CN110130945A - A kind of contractible joint for scalable steel arch-shelf - Google Patents
A kind of contractible joint for scalable steel arch-shelf Download PDFInfo
- Publication number
- CN110130945A CN110130945A CN201910516168.0A CN201910516168A CN110130945A CN 110130945 A CN110130945 A CN 110130945A CN 201910516168 A CN201910516168 A CN 201910516168A CN 110130945 A CN110130945 A CN 110130945A
- Authority
- CN
- China
- Prior art keywords
- guide rail
- shelf
- profile steel
- welded
- wing plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 93
- 239000010959 steel Substances 0.000 title claims abstract description 93
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 9
- 238000003780 insertion Methods 0.000 claims description 7
- 230000037431 insertion Effects 0.000 claims description 7
- 229910052742 iron Inorganic materials 0.000 claims description 4
- 238000003466 welding Methods 0.000 claims 1
- 238000000034 method Methods 0.000 abstract description 5
- 238000010276 construction Methods 0.000 abstract description 2
- 238000009826 distribution Methods 0.000 abstract description 2
- 239000011435 rock Substances 0.000 description 6
- 238000005452 bending Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000001125 extrusion Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/18—Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
- E21D11/22—Clamps or other yieldable means for interconnecting adjacent arch members either rigidly, or allowing arch member parts to slide when subjected to excessive pressure
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910516168.0A CN110130945A (en) | 2019-06-14 | 2019-06-14 | A kind of contractible joint for scalable steel arch-shelf |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910516168.0A CN110130945A (en) | 2019-06-14 | 2019-06-14 | A kind of contractible joint for scalable steel arch-shelf |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110130945A true CN110130945A (en) | 2019-08-16 |
Family
ID=67577364
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910516168.0A Pending CN110130945A (en) | 2019-06-14 | 2019-06-14 | A kind of contractible joint for scalable steel arch-shelf |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110130945A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110617077A (en) * | 2019-09-20 | 2019-12-27 | 中铁十八局集团有限公司 | Construction method for preventing floor heave of tunnel bottom inverted arch |
CN111535839A (en) * | 2020-05-11 | 2020-08-14 | 宁波朗达工程科技有限公司 | Telescopic tunnel steel arch frame |
CN111610101A (en) * | 2020-04-28 | 2020-09-01 | 中铁工程服务有限公司 | Steel bow member compression experiment platform |
CN111663951A (en) * | 2020-06-24 | 2020-09-15 | 中水北方勘测设计研究有限责任公司 | Connection method of annular steel arch frame sealing unit for TBM construction tunnel support |
CN113882877A (en) * | 2021-10-27 | 2022-01-04 | 宁波市交通建设工程试验检测中心有限公司 | Telescopic tunnel steel arch frame joint |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20130018516A (en) * | 2011-08-09 | 2013-02-25 | 조용진 | Coupler type device for joint of h-shape steel |
KR20140014473A (en) * | 2012-07-24 | 2014-02-06 | 주식회사 세안 | Yieldable steel arches supports in tunnel construction |
KR101388416B1 (en) * | 2013-02-13 | 2014-04-22 | 주식회사 디알비동일 | Brace type damper |
CN107780951A (en) * | 2017-11-01 | 2018-03-09 | 中交第公路勘察设计研究院有限公司 | High ground stress soft rock stress large deformation preliminary bracing system |
CN108386211A (en) * | 2018-03-06 | 2018-08-10 | 兰州理工大学 | Anchor pole-steelframe, which combines to allow, presses preliminary bracing structure and construction method |
CN108561161A (en) * | 2018-06-01 | 2018-09-21 | 齐鲁交通发展集团有限公司 | A kind of scalability steel arch-shelf |
CN210217777U (en) * | 2019-06-14 | 2020-03-31 | 中铁工程服务有限公司 | Contractible joint for telescopic steel arch frame |
-
2019
- 2019-06-14 CN CN201910516168.0A patent/CN110130945A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20130018516A (en) * | 2011-08-09 | 2013-02-25 | 조용진 | Coupler type device for joint of h-shape steel |
KR20140014473A (en) * | 2012-07-24 | 2014-02-06 | 주식회사 세안 | Yieldable steel arches supports in tunnel construction |
KR101388416B1 (en) * | 2013-02-13 | 2014-04-22 | 주식회사 디알비동일 | Brace type damper |
CN107780951A (en) * | 2017-11-01 | 2018-03-09 | 中交第公路勘察设计研究院有限公司 | High ground stress soft rock stress large deformation preliminary bracing system |
CN108386211A (en) * | 2018-03-06 | 2018-08-10 | 兰州理工大学 | Anchor pole-steelframe, which combines to allow, presses preliminary bracing structure and construction method |
CN108561161A (en) * | 2018-06-01 | 2018-09-21 | 齐鲁交通发展集团有限公司 | A kind of scalability steel arch-shelf |
CN210217777U (en) * | 2019-06-14 | 2020-03-31 | 中铁工程服务有限公司 | Contractible joint for telescopic steel arch frame |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110617077A (en) * | 2019-09-20 | 2019-12-27 | 中铁十八局集团有限公司 | Construction method for preventing floor heave of tunnel bottom inverted arch |
CN111610101A (en) * | 2020-04-28 | 2020-09-01 | 中铁工程服务有限公司 | Steel bow member compression experiment platform |
CN111610101B (en) * | 2020-04-28 | 2023-10-24 | 中铁工程服务有限公司 | Steel arch compression experiment table |
CN111535839A (en) * | 2020-05-11 | 2020-08-14 | 宁波朗达工程科技有限公司 | Telescopic tunnel steel arch frame |
CN111663951A (en) * | 2020-06-24 | 2020-09-15 | 中水北方勘测设计研究有限责任公司 | Connection method of annular steel arch frame sealing unit for TBM construction tunnel support |
CN113882877A (en) * | 2021-10-27 | 2022-01-04 | 宁波市交通建设工程试验检测中心有限公司 | Telescopic tunnel steel arch frame joint |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110130945A (en) | A kind of contractible joint for scalable steel arch-shelf | |
CN106812543A (en) | It is a kind of can multistage power consumption collaboration allow the roadway support structure and joining method of pressure | |
CN206647113U (en) | It is a kind of can multistage power consumption collaboration allow the roadway support structure of pressure | |
CN204378319U (en) | A kind of plug-in type desk | |
CN107598400B (en) | Fixture for laser welding T connector | |
CN104294921A (en) | Connecting joint of concrete column and steel beam | |
CN107387136A (en) | A kind of constructing tunnel special stand | |
CN210217777U (en) | Contractible joint for telescopic steel arch frame | |
CN208668599U (en) | A kind of quick fixation structure of steel construction | |
CN211499831U (en) | High-stability assembling structure for roof parts | |
CN214169489U (en) | Steel construction assembled auxiliary device | |
CN210227450U (en) | Embracing beam | |
CN207255062U (en) | Material supporting rack | |
CN208934170U (en) | A kind of assembled modified tone stiffness and damping composite viscoelasticity support | |
CN112252510A (en) | Two-end pin shaft type buckling restrained brace connecting node | |
CN208169270U (en) | A kind of jointing device and prestressing force prefabricated component | |
CN106640887B (en) | Firm vertical brace structure | |
CN206829355U (en) | A kind of crossbeam of cross wall plate and the attachment structure of pillar | |
KR101897919B1 (en) | Strengthened high-strength metal pipe | |
CN211168455U (en) | Aluminum alloy holds in palm material device | |
CN219491473U (en) | H-shaped steel with adjustable wing plate supporting points | |
CN212743135U (en) | High-strength channel steel structure | |
CN218176148U (en) | Novel assembled steel component | |
CN212899274U (en) | Rod mortise and tenon type connecting structure | |
CN209614883U (en) | A kind of iron bed clamp device and the square tube iron bed comprising it |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Li Jianbin Inventor after: Zhou Yuanyi Inventor after: Jiao Junqi Inventor after: Li Heng Inventor after: Gao Xudong Inventor after: Mei Yuanyuan Inventor after: Zhou Hongchu Inventor after: Wang Yuchen Inventor after: Zheng Jun Inventor after: Zhang Haowen Inventor after: Bai Jiangtao Inventor before: Li Heng Inventor before: Jiao Junqi Inventor before: Gao Xudong Inventor before: Mei Yuanyuan Inventor before: Zhou Hongchu Inventor before: Wang Yuchen Inventor before: Zheng Jun Inventor before: Zhang Haowen Inventor before: Bai Jiangtao Inventor before: Zhou Yuanyi |