CN110130576A CN201910493680.8A CN201910493680A CN110130576A CN 110130576 A CN110130576 A CN 110130576A CN 201910493680 A CN201910493680 A CN 201910493680A CN 110130576 A CN110130576 A CN 110130576A
Authority
CN
China
Prior art keywords
steel plate
composite beam
ear
fixedly mounted
embedded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910493680.8A
Other languages
Chinese (zh)
Inventor
彭昊
叶彬
段鑫朋
杨尚荣
汪文泰
伍兴辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenshan Special Cooperation Zone Shengteng Technology Industrial Park Co ltd
Original Assignee
Shenshan Special Cooperation Zone Shengteng Technology Industrial Park Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenshan Special Cooperation Zone Shengteng Technology Industrial Park Co ltd filed Critical Shenshan Special Cooperation Zone Shengteng Technology Industrial Park Co ltd
Priority to CN201910493680.8A priority Critical patent/CN110130576A/en
Publication of CN110130576A publication Critical patent/CN110130576A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/90Curtain walls comprising panels directly attached to the structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/20Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention discloses a kind of prefabricated overlapping side bars, including composite beam, choose ear, U-stirrups, beam-ends steel plate, pre-embedded steel slab, beam-ends groove, Side fascia, pre-embedded bolt, overlap joint groove, the outgoing muscle of secondary beam and secondary beam, the side for stating composite beam, which is equipped with, chooses ear, the top of the composite beam is fixedly installed with U-stirrups, the side for choosing ear is equipped with beam-ends steel plate, and the beam-ends Interal fixation is mounted on composite beam.This prefabricated overlapping side bar, the beam-ends steel plate and pre-embedded steel slab for choosing ear two sides can prevent reinforcing bar and built-in fitting at node from colliding, the top of composite beam uses U-stirrups, facilitate the construction and design that water-proofing treatment is carried out at Side fascia ontology, when the span of composite beam is larger, reinforce steel plate, the second reinforcement steel plate and third for first and reinforces the firm form of steel plate formation triangle, and it can be with disassembly & recycling Reusability, it economizes on resources, it can also ensure that the globality and safety of structure, simultaneously in such a way that involvement connects, it is convenient for site operation.

Description

Prefabricated overlapping side bar of one kind and preparation method thereof
Technical field
The present invention relates to precast beam technical field, specially a kind of prefabricated overlapping side bar and preparation method thereof.
Background technique
In the interprocedual for developing assembled architecture, prefabricated concrete structure has pole there are many technical problems Big progress space.Wherein one of key problem is how to reduce wet connection, and guarantee that structure has preferable globality, peace It is complete reliable.Because the wet connection for reducing node will greatly accelerate the construction efficiency speed at scene, if can guarantee whole involvements Under conditions of connecing, the speed of cross construction will be greatly promoted, can achieve the installation of a index bed more than a day.
Summary of the invention
The purpose of the present invention is to provide a kind of prefabricated overlapping side bars and preparation method thereof, can guarantee the globality of structure And safety, while in such a way that involvement connects, it is convenient for site operation, can solve the problems of the prior art.
To achieve the above object, it the invention provides the following technical scheme: a kind of prefabricated overlapping side bar, including composite beam, chooses Ear, U-stirrups, beam-ends steel plate, pre-embedded steel slab, beam-ends groove, Side fascia, pre-embedded bolt, overlap joint groove, secondary beam go out muscle and Secondary beam, the side of the composite beam, which is equipped with, chooses ear, and the top of the composite beam is fixedly installed with U-stirrups, described to choose the one of ear Side is equipped with beam-ends steel plate, and the beam-ends Interal fixation is mounted on composite beam, and the other side for choosing ear is equipped with pre-embedded steel slab, institute Pre-embedded steel slab is stated to be fixedly mounted on composite beam, the both ends of the composite beam offer beam-ends groove, the composite beam it is another Side is equipped with Side fascia, and pre-embedded bolt is offered on the Side fascia, and the inside of the pre-embedded bolt is equipped with the outgoing muscle of secondary beam, institute The outgoing muscle of secondary beam is stated to be fixedly mounted on secondary beam.
Preferably, the Side fascia includes Side fascia ontology, overhead, top installation corner brace, embodiment in which top gasket, top pair Nut, bottom member, bottom installation corner brace, bottom gasket and bottom double nut, one end of the Side fascia ontology are equipped with top Component, the outside of the overhead are equipped with top and install corner brace, and the top installation corner brace is run through by screw rod, the top The outside for installing corner brace is equipped with embodiment in which top gasket, and the outside of the embodiment in which top gasket is equipped with top double nut, and the top double nut is solid On screw rod, the other end of the Side fascia ontology is equipped with bottom member for Dingan County, and the outside of the bottom member is equipped with bottom Corner brace is installed, the bottom installation corner brace is run through by screw rod, and the outside of the bottom installation corner brace is equipped with bottom gasket, described The outside of bottom gasket is equipped with bottom double nut, and the bottom double nut is fixedly mounted on screw rod.
Preferably, the overlap joint groove includes groove ontology, the first reinforcement steel plate, the second reinforcement steel plate, third reinforcement steel Plate and clamping screw, the outside of the groove ontology are equipped with second and reinforce steel plate, and the both ends of the second reinforcement steel plate are locked Tight bolt is run through, and the described second outside for reinforcing steel plate is equipped with third and reinforces steel plate, and the both ends that the third reinforces steel plate are equal The bolt that is locked is run through, and the outside that the third reinforces steel plate is equipped with first and reinforces steel plate, and the first reinforcement steel plate passes through Clamping screw is fixedly mounted on third and reinforces on steel plate.
Preferably, the hole size inside the embodiment in which top gasket and bottom gasket is not less than the diameter of screw rod.
It is a kind of it is prefabricated overlapping side bar preparation method, the prefabricated overlapping side bar include composite beam, choose ear, U-stirrups, Beam-ends steel plate, pre-embedded steel slab, beam-ends groove, Side fascia, pre-embedded bolt, overlap joint groove, the outgoing muscle of secondary beam and secondary beam, the preparation Method includes: that ear is chosen in the side setting of the composite beam, the top of the composite beam is fixedly mounted U-stirrups, the ear of choosing Beam-ends steel plate is arranged in side, and the beam-ends Interal fixation is mounted on composite beam, the other side setting pre-embedded steel slab for choosing ear, The pre-embedded steel slab is fixedly mounted on composite beam, and the both ends of the composite beam open up beam-ends groove, the composite beam it is another Side fascia is arranged in side, and pre-embedded bolt is offered on the Side fascia, and the outgoing muscle of inside installation secondary beam of the pre-embedded bolt is described The outgoing muscle of secondary beam is fixedly mounted on secondary beam.
Compared with prior art, beneficial effects of the present invention are as follows:
The prefabricated overlapping side bar of the present invention, is chosen ear one side towards outdoor, chosen without the one side for choosing ear by composite beam towards interior The beam-ends steel plate and pre-embedded steel slab of ear two sides can prevent reinforcing bar and built-in fitting at node from colliding, and the top of composite beam uses U-stirrups, facilitate the construction and design that water-proofing treatment is carried out at Side fascia ontology, and top installation corner brace runs through peace by screw rod On overhead, screw rod locking is made top installation corner brace complete to fix by top double nut by embodiment in which top gasket, bottom peace Dress corner brace is installed through on bottom member by screw rod, and screw rod locking installs bottom by bottom double nut by bottom gasket Corner brace completes installation, and the first reinforcement steel plate, the second reinforcement steel plate and third reinforcement steel plate are fixedly mounted on recessed by clamping screw The outside of slot ontology is formed triangle and consolidates form, and can economized on resources, additionally it is possible to guarantee structure with disassembly & recycling Reusability Globality and safety be convenient for site operation while in such a way that involvement connects.
Detailed description of the invention
Fig. 1 is composite beam structural schematic diagram of the invention;
Fig. 2 is composite beam connection schematic diagram of the invention;
Fig. 3 is overhead partial enlarged view of the invention;
Fig. 4 is bottom member partial enlarged view of the invention;
Fig. 5 is overlap joint groove partial enlarged view of the invention.
In figure: 1, composite beam;2, ear is chosen;3, U-stirrups;4, beam-ends steel plate;5, pre-embedded steel slab;6, beam-ends groove;7, outer Wallboard;71, Side fascia ontology;72, overhead;73, corner brace is installed at top;74, embodiment in which top gasket;75, top double nut;76, Bottom member;77, corner brace is installed in bottom;78, bottom gasket;79, bottom double nut;8, pre-embedded bolt;9, groove is overlapped;91, Groove ontology;92, first reinforces steel plate;93, second reinforces steel plate;94, third reinforces steel plate;95, clamping screw;10, secondary beam Outgoing muscle;11, secondary beam.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
A kind of prefabricated overlapping side bar referring to FIG. 1-2, including composite beam 1, choose ear 2, is U-stirrups 3, beam-ends steel plate 4, pre- Steel plate 5, beam-ends groove 6, Side fascia 7, pre-embedded bolt 8, overlap joint groove 9, the outgoing muscle 10 of secondary beam and secondary beam 11 are buried, composite beam 1 Side is equipped with and chooses ear 2, and the top of composite beam 1 is fixedly installed with U-stirrups 3, and the side for choosing ear 2 is equipped with beam-ends steel plate 4, beam-ends Steel plate 4 is fixedly mounted on composite beam 1, and the other side for choosing ear 2 is equipped with pre-embedded steel slab 5, and pre-embedded steel slab 5 is fixedly mounted on composite beam On 1, composite beam 1 chooses 2 one side of ear towards outdoor without the one side of ear 2 is chosen towards interior, chooses the beam-ends steel plate 4 of 2 two sides of ear and pre-buried Steel plate 5 can prevent reinforcing bar and built-in fitting at node from colliding, and the top of composite beam 1 uses U-stirrups 3, facilitate and prevented The construction and design of water process, the both ends of composite beam 1 offer beam-ends groove 6, and the other side of composite beam 1 is equipped with Side fascia 7, outside Pre-embedded bolt 8 is offered on wallboard 7, the inside of pre-embedded bolt 8 is equipped with the outgoing muscle 10 of secondary beam, and the outgoing muscle 10 of secondary beam is fixedly mounted On secondary beam 11.
Fig. 3-4 is please referred to, Side fascia 7 includes Side fascia ontology 71, overhead 72, top installation corner brace 73, bottom pad Piece 74, top double nut 75, bottom member 76, bottom installation corner brace 77, bottom gasket 78 and bottom double nut 79, Side fascia sheet One end of body 71 is equipped with overhead 72, and the outside of overhead 72 is equipped with top and installs corner brace 73, and 73 quilt of corner brace is installed at top Screw rod is run through, and the outside that corner brace 73 is installed at top is equipped with embodiment in which top gasket 74, and the outside of embodiment in which top gasket 74 is equipped with top double nut 75, top double nut 75 is fixedly mounted on screw rod, and the other end of Side fascia ontology 71 is equipped with bottom member 76, bottom member 76 Outside be equipped with bottom install corner brace 77, bottom installation corner brace 77 run through by screw rod, bottom installation corner brace 77 outside be equipped with Hole size inside bottom gasket 78, embodiment in which top gasket 74 and bottom gasket 78 is not less than the diameter of screw rod, can make to push up Portion's gasket 74 and bottom gasket 78 are run through by screw rod, and the outside of bottom gasket 78 is equipped with bottom double nut 79, the double spiral shells in bottom Mother 79 is fixedly mounted on screw rod.
Referring to Fig. 5, overlap joint groove 9 includes that groove ontology 91, first reinforces steel plate 92, second reinforcement steel plate 93, third Reinforce steel plate 94 and clamping screw 95, the outside of groove ontology 91 is equipped with second and reinforces steel plate 93, and second reinforces the two of steel plate 93 The bolt 95 that is locked is held to be run through, the second outside for reinforcing steel plate 93 is equipped with third and reinforces steel plate 94, and third reinforces steel plate 94 The both ends bolt 95 that is locked run through, the outside that third reinforces steel plate 94 is equipped with first and reinforces steel plate 92, and first reinforces steel Plate 92 is fixedly mounted on third by clamping screw 95 and reinforces on steel plate 94, and when the span of composite beam 1 is larger, first is reinforced Steel plate 92, second reinforces steel plate 93 and third reinforces steel plate 94 and is fixedly mounted on the outer of groove ontology 91 by clamping screw 95 Side is formed triangle and consolidates form, and can economized on resources with disassembly & recycling Reusability.
Working principle: 2 one side of ear is chosen towards outdoor, chooses 2 two sides of ear towards interior without the one side for choosing ear 2 by composite beam 1 Beam-ends steel plate 4 and pre-embedded steel slab 5 can prevent reinforcing bar and built-in fitting at node from colliding, the top of composite beam 1 is using opening Mouth stirrup 3, facilitates the construction and design that water-proofing treatment is carried out at Side fascia ontology 71, and top installation corner brace 73 is run through by screw rod It is mounted on overhead 72, screw rod locking is kept the installation completion of corner brace 73 in top solid by top double nut 75 by embodiment in which top gasket 74 Fixed, bottom installation corner brace 77 is installed through on bottom member 76 by screw rod, and bottom double nut 79 will by bottom gasket 78 Screw rod locking makes bottom installation corner brace 77 complete installation, and the first reinforcement steel plate 92, second reinforces steel plate 93 and third reinforces steel plate 94 are fixedly mounted on the outside of groove ontology 91 by clamping screw 95, form triangle and consolidate form, and can be anti-with disassembly & recycling It is multiple to use.
The invention further relates to a kind of preparation method of prefabricated overlapping side bar, the prefabricated overlapping side bar includes composite beam 1, chooses Ear 2, U-stirrups 3, beam-ends steel plate 4, pre-embedded steel slab 5, beam-ends groove 6, Side fascia 7, pre-embedded bolt 8, overlap joint groove 9, secondary beam Outgoing muscle 10 and secondary beam 11, the preparation method include: that ear 2, the top of the composite beam 1 are chosen in the side setting of the composite beam 1 U-stirrups 3, the side setting beam-ends steel plate 4 for choosing ear 2 are fixedly mounted in end, and the beam-ends steel plate 4 is fixedly mounted on overlapping On beam 1, the other side setting pre-embedded steel slab 5 for choosing ear 2, the pre-embedded steel slab 5 is fixedly mounted on composite beam 1, described folded The both ends for closing beam 1 open up beam-ends groove 6, and the other side of the composite beam 1 is arranged Side fascia 7, offers on the Side fascia 7 pre- Bolt 8, the outgoing muscle 10 of inside installation secondary beam of the pre-embedded bolt 8 are buried, the outgoing muscle 10 of the secondary beam is fixedly mounted on secondary beam 11 On.
In summary: the prefabricated overlapping side bar of the present invention chooses ear 2 one towards interior without the one side for choosing ear 2 by composite beam 1 Towards outdoor, the beam-ends steel plate 4 and pre-embedded steel slab 5 for choosing 2 two sides of ear can prevent reinforcing bar and built-in fitting at node from colliding for side, The top of composite beam 1 uses U-stirrups 3, facilitates the construction and design that water-proofing treatment is carried out at Side fascia ontology 71, top peace Dress corner brace 73 is installed through on overhead 72 by screw rod, and top double nut 75 is made screw rod locking by embodiment in which top gasket 74 Top installs corner brace 73 and completes to fix, and bottom installation corner brace 77 is installed through on bottom member 76 by screw rod, the double spiral shells in bottom Screw rod locking is made bottom install the completion installation of corner brace 77 by mother 79 by bottom gasket 78, and first, which reinforces steel plate 92, second, reinforces Steel plate 93 and third reinforce the outside that steel plate 94 is fixedly mounted on groove ontology 91 by clamping screw 95, form triangle and consolidate shape State, and can be economized on resources with disassembly & recycling Reusability, additionally it is possible to guarantee the globality and safety of structure, while using dry The mode of connection is convenient for site operation.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (5)

1. a kind of prefabricated overlapping side bar, including composite beam (1), choose ear (2), U-stirrups (3), beam-ends steel plate (4), pre-embedded steel slab (5), beam-ends groove (6), Side fascia (7), pre-embedded bolt (8), overlap joint groove (9), secondary beam outgoing muscle (10) and secondary beam (11), Be characterized in that: the side of the composite beam (1) is equipped with and chooses ear (2), and the top of the composite beam (1) is fixedly installed with U-stirrups (3), the side for choosing ear (2) is equipped with beam-ends steel plate (4), and the beam-ends steel plate (4) is fixedly mounted on composite beam (1), institute The other side for choosing ear (2) is stated equipped with pre-embedded steel slab (5), the pre-embedded steel slab (5) is fixedly mounted on composite beam (1), described folded The both ends for closing beam (1) offer beam-ends groove (6), and the other side of the composite beam (1) is equipped with Side fascia (7), the Side fascia (7) it is offered on pre-embedded bolt (8), the inside of the pre-embedded bolt (8) is equipped with secondary beam and goes out muscle (10), and the secondary beam is outgoing Muscle (10) is fixedly mounted on secondary beam (11).
2. prefabricated overlapping side bar according to claim 1, it is characterised in that: the Side fascia (7) includes Side fascia ontology (71), overhead (72), top installation corner brace (73), embodiment in which top gasket (74), top double nut (75), bottom member (76), Corner brace (77), bottom gasket (78) and bottom double nut (79) are installed in bottom, and one end of the Side fascia ontology (71) is equipped with top Portion's component (72), the outside of the overhead (72) are equipped with top installation corner brace (73), and corner brace (73) quilt is installed at the top Screw rod is run through, and the outside of top installation corner brace (73) is equipped with embodiment in which top gasket (74), the outside of the embodiment in which top gasket (74) Equipped with top double nut (75), the top double nut (75) is fixedly mounted on screw rod, the Side fascia ontology (71) it is another One end is equipped with bottom member (76), and the outside of the bottom member (76) is equipped with bottom installation corner brace (77), the bottom installation Corner brace (77) is run through by screw rod, and the outside of bottom installation corner brace (77) is equipped with bottom gasket (78), the bottom gasket (78) outside is equipped with bottom double nut (79), and the bottom double nut (79) is fixedly mounted on screw rod.
3. prefabricated overlapping side bar according to claim 1, it is characterised in that: the overlap joint groove (9) includes groove ontology (91), first reinforces steel plate (92), the second reinforcement steel plate (93), third reinforcement steel plate (94) and clamping screw (95), described recessed The outside of slot ontology (91) is equipped with second and reinforces steel plate (93), and the described second both ends for reinforcing steel plate (93) are locked bolt (95) run through, the described second outside for reinforcing steel plate (93) is equipped with third and reinforces steel plate (94), and the third reinforces steel plate (94) the both ends bolt (95) that is locked is run through, and the outside that the third reinforces steel plate (94) is equipped with first and reinforces steel plate (92), first reinforcement steel plate (92) is fixedly mounted on third by clamping screw (95) and reinforces on steel plate (94).
4. prefabricated overlapping side bar according to claim 1, it is characterised in that: the embodiment in which top gasket (74) and bottom gasket (78) internal hole size is not less than the diameter of screw rod.
5. a kind of preparation method of prefabricated overlapping side bar, the prefabricated overlapping side bar include composite beam (1), choose ear (2), open stirrups Muscle (3), beam-ends steel plate (4), pre-embedded steel slab (5), beam-ends groove (6), Side fascia (7), pre-embedded bolt (8), overlap joint groove (9), Secondary beam is gone out muscle (10) and secondary beam (11), which is characterized in that the preparation method includes: the side setting of the composite beam (1) It chooses ear (2), U-stirrups (3) are fixedly mounted in the top of the composite beam (1), the side setting beam-ends steel plate for choosing ear (2) (4), the beam-ends steel plate (4) is fixedly mounted on composite beam (1), other side setting pre-embedded steel slab (5) for choosing ear (2), The pre-embedded steel slab (5) is fixedly mounted on composite beam (1), and the both ends of the composite beam (1) open up beam-ends groove (6), described Side fascia (7) are arranged in the other side of composite beam (1), offer pre-embedded bolt (8), the pre-embedded bolt on the Side fascia (7) (8) inside installation secondary beam goes out muscle (10), and secondary beam muscle (10) of going out is fixedly mounted on secondary beam (11).
CN201910493680.8A 2019-06-06 2019-06-06 Prefabricated overlapping side bar of one kind and preparation method thereof Pending CN110130576A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910493680.8A CN110130576A (en) 2019-06-06 2019-06-06 Prefabricated overlapping side bar of one kind and preparation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910493680.8A CN110130576A (en) 2019-06-06 2019-06-06 Prefabricated overlapping side bar of one kind and preparation method thereof

Publications (1)

Publication Number Publication Date
CN110130576A true CN110130576A (en) 2019-08-16

Family

ID=67580539

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910493680.8A Pending CN110130576A (en) 2019-06-06 2019-06-06 Prefabricated overlapping side bar of one kind and preparation method thereof

Country Status (1)

Country Link
CN (1) CN110130576A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2559186A1 (en) * 1984-02-02 1985-08-09 Chevanne Michel Prefabricated lintel-tie.
DE10041452A1 (en) * 2000-08-23 2002-03-07 Arbeitsgemeinschaft Mauerziege Building for earthquake areas comprises a number of vertical walls with movement gaps
CN102720303A (en) * 2012-06-15 2012-10-10 吴方伯 Concrete composite beam
CN205742662U (en) * 2015-12-28 2016-11-30 中民筑友有限公司 Node installed by a kind of connector and Side fascia
CN106759935A (en) * 2017-01-19 2017-05-31 香港华艺设计顾问(深圳)有限公司 A kind of attachment structure of precast concrete exterior wall cladding
CN106836479A (en) * 2017-03-31 2017-06-13 浙江工业大学工程设计集团有限公司 A kind of prefabricated PC concrete frame structure
WO2017196191A1 (en) * 2016-05-09 2017-11-16 Bryzik Grzegorz Floor prefabricated element
WO2019056717A1 (en) * 2017-09-21 2019-03-28 中国建筑股份有限公司 Post-tensioned prestressed assembly-style system of concrete framework and shock-resistant and energy-dissipating components, and construction method
CN210216911U (en) * 2019-06-06 2020-03-31 深汕特别合作区盛腾科技工业园有限公司 Prefabricated coincide boundary beam

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2559186A1 (en) * 1984-02-02 1985-08-09 Chevanne Michel Prefabricated lintel-tie.
DE10041452A1 (en) * 2000-08-23 2002-03-07 Arbeitsgemeinschaft Mauerziege Building for earthquake areas comprises a number of vertical walls with movement gaps
CN102720303A (en) * 2012-06-15 2012-10-10 吴方伯 Concrete composite beam
CN205742662U (en) * 2015-12-28 2016-11-30 中民筑友有限公司 Node installed by a kind of connector and Side fascia
WO2017196191A1 (en) * 2016-05-09 2017-11-16 Bryzik Grzegorz Floor prefabricated element
CN106759935A (en) * 2017-01-19 2017-05-31 香港华艺设计顾问(深圳)有限公司 A kind of attachment structure of precast concrete exterior wall cladding
CN106836479A (en) * 2017-03-31 2017-06-13 浙江工业大学工程设计集团有限公司 A kind of prefabricated PC concrete frame structure
WO2019056717A1 (en) * 2017-09-21 2019-03-28 中国建筑股份有限公司 Post-tensioned prestressed assembly-style system of concrete framework and shock-resistant and energy-dissipating components, and construction method
CN210216911U (en) * 2019-06-06 2020-03-31 深汕特别合作区盛腾科技工业园有限公司 Prefabricated coincide boundary beam

Similar Documents

Publication Publication Date Title
CN109881789A (en) A kind of dismountable girder steel-steel core concrete column punching connecting node
CN207846687U (en) Prefabricated assembled modularization frame node
CN106121107A (en) Assemble type concrete slab and plate dry type method of attachment thereof
CN106638671A (en) High and low bin assembling integrated utility tunnel or draining canal
CN109537775A (en) The method for preparing assembly concrete shear wall using local corrugated thin-wall steel pipe
CN108035241A (en) Assembled steel-concrete composite bridge and construction process thereof
CN208815676U (en) Band steel pipe concrete column and section steel beam interior joint connection structure
CN110056126A (en) A kind of reinforced composite beam of loss of weight
CN110130576A (en) Prefabricated overlapping side bar of one kind and preparation method thereof
CN109057011A (en) A kind of prefabricated assembled concrete frame joint component and its preparation construction method
CN109024904A (en) A kind of fabricated shear wall vertical abutment joint curved bar bolt fastening structure and construction method
CN211421637U (en) Connecting structure of prefabricated gutter
CN209468856U (en) A kind of assembly concrete column beam connecting node
CN209260960U (en) It is a kind of to facilitate the wall for installing interim bearing diagonal
CN209163167U (en) A kind of precast floor slab connecting node construction
CN208748824U (en) A kind of assembled beam-column node
CN207672745U (en) A kind of node structure of precast prestressed assembled composite beam-prefabricated post
CN207003645U (en) A kind of connecting node of prefabricated post and precast beam
CN109778910A (en) The superimposed sheet for overlapping prefabricated piping lane reinforces mounting device and its method
CN108755929A (en) A kind of assembled pre-tensioned prestressed concrete frame and its construction technology
CN208884728U (en) Steel-concrete combines precast beam and prefabricated post connection structure
CN208965799U (en) Fabricated shear wall
CN207469595U (en) A kind of combined reinforced beam
CN106638956A (en) Concrete wallboard and ribbed slab dry type connection node
CN208996213U (en) The integral prefabricated node of beam column of the junction with rigid template bracket

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190816