CN110130357A - Fashioned iron combination stirring pile pit support system construction method is plugged at the top of bored concrete pile - Google Patents

Fashioned iron combination stirring pile pit support system construction method is plugged at the top of bored concrete pile Download PDF

Info

Publication number
CN110130357A
CN110130357A CN201910258016.5A CN201910258016A CN110130357A CN 110130357 A CN110130357 A CN 110130357A CN 201910258016 A CN201910258016 A CN 201910258016A CN 110130357 A CN110130357 A CN 110130357A
Authority
CN
China
Prior art keywords
pile
support system
profile steel
fashioned iron
crown beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910258016.5A
Other languages
Chinese (zh)
Other versions
CN110130357B (en
Inventor
江晓昕
吴建华
吴海洪
吴疆
丁凌云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING NINTH BUILDING INSTALLATION ENGINEERING Co Ltd
Original Assignee
NANJING NINTH BUILDING INSTALLATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANJING NINTH BUILDING INSTALLATION ENGINEERING Co Ltd filed Critical NANJING NINTH BUILDING INSTALLATION ENGINEERING Co Ltd
Priority to CN201910258016.5A priority Critical patent/CN110130357B/en
Publication of CN110130357A publication Critical patent/CN110130357A/en
Application granted granted Critical
Publication of CN110130357B publication Critical patent/CN110130357B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The present invention provides and plugs fashioned iron combination stirring pile pit support system construction method at the top of bored concrete pile, it is related to support system construction method field, including simulation analysis early period and Deepen Design-levelling of the land-cement mixing pile driving construction-rotary digging filling pile construction-accurate positioning H profile steel insertion-earth excavation to crown beam-crown beam construction-gunite concrete retaining wall-recycling H profile steel processing step.H profile steel is plugged at the top of support system bored concrete pile, and it pours waist rail and connects peripheral cement mixing pile, it is combination stressed using H profile steel, waist rail and outlet cement mixing pile, it is common to resist earthwork lateral pressure, efficiently avoid the security risk that may occur before foundation pit backfill, simulation analysis is carried out to this technology support pattern using FEM software ANSYS, more accurately reflects stress distribution situation and structural deformation conditions of the support system under soil lateral pressure effect.

Description

Fashioned iron combination stirring pile pit support system construction method is plugged at the top of bored concrete pile
Technical field
The present invention relates to plug fashioned iron combination stirring pile at the top of support system construction method field more particularly to bored concrete pile Cheat support system construction method.
Background technique
In recent years, as the acceleration of Chinese Urbanization construction promotes, building just develops towards highly denseization, and traditional puts It excavates and is also gradually backed out Process of Urbanization Construction in slope.And mutually echoed with ground level, the subterranean excavation depth of building also increasingly increases, Deep foundation pit technology grows up therewith, and Base hole supporting technology is even more wherein important content.
Base hole supporting technology refers to meet the construction requirement of underground structure and protecting the safety of surrounding deep foundation pit environment, right Supporting and retaining system, reinforcing and the safeguard measure that foundation pit side-wall is taken.With support technology safety, economy, in terms of require mention High and support technology continuous development, the supporting construction form used in practical projects are also more and more.
It is inserted into recyclable H profile steel at the top of the foundation pit supporting system of bored concrete pile combination mixing pile, forms the base of common stress Hole top composite support system, and the application experience of the multiple projects of pooled analysis, form and plug fashioned iron at the top of bored concrete pile In conjunction with stirring pile pit support system construction technology, and form construction.This working skill has reached domestic top standard, has Effect solves vertical cut overhang mill system cantilever part security hidden trouble that may be present before backfilling of earthwork, it is ensured that The safety of support form construction, while shortening the duration, reducing construction cost, to similar vertical cut cantilevered branch Shield filling pile construction has preferable directive function, has preferable application and promotion prospect.
Summary of the invention
The purpose of the present invention is to provide bored concrete pile tops to plug fashioned iron combination stirring pile pit support system construction method, To solve the above technical problems.
The present invention using following technical scheme in order to solve the above technical problems, realized:
Fashioned iron combination stirring pile pit support system construction method, including simulation analysis early period and depth are plugged at the top of bored concrete pile Change design-levelling of the land-cement mixing pile driving construction-rotary digging filling pile construction-accurate positioning H profile steel insertion-earth excavation to hat Beam-crown beam construction-gunite concrete retaining wall-recycling H profile steel processing step, the specific steps are as follows:
(1) simulation analysis early period and Deepen Design: carrying out simulation analysis by FEM-software ANSYS, mono- with SOLID65 Member makees concrete structure, is inserted in waist rail elasticity modulus, Poisson's ratio, then inputs other basic parameters respectively;With SOLID45 unit work Mixing pile and H profile steel are inserted in elasticity modulus, Poisson's ratio, (yield strength), (compression strength design value), establish pattern foundation pit supporting structure system System model substitutes into the soil parameters of support system overhanging section, deformation is calculated
(2) levelling of the land: first to earth's surface mud in mixing pile construction region, sundries is purged and levelling of the land, reinforce Accomplish that ground is solid smooth, guarantees along construction site that path formation, unimpeded and place roadbed can walk 50t large size crane Subject to, and carry out drainage works.
(3) cement mixing pile driving construction: first positioning pile foundation, cuts soil using drilling row, the cement slurry that will be prepared Injection is stirred, and carries out cutting soil in Song Jiang, and repeat sinking and promoted, and finally succeed pile, then using flushing system System is rinsed, and stake machine is moved to next position after the completion.
(4) rotary digging filling pile construction: guide pile position first, setting positioning gantry stake, then buries casing simultaneously outside stake position And repetition measurement, correction stake position and casing centre deviation, pore-forming then is pierced using drilling machine, the steel reinforcement cage made is put into hole, It is welded fixed steel bars cage, lower perfusion conduit, and secondary pile hole cleaning with main reinforcement, and Underwater Concrete is perfused, and sends special messenger to measure conduit and buries Enter depth, to complete to pour bored concrete pile.
(5) it is accurately positioned H profile steel insertion: secondary leveling being carried out to the construction site after the completion of supporting bored concrete pile first, then Setting-out is carried out to fashioned iron insertion position according to design drawing change request using total station, interim telltale mark is carried out, using hanging Machine is in place by H profile steel, and carries out position review with tape measure, after H profile steel is in place, is pressed into mud 30cm, utilizes plumb bob control The verticality of fashioned iron processed guarantees its perpendicularity deviation within 0.5%.
(6) earth excavation is to crown beam: after the installation of whole fashioned iron is in place, can carry out earth excavation, be excavated to waist rail bottom Portion's absolute altitude, earth excavation carry out second to bored concrete pile top crown beam position and excavate, first use mechanical excavation mode, be excavated to crown beam When the above 20cm of bottom absolute altitude, stop mechanical excavation, it is artificial to cut the earth to hat bottom elevation, it is compacted.
(7) crown beam is constructed: leveling crown beam substratum, supporting bored concrete pile region remove slag, cut the loose concrete of stake top, and The vertical reinforcement of stake top is all put in into pile cover, is no less than 50cm into length, is welded together with the reinforcing bar of pile cover crown beam, is cleared up Sundries simultaneously sets up crown beam side template, pours crown beam and supporting beam concrete.
(8) it gunite concrete retaining wall: removes crown beam side form and the mixing pile side wall between top waist rail and crown beam is done mixed Solidifying soil retaining wall is protected.
(9) H profile steel is recycled: after the completion of support changing structure for use construction, i.e., recyclable H profile steel.
Further, during insertion, the moment measures section steel flange to interim positioning mark with tape measure to the insertion H profile steel The distance of note, and its verticality is controlled, when the 2/3 of fashioned iron enters under mud, its depth being inserted under mud is controlled with tape measure.
Further, the earth excavation mode has mechanical excavation and the artificial mode of rising as high as the banks to be excavated.
Further, scheme location and installation waist rail template is pressed in the waist rail template installation and concreting, carries out reinforcing bar Blanking and binding.
Further, after the injection cantilever segment waist rail top concrete guard wall removes waist rail side form, in waist rail upper water 120mm concrete guard wall, strength grade of concrete C20 are sprayed on the inside of mud mixing pile.
Further, the H profile steel is preferably H488*300*11*18.
Further, the concrete is preferably C20.
The beneficial effects of the present invention are:
H profile steel is plugged at the top of support system bored concrete pile of the present invention, and pours waist rail and connects peripheral cement mixing pile, utilizes H Fashioned iron, waist rail and outlet cement mixing pile are combination stressed, common to resist earthwork lateral pressure, and efficiently avoiding can before foundation pit backfills The security risk that can occur carries out simulation analysis to this technology support pattern using FEM software ANSYS, more accurately Reflect stress distribution situation and structural deformation conditions of the support system under soil lateral pressure effect, is provided for site operation Theoretical direction, foundation pit vertical cut provide lateral reaction by cantilever H profile steel, efficiently solve in pattern foundation pit supporting structure and be commonly encountered Building dense, narrow space problem, foundation pit vertical cut, by cantilever H profile steel provide lateral reaction, efficiently solve The problem of the building dense, narrow space that are commonly encountered in pattern foundation pit supporting structure, H profile steel are constructed not shadow after the completion of supporting bored concrete pile pours It rings the duration, waist rail only about needs 4 days to installation, then to pouring from binding, and compared with traditional support pattern, procedure connection is more It to be close, can effectively accelerate construction progress, after completing pit earthwork backfill, supporting H profile steel is recyclable to be recycled, and is effectively saved Construction cost.
Specific embodiment
In order to be easy to understand the technical means, the creative features, the aims and the efficiencies achieved by the present invention, tie below Specific embodiment is closed, the present invention is further explained, and however, the following embodiments are merely preferred embodiments of the present invention, and not all. Based on the implementation example in the implementation mode, those skilled in the art's obtained other realities without making creative work Example is applied, protection scope of the present invention is belonged to.Experimental method in following embodiments is unless otherwise specified conventional method, The materials, reagents and the like used in the following examples is commercially available unless otherwise specified.
Embodiment 1
Fashioned iron combination stirring pile pit support system construction method, including simulation analysis early period and depth are plugged at the top of bored concrete pile Change design-levelling of the land-cement mixing pile driving construction-rotary digging filling pile construction-accurate positioning H profile steel insertion-earth excavation to hat Beam-crown beam construction-gunite concrete retaining wall-recycling H profile steel processing step, the specific steps are as follows:
(1) simulation analysis early period and Deepen Design: carrying out simulation analysis by FEM-software ANSYS, mono- with SOLID65 Member makees concrete structure, is inserted in waist rail elasticity modulus, Poisson's ratio, then inputs other basic parameters respectively;With SOLID45 unit work Mixing pile and H profile steel are inserted in elasticity modulus, Poisson's ratio, (yield strength), (compression strength design value), establish pattern foundation pit supporting structure system System model substitutes into the soil parameters of support system overhanging section, deformation is calculated.
(2) levelling of the land: first to earth's surface mud in mixing pile construction region, sundries is purged and levelling of the land, reinforce Accomplish that ground is solid smooth, guarantees along construction site that path formation, unimpeded and place roadbed can walk 50t large size crane Subject to, and carry out drainage works.
(3) cement mixing pile driving construction: first positioning pile foundation, cuts soil using drilling row, the cement slurry that will be prepared Injection is stirred, and carries out cutting soil in Song Jiang, and repeat sinking and promoted, and finally succeed pile, then using flushing system System is rinsed, and stake machine is moved to next position after the completion.
(4) rotary digging filling pile construction: guide pile position first, setting positioning gantry stake, then buries casing simultaneously outside stake position And repetition measurement, correction stake position and casing centre deviation, pore-forming then is pierced using drilling machine, the steel reinforcement cage made is put into hole, It is welded fixed steel bars cage, lower perfusion conduit, and secondary pile hole cleaning with main reinforcement, and Underwater Concrete is perfused, and sends special messenger to measure conduit and buries Enter depth, to complete to pour bored concrete pile.
(5) it is accurately positioned H profile steel insertion: secondary leveling being carried out to the construction site after the completion of supporting bored concrete pile first, then Setting-out is carried out to fashioned iron insertion position according to design drawing change request using total station, interim telltale mark is carried out, using hanging Machine is in place by H profile steel, and carries out position review with tape measure, after H profile steel is in place, is pressed into mud 30cm, utilizes plumb bob control The verticality of fashioned iron processed guarantees its perpendicularity deviation within 0.5%.
(6) earth excavation is to crown beam: after the installation of whole fashioned iron is in place, can carry out earth excavation, be excavated to waist rail bottom Portion's absolute altitude, earth excavation carry out second to bored concrete pile top crown beam position and excavate, first use mechanical excavation mode, be excavated to crown beam When the above 20cm of bottom absolute altitude, stop mechanical excavation, it is artificial to cut the earth to hat bottom elevation, it is compacted.
(7) crown beam is constructed: leveling crown beam substratum, supporting bored concrete pile region remove slag, cut the loose concrete of stake top, and The vertical reinforcement of stake top is all put in into pile cover, is no less than 50cm into length, is welded together with the reinforcing bar of pile cover crown beam, is cleared up Sundries simultaneously sets up crown beam side template, pours crown beam and supporting beam concrete.
(8) it gunite concrete retaining wall: removes crown beam side form and the mixing pile side wall between top waist rail and crown beam is done mixed Solidifying soil retaining wall is protected.
(9) H profile steel is recycled: after the completion of support changing structure for use construction, i.e., recyclable H profile steel.
Embodiment 2
Fashioned iron combination stirring pile pit support system construction method, including simulation analysis early period and depth are plugged at the top of bored concrete pile Change design-levelling of the land-cement mixing pile driving construction-rotary digging filling pile construction-accurate positioning H profile steel insertion-earth excavation to hat Beam-crown beam construction-gunite concrete retaining wall-recycling H profile steel processing step, the specific steps are as follows:
(1) simulation analysis early period and Deepen Design: carrying out simulation analysis by FEM-software ANSYS, mono- with SOLID65 Member makees concrete structure, is inserted in waist rail elasticity modulus, Poisson's ratio, then inputs other basic parameters respectively;With SOLID45 unit work Mixing pile and H profile steel are inserted in elasticity modulus, Poisson's ratio, (yield strength), (compression strength design value), establish pattern foundation pit supporting structure system System model substitutes into the soil parameters of support system overhanging section, deformation is calculated.
(2) levelling of the land: first to earth's surface mud in mixing pile construction region, sundries is purged and levelling of the land, reinforce Accomplish that ground is solid smooth, guarantees along construction site that path formation, unimpeded and place roadbed can walk 50t large size crane Subject to, and carry out drainage works.
(3) cement mixing pile driving construction: first positioning pile foundation, cuts soil using drilling row, the cement slurry that will be prepared Injection is stirred, and carries out cutting soil in Song Jiang, and repeat sinking and promoted, and finally succeed pile, then using flushing system System is rinsed, and stake machine is moved to next position after the completion.
(4) rotary digging filling pile construction: guide pile position first, setting positioning gantry stake, then buries casing simultaneously outside stake position And repetition measurement, correction stake position and casing centre deviation, pore-forming then is pierced using drilling machine, the steel reinforcement cage made is put into hole, It is welded fixed steel bars cage, lower perfusion conduit, and secondary pile hole cleaning with main reinforcement, and Underwater Concrete is perfused, and sends special messenger to measure conduit and buries Enter depth, to complete to pour bored concrete pile.
(5) it is accurately positioned H profile steel insertion: secondary leveling being carried out to the construction site after the completion of supporting bored concrete pile first, then Setting-out is carried out to fashioned iron insertion position according to design drawing change request using total station, interim telltale mark is carried out, using hanging Machine is in place by H profile steel, and carries out position review with tape measure, after H profile steel is in place, is pressed into mud 30cm, utilizes plumb bob control The verticality of fashioned iron processed guarantees its perpendicularity deviation within 0.5%.
(6) earth excavation is to crown beam: after the installation of whole fashioned iron is in place, can carry out earth excavation, be excavated to waist rail bottom Portion's absolute altitude, earth excavation carry out second to bored concrete pile top crown beam position and excavate, first use mechanical excavation mode, be excavated to crown beam When the above 20cm of bottom absolute altitude, stop mechanical excavation, it is artificial to cut the earth to hat bottom elevation, it is compacted.
(7) crown beam is constructed: leveling crown beam substratum, supporting bored concrete pile region remove slag, cut the loose concrete of stake top, and The vertical reinforcement of stake top is all put in into pile cover, is no less than 50cm into length, is welded together with the reinforcing bar of pile cover crown beam, is cleared up Sundries simultaneously sets up crown beam side template, pours crown beam and supporting beam concrete.
(8) it gunite concrete retaining wall: removes crown beam side form and the mixing pile side wall between top waist rail and crown beam is done mixed Solidifying soil retaining wall is protected.
(9) H profile steel is recycled: after the completion of support changing structure for use construction, i.e., recyclable H profile steel.
It is inserted into H profile steel during insertion, the distance of moment tape measure measurement section steel flange to interim telltale mark, and control Its verticality is made, when the 2/3 of fashioned iron enters under mud, controls its depth being inserted under mud with tape measure.
Earth excavation mode has mechanical excavation and the artificial mode of rising as high as the banks to be excavated.
Scheme location and installation waist rail template is pressed in the installation of waist rail template and concreting, carries out Steel Reinforcing Bar Material and binding.
After spraying cantilever segment waist rail top concrete guard wall dismounting waist rail side form, the side spray in the cement mixing pile of waist rail top Penetrate 120mm concrete guard wall, strength grade of concrete C20.
H profile steel is preferably H488*300*11*18.
Concrete is preferably C20.
Working principle: this engineering method is that recyclable H profile steel is inserted at the top of the foundation pit supporting system of bored concrete pile combination mixing pile, Composite support system at the top of the foundation pit of common stress is formed, row's supporting perfusion pile center is type within which implements Steel is inserted into central point, can carry out H profile steel insertion immediately after the completion of supporting bored concrete pile, and procedure connection is close, guarantees fashioned iron With combining closely for bored concrete pile;The construction of 300 × 300mm waist rail can be carried out after fashioned iron insertion, can pass through H profile steel, waist in this way Beam and outlet cement mixing pile are combination stressed, common to resist earthwork lateral pressure, may occur before efficiently avoiding foundation pit backfill Security risk, directly excavates compared to conventional boom-mounted supporting bored concrete pile to crown beam bottom, more for economy, safety and fits The property used.
This engineering method is during project implementation, using FEM software ANSYS to support system before excavation of foundation pit Carrying out simulation is the crucial first step, and a preview in advance is made in the deformation and internal stress distribution to support system.Using perfusion Stake top portion plugs fashioned iron combination stirring pile pit support system construction technology and establishes building by FEM-software ANSYS Threedimensional model can intuitively calculate H profile steel deformation and local stress, adjust H profile steel spacing, size and supporting according to analog result Can system detail structure avoid fashioned iron that buckling occurs because of bearing capacity deficiency, work normally for system and provide theoretical foundation And technological guidance.
The basic principles, main features and advantages of the present invention have been shown and described above.The technology of the industry For personnel it should be appreciated that the present invention is not limited to the above embodiments, described in the above embodiment and specification is only the present invention Preference, be not intended to limit the invention, without departing from the spirit and scope of the present invention, the present invention also has various Changes and improvements, these changes and improvements all fall within the protetion scope of the claimed invention.The claimed scope of the invention is by institute Attached claims and its equivalent thereof.

Claims (7)

1. plugging fashioned iron combination stirring pile pit support system construction method at the top of bored concrete pile, it is characterised in that: imitative including early period True analysis and Deepen Design-levelling of the land-cement mixing pile driving construction-rotary digging filling pile construction-accurate positioning H profile steel insertion-soil Side is excavated to crown beam-crown beam construction-gunite concrete retaining wall-recycling H profile steel processing step, the specific steps are as follows:
(1) simulation analysis early period and Deepen Design: carrying out simulation analysis by FEM-software ANSYS, with SOLID65 unit work Concrete structure is inserted in waist rail elasticity modulus, Poisson's ratio, then inputs other basic parameters respectively;It is mixed with SOLID45 unit Stake and H profile steel, are inserted in elasticity modulus, Poisson's ratio, (yield strength), (compression strength design value), establish foundation pit support system mould Type substitutes into the soil parameters of support system overhanging section, deformation is calculated.
(2) levelling of the land: first to earth's surface mud in mixing pile construction region, sundries is purged and levelling of the land, reinforcing is accomplished Ground is solid smooth, guarantees along construction site that path formation, unimpeded and place roadbed can walk subject to 50t large size crane, And carry out drainage works.
(3) cement mixing pile driving construction: first positioning pile foundation, cuts soil using drilling row, the cement slurry prepared is injected Be stirred, carry out cutting soil in Song Jiang, and repeat and be promoted, finally succeed pile, then using rinse-system into Row rinses, and stake machine is moved to next position after the completion.
(4) rotary digging filling pile construction: then casing and multiple is buried in guide pile position first, setting positioning gantry stake outside stake position It surveys, correct stake position and casing centre deviation, then pierce pore-forming using drilling machine, the steel reinforcement cage made is put into hole, with master Muscle is welded fixed steel bars cage, lower perfusion conduit, and secondary pile hole cleaning, and Underwater Concrete is perfused, and it is deep to send special messenger to measure conduit embedment Degree, to complete to pour bored concrete pile.
(5) it is accurately positioned H profile steel insertion: secondary leveling being carried out to the construction site after the completion of supporting bored concrete pile first, recycle Total station carries out setting-out to fashioned iron insertion position according to design drawing change request, carries out interim telltale mark, using loop wheel machine by H Fashioned iron is in place, and carries out position review with tape measure, after H profile steel is in place, is pressed into mud 30cm, controls fashioned iron using plumb bob Verticality, guarantee its perpendicularity deviation within 0.5%.
(6) earth excavation is to crown beam: after the installation of whole fashioned iron is in place, can carry out earth excavation, be excavated to waist rail bottom mark Height, earth excavation carry out second to bored concrete pile top crown beam position and excavate, first use mechanical excavation mode, be excavated to crown beam bottom and mark When the above 20cm of height, stop mechanical excavation, it is artificial to cut the earth to hat bottom elevation, it is compacted.
(7) crown beam is constructed: leveling crown beam substratum, supporting bored concrete pile region removes slag, cuts the loose concrete of stake top, and by stake The vertical reinforcement on top all puts in pile cover, is no less than 50cm into length, is welded together with the reinforcing bar of pile cover crown beam, clears up sundries And crown beam side template is set up, pour crown beam and supporting beam concrete.
(8) it gunite concrete retaining wall: removes crown beam side form and concrete is done to the mixing pile side wall between top waist rail and crown beam Retaining wall is protected.
(9) H profile steel is recycled: after the completion of support changing structure for use construction, i.e., recyclable H profile steel.
2. fashioned iron combination stirring pile pit support system construction method is plugged at the top of bored concrete pile according to claim 1, Be characterized in that: the insertion H profile steel during insertion, the moment with tape measure measure section steel flange to interim telltale mark away from From, and its verticality is controlled, when the 2/3 of fashioned iron enters under mud, its depth being inserted under mud is controlled with tape measure.
3. fashioned iron combination stirring pile pit support system construction method is plugged at the top of bored concrete pile according to claim 1, Be characterized in that: the earth excavation mode has mechanical excavation and the artificial mode of rising as high as the banks to be excavated.
4. fashioned iron combination stirring pile pit support system construction method is plugged at the top of bored concrete pile according to claim 1, Be characterized in that: the waist rail template installation and concreting are carried out Steel Reinforcing Bar Material and are tied up by scheme location and installation waist rail template It pricks.
5. fashioned iron combination stirring pile pit support system construction method is plugged at the top of bored concrete pile according to claim 1, It is characterized in that: after the injection cantilever segment waist rail top concrete guard wall removes waist rail side form, in waist rail top cement mixing pile Spray 120mm concrete guard wall, strength grade of concrete C20 in inside.
6. fashioned iron combination stirring pile pit support system construction method is plugged at the top of bored concrete pile according to claim 1, Be characterized in that: the H profile steel is preferably H488*300*11*18.
7. fashioned iron combination stirring pile pit support system construction method is plugged at the top of bored concrete pile according to claim 1, Be characterized in that: the concrete is preferably C20.
CN201910258016.5A 2019-04-01 2019-04-01 Construction method of cast-in-place pile top inserting type steel combined stirring pile foundation pit supporting system Active CN110130357B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910258016.5A CN110130357B (en) 2019-04-01 2019-04-01 Construction method of cast-in-place pile top inserting type steel combined stirring pile foundation pit supporting system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910258016.5A CN110130357B (en) 2019-04-01 2019-04-01 Construction method of cast-in-place pile top inserting type steel combined stirring pile foundation pit supporting system

Publications (2)

Publication Number Publication Date
CN110130357A true CN110130357A (en) 2019-08-16
CN110130357B CN110130357B (en) 2021-05-04

Family

ID=67569114

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910258016.5A Active CN110130357B (en) 2019-04-01 2019-04-01 Construction method of cast-in-place pile top inserting type steel combined stirring pile foundation pit supporting system

Country Status (1)

Country Link
CN (1) CN110130357B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3638664A1 (en) * 1986-11-12 1988-05-19 Holzmann Philipp Ag Method of constructing a sheet pile wall
JP2004107953A (en) * 2002-09-17 2004-04-08 Iwami Kaihatsu Kk Balancer for deep composite pile and pile foundation structure
KR20060092552A (en) * 2005-02-18 2006-08-23 (주)한국건설공법 The non-strut down framework construction method of having used cast in place concrete pile
JP2009035997A (en) * 2007-08-01 2009-02-19 Takahashi Kanri:Kk H-shaped steel earth-retaining method utilizing columnar improvement
CN102635120A (en) * 2012-05-04 2012-08-15 张全胜 Supportless construction structure and supportless construction method for round deep base pit
CN105421468A (en) * 2015-11-24 2016-03-23 叶长青 Basement support without concrete diagonal brace
CN108643190A (en) * 2018-04-12 2018-10-12 中铁上海工程局集团有限公司 A kind of construction method suitable for the larger deep foundation pit supporting structure of excavation area
CN109469069A (en) * 2018-11-27 2019-03-15 浙江坤德创新岩土工程有限公司 A kind of I-shaped support pile of prestressing force and foundation pit supporting method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3638664A1 (en) * 1986-11-12 1988-05-19 Holzmann Philipp Ag Method of constructing a sheet pile wall
JP2004107953A (en) * 2002-09-17 2004-04-08 Iwami Kaihatsu Kk Balancer for deep composite pile and pile foundation structure
KR20060092552A (en) * 2005-02-18 2006-08-23 (주)한국건설공법 The non-strut down framework construction method of having used cast in place concrete pile
JP2009035997A (en) * 2007-08-01 2009-02-19 Takahashi Kanri:Kk H-shaped steel earth-retaining method utilizing columnar improvement
CN102635120A (en) * 2012-05-04 2012-08-15 张全胜 Supportless construction structure and supportless construction method for round deep base pit
CN105421468A (en) * 2015-11-24 2016-03-23 叶长青 Basement support without concrete diagonal brace
CN108643190A (en) * 2018-04-12 2018-10-12 中铁上海工程局集团有限公司 A kind of construction method suitable for the larger deep foundation pit supporting structure of excavation area
CN109469069A (en) * 2018-11-27 2019-03-15 浙江坤德创新岩土工程有限公司 A kind of I-shaped support pile of prestressing force and foundation pit supporting method

Also Published As

Publication number Publication date
CN110130357B (en) 2021-05-04

Similar Documents

Publication Publication Date Title
CN104500077B (en) A kind of shallow-depth-excavation tunnel passes through cottage area construction method
CN104564128B (en) A kind of shallow-depth-excavation tunnel construction deformation monitoring method
CN102518135B (en) Horizontal jet grouting soil anchor and castinplace pile Composite Foundation Pit supporting construction engineering method
CN107313431B (en) Close on not contour foundation pit method for synchronously constructing
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN106759473B (en) The constructing structure and its construction method of underground pipe gallery and road
CN102094425B (en) Foundation pit construction method adopting shallow buried depth Larsen steel plate pile as protective cofferdam
CN103244128B (en) A kind of big cross section Karst Tunnel double-side approach remaining core soil in advance construction method
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN108005660A (en) A kind of Optimization of Expressway Tunnel Construction method
CN106761778A (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN104846829A (en) Shield-reserved penetration composite type foundation pit support wall and construction method thereof
CN102758458B (en) Underground continuous wall repairing method
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN106837341B (en) A kind of Metro construction construction method of shaft wall
CN108560536A (en) The continuous piling wall construction method of Soil-cement
CN109778869A (en) Foundation ditch construction method
CN106049195A (en) Method for strengthening subgrade basement of existing high speed railway line
CN113266392B (en) Pipe jacking construction method for penetrating through existing anchor cable group
CN108842819A (en) A kind of urban track traffic cable run method for tunnel construction
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN110424460A (en) A kind of tunnel open excavation construction technology
CN110306531A (en) High water level erratic boulder stratum construction of diaphragm wall technique
CN113216832A (en) Water-mill drilling construction method for pile hole in karst area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Wu Haihong

Inventor after: Wu Jianhua

Inventor after: Jiang Xiaoxin

Inventor after: Wu Jiang

Inventor after: Ding Lingyun

Inventor before: Jiang Xiaoxin

Inventor before: Wu Jianhua

Inventor before: Wu Haihong

Inventor before: Wu Jiang

Inventor before: Ding Lingyun

GR01 Patent grant
GR01 Patent grant