CN110130814A - A kind of assembled Flood gate - Google Patents
A kind of assembled Flood gate Download PDFInfo
- Publication number
- CN110130814A CN110130814A CN201910413907.3A CN201910413907A CN110130814A CN 110130814 A CN110130814 A CN 110130814A CN 201910413907 A CN201910413907 A CN 201910413907A CN 110130814 A CN110130814 A CN 110130814A
- Authority
- CN
- China
- Prior art keywords
- center pillar
- door leaf
- doorframe
- door
- cone column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E06—DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
- E06B—FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
- E06B3/00—Window sashes, door leaves, or like elements for closing wall or like openings; Layout of fixed or moving closures, e.g. windows in wall or like openings; Features of rigidly-mounted outer frames relating to the mounting of wing frames
- E06B3/70—Door leaves
- E06B3/72—Door leaves consisting of frame and panels, e.g. of raised panel type
-
- E—FIXED CONSTRUCTIONS
- E06—DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
- E06B—FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
- E06B5/00—Doors, windows, or like closures for special purposes; Border constructions therefor
- E06B5/02—Doors, windows, or like closures for special purposes; Border constructions therefor for out-buildings or cellars; Other simple closures not designed to be close-fitting
-
- E—FIXED CONSTRUCTIONS
- E06—DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
- E06B—FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
- E06B7/00—Special arrangements or measures in connection with doors or windows
- E06B7/16—Sealing arrangements on wings or parts co-operating with the wings
-
- E—FIXED CONSTRUCTIONS
- E06—DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
- E06B—FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
- E06B9/00—Screening or protective devices for wall or similar openings, with or without operating or securing mechanisms; Closures of similar construction
-
- E—FIXED CONSTRUCTIONS
- E06—DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
- E06B—FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
- E06B9/00—Screening or protective devices for wall or similar openings, with or without operating or securing mechanisms; Closures of similar construction
- E06B2009/007—Flood panels
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- Housing For Livestock And Birds (AREA)
- Special Wing (AREA)
Abstract
The invention discloses a kind of assembled Flood gates, including door leaf, the doorframe of left and right two for fixing with external environment, the center pillar for fixing with external environment, the doorframe door leaf mounting portion of the detachable installation in end for door leaf is equipped on the left of the right side of left doorframe and right doorframe;The center pillar is for being mounted between left doorframe and right doorframe;The two sides of the center pillar are equipped with the center pillar door leaf mounting portion of the detachable installation in end for door leaf;A part of door leaf is stacked on top of one another to be arranged between left doorframe and center pillar, and the first door-plate is formed as;Door leaf described in another part is stacked on top of one another to be arranged between center pillar and right doorframe, and the second door-plate is formed as;By the way that center pillar is arranged between the doorframe of left and right, Flood gate is divided into multiple door-plates in the direction of the width and is configured;To solve the problem of to need in wide place that very long door leaf is arranged;With easy storage, easy to use, the features such as emergency speed is fast.
Description
Technical field
The invention belongs to flood protection device technical field, in particular to a kind of assembled Flood gate.
Background technique
In recent years, the development and utilization of urban underground space have developed rapidly, it is mark, ground with subway, large scale business facility
The development and utilization of down space show extensive, multi-level, multi-class trend, and the underground for realizing city function extends,
As the important component of urban construction and the important symbol of measurement Level of Urban Modernization.
Underground space development is that government fund dominates behavior earlier, belongs to the underground space of people's air defense department planning construction
It is civil air defense constructions and installations, auxiliary facility is complete, and correct to grasp using having the function of flood of controlling flood, still, people's air defense safeguard is strong
Wartime protective capacities is adjusted, has uncertain condition to limit flood control of usually meeting an urgent need.Defence to floods, arranges equipped with flood individually
The civil air defense constructions and installations applied still has the ability to play a role within a certain period of time, and general hypogee is then without this defence capability.Its
The underground space of the leading construction of its Shu Fei people's air defense department is non-civil air defense constructions and installations, does not build emergency flood flood protection device substantially.Underground
Room oral area adds quickly emergency flood control flood door equipment, basement can be made to have protective capacities in flood, thus basement
Interior personnel's substance protection is got up, and lesser cost is spent to bring very high social benefit.
Existing defensive measure is substantially that heap builds sandbag water blocking, and operation large labor intensity, carrying operation is heavy, usually deposits
Putting difficulty has the shortcomings that emergency mobile is poor.In order to solve to control flood using sandbag, storage difficulty, the disadvantage of mobility difference, this
Company has developed a kind of assembled Flood gate, as shown in Figure 1, passing through two doorframes 1 in left and right and intermediate stacked on top of one another multiple
Door leaf 2 carries out detachable installation;Two sides doorframe, can be by door leaf 2 from doorframe 1 usually for being fixed on external environment
It is removed;When flood control emergency, and can quickly it be installed in place;Using upper very convenient;
But a kind of assembled Flood gate as shown in Figure 1 now developed, it is only applicable to relatively narrow channel;If
It is that channel is wide, two doorframe spacing are big, and door leaf must also be arranged very long, that is just unfavorable for the dismounting of door leaf and stores;Therefore
Wider channel or the assembled Flood gate compared with wide field ground can be applicable in by needing further to develop one kind on this basis,
Be provided simultaneously with easily storage, it is easy to use, emergency speed it is fast the features such as.
It should be noted that technical solution described in Fig. 1, the prior art not having before the application applying date will
It is put is illustrated in the background technology, be in order to it is more convenient it is appreciated that technical scheme invention thinking.
Summary of the invention
In order to overcome the shortcomings of the prior art, the present invention provides a kind of assembled Flood gates, by left and right two
Center pillar is set between a doorframe, to solve the problem of to need that very long door leaf is arranged in wide place;Simultaneously with easy
Storage, it is easy to use, emergency speed it is fast the features such as.
The technical solution adopted by the present invention to solve the technical problems is:
A kind of assembled Flood gate, including door leaf, for left and right two doorframe fixed with external environment, be used for and outside
Environment fixed center pillar is equipped with the door of the detachable installation in end for door leaf on the left of the right side of left doorframe and right doorframe
Frame door leaf mounting portion;The center pillar is for being mounted between left doorframe and right doorframe;The two sides of the center pillar are equipped with for door
The center pillar door leaf mounting portion of the detachable installation in the end of fan;A part of door leaf is stacked on top of one another to be arranged in left doorframe and center pillar
Between, be formed as the first door-plate;Door leaf described in another part is stacked on top of one another to be arranged between center pillar and right doorframe, is formed as second
Door-plate.
In above-mentioned technical proposal, a kind of assembled Flood gate, by the way that center pillar, the left and right of center pillar are arranged between the doorframe of left and right
Center pillar door leaf mounting portion is arranged in two sides, to be suitable for wider channel or place, does not need that very long door leaf is arranged;But
It is divided into multiple door-plates in width direction to be configured;So just to solve to need in wide place that very long door leaf is arranged
The problem of;Simultaneously with easy storage, easy to use, the features such as emergency speed is fast.
In certain embodiments, more than two center pillars are arranged at intervals between left doorframe and right doorframe;The center pillar
Ground stacked on top of one another door leaf is provided between center pillar.Center pillar can be set one, and multiple, the situation of setting one also can be set
Under, it is divided into two door-plates in left and right, the first door-plate and the second door-plate;Often add a center pillar, will have more one need door leaf into
The door-plate of row assembling;The quantity of center pillar and door-plate according to channel and protects the actual demand of place width to be configured.
In certain embodiments, the center pillar includes center pillar main body, firm banking;The two sides of the center pillar main body are set respectively
There is center pillar door leaf mounting portion, for removably installing door leaf;The firm banking is used to be fixedly connected with external environment,
The center pillar main body is securely removably connected on the firm banking.Center pillar is set as center pillar main body, firm banking, and can
It is detachably connected with;During actual use, the fixed setting that firm banking can be long-term on the ground, if certainly on ground
In lower channel, firm banking is also possible to fixed setting on the ceiling;It, can be by center pillar main body under non-flood control emergency rating
It is separated with firm banking;In this way, the setting of center pillar does not just interfere the passage in channel;It, can be rapidly by under emergency rating of controlling flood
Column carries out equipment assembling, then carries out flood control Emergency use.
In certain embodiments, it is equipped with through-hole in the middle part of the center pillar main body, has provided a standing screw in through-hole;The spiral shell
Outside the upper end stretching of bar and through-hole, and it is equipped with fastening nut;The lower end of the screw rod is connect for being screwed with firm banking;
The fastening nut is used for the locking of center pillar main body on the fixed base;The firm banking includes base body and pedestal master
The cone column of body detachable connection and the pedestal lid with base body detachable connection;Peace is equipped with inside the base body
Hole is filled, the lower end of the mounting hole is the bellmouth that fitting is adapted to the conehead of cone column, and the upper end of the mounting hole is fixation hole,
Helix angle limited block there are three circumferentially equidistantly being set on the medial surface of fixation hole;Corresponding three spirals of lateral surface of the cone column
Lift angle limited block is equipped with the three spirals drop angle limited block being adapted to it;The base body is for being inserted into ground and external environment
Be fixedly connected, it is described cone column conehead one end insertion bellmouth in, and by rotating cone column make spiral drop angle limited block and
The adaptation limit of helix angle limited block carries out detachable be fixedly connected;The upper surface of the cone column, which is equipped with, to be used for and fixed bolt
The threaded hole being screwed on;The pedestal lid is used to close in the period of the non-flood control detachable lid that is fixedly connected in base body
On mounting hole.
In certain embodiments, the upper end of the pedestal is equipped with base flange;The cone column corresponds to base flange and is equipped with cone
The lower end surface of column flange, the cone column flange is equipped with seal gasket;The upper end of the cone column is used to protrude into the logical of center pillar main body
It is connect in hole with the lower thread of fixed bolt;The lower end of the center pillar main body is by nut lock tight against the upper end for withstanding on cone column flange
On face.
In certain embodiments, the lower end surface of the door leaf is equipped with seal gasket.In the lower end surface of door leaf, sealant is set
Pad, door leaf is stacked on top of one another be configured in the case where, by the self weight combination seal gasket of door leaf, so that it may improve leakproofness
Energy.
In certain embodiments, the left doorframe and/or right doorframe upper end are equipped with doorframe sealing clamp, the doorframe sealing
One end of pressing plate is rotationally screwed on the end face of left doorframe and/or right doorframe upper end, and the other end is free end;The doorframe
The side of sealing clamp is the inclined surface from top to bottom drawn close to doorframe sealing clamp center line;Multiple door leafs are stacked on top of one another
It is assembled into door-plate;The height of the upper surface of the door-plate, higher than the height of doorframe sealing clamp lower end surface, lower than doorframe sealing pressure
The height of plate upper surface;Sealing clamp, which is rotated to door-plate top, under external force compresses lift-off seal for door leaf stacked on top of one another
It can be possible.Promote the sealing performance under flood control state.
In certain embodiments, the upper end of the center pillar is equipped with center pillar sealing clamp, the middle part of the center pillar sealing clamp
It is hinged on the upper surface of the center pillar;The both ends of the center pillar sealing clamp are free end, for rotating to the center pillar
Door leaf is compressed above the door leaf of two sides.The sealing performance of styletable in promotion.
In certain embodiments, the doorframe door leaf mounting portion and center pillar door leaf mounting portion are slideway;The slideway it is upper
End is that uncovered structure slides into slideway from top to bottom for the door leaf, and stacks gradually;The slideway medial surface and door leaf it
Between be equipped with seal gasket.
Alternatively, the doorframe door leaf mounting portion includes that the multiple door leaf shelves items being arranged on doorframe leading flank and setting exist
Doorframe door leaf jointing plate on doorframe medial surface;Between the leading flank of the doorframe door leaf jointing plate and the leading flank of the doorframe
With clipping room away from;One end of the doorframe door leaf shelves item is rotatably screwed on doorframe, and the other end is free end;The door
Frame leading flank is the side near water contacted with flood;The doorframe medial surface is the right side of left doorframe or the left side of right doorframe;It will
The door leaf from side near water push-in doorframe clipping room away from, then by the free end of doorframe door leaf shelves item dial to door leaf side into
Row limit is possible;The center pillar door leaf mounting portion include the multiple center pillar door leaf shelves items being arranged on center pillar leading flank and
Center pillar door leaf jointing plate in center pillar left and right sides is set;The leading flank of the center pillar door leaf jointing plate and the center pillar
Between leading flank be equipped with clipping room away from;One end of the center pillar door leaf shelves item is rotatably screwed on center pillar, and the other end is certainly
By holding;The center pillar leading flank is the side near water contacted with flood;The door leaf is pushed into the clipping room of center pillar from side near water
Away from, then by the free end of center pillar door leaf shelves item dial to door leaf side carry out limit be possible.Doorframe door leaf mounting portion and
Two kinds of implementation structures of center pillar door leaf mounting portion;Slideway structure can be used, structure is simple, easy to use;Highly higher, no
It is convenient from top to bottom when assemble, can also be pushed into using side-push, limitation locking is then carried out by door leaf shelves item again.
In certain embodiments, inclination is from top to bottom gradually drawn close to door leaf middle part in the end face at the door leaf both ends;It is described
The left and right sides of the medial surface of doorframe and the center pillar correspondence is obliquely installed, and suitability is bonded the inclination of door leaf end
Face.The phenomenon that setting gradient guides, prevents door leaf left and right end in dropping process stuck, avoid one end high and another end low,
Preferred gradient is 1 to 30.
The beneficial effects of the present invention are: a kind of assembled Flood gate of the invention, in being arranged between the doorframe of left and right
Center pillar door leaf mounting portion is arranged in the left and right sides of column, center pillar, to be suitable for wider channel or place, it is very long not need setting
Door leaf;But it is divided into multiple door-plates in the direction of the width and is configured;So just to solve to need to set in wide place
The problem of setting very long door leaf;Simultaneously with easy storage, easy to use, the features such as emergency speed is fast.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples.
Fig. 1 is a kind of the application structural schematic diagram of assembled Flood gate described in background technology;
Fig. 2 is a kind of the application structural schematic diagram of assembled Flood gate as described in the examples;
Fig. 3 is the enlarged structure schematic diagram of region A in Fig. 2;
Fig. 4 is the enlarged structure schematic diagram of region B in Fig. 2;
Fig. 5 is a kind of the application surface structure signal of the side near water of assembled Flood gate as described in the examples
Figure;
Fig. 6 is the structural schematic diagram of the doorframe in embodiment illustrated in fig. 5;
Fig. 7 is the mounting structure schematic diagram at the center pillar in embodiment illustrated in fig. 5;
Fig. 8 is the surface structure schematic diagram of the application center pillar as described in the examples;
Fig. 9 be in Fig. 8 A-A to partial cross-sectional structural diagram;
Figure 10 is the enlarged structure schematic diagram of region I in Fig. 9;
Figure 11 is the enlarged structure schematic diagram of region II in Fig. 9;
Figure 12 is the structural schematic diagram of the application cone column as described in the examples;
Figure 13 is the surface structure schematic diagram of base body described in the application embodiment;
Figure 14 is the surface structure schematic diagram of the application pedestal lid as described in the examples.
Specific embodiment
In conjunction with the accompanying drawings, the present invention is further explained in detail.These attached drawings are simplified schematic diagram, only with
Illustration illustrates basic structure of the invention, therefore it only shows the composition relevant to the invention.
In the description of the present application, it is to be understood that term " longitudinal direction ", " radial direction ", " length ", " width ", " thickness ",
The orientation of the instructions such as "upper", "lower", "left", "right", "front", "rear", "vertical", "horizontal", "top", "bottom", "inner", "outside" or
Positional relationship is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of description of the present invention and simplification of the description, without
It is that the device of indication or suggestion meaning or element must have a particular orientation, be constructed and operated in a specific orientation, therefore not
It can be interpreted as limitation of the present invention.In the description of the present application, unless otherwise indicated, the meaning of " plurality " is two or two
More than.
In the description of the present application, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase
Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can
To be mechanical connection, it is also possible to be electrically connected;It can be connected directly, two can also be can be indirectly connected through an intermediary
Connection inside a element.For the ordinary skill in the art, above-mentioned term can be understood in this Shen with concrete condition
Please in concrete meaning.
A kind of assembled Flood gate as shown in Figure 2, including door leaf 2, for the door of left and right two fixed with external environment
Frame 1, the center pillar 3 for fixing with external environment, the right side of left doorframe 1 and the left side of right doorframe 1 are equipped with the end for door leaf 2
The doorframe door leaf mounting portion of the detachable installation in portion;The center pillar 3 is for being mounted between left doorframe and right doorframe;The center pillar
Two sides be equipped with the center pillar door leaf mounting portion of the detachable installation in end for door leaf;A part of door leaf is stacked on top of one another
It is arranged between left doorframe 1 and center pillar 3, is formed as the first door-plate 4;Door leaf 2 described in another part is stacked on top of one another to be arranged in center pillar 3
Between right doorframe 1, be formed as the second door-plate 5.
One of above-mentioned technical proposal assembled Flood gate, by the way that center pillar 3 is arranged between left and right doorframe 1, center pillar 3
Center pillar door leaf mounting portion is arranged in the left and right sides, to be suitable for wider channel or place, does not need that very long door leaf 2 is arranged;
But it is divided into multiple door-plates 4,5 in the direction of the width and carries out assembly setting;So just to solve to need to set in wide place
The problem of setting very long door leaf 2;Simultaneously with easy storage, easy to use, the features such as emergency speed is fast.
In certain embodiments, since place is excessively broad, need to be arranged more than two center pillars 3 at this time;Using two
Center pillar 3 described above is arranged at intervals between left doorframe and right doorframe;It is stacked on top of one another between the center pillar 3 and center pillar 3 to be provided with
Door leaf 2.Center pillar 3 can be set one, also can be set it is multiple, setting one in the case where, be divided into left and right two door-plates, first
Door-plate 4 and the second door-plate 5;Often add a center pillar 3, the door-plate for needing door leaf to be assembled will be had more;Center pillar 3 and
The quantity of door-plate according to channel and protects the actual demand of place width to be configured.Specifically it is provided with multiple center pillars 3
Embodiment is not through attached drawing and is shown;In the embodiment in figure 1, left doorframe 1 and right doorframe 1 pass through implantation reinforcing bar
Carry out crotch anchoring;In other embodiments, company can also be fixed in doorframe 1 and external environment by another way
It connects;It is attached by way of bar planting, the adaptability to geology soil can be improved, if soil property is loose, bar planting is more
Deeply a bit.In certain embodiments, it is solid can to carry out bar planting by bottom end and ground for the fixation of center pillar 3 and external environment
It is fixed;When carrying out flood control emergency on the underpass such as basement, bar planting can also be carried out by top and fixed;Concrete condition can be with
Concrete analysis, is preferably fixed by bottom end.
In certain embodiments, the center pillar 3 includes center pillar main body 32, firm banking 31;The two of the center pillar main body 32
Side is respectively equipped with center pillar door leaf mounting portion, for removably installing door leaf 2;The firm banking 31 is used for and external environment
Be fixedly connected, the center pillar main body 32 is securely removably connected on the firm banking 31.Center pillar main body 32 and fixation
The detachable fixation of pedestal 31 can separate center pillar main body 32 with firm banking 31 under non-flood control emergency rating;In this way,
The setting of center pillar 3 does not just interfere the passage in channel;Under emergency rating of controlling flood, center pillar 3 can be subjected to assembly assembling rapidly, then
Carry out flood control Emergency use.During actual use, the fixed setting that firm banking 31 can be long-term on the ground, certainly
If firm banking 31 is also possible to fixed setting on the ceiling in underpass, certainly in this case, cannot adopt
With the form that door leaf mounting portion is arranged to slideway;And it should be specifically aftermentioned to incite somebody to action using the push-in mounting means being pushed into from side
It is illustrated;The lower end of the firm banking 31 be used for the fixation of external environment (in the present embodiment, by implantation ground with
Ground is fixed;According to the difference of soil property, the length of firm banking 31 can be arranged different, soil property is soft, can be with
Implantation is deeper, to guarantee the flood control endurance of center pillar 3);
In certain embodiments, the lower end surface of the door leaf 2 is equipped with seal gasket.In the lower end surface of door leaf 2, sealing is set
Rubber mat, door leaf 2 is stacked on top of one another be configured in the case where, by the self weight combination seal gasket of door leaf 2, so that it may improve sealing
Performance.Certainly in certain embodiments, it is also possible to the upper end setting seal gasket of door leaf;Or the upper and lower end face of door leaf is all provided with
Set seal gasket;These schemes belong to the scheme of equivalent substitution, should belong to the protection category of the application.
As shown in Figure 2 and Figure 4, in certain embodiments, the left doorframe 1 and/or 1 upper end of right doorframe are sealed equipped with doorframe
Pressing plate 6, one end of the doorframe sealing clamp 6 are rotationally screwed on the end face of 1 upper end of left doorframe 1 and/or right doorframe, separately
One end is free end;The side of the doorframe sealing clamp 6 is the inclination from top to bottom drawn close to 6 center line of doorframe sealing clamp
Face;Multiple door leafs 2 are stacked on top of one another to be assembled into door-plate;The height of the upper surface of the door-plate is higher than under doorframe sealing clamp 6
The height of end face, lower than the height of 6 upper surface of doorframe sealing clamp;It will above the rotation to door-plate of sealing clamp 6 under external force
Door leaf stacked on top of one another compresses lift-off seal performance and is possible.Promote the sealing performance under flood control state.
As shown in Figures 2 and 3, in certain embodiments, the upper end of the center pillar 3 be equipped with center pillar sealing clamp 7, it is described in
The middle part of column sealing pressing plate 7 is hinged on the upper surface of the center pillar 3;The both ends of the center pillar sealing clamp 7 are free end,
Door leaf top for rotating to 3 two sides of center pillar compresses door leaf.The sealing performance of styletable in promotion.
In certain embodiments, the doorframe door leaf mounting portion and center pillar door leaf mounting portion are slideway;The slideway it is upper
End is that uncovered structure slides into slideway from top to bottom for the door leaf, and stacks gradually;The slideway medial surface and door leaf it
Between be equipped with seal gasket.It is arranged to the structure of slideway, structure is simple, easy to use;Certainly under this configuration, Flood gate is upper
Fang Bixu is reserved with certain installation space, to be put into door-plate.
In certain embodiments, the structure that doorframe door leaf mounting portion is arranged to slideway can not also be used;It can also set
It is set to other structures;As shown in Figure 5 and Figure 6, in certain embodiments, the doorframe door leaf mounting portion includes being arranged in doorframe
Multiple door leaf shelves items 12 on 1 leading flank and the doorframe door leaf jointing plate 11 being arranged on 1 medial surface of doorframe;The doorframe door
Fan jointing plate 11 leading flank and the doorframe leading flank between have clipping room away from;One end of the doorframe door leaf shelves item 12
It is rotatably screwed on doorframe 1, the other end is free end;1 leading flank of doorframe is the side near water contacted with flood;Institute
State the left side on right side or right doorframe that 1 medial surface of doorframe is left doorframe;The door leaf 2 is pushed into the installation of doorframe 1 from side near water
In spacing, then by the free end of doorframe door leaf shelves item 12 dial to 2 side of door leaf carry out limit be possible;
Likewise, in certain embodiments, the center pillar door leaf mounting portion can also be arranged to the form of non-slideway;Such as
Shown in Fig. 5 and Fig. 7, in certain embodiments, the center pillar door leaf mounting portion includes being arranged in multiple on 3 leading flank of center pillar
Column door leaf shelves item 13 and the center pillar door leaf jointing plate being arranged in 3 left and right sides of center pillar (are not shown in Fig. 5 and Fig. 7;It can be with
It is configured referring to doorframe door leaf jointing plate 11);The leading flank of the leading flank of the center pillar door leaf jointing plate and the center pillar 3 it
Between be equipped with clipping room away from;One end of the center pillar door leaf shelves item 13 is rotatably screwed on center pillar 3, and the other end is free end;
3 leading flank of center pillar is the side near water contacted with flood;By the door leaf 2 from side near water push-in center pillar 3 clipping room away from
In, then by the free end of center pillar door leaf shelves item 13 dial to 3 side of door leaf carry out limit be possible.In this case, may be used
Seal gasket is arranged in the leading flank of the leading flank of doorframe door leaf jointing plate or center pillar door leaf jointing plate;Under flood control state, flood
Water has pressure to door leaf, and pressure compresses door leaf and seal gasket, can automatic lifting sealing performance;Certainly subsequent by door
It fans in the embodiment that is obliquely installed, end face at door leaf both ends and the contact of doorframe or center pillar also can be set in seal gasket
Between face;Because having gradient, under the action of door leaf self weight, it can also compress and be arranged in door leaf both ends end face or door
Sealing joint strip on frame medial surface or center pillar door leaf mounting portion left and right side.
Doorframe door leaf mounting portion and center pillar door leaf mounting portion can use slideway structure, and structure is simple, easy to use;?
Height it is higher, it has not been convenient to from top to bottom when carrying out assembly door leaf, door leaf jointing plate and door leaf shelves item also can be set, using side
Pushing-type push-in after being pushed into door leaf, then passes through door leaf shelves item progress limitation locking.
In certain embodiments, the end face at 2 both ends of door leaf is from top to bottom gradually to drawing close inclination in the middle part of door leaf 2;Institute
The left and right sides of the medial surface and the center pillar 3 of stating doorframe 1 correspondence is obliquely installed, and suitability is bonded 2 end of door leaf
Inclined surface.Setting gradient guides, and prevents the left and right end in dropping process of door leaf 2 stuck, avoids one end high and another end low
The phenomenon that, preferred gradient is 1 to 30.
As seen in figures 8-14, in certain embodiments, it is equipped with through-hole in the middle part of the center pillar main body 32, has provided one in through-hole
Standing screw 33;Outside the upper end stretching of the standing screw 33 and through-hole, and it is equipped with fastening nut;Under the standing screw 33
End is connect for being screwed with firm banking 31;The fastening nut is used to center pillar main body 32 being locked at firm banking 31
On.Standing screw 33 is set in center pillar main body 32;If center pillar main body 32 is directly threadedly coupled with firm banking 31, normal
Under the threaded connection state of rule, it is not easy to the direction of center pillar main body left and right side after control rotation connection, and in the application, center pillar 3
The left and right sides after assembling successfully, need to carry out with two doorframes 1 in left and right it is corresponding, and for installing door leaf;Therefore it is arranged solid
Determine screw rod 33 and wear to connect center pillar main body 32;After standing screw 33 is fixed on firm banking 31 in this way, adjustable center pillar main body
The orientation of 32 two sides;The orientation of center pillar main body 32 is locked by the nut of 33 upper end of standing screw again.By center pillar main body
32 with firm banking 31 carry out it is detachable be fixedly connected, in the actual use process, under non-emergency flood control state, so that it may
Not have to be assembled into complete center pillar 3, retain firm banking 31;In this way, installation center pillar 3 can be reduced to the current shape in channel
At obstruction.
The firm banking 31 includes base body 311 (as shown in figure 13) and 311 detachable connection of base body
Bore column 312 (as shown in figure 12) and the pedestal lid 313 (as shown in figure 14) with 311 detachable connection of base body;Such as figure
Shown in 9-11, mounting hole is equipped with inside the base body 311, the lower end of the mounting hole is to be adapted to the conehead of cone column 312
The bellmouth 3111 of fitting, the upper end of the mounting hole are fixation hole 3112, and circumferential direction is equidistant on the medial surface of fixation hole 3112
If there are three helix angle limited blocks 3113;The corresponding three helix angle limited blocks 3113 of lateral surface of the cone column 312 are equipped with
The three spirals drop angle limited block 3121 being adapted to it;For being arranged, (terrace refers to ground to the base body 311 under terrace
Terrace line) be fixedly connected with external environment, in conehead one end insertion bellmouth 3111 of the cone column 312, and pass through
Rotating cone column 312 makes spiral drop angle limited block 3121 be adapted to the detachable fixation of limit progress with helix angle limited block 3113 even
It connects;The upper surface of the cone column 312 is equipped with the threaded hole for being screwed on fixed bolt 33;The pedestal lid 313 is used for
The time section lid of non-flood control is closed on the mounting hole of base body 311.Also the angle limit of spiral drop can be set on pedestal lid 313
Block 3121, with the detachable fixation of base body 311;Mounting hole is closed under non-emergency flood control state, prevents external silt
Block mounting hole.Under emergency rating, pedestal lid 313 is disassembled, then cone column 312 and center pillar main body 32 are installed again;
It bores column flange lower end surface and is equipped with seal gasket, under the gravity of center pillar main body, there is self-closing sealing performance;Why it is arranged
Column 312 and pedestal lid 313 are bored, is because the leakproofness of the mounting structure of center pillar main body and firm banking can be promoted in this way
Can, it prevents connection screw thread to be rusted and the inconvenient problem of connection occurs.
As shown in Figure 10, in certain embodiments, the upper end of the base body 311 is equipped with base flange 3114;It is described
It bores the corresponding base flange of column 312 and is equipped with cone column flange 3122, the lower end surface of the cone column flange 3122 is equipped with seal gasket;Institute
It states and is connect with the lower thread of fixed bolt 33 in through-hole of the upper end of cone column 312 for protruding into center pillar main body 32 (specifically at this
It is the recessed threaded hole in upper surface in cone column 312 in embodiment, fixed bolt is screwed in threaded hole;In other embodiments
In, it is also possible in the recessed threaded hole in the lower end surface of fixed bolt, and stud is set in the upper end of cone column 312, it forms screw thread and connects
It connects;It should belong to the protection category of the application);The lower end of the center pillar main body 32 by nut lock tight against withstand on cone column flange 3122
Upper surface on.
Taking the above-mentioned ideal embodiment according to the present invention as inspiration, through the above description, relevant staff is complete
Various changes and amendments can be carried out without departing from the scope of the technological thought of the present invention' entirely.The technology of this invention
Property range is not limited to the contents of the specification, it is necessary to which the technical scope thereof is determined according to the scope of the claim.
Claims (10)
1. a kind of assembled Flood gate, it is characterised in that: including door leaf, for left and right two doorframe fixed with external environment,
For the center pillar fixed with external environment, it is equipped on the left of the right side of left doorframe and right doorframe detachable for the end of door leaf
The doorframe door leaf mounting portion of formula installation;The center pillar is for being mounted between left doorframe and right doorframe;The two sides of the center pillar are equal
Center pillar door leaf mounting portion equipped with the detachable installation in end for door leaf;A part of door leaf is stacked on top of one another to be arranged on a left side
Between doorframe and center pillar, be formed as the first door-plate;Door leaf described in another part is stacked on top of one another to be arranged between center pillar and right doorframe,
Be formed as the second door-plate.
2. a kind of assembled Flood gate according to claim 1, it is characterised in that: more than two center pillar interval settings
Between left doorframe and right doorframe;Ground stacked on top of one another door leaf is provided between the center pillar and center pillar.
3. a kind of assembled Flood gate according to claim 1 or 2, it is characterised in that: the center pillar include center pillar main body,
Firm banking;The two sides of the center pillar main body are respectively equipped with center pillar door leaf mounting portion, for removably installing door leaf;It is described
Firm banking is used to be fixedly connected with external environment, and the center pillar main body is securely removably connected at the firm banking
On.
4. a kind of assembled Flood gate according to claim 3, it is characterised in that: be equipped in the middle part of the center pillar main body logical
Hole has provided a standing screw in through-hole;Outside the upper end stretching of the standing screw and through-hole, and it is equipped with fastening nut;It is described
The lower end of standing screw is connect for being screwed with firm banking;The fastening nut is used to center pillar main body being locked at fixation
On pedestal;The firm banking includes base body, removable with the cone column of base body detachable connection and with base body
Unload the pedestal lid of formula connection;Mounting hole is equipped with inside the base body, the lower end of the mounting hole is the conehead with cone column
Be adapted to the bellmouth of fitting, the upper end of the mounting hole is fixation hole, on the medial surface of fixation hole it is circumferential equidistantly set there are three
Helix angle limited block;The corresponding three helix angle limited blocks of lateral surface of the cone column are equipped with the three spirals drop being adapted to it
Angle limited block;The base body is fixedly connected for being inserted into ground with external environment, and conehead one end of the cone column is inserted
Enter in bellmouth, and so that spiral is dropped angle limited block by rotating cone column and be adapted to helix angle limited block that limit progress detachable
It is fixedly connected;The upper surface of the cone column is equipped with the threaded hole for being screwed on fixed bolt;The pedestal lid is used for non-
The period of flood control, the detachable lid that is fixedly connected closed on the mounting hole of base body.
5. a kind of assembled Flood gate according to claim 4, it is characterised in that: the upper end of the base body is equipped with bottom
Seat flange;The cone column corresponds to base flange and is equipped with cone column flange, and the lower end surface of the cone column flange is equipped with seal gasket;Institute
It states and is connect in through-hole of the upper end of cone column for protruding into center pillar main body with the lower thread of fixed bolt;Under the center pillar main body
End by nut lock tight against withstand on cone column flange upper surface on.
6. a kind of assembled Flood gate according to claim 1, it is characterised in that: the lower end surface of the door leaf is equipped with sealing
Rubber mat.
7. a kind of assembled Flood gate according to claim 6, it is characterised in that: in the left doorframe and/or right doorframe
End is equipped with doorframe sealing clamp, and one end of the doorframe sealing clamp is rotationally screwed in left doorframe and/or right doorframe upper end
End face on, the other end is free end;The side of the doorframe sealing clamp is from top to bottom to doorframe sealing clamp center line
The inclined surface drawn close;Multiple door leafs are stacked on top of one another to be assembled into door-plate;It is close to be higher than doorframe for the height of the upper surface of the door-plate
The height for sealing pressing plate lower end surface, lower than the height of doorframe sealing clamp upper surface;Sealing clamp is rotated to door-plate under external force
Door leaf stacked on top of one another is compressed lift-off seal performance and is possible by top.
8. a kind of assembled Flood gate according to claim 6, it is characterised in that: it is close that the upper end of the center pillar is equipped with center pillar
Pressing plate is sealed, is hinged on the upper surface of the center pillar in the middle part of the center pillar sealing clamp;The both ends of the center pillar sealing clamp
It is free end, the door leaf top for rotating to the center pillar two sides compresses door leaf.
9. a kind of assembled Flood gate according to claim 1, it is characterised in that: the doorframe door leaf mounting portion and center pillar
Door leaf mounting portion is slideway;The upper end of the slideway slides into slideway for uncovered structure for the door leaf from top to bottom, and according to
Secondary stacking;Seal gasket is equipped between the slideway medial surface and door leaf;
Alternatively, the doorframe door leaf mounting portion includes the multiple door leaf shelves items being arranged on doorframe leading flank and is arranged in doorframe
Doorframe door leaf jointing plate on medial surface;Have between the leading flank of the doorframe door leaf jointing plate and the leading flank of the doorframe
Clipping room away from;One end of the doorframe door leaf shelves item is rotatably screwed on doorframe, and the other end is free end;Before the doorframe
Side is the side near water contacted with flood;The doorframe medial surface is the right side of left doorframe or the left side of right doorframe;It will be described
The free end of doorframe door leaf shelves item away from, then is dialed to door leaf side and limited by door leaf from the clipping room of the push-in doorframe of side near water
Position is possible;The center pillar door leaf mounting portion includes the multiple center pillar door leaf shelves items being arranged on center pillar leading flank and setting
Center pillar door leaf jointing plate in center pillar left and right sides;The leading flank of the center pillar door leaf jointing plate and the front side of the center pillar
Between face be equipped with clipping room away from;One end of the center pillar door leaf shelves item is rotatably screwed on center pillar, and the other end is free end;
The center pillar leading flank is the side near water contacted with flood;By the door leaf from side near water push-in center pillar clipping room away from,
Again by the free end of center pillar door leaf shelves item dial to door leaf side carry out limit be possible.
10. -9 described in any item a kind of assembled Flood gates according to claim 1, it is characterised in that: the door leaf both ends
Inclination is from top to bottom gradually drawn close to door leaf middle part in end face;The left and right sides of the medial surface of the doorframe and the center pillar are right
It should be obliquely installed, suitability is bonded the inclined surface of door leaf end.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910413907.3A CN110130814B (en) | 2019-05-17 | 2019-05-17 | Assembled flood-proof door |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910413907.3A CN110130814B (en) | 2019-05-17 | 2019-05-17 | Assembled flood-proof door |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110130814A true CN110130814A (en) | 2019-08-16 |
CN110130814B CN110130814B (en) | 2020-10-16 |
Family
ID=67575095
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910413907.3A Active CN110130814B (en) | 2019-05-17 | 2019-05-17 | Assembled flood-proof door |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110130814B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111608557A (en) * | 2020-07-01 | 2020-09-01 | 徐洪增 | Flood control gate |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2263517A1 (en) * | 1996-08-20 | 1998-02-26 | Gerhard Rumpp | Coupling means for a vehicle |
CN201665852U (en) * | 2010-04-22 | 2010-12-08 | 金志刚 | Detachable inserting plate water barrier |
CN103306237A (en) * | 2013-07-09 | 2013-09-18 | 徐朝辉 | Movable anti-flood wall |
CN203283144U (en) * | 2013-06-14 | 2013-11-13 | 东风汽车公司 | Installing and fixing device of automotive trim board |
CN105735862A (en) * | 2016-04-01 | 2016-07-06 | 湖南力威泵阀设备有限公司 | Flood prevention water-retaining door with rotating shaft structure |
CN106481144A (en) * | 2015-08-28 | 2017-03-08 | 广东兴发铝业有限公司 | Aluminium alloy extrusions combination prevention waterlogging anti-flood wall |
-
2019
- 2019-05-17 CN CN201910413907.3A patent/CN110130814B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2263517A1 (en) * | 1996-08-20 | 1998-02-26 | Gerhard Rumpp | Coupling means for a vehicle |
CN201665852U (en) * | 2010-04-22 | 2010-12-08 | 金志刚 | Detachable inserting plate water barrier |
CN203283144U (en) * | 2013-06-14 | 2013-11-13 | 东风汽车公司 | Installing and fixing device of automotive trim board |
CN103306237A (en) * | 2013-07-09 | 2013-09-18 | 徐朝辉 | Movable anti-flood wall |
CN106481144A (en) * | 2015-08-28 | 2017-03-08 | 广东兴发铝业有限公司 | Aluminium alloy extrusions combination prevention waterlogging anti-flood wall |
CN105735862A (en) * | 2016-04-01 | 2016-07-06 | 湖南力威泵阀设备有限公司 | Flood prevention water-retaining door with rotating shaft structure |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111608557A (en) * | 2020-07-01 | 2020-09-01 | 徐洪增 | Flood control gate |
CN111608557B (en) * | 2020-07-01 | 2022-02-08 | 徐洪增 | Flood control gate |
Also Published As
Publication number | Publication date |
---|---|
CN110130814B (en) | 2020-10-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110130814A (en) | A kind of assembled Flood gate | |
US9315965B1 (en) | Flood control system panels for subway entrance | |
CN102071961A (en) | Downward gas drainage drill hole and pressure testing drill hole sealing method | |
US20120301227A1 (en) | Foundation pile and installing method thereof | |
CN108612447A (en) | Slidingtype protection airtight plugging plate | |
CN106639087A (en) | Aluminum plate curtain wall connecting device | |
US20190017315A1 (en) | Flood defense system | |
CN206071448U (en) | Cluster type down-hole hammer and its down-hole hammer monomer locked mechanism | |
CN103898903B (en) | A kind of releasable grappling apparatus and method for dismounting thereof | |
CN207194016U (en) | The spliced prefabricated inspection-pit of multistage | |
CN105178322B (en) | A kind of grouting construction method | |
CN206608203U (en) | A kind of sliding closed plugging structure | |
CN209179151U (en) | A kind of steel structure water shut-in well | |
EP3569768B1 (en) | Flood prevention device | |
CN216477439U (en) | Rotary adjusting air window in underground coal mine | |
CN110513067A (en) | A kind of righting casing blocks pipe | |
CN204921038U (en) | Simple and easy fixed connection structure of railway tunnel guard gate | |
CN109706972A (en) | Town road inspection shaft and its construction method are just installed | |
CN215630065U (en) | A secret open caisson for municipal works | |
CN205654211U (en) | Translation door structure | |
CN211690462U (en) | Multifunctional communicating pipe type monitoring equipment | |
CN215165663U (en) | Truss-type foundation pit supporting structure for building construction | |
CN218622526U (en) | Construction rainwater drainage clearance structure | |
CN208203322U (en) | Bracing means for anchor cable | |
CN109594559A (en) | Detachable counter-force anchor rod component and its application method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |