CN110136026A CN201910359905.0A CN201910359905A CN110136026A CN 110136026 A CN110136026 A CN 110136026A CN 201910359905 A CN201910359905 A CN 201910359905A CN 110136026 A CN110136026 A CN 110136026A
Authority
CN
China
Prior art keywords
water
value
factory
water factory
towns
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910359905.0A
Other languages
Chinese (zh)
Inventor
郝鹏
陈永建
李汉杰
陆耀荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Water Group Gaoming Water Supply Co Ltd
Original Assignee
Foshan Water Group Gaoming Water Supply Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan Water Group Gaoming Water Supply Co Ltd filed Critical Foshan Water Group Gaoming Water Supply Co Ltd
Priority to CN201910359905.0A priority Critical patent/CN110136026A/en
Publication of CN110136026A publication Critical patent/CN110136026A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B7/00Water main or service pipe systems
    • E03B7/02Public or like main pipe systems
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B7/00Water main or service pipe systems
    • E03B7/07Arrangement of devices, e.g. filters, flow controls, measuring devices, siphons or valves, in the pipe systems
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05DSYSTEMS FOR CONTROLLING OR REGULATING NON-ELECTRIC VARIABLES
    • G05D16/00Control of fluid pressure
    • G05D16/20Control of fluid pressure characterised by the use of electric means
    • G05D16/2006Control of fluid pressure characterised by the use of electric means with direct action of electric energy on controlling means
    • G05D16/2013Control of fluid pressure characterised by the use of electric means with direct action of electric energy on controlling means using throttling means as controlling means
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Business, Economics & Management (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Fluid Mechanics (AREA)
  • General Health & Medical Sciences (AREA)
  • Automation & Control Theory (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Fluid-Pressure Circuits (AREA)

Abstract

The invention discloses the control methods and its control system of a kind of water factory's water distribution, if the hydraulic pressure intensity value between water factory and the first cities and towns is QAIf the hydraulic pressure intensity value between water factory and the second cities and towns is QBIf the Real-time Water pressure angle value between water factory and the first pressurizing point is QC, control method mainly comprise the steps that S100, detection water factory and the first pressurizing point between Real-time Water pressure angle value QC;S200, according to Real-time Water pressure angle value Q detectedCHydraulic pressure intensity value Q between water factory and the first cities and towns is adjusted using sliding scaleAHydraulic pressure intensity value Q between water factory and the second cities and townsB;Pass through the Real-time Water pressure angle value between detection water factory and the first pressurizing point, and the hydraulic pressure intensity between water factory and each cities and towns is adjusted according to Real-time Water pressure angle value detected, the real-time adjustment for realizing water source distribution ratio of liquid flow, avoids the lower city of hydraulic pressure intensity requirement value from the phenomenon that insufficient water occur.

Description

A kind of control method and its control system of water factory's water distribution
Technical field
The present invention relates to water treatment plant's production monitoring and management domain, in particular to the control method of a kind of water factory's water distribution and Its control system.
Background technique
During water factory distributes water source toward cities and towns, by each cities and towns to the hydraulic pressure intensity requirement at distributed water source not Unanimously;During the water distribution of water factory's distribution reservoir, if not adjusting the water source distribution ratio of liquid flow between water factory and each cities and towns, water The occupied water source flow proportional in the more demanding cities and towns of Compressive Strength is larger, goes out so as to cause the lower cities and towns of hydraulic pressure intensity requirement The phenomenon that existing insufficient water.
As it can be seen that the prior art could be improved and improve.
Summary of the invention
Place in view of above-mentioned deficiencies of the prior art, the purpose of the present invention is to provide a kind of control methods of water factory's water distribution And its control system, by the Real-time Water pressure angle value between detection water factory and the first cities and towns, and according to Real-time Water detected Pressure angle value adjusts the hydraulic pressure intensity between water factory and each cities and towns, realizes the real-time adjustment of water source distribution ratio of liquid flow, avoids water There is the phenomenon that insufficient water in the lower city of Compressive Strength required value.
In order to achieve the above object, this invention takes following technical schemes:
A kind of control method of water factory's water distribution, if the hydraulic pressure intensity value between water factory and the first cities and towns is QAIf water factory and second Hydraulic pressure intensity value between cities and towns is QBIf the Real-time Water pressure angle value between water factory and the first pressurizing point is QC;The controlling party Method mainly comprises the steps that
Real-time Water pressure angle value Q between S100, detection water factory and the first pressurizing pointC
S200, according to Real-time Water pressure angle value Q detectedCWater between water factory and the first cities and towns is adjusted using sliding scale Pressure angle value QAHydraulic pressure intensity value Q between water factory and the second cities and townsB
In the control method of water factory's water distribution, the sliding scale are as follows:
Work as QCValue be QCWhen >=0.40Mpa, the first pressurizing point is wanted using the upper limit hydraulic pressure intensity value in the second cities and towns as hydraulic pressure intensity It asks and supplies water to the second cities and towns;
Work as QCValue be 0.39Mpa≤QCWhen < 0.40Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=1.0:9.0 is set It sets;
Work as QCValue be 0.38Mpa≤QCWhen < 0.39Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=1.0:4.0 is set It sets;
Work as QCValue be 0.37Mpa≤QCWhen < 0.38Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=3.0:7.0 is set It sets;
Work as QCValue be 0.36Mpa≤QCWhen < 0.37Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=2.0:3.0 is set It sets;
Work as QCValue be 0.35Mpa≤QCWhen < 0.36Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=1.0:1.0 is set It sets;
Work as QCValue be 0.34Mpa≤QCWhen < 0.35Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=3.0:2.0 is set It sets;
Work as QCValue be 0.33Mpa≤QCWhen < 0.34Mpa, the water source distribution ratio of liquid flow of water factory is set by QA: QB=7.0:3.0 It sets;
Work as QCValue be 0.32Mpa≤QCWhen < 0.33Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=4.0:1.0 is set It sets;
Work as QCValue be 0.31Mpa≤QCWhen < 0.32Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=9.0:1.0 is set It sets;
Work as QCValue be QCWhen < 0.31Mpa, the first pressurizing point stops working, and is in hot stand-by duty, water is in a manner of flowing automatically Flow to the second cities and towns.
The present invention further correspondingly provides a kind of control system of water factory's water distribution, including distribution reservoir, is set to water factory and first The first pipeline between pressurizing point, the second pipeline being set between water factory and the second cities and towns, the first detection device and the second inspection Survey device;First detection device is set in the first pipeline, for detecting the hydraulic pressure intensity in the first pipeline;Described second Detection device is set in the second pipeline, for detecting the hydraulic pressure intensity in the second pipeline;First detection device and second Information detected is fed back to distribution reservoir respectively by detection device.
In the control system of water factory's water distribution, the distribution reservoir is configured with the valve regulated for adjusting valve opening System, the water supply pump installation for realizing water supply and the water source micro-tensioning system for realizing the fine tuning of water source sendout;The water supply Pump installation and water source micro-tensioning system are connected to valving system, first detection device and second detection device difference Information detected is fed back into valving system.
In the control system of water factory's water distribution, the first detection detection device includes several first pressure sensings Device, the first pressure sensor are evenly arranged in the first pipeline;The second detection device includes several second pressures Sensor, the second pressure sensor are evenly arranged in the second pipeline.
Beneficial effect
Compared with prior art, the present invention provides the control method and its control system of a kind of water factory's water distribution, the controlling parties Real-time Water pressure angle value between method real-time detection water factory and the first pressurizing point, and according to Real-time Water pressure angle value tune detected Hydraulic pressure intensity between whole water factory and each cities and towns realizes the real-time adjustment of water factory water source distribution ratio of liquid flow, avoids hydraulic pressure intensity There is the phenomenon that insufficient water in the lower city of required value.
Detailed description of the invention
Fig. 1 is the logic diagram of the control method of water factory's water distribution provided by the present invention;
Fig. 2 is the structural schematic diagram of the control system of water factory's water distribution provided by the present invention.
Specific embodiment
The present invention provides the control methods and its control system of a kind of water factory's water distribution, to make the purpose of the present invention, technology Scheme and effect are clearer, clear, and invention is further described in detail as follows in conjunction with drawings and embodiments.It should manage Solution, described herein specific examples are only used to explain the present invention, is not intended to limit the present invention.
In the description of the present invention, it is to be understood that, term " first ", " second " are used for description purposes only, and cannot It is interpreted as indication or suggestion relative importance or implicitly indicates the quantity of indicated technical characteristic.
Referring to Fig. 1, the present invention provides a kind of control method of water factory's water distribution, if the water between water factory and the first cities and towns Pressure angle value is QAIf the hydraulic pressure intensity value between water factory and the second cities and towns is QBIf real-time between water factory and the first pressurizing point Hydraulic pressure intensity value is QC;The control method mainly comprises the steps that
Real-time Water pressure angle value Q between S100, detection water factory and the first pressurizing pointC
S200, according to Real-time Water pressure angle value Q detectedCWater between water factory and the first cities and towns is adjusted using sliding scale Pressure angle value QAHydraulic pressure intensity value Q between water factory and the second cities and townsB
Further, the sliding scale are as follows:
Work as QCValue be QCWhen >=0.40Mpa, the first pressurizing point is wanted using the upper limit hydraulic pressure intensity value in the second cities and towns as hydraulic pressure intensity It asks and supplies water to the second cities and towns;In the present embodiment, the upper limit hydraulic pressure intensity value in second cities and towns is QB=1MPa;
Work as QCValue be 0.39Mpa≤QCWhen < 0.40Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=1.0:9.0 is set It sets;
Work as QCValue be 0.38Mpa≤QCWhen < 0.39Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=1.0:4.0 is set It sets;
Work as QCValue be 0.37Mpa≤QCWhen < 0.38Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=3.0:7.0 is set It sets;
Work as QCValue be 0.36Mpa≤QCWhen < 0.37Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=2.0:3.0 is set It sets;
Work as QCValue be 0.35Mpa≤QCWhen < 0.36Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=1.0:1.0 is set It sets;
Work as QCValue be 0.34Mpa≤QCWhen < 0.35Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=3.0:2.0 is set It sets;
Work as QCValue be 0.33Mpa≤QCWhen < 0.34Mpa, the water source distribution ratio of liquid flow of water factory is set by QA: QB=7.0:3.0 It sets;
Work as QCValue be 0.32Mpa≤QCWhen < 0.33Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=4.0:1.0 is set It sets;
Work as QCValue be 0.31Mpa≤QCWhen < 0.32Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=9.0:1.0 is set It sets;
Work as QCValue be QCWhen < 0.31Mpa, the first pressurizing point stops working, and is in hot stand-by duty, water is in a manner of flowing automatically Flow to the second cities and towns;In the present embodiment, the hydraulic pressure intensity when the first pressurizing point stops working, between water factory and the first cities and towns Value QA=0.3MPa。
Referring to Fig. 2, the present invention further correspondingly provides a kind of control system of water factory's water distribution, including distribution reservoir, it is set to The first pipeline between water factory and the first pressurizing point, the second pipeline being set between water factory and the second cities and towns, the first detection dress It sets and second detection device;First detection device is set in the first pipeline, strong for detecting the hydraulic pressure in the first pipeline Degree;The second detection device is set in the second pipeline, for detecting the hydraulic pressure intensity in the second pipeline;First detection Information detected is fed back to distribution reservoir respectively by device and second detection device.
Further, the distribution reservoir is configured with for adjusting the valving system of valve opening, for realizing water supply Water supply pump installation and for realizing water source sendout fine tuning water source micro-tensioning system;The water supply pump installation and water source fine tuning system System is connected to valving system, and first detection device and second detection device respectively feed back information detected To valving system.
The control system working principle of above-mentioned water factory's water distribution is as follows: the first detection device real-time detection water factory and the first pressurization Real-time Water pressure angle value Q between standingC, and information detected is fed back into valving system, valving system according to Real-time Water pressure angle value QCThe aperture of valve is adjusted, and by Real-time Water pressure angle value QCIt is transmitted to water source micro-tensioning system, the water source Micro-tensioning system adjusts Q using aforementioned proportion adjusting methodAWith QBValue, that is, adjust water factory water source distribution ratio of liquid flow, to realize The dynamic of water factory's water source distribution ratio of liquid flow adjusts, and the lower cities and towns of hydraulic pressure intensity requirement is avoided the phenomenon that insufficient water occur.
Further, the first detection detection device includes several first pressure sensors, the first pressure sensing Device is evenly arranged in the first pipeline;The second detection device includes several second pressure sensors, the second pressure Sensor is evenly arranged in the second pipeline;In the present embodiment, the first pressure sensor can be 4, set respectively It is placed in the starting point of the first pipeline, the midpoint of the first pipeline, in the first cities and towns and in the first pressurizing point;The second pressure sensor It can be 3, be respectively arranged at the terminal of the starting point of the second pipeline, the midpoint of the second pipeline and the second pipeline;In actual operation, Real-time Water pressure angle value Q between the water factory and the first pressurizing pointCFor data measured by each first pressure sensor Average value.
It, can according to the technique and scheme of the present invention and its hair it is understood that for those of ordinary skills Bright design is subject to equivalent substitution or change, and all these replacements or change all should belong to claims appended hereto Protection scope in.

Claims (5)

1. a kind of control method of water factory's water distribution, if the hydraulic pressure intensity value between water factory and the first cities and towns is QAIf water factory and second Hydraulic pressure intensity value between cities and towns is QBIf the Real-time Water pressure angle value between water factory and the first pressurizing point is QC, feature exists In the control method mainly comprises the steps that
Real-time Water pressure angle value Q between S100, detection water factory and the first pressurizing pointC
S200, according to Real-time Water pressure angle value Q detectedCWater between water factory and the first cities and towns is adjusted using sliding scale Pressure angle value QAHydraulic pressure intensity value Q between water factory and the second cities and townsB
2. a kind of control method of water factory's water distribution according to claim 1, which is characterized in that the sliding scale are as follows:
Work as QCValue be QCWhen >=0.40Mpa, the first pressurizing point is using the upper limit hydraulic pressure intensity value in the second cities and towns as hydraulic pressure intensity requirement It supplies water to the second cities and towns;
Work as QCValue be 0.39Mpa≤QCWhen < 0.40Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=1.0:9.0 setting;
Work as QCValue be 0.38Mpa≤QCWhen < 0.39Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=1.0:4.0 setting;
Work as QCValue be 0.37Mpa≤QCWhen < 0.38Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=3.0:7.0 setting;
Work as QCValue be 0.36Mpa≤QCWhen < 0.37Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=2.0:3.0 setting;
Work as QCValue be 0.35Mpa≤QCWhen < 0.36Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=1.0:1.0 setting;
Work as QCValue be 0.34Mpa≤QCWhen < 0.35Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=3.0:2.0 setting;
Work as QCValue be 0.33Mpa≤QCWhen < 0.34Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=7.0:3.0 setting;
Work as QCValue be 0.32Mpa≤QCWhen < 0.33Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=4.0:1.0 setting;
Work as QCValue be 0.31Mpa≤QCWhen < 0.32Mpa, the water source distribution ratio of liquid flow of water factory presses QA: QB=9.0:1.0 setting;
Work as QCValue be QCWhen < 0.31Mpa, the first pressurizing point stops working, and is in hot stand-by duty, water stream in a manner of flowing automatically To the second cities and towns.
3. a kind of control system of water factory's water distribution, which is characterized in that including distribution reservoir, be set between water factory and the first pressurizing point The first pipeline, the second pipeline, the first detection device and the second detection device that are set between water factory and the second cities and towns;It is described First detection device is set in the first pipeline, for detecting the hydraulic pressure intensity in the first pipeline;The second detection device is set It is placed in the second pipeline, for detecting the hydraulic pressure intensity in the second pipeline;First detection device and second detection device point Information detected distribution reservoir is not fed back into.
4. a kind of control system of water factory's water distribution according to claim 3, which is characterized in that the distribution reservoir configuration is useful In adjustment valve opening valving system, for realizing water supply water supply pump installation and for realizing water source sendout fine tuning Water source micro-tensioning system;The water supply pump installation and water source micro-tensioning system are connected to valving system, first inspection It surveys device and information detected is fed back to valving system respectively by second detection device.
5. a kind of control system of water factory's water distribution according to claim 4, which is characterized in that the first detection detection dress It sets including several first pressure sensors, the first pressure sensor is evenly arranged in the first pipeline;Second inspection Surveying device includes several second pressure sensors, and the second pressure sensor is evenly arranged in the second pipeline.
CN201910359905.0A 2019-04-30 2019-04-30 A kind of control method and its control system of water factory's water distribution Pending CN110136026A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910359905.0A CN110136026A (en) 2019-04-30 2019-04-30 A kind of control method and its control system of water factory's water distribution

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910359905.0A CN110136026A (en) 2019-04-30 2019-04-30 A kind of control method and its control system of water factory's water distribution

Publications (1)

Publication Number Publication Date
CN110136026A true CN110136026A (en) 2019-08-16

Family

ID=67575905

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910359905.0A Pending CN110136026A (en) 2019-04-30 2019-04-30 A kind of control method and its control system of water factory's water distribution

Country Status (1)

Country Link
CN (1) CN110136026A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114506912A (en) * 2021-12-28 2022-05-17 华航环境发展有限公司 Water plant control method and system based on operation cost analysis

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005024375A (en) * 2003-07-02 2005-01-27 Hitachi Ltd Water service control and support system and water service control and support method
CN1773030A (en) * 2004-11-10 2006-05-17 雍尚平 City water-supply antifreezing new technique at highland and cold region
CN102341352A (en) * 2008-12-30 2012-02-01 I2O供应水有限公司 Regulated supply of treated water for regional supply networks
WO2013026731A1 (en) * 2011-08-22 2013-02-28 Abb Technology Ag System and method to optimize operation of a water network
CN207672658U (en) * 2017-11-14 2018-07-31 嘉兴市泰石漂染有限公司 A kind of cistern pressure-stabilizing water supply system
CN208121868U (en) * 2018-03-27 2018-11-20 天津晨天自动化设备工程有限公司 A kind of auxiliary pressurized pumping plant of water supply network
CN109210388A (en) * 2018-10-31 2019-01-15 贝滨(广东)科技有限公司 Intelligent water affair management system based on internet and application thereof
CN208520856U (en) * 2018-08-02 2019-02-19 苏州市自来水有限公司 Water utilities control platform

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005024375A (en) * 2003-07-02 2005-01-27 Hitachi Ltd Water service control and support system and water service control and support method
CN1773030A (en) * 2004-11-10 2006-05-17 雍尚平 City water-supply antifreezing new technique at highland and cold region
CN102341352A (en) * 2008-12-30 2012-02-01 I2O供应水有限公司 Regulated supply of treated water for regional supply networks
WO2013026731A1 (en) * 2011-08-22 2013-02-28 Abb Technology Ag System and method to optimize operation of a water network
CN207672658U (en) * 2017-11-14 2018-07-31 嘉兴市泰石漂染有限公司 A kind of cistern pressure-stabilizing water supply system
CN208121868U (en) * 2018-03-27 2018-11-20 天津晨天自动化设备工程有限公司 A kind of auxiliary pressurized pumping plant of water supply network
CN208520856U (en) * 2018-08-02 2019-02-19 苏州市自来水有限公司 Water utilities control platform
CN109210388A (en) * 2018-10-31 2019-01-15 贝滨(广东)科技有限公司 Intelligent water affair management system based on internet and application thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
潘大林,赵晓川 编: "《城镇管网规划设计》", vol. 1998, 广东高等教育出版社, pages: 204 - 207 *
韩洁: "对解决城镇供水水压不足的探讨", 《黑龙江水利科技》, no. 04, 20 December 2002 (2002-12-20) *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114506912A (en) * 2021-12-28 2022-05-17 华航环境发展有限公司 Water plant control method and system based on operation cost analysis

Similar Documents

Publication Publication Date Title
EP3196482A3 (en) System for controlling the supply of hydraulic fluid to a work vehicle implement
WO2011094512A3 (en) Control system and method for optimizing chemical looping processes
CN110136026A (en) A kind of control method and its control system of water factory&#39;s water distribution
RU2013147893A (en) METHOD OF ACOUSTIC DETERMINATION OF CHANGE OF STATE OF FLUID FLOW IN PIPELINE, METHOD OF ACOUSTIC DETERMINATION OF CHANGE OF STATE OF FLUID FLOW IN MEASURING STATION AND SYSTEM OF RANGE
WO2010048168A3 (en) Flow regulator assembly
MY152728A (en) Valve with a delta p-function and flow limiting function
CN110486026A (en) A kind of support pressure control system
CN207088742U (en) A kind of negative pressure generating device suitable for digital ink-jet equipment
SG10201902956WA (en) Cleaning liquid supplying system, substrate processing apparatus and substrate processing system
CN107291110A (en) Mining pond quantitative water supply system
CN102067056A (en) Control arrangement having a pressure limiting valve
CN101182672B (en) Dry can temperature control method of mercerizer
CN210573406U (en) Scribble board and drench sour acid density automatic regulating apparatus
CN207295332U (en) A kind of slurry concentration regulating device of paper making equipment
CN207211245U (en) Water system with decrease of noise functions
CN104878641A (en) Automatic pulp concentration adjusting device
CN208984506U (en) A kind of concrete water-permeating detection device
CN208763109U (en) A kind of tier building water system
CN105728680A (en) Gas-water balance dynamical control method for continuous-casting machine
KR20160044715A (en) System for supplying water
CN206128186U (en) Municipal water supply pipe network terminal water supply installation
CN105695648B (en) A kind of control method for pressure balance of bf coal injection system
CN106353237B (en) Test device for net type filtering system of water-saving irrigation engineering
CN203070113U (en) Automatic adhesive flow monitoring and controlling device after emulsification procedure
CN204953261U (en) Removable guide rails&#39;s glue feeding device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190816