341 is connected to completion with No. two spliced eyes 351 When dynamic pipe 35 can not continue slide downward, as the increase rubber membrane 38 of air pressure will continue to expand, and sliding tube out is finally expanded 35 enter in No. two walls 2, but because under the both ends of insertion pipe 34 side external surface rack 37, and rack be engaged with by gear 37 upper end is engaged with sliding panel 36 by gear, so entering No. two walls 2 in insertion pipe 34, when 35 slide downward of sliding tube The sliding panel 36 at both ends understands gradually slid inward, and eventually passes through No.1 spliced eye 341 and No. two spliced eyes 351 for rubber membrane 38 Intermediate position withstand, with the gas of 38 lower section of this seal rubber film, to make in mounting groove 33 and appendix in negative pressure shape State reinforces connectivity to generate one adsorption capacity to protrusive board 21, and by the way that No.1 spliced eye 341 is arranged on insertion pipe 34, No. two spliced eyes 351 are set on sliding tube 35 and sliding panel 36 can be made to carry out grafting, thus to No.1 wall 1 and No. two walls Body 2 is further fixed, and avoids high wind that wall is caused to shake.
The inner end of the sliding panel 36 is fixedly connected with magnet block 39;When insertion pipe 34 is in the grafting in No. two walls 2, Because side external surface by gear is engaged with rack 37 under the both ends of insertion pipe 34, and 37 upper end of rack is engaged with by gear Sliding panel 36, so the sliding panel 36 at both ends can gradually grafting when the grafting in No. two walls 2 in insertion pipe 34 and sliding tube 35 Into No.1 spliced eye 341 and No. two spliced eyes 351, and because the inner end of sliding panel 36 is fixedly connected with magnet block 39, so when sliding The distance between movable plate 36 can generate one active force mutually adsorbed when moving closer to, when 35 grafting of insertion pipe 34 and sliding tube Mean that 36 inner end of sliding panel at both ends is opposite when completion, it, can be into one at this time since there are the adsorption capacities of magnet block 39 Step guarantees that rubber membrane 38 is completely sealed, it is ensured that negative pressure state is remained in mounting groove 33 and transfer port 32, thus guarantee group The stability of dress.
Rubber slab 22 is symmetrically slidably fitted in the end walls of the protrusive board 21;The upper end width of the rubber slab 22 is than defeated The diameter of stomata 32 is two centimetres long, and the both ends outer surface of rubber slab 22 is fixedly installed with hangnail 23;When protrusive board 21 is toward groove 11 When interior grafting, because being symmetrically slidably fitted with rubber slab 22 in the end walls of protrusive board 21, and the upper end width of rubber slab 22 compares gas transmission Long centimetre of the diameter in hole 32, so the upper end of rubber slab 22 can be to gas transmission when protrusive board 21 is plugged into certain distance in groove 11 Hole 32 is sealed, and as the increase of 21 grafting distance of protrusive board can cause the upper end of rubber slab 22 to be extruded and enter gas transmission In hole 32, and engaging is completed by the hangnail 23 that its both ends outer surface is fixedly mounted, the other end of transfer port 32 is sealed, It further ensures that in negative pressure state in transfer port 32 and mounting groove 33, to further increase sealing effect.
The lower end of the rubber slab 22 can offer inside the upper end of rubber slab 22 with grafting into the inside of No.1 wall 1 No.1 cavity 24 offers No. two cavitys 25 inside the lower end of rubber slab 22;No. two cavitys 25 are connected to No.1 cavity 24, And steel ball 26 is filled in No. two cavitys 25;When the grafting in groove 11 of protrusive board 21, with the grafting in groove 11 of protrusive board 21 Distance is goed deep into, and rubber slab 22 is eventually made to withstand transfer port 32, and is in the state for going deep into grafting because protrusive board 21 is consistent at this time, So the lower end of rubber slab 22 can be first extruded into No.1 wall 1, while rubber slab 22 is continued deeper into protrusive board 21 Upper end is extruded into transfer port 32, at this time because offering No.1 cavity 24,22 lower end of rubber slab inside the upper end of rubber slab 22 Inside offers No. two cavitys 25, and No.1 cavity 24 is connected to No. two cavitys 25, so when 22 upper end of rubber slab is extruded Gas in No.1 cavity 24 can be injected into No. two cavitys 25, so that the connection of rubber slab 22 and No.1 wall 1 is more Closely, while because being filled with steel ball 26 in No. two cavitys 25, so steel ball 26 can also be made to play when No. two cavitys 25 expand Certain position-limiting action, so that the lower end of rubber slab 22 and No.1 wall 1 be avoided to be detached from.
Uniform intervals are filled with sealant 27 in the lower end wall of the rubber slab 22;The sealant 27 is filled in No. two skies The outside of chamber 25;When No. two cavitys 25 are inflated, because uniform intervals are filled with sealant 27, institute in the lower end wall of rubber slab 22 With when No. two cavitys 25 expand, that is, lower end of rubber slab 22 expands, one extruding force is generated to the sealant 27 in it, by The effect sealant 27 of extruding force wraps up its lower surface through outflow in the aperture of 22 lower end of rubber slab, thus by rubber slab 22 Lower end is completely fixed with No.1 wall 1, not only can be further improved sealing effect, while can also improve the whole steady of structure It is qualitative.
Outer lower face surface is fixedly connected with sheet rubber 28 on the lower end of the rubber slab 22;The other end of the sheet rubber 28 is solid Surely it is connected to the inside of rubber patch 31;When the lower end of rubber slab 22 is extruded into No.1 wall 1, because of appearance above and below its lower end Face is fixedly connected with sheet rubber 28, and the other end of sheet rubber 28 is fixedly connected on the inside of rubber patch 31, so in rubber slab 22 lower end will pull the extension of sheet rubber 28 when moving in No.1 wall 1, it is ensured that the intersection of rubber slab 22 and rubber patch 31 Because rubber slab 22 motive force caused by gap weaken sealing effect.
Specific workflow is as follows:
When work, if necessary to assemble to shear wall, No.1 wall 1 and No. two walls 2 can be passed through groove 11 It is attached with protrusive board 21, while the insertion pipe 34 on No.1 wall 1 understands grafting into No. two walls 2, because of two end sides of protrusive board 21 Surface is fixedly connected with rubber patch 31, so protrusive board 21 can cause the air in groove 11 to be squeezed when carrying out grafting with groove 11 Pressure runs through because of the inside both ends of groove 11 and is communicated with transfer port 32, and the other end of transfer port 32 is connected to mounting groove 33, so It can be entered in mounting groove 33 by transfer port 32 when the air in groove 11 is extruded, lower end and insertion pipe because of mounting groove 33 34 connections, the internal slide of insertion pipe 34 is connected with sliding tube 35, and the inner end of sliding tube 35 is connected to peace by spring The inside of tankage 33, the inner wall of sliding tube 35 are fixedly connected with rubber membrane 38, so can be by when air enters in mounting groove 33 The motive force for gradually causing one downward rubber membrane 38, and the slide downward in insertion pipe 34 of sliding tube 35 is finally driven, so that Be connected to the No.1 spliced eye 341 on insertion pipe 34 with No. two spliced eyes 351 on sliding tube 35, when No.1 spliced eye 341 with When No. two connection completion sliding tubes 35 of spliced eye 351 can not continue slide downward, as the increase rubber membrane 38 of air pressure will continue to Expansion, and finally expand sliding tube 35 out and enter in No. two walls 2, but because under the both ends of insertion pipe 34 side external surface pass through gear It is engaged with rack 37, and the upper end of rack 37 is engaged with sliding panel 36 by gear, so entering No. two in insertion pipe 34 Wall 2, when 35 slide downward of sliding tube the sliding panel 36 at both ends can gradually slid inward, and eventually pass through No.1 spliced eye 341 The intermediate position of rubber membrane 38 is withstood with No. two spliced eyes 351, with the gas of this 38 lower section of seal rubber film, to make to install It is in negative pressure state in slot 33 and appendix, to generate one adsorption capacity to protrusive board 21, reinforces connectivity, and by grafting No.1 spliced eye 341 is set on pipe 34, No. two spliced eyes 351 are set on sliding tube 35 and that sliding panel 36 can be made to carry out is slotting It connects, to further fix to No.1 wall 1 and No. two walls 2, avoids high wind that wall is caused to shake.
The embodiment of the present invention is described with above attached drawing, but the invention is not limited to above-mentioned specific Embodiment, the above mentioned embodiment is only schematical, rather than restrictive, those skilled in the art Under the inspiration of the present invention, without breaking away from the scope protected by the purposes and claims of the present invention, it can also make very much Form, all of these belong to the protection of the present invention.

Claims (6)

1. a kind of Prefabricated composite assembling steel plate shear wall, including No.1 wall (1), No. two walls (2) and fixed mechanism (3); It is characterized by: the upper and lower ends of the No.1 wall (1) open up fluted (11), it is equipped with inside the both ends of No.1 wall (1) Fixed mechanism (3);The upper and lower ends of No. two walls (2) are provided with protrusive board (21);The protrusive board (21) can be with grafting into recessed In slot (11);The fixed mechanism (3) includes rubber patch (31), transfer port (32), mounting groove (33), insertion pipe (34), sliding Manage (35), sliding panel (36), rack (37) and rubber membrane (38);The rubber patch (31) is fixedly connected on the two of protrusive board (21) End side surface;The transfer port (32) is in bending, and transfer port (32) is symmetrically provided in the upper and lower ends of No.1 wall (1) One end perforation in portion, transfer port (32) is located in groove (11), and the other end of transfer port (32) is connected to mounting groove (33);It is described The lower end of mounting groove (33) is equipped with insertion pipe (34);The insertion pipe (34) is fixedly mounted on the upper and lower ends of No.1 wall (1) It in wall, is symmetrically offered in the end walls of insertion pipe (34) No.1 spliced eye (341), the internal slide of insertion pipe (34) is connected with Sliding tube (35), side external surface is engaged with rack (37) by gear under the both ends of insertion pipe (34);The sliding tube (35) Inner end the inside of mounting groove (33) is connected to by spring, No. two are symmetrically offered in the end walls of sliding tube (35) and is inserted It connects hole (351), the inner wall of sliding tube (35) is fixedly connected with rubber membrane (38);It is engaged by gear rack (37) upper end There are sliding panel (36);The sliding panel (36) is slidably mounted in the upper and lower ends wall of No. two walls (2).
2. a kind of Prefabricated composite assembling steel plate shear wall according to claim 1, it is characterised in that: the sliding panel (36) inner end is fixedly connected with magnet block (39).
3. a kind of Prefabricated composite assembling steel plate shear wall according to claim 1, it is characterised in that: the protrusive board (21) End walls in be symmetrically slidably fitted with rubber slab (22);Diameter of the upper end width of the rubber slab (22) than transfer port (32) It is two centimetres long, and the both ends outer surface of rubber slab (22) is fixedly installed with hangnail (23).
4. a kind of Prefabricated composite assembling steel plate shear wall according to claim 3, it is characterised in that: the rubber slab (22) lower end can offer No.1 cavity (24) inside the upper end of rubber slab (22) with grafting into the inside of No.1 wall (1), No. two cavitys (25) are offered inside the lower end of rubber slab (22);No. two cavitys (25) are connected to No.1 cavity (24), and Steel ball (26) are filled in No. two cavitys (25).
5. a kind of Prefabricated composite assembling steel plate shear wall according to claim 3, it is characterised in that: the rubber slab (22) uniform intervals are filled with sealant (27) in lower end wall;The sealant (27) is filled in the outer of No. two cavitys (25) Side.
6. a kind of Prefabricated composite assembling steel plate shear wall according to claim 1, it is characterised in that: the rubber slab (22) outer lower face surface is fixedly connected with sheet rubber (28) on lower end;The other end of the sheet rubber (28) is fixedly connected on rubber Paste the inside of (31).
CN201910453650.4A 2019-05-28 2019-05-28 Prefabricated combination assembled steel sheet shear force wall Active CN110158807B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910453650.4A CN110158807B (en) 2019-05-28 2019-05-28 Prefabricated combination assembled steel sheet shear force wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910453650.4A CN110158807B (en) 2019-05-28 2019-05-28 Prefabricated combination assembled steel sheet shear force wall

Publications (2)

Publication Number Publication Date
CN110158807A true CN110158807A (en) 2019-08-23
CN110158807B CN110158807B (en) 2020-09-01

Family

ID=67629714

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910453650.4A Active CN110158807B (en) 2019-05-28 2019-05-28 Prefabricated combination assembled steel sheet shear force wall

Country Status (1)

Country Link
CN (1) CN110158807B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100287865A1 (en) * 2009-05-15 2010-11-18 Michael Hatzinikolas Pre-cast rain screen wall panel
CN105544776A (en) * 2015-12-07 2016-05-04 金陵科技学院 Wall used in building
CN205242675U (en) * 2015-12-01 2016-05-18 沈阳建筑大学 Prefabricated assembled shear force wall horizontal bolt joint construction
CN105604208A (en) * 2016-03-03 2016-05-25 华汇工程设计集团股份有限公司 Prefabricated shear wall in cast-in-situ connection mode
CN206752735U (en) * 2017-03-29 2017-12-15 河北建筑工程学院 Precast shear wall insert-type steel board connecting structure
CN208072702U (en) * 2018-04-10 2018-11-09 常州工程职业技术学院 One kind exempting from formwork fabricated shear wall perps connection unit

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100287865A1 (en) * 2009-05-15 2010-11-18 Michael Hatzinikolas Pre-cast rain screen wall panel
CN205242675U (en) * 2015-12-01 2016-05-18 沈阳建筑大学 Prefabricated assembled shear force wall horizontal bolt joint construction
CN105544776A (en) * 2015-12-07 2016-05-04 金陵科技学院 Wall used in building
CN105604208A (en) * 2016-03-03 2016-05-25 华汇工程设计集团股份有限公司 Prefabricated shear wall in cast-in-situ connection mode
CN206752735U (en) * 2017-03-29 2017-12-15 河北建筑工程学院 Precast shear wall insert-type steel board connecting structure
CN208072702U (en) * 2018-04-10 2018-11-09 常州工程职业技术学院 One kind exempting from formwork fabricated shear wall perps connection unit

Also Published As

Publication number Publication date
CN110158807B (en) 2020-09-01

Similar Documents

Publication Publication Date Title
CN203640113U (en) Unit curtain wall system
CN105014785B (en) Prefabricated assembled concrete component Bar Anchorage preformed hole hole-forming device and method
CN110158807A (en) A kind of Prefabricated composite assembling steel plate shear wall
CN201649380U (en) Small clearance fit opening-type unit glass curtain wall aluminum alloy system
CN111571767B (en) Toilet seat and split forming method thereof
CN203640112U (en) Transverse beam structure of unit curtain wall
CN115126490A (en) Small-clear-distance triple-arch progressive station tunnel construction method
CN112593631B (en) Main structure of green assembly type building
CN104314047A (en) Water bag concrete engineering deformation joint water stop type cavity die and manufacturing and construction method thereof
CN107965076A (en) Hollow extrusion molding cement plate Curtain Wall and its construction method
CN210599021U (en) Rear embedded shield tunnel elastic sealing gasket and sealing structure
CN108999047B (en) Landscaping brick
CN201140434Y (en) Molding mold for producing hollow wallboard
CN206888029U (en) A kind of prefabricated box culvert structure containing glass fiber-reinforced polymer
CN218933040U (en) Flood discharge tunnel accident access door runner structure
CN211200353U (en) Detachable mutually-embedded vertical joint suitable for prefabricated underground diaphragm wall
CN220434544U (en) Prefabricated bay window connection reinforced structure of assembled
CN219886841U (en) Bag anchor rod grouting mechanism with exhaust backflow prevention function
CN215055233U (en) Concrete formwork for water inlet runner
CN208533844U (en) A kind of light-high-strength steam-pressing aero-concrete
CN204590309U (en) Door and window hole surrounding body of wall seal modules
CN213572640U (en) Light energy-saving door and window plate
CN220035199U (en) Anti-seepage steel structure pier body steel mould
CN217269716U (en) Bridge cut-off aluminium door and window structure with sound insulation and heat insulation functions
CN220014115U (en) Assembled floor board

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20200806

Address after: 350007 5 / F, building 2, Hangxing garden, 38 Nantai Road, Cangshan District, Fuzhou City, Fujian Province

Applicant after: FUJIAN YONGFU CONSTRUCTION GROUP Co.,Ltd.

Address before: 510000 Third Floor of Post and Telecommunications Building, No. 2 Zhongshan Road, Yuexiu District, Guangzhou City, Guangdong Province

Applicant before: Wang Xiaoyong

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 350700 South Lake Garden Building No. 18, Zhangcheng, Yongtai County, Fuzhou City, Fujian Province 202

Patentee after: Yongfu Construction Engineering Group Co., Ltd

Address before: 350007 5th floor, building 2, Hangxing garden, 38 Nantai Road, Cangshan District, Fuzhou City, Fujian Province

Patentee before: FUJIAN YONGFU CONSTRUCTION GROUP Co.,Ltd.

CP03 Change of name, title or address