CN110080806A - A kind of construction technology of tunnel trunk secondary lining - Google Patents

A kind of construction technology of tunnel trunk secondary lining Download PDF

Info

Publication number
CN110080806A
CN110080806A CN201910379864.1A CN201910379864A CN110080806A CN 110080806 A CN110080806 A CN 110080806A CN 201910379864 A CN201910379864 A CN 201910379864A CN 110080806 A CN110080806 A CN 110080806A
Authority
CN
China
Prior art keywords
concrete
inverted arch
arch
construction
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910379864.1A
Other languages
Chinese (zh)
Inventor
陈航博
陈仲达
赖清海
杨群锋
陈继
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
In Sanhang (xiamen) Engineering Co Ltd
China Construction Third Engineering Bureau Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Original Assignee
In Sanhang (xiamen) Engineering Co Ltd
China Construction Third Engineering Bureau Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by In Sanhang (xiamen) Engineering Co Ltd, China Construction Third Engineering Bureau Co Ltd, CCCC Third Harbor Engineering Co Ltd Xiamen Branch filed Critical In Sanhang (xiamen) Engineering Co Ltd
Priority to CN201910379864.1A priority Critical patent/CN110080806A/en
Publication of CN110080806A publication Critical patent/CN110080806A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of construction technologies of tunnel trunk secondary lining, including following below scheme: preparation of construction, inverted arch construction, inverted arch filling construction and arch wall construction.For preparation of construction process the following steps are included: establishing automatic gauge concrete mixing plant, design concrete proportioning, concrete stirring is pumped into mould.For inverted arch construction process the following steps are included: inverted arch excavates basement process, inverted arch trestle is in place, and preliminary bracing is laid with waterproof layer, and the binding of inverted arch reinforcing bar installs inverted arch template, pours inverted arch concrete, conserves to strong.Inverted arch fills construction process the following steps are included: installation inverted arch filling template, pours inverted arch fill concrete, maintenance is to strong.For arch wall construction process the following steps are included: arch wall reinforcing bar is bound, arch wall template and trolley are in place, and arch wall construction joint joint part reason installs blocking plate and waterstop, pour arch wall concrete, and to strong, demoulding is simultaneously mobile trolley used for maintenance.The construction technology of secondary lining of the invention can save construction cost and save the construction time.

Description

A kind of construction technology of tunnel trunk secondary lining
Technical field
The present invention relates to a kind of construction technologies of tunnel trunk secondary lining.
Background technique
In recent years, developing by leaps and bounds with China's communication, a large amount of buried mountain tunnels will be travelling through rich water high-ground stress Area, construction faces prominent mud water burst, country rock squeezes large deformation and the serious problems such as even caves in, if supporting is not in time or mode is improper, Tunnel cross-section is easily led to reduce and supporting construction unstability, the rapid construction for seriously affecting tunnel and safe operation in the future.Tunnel It after excavation, discharges and deforms in right amount for control surrouding rock stress, increase strcture safety and facilitate construction, applied immediately after tunnel excavation Make that rigidity is smaller and structure sheaf as permanent bearing structure a part, including preliminary bracing, secondary lining and waterproof layer.How Construction secondary lining is always the project that insider endeavours research.
Summary of the invention
A kind of construction work of tunnel trunk secondary lining is provided it is an object of the invention to overcome the deficiencies of existing technologies Skill, it can save the cost of construction, and can save the construction time.
The object of the present invention is achieved like this: a kind of construction technology of tunnel trunk secondary lining, including following below scheme: Preparation of construction, inverted arch construction, inverted arch filling construction and arch wall construction;
The preparation of construction process designs concrete proportioning the following steps are included: establish automatic gauge concrete mixing plant, Concrete stirring, is pumped into mould;
The inverted arch construction process is the following steps are included: inverted arch excavates basement process, and inverted arch just props up, and inverted arch trestle is in place, The binding of inverted arch reinforcing bar, installs inverted arch template, pours inverted arch concrete, conserves to strong;
The inverted arch fills construction process the following steps are included: installing inverted arch filling template, pours inverted arch fill concrete, Maintenance is to strong;
The arch wall construction process is the following steps are included: preliminary bracing is laid with waterproof layer, the binding of arch wall reinforcing bar, built-in fitting peace If arch wall template and trolley are in place, arch wall construction joint joint part reason installs blocking plate and waterstop, pours arch wall concrete, supports For shield to strong, demoulding is simultaneously mobile trolley used;
When carrying out inverted arch reinforcing bar step of ligation and arch wall reinforcing bar step of ligation, reinforcement fabrication is first carried out, reinforcing bar is expired Foot is claimed below:
(1) end of tension hot rolling plain bar should make 180 ° of crotches, and bending diameter cannot be less than the 2.5 of bar diameter Times, hook end should there are the straightways for being not less than 3 times of bar diameter;
(2) the round end with Ribbed Bar of tension hot calendering, when using square crotch, the bending diameter of straight hook must not be small In 5 times of bar diameter, hook end should there are the straightways for being not less than 3 times of bar diameter;
(3) bent-up bar should curve smooth curve, and for plain bar, bending radius cannot be less than the 10 of bar diameter Times, for Ribbed Bar, bending radius cannot be less than 12 times of bar diameter;
(4) stirrup made of plain bar, end should make the crotch not less than 90 °, have the structure of shockproof requirements to answer Make 135 ° or 180 ° of crotch;
(5) bending diameter of crotch should be greater than steel bar stress diameter, and cannot be less than 7.5 times of stirrup diameter;Crotch end The length of straightway cannot be less than 5 times of stirrup diameter, there is the structure of shockproof requirements, cannot be less than 10 times of stirrup diameter;
(6) splice: when overlap joint arc welding, the length of double welded joint is not less than 5d, and the length of inconel weld is not less than 10d, d are bar diameter;Binding lap of splice tensile region is 35d, and compressive region 25d, d are bar diameter;Steel bar stress welding Or binding connector is arranged in internal force smaller part, and is staggeredly arranged, and connector spacing is not less than 1.3 times of laps of splice;
When carrying out the inverted arch and inverted arch filling construction process, constructed using self-propelled hydraulic inverted arch trestle;Inverted arch template Using set shaped steel formwork on-site consolidation, and prop up vertical secured;It is symmetrically poured from intermediate to two sides when pouring inverted arch concrete using chute It builds, with poker vibrator vibration compacting;Inverted arch filling construction is carried out after inverted arch intensity final set immediately, inverted arch concrete strength reaches Allow walk after to 5MPa, inverted arch concrete strength reach design strength 100% after allow vehicle pass-through;
Carry out the sequence of the arch wall reinforcing bar step of ligation of the arch wall construction process are as follows: the reinforcing bar processed is transported in hole → operation platform in place → with welding manner install outside main reinforcement → installation on the outside of longitudinally connected reinforcing bar and adjust outside main reinforcement between Away from → longitudinally connected reinforcing bar on the inside of the main reinforcement → installation of inside is installed with welding manner and adjust inside main reinforcement spacing → installation stirrup;
The built-in fitting for carrying out the arch wall construction process installs, template and trolley step in place: according to design document, in steel Embedded box, pipeline etc. are installed in muscle frame slot, accurately release tunnel middle line and elevation with total station and level, it will by track Trolley moves to lining cutting position, mixes up absolute altitude, by the support lever arm of the good template of tunnel-liner inner outline size adjusting, starts trolley Hydraulic system, make arch wall Template Location, guarantee that trolley middle line is consistent with tunnel middle line, fixation after the molding of arch wall template, and pacifying Locking plug template is filled, delivery pump pipeline is reconnected, preparation pours arch wall concrete;
When pouring arch wall concrete step of the arch wall construction process is carried out, is constructed using tunneling boring once moulding method; It is vibrated using the attached vibrator two ways hung on poker vibrator and trolley;Between the movement of poker vibrator Away from 1.5 times no more than its operating radius, and the depth being inserted into lower-layer concrete is 5~10cm, and each vibrating for vibration point is held It the continuous time, is no longer sunk with concrete, bubble no longer occurs, surface laitance occurs obviously for degree;Attached vibrator starts Time with concrete pour full attached vibrator vibrate range when unlatching, each time of vibration be 1~2 minute.
The construction technology of above-mentioned tunnel trunk secondary lining, wherein carry out the template and platform of the arch wall construction process Before vehicle step in place, first trolley track is laid with according to tunnel middle line and elevation, trolley track uses standard sleeper and fish platee; Gauge is consistent with the wheelspan of trolley, and the height difference < 10mm of left and right rail level, restarting motor keeps trolley in place, and applies in template Brush release agent.
The construction technology of above-mentioned tunnel trunk secondary lining, wherein carry out the arch wall construction process pours arch wall When concrete step, prevent concrete surface from defect occur using following measures:
A, window is divided to be poured, pump concrete puts in storage should from bottom to top, from placing section joint to non-placing direction Layering is symmetrical to pour, and prevents bias from making template deformation;When lower-layer concrete is perfused, trolley middle layer window is opened, with benefit exhaust; In perfusion when layer concrete, trolley top-level windows are opened, with benefit exhaust;
B, when concrete perfusion, several meters of hose is lengthened in pump line front end, should be protruded into window when into window and makes pipe Mouth as far as possible vertically downward, directly pumps to scar to avoid concrete, corner and abutment wall is caused voids and pits occur;
C, the drop height degree that freely inclines when concreting is no more than 2 meters, when being more than, using utensils such as sliding slot, tumbling barrels, or It is poured by the aperture reserved in template;
D, guarantee the ratio of mud of concrete;
E, concrete bind the inward end mould direction Shi Yingcong perfusion, exclude air, with guarantee vault perfusion it is full and closely knit Degree;
F, guarantee continuous concreting, avoid the intermittent time too long, if more than 2 hours, must by pour interrupt into The processing of row construction joint.
The construction technology of tunnel trunk secondary lining of the invention, can save the cost of construction, and can save the construction time, Have the function that support reinforcement tunnel, to adapt to the requirement of modernization super expressway tunnel construction.
Specific embodiment
A kind of construction technology of tunnel trunk secondary lining of the invention, including following below scheme: preparation of construction, inverted arch are applied Work, inverted arch filling construction and arch wall construction.
Preparation of construction process designs concrete proportioning, coagulation the following steps are included: establish automatic gauge concrete mixing plant Soil stirring, is pumped into mould;
For inverted arch construction process the following steps are included: inverted arch excavates basement process, inverted arch trestle is in place, and preliminary bracing is laid with anti- Water layer, inverted arch reinforcing bar binding, installs inverted arch template, pours inverted arch concrete, conserves to strong;
Inverted arch fills construction process the following steps are included: installing inverted arch filling template, pours inverted arch fill concrete, conserves To strong;
For arch wall construction process the following steps are included: arch wall reinforcing bar is bound, arch wall template and trolley are in place, and arch wall construction is sewed up Stubble processing, installs blocking plate and waterstop, pours arch wall concrete, and to strong, demoulding is simultaneously mobile trolley used for maintenance;
When carrying out inverted arch reinforcing bar step of ligation and arch wall reinforcing bar step of ligation, reinforcement fabrication is first carried out, reinforcing bar is expired Foot is claimed below:
(1) end of tension hot rolling plain bar should make 180 ° of crotches, and bending diameter cannot be less than the 2.5 of bar diameter Times, hook end should there are the straightways for being not less than 3 times of bar diameter;
(2) the round end with Ribbed Bar of tension hot calendering, when using square crotch, the bending diameter of straight hook must not be small In 5 times of bar diameter, hook end should there are the straightways for being not less than 3 times of bar diameter;
(3) bent-up bar should curve smooth curve, and for plain bar, bending radius cannot be less than the 10 of bar diameter Times, for Ribbed Bar, bending radius cannot be less than 12 times of bar diameter;
(4) stirrup made of plain bar, end should make the crotch not less than 90 °, have the structure of shockproof requirements to answer Make 135 ° or 180 ° of crotch;
(5) bending diameter of crotch should be greater than steel bar stress diameter, and cannot be less than 7.5 times of stirrup diameter;Crotch end The length of straightway cannot be less than 5 times of stirrup diameter, there is the structure of shockproof requirements, cannot be less than 10 times of stirrup diameter;
(6) splice: when overlap joint arc welding, the length of double welded joint is not less than 5d, and the length of inconel weld is not less than 10d, d are bar diameter;Binding lap of splice tensile region is 35d, and compressive region 25d, d are bar diameter;Steel bar stress welding Or binding connector is arranged in internal force smaller part, and is staggeredly arranged, and connector spacing is not less than 1.3 times of laps of splice;
When carrying out inverted arch construction process, to reduce the interference with muck removal transport, constructed using inverted arch trestle;Inverted arch template is adopted With set shaped steel formwork on-site consolidation, and prop up vertical secured;It is symmetrically poured from intermediate to two sides when pouring inverted arch concrete using chute, With poker vibrator vibration compacting;Inverted arch answers advanced arch wall lining cutting, and crossover distance is no less than 20m;Inverted arch concrete strength reaches Allow walk after to 5MPa, inverted arch concrete strength reach design strength 100% after allow vehicle pass-through, inverted arch intensity Inverted arch filling construction is carried out after final set immediately;
When carrying out inverted arch filling construction process, equally constructed using inverted arch trestle;Inverted arch filling template is using sizing punching block Plate on-site consolidation, and prop up vertical secured;Concrete is transported in hole using concrete tank car, using chute when pouring inverted arch fill concrete It is symmetrically poured from centre to two sides, with poker vibrator vibration compacting;Inverted arch fill concrete intensity allows after reaching 5MPa Walk, inverted arch fill concrete intensity reach design strength 100% after allow vehicle pass-through;
Carry out the sequence of the arch wall reinforcing bar step of ligation of arch wall construction process are as follows: the reinforcing bar processed is transported in hole → is made Industry rack in place → longitudinally connected reinforcing bar is installed on the outside of the main reinforcement → installation of outside with welding manner and adjust outside main reinforcement spacing → Longitudinally connected reinforcing bar on the inside of inside main reinforcement → installation is installed with welding manner and adjusts inside main reinforcement spacing → installation stirrup;
When carrying out the template and trolley step in place of arch wall construction process, accurately released in tunnel with total station and level Line and elevation are laid with trolley track then according to tunnel middle line and elevation, and trolley track uses standard sleeper and fish platee;Gauge Consistent with the wheelspan of trolley, the height difference < 10mm of left and right rail level starts motor by track and trolley is moved to lining cutting position, adjusts Good absolute altitude starts the hydraulic system of trolley by the support lever arm of the good template of tunnel-liner inner outline size adjusting, makes arch wall mould Plate positioning guarantees that trolley middle line is consistent with tunnel middle line, fixed after the molding of arch wall template, and installed plug template, in template Brushing release agent, reconnects delivery pump pipeline, and preparation pours arch wall concrete;
When pouring arch wall concrete step of arch wall construction process is carried out, is constructed using tunneling boring once moulding method;Using The attached vibrator two ways hung on poker vibrator and trolley is vibrated;The mobile spacing of poker vibrator is not Greater than 1.5 times of its operating radius, and the depth being inserted into lower-layer concrete is 5~10cm, when vibrating lasting of each vibration point Between, it is no longer sunk with concrete, bubble no longer occurs, surface laitance occurs obviously for degree;The running time of attached vibrator With concrete pour full attached vibrator vibrate range when unlatching, each time of vibration be 1~2 minute.
Mostly there are the surface defects such as pitted skin, bubble and bubble on spring line abutment wall below in lining construction, seriously Influence Surface Quality of Concrete, the generation of defect with pour and the control for link of vibrating is related, prevent coagulation using following measures There is defect in native surface:
A, window is divided to be poured, pump concrete puts in storage should from bottom to top, from placing section joint to non-placing direction Layering is symmetrical to pour, and prevents bias from making template deformation;When lower-layer concrete is perfused, trolley middle layer window is opened, with benefit exhaust; In perfusion when layer concrete, trolley top-level windows are opened, with benefit exhaust;
B, when concrete perfusion, several meters of hose is lengthened in pump line front end, should be protruded into window when into window and makes pipe Mouth as far as possible vertically downward, directly pumps to scar to avoid concrete, corner and abutment wall is caused voids and pits occur;
C, the drop height degree that freely inclines when concreting is no more than 2 meters, when being more than, using utensils such as sliding slot, tumbling barrels, or It is poured by the aperture reserved in template;
D, guarantee the ratio of mud of concrete;
E, concrete bind the inward end mould direction Shi Yingcong perfusion, exclude air, with guarantee vault perfusion it is full and closely knit Degree;
F, guarantee continuous concreting, avoid the intermittent time too long, if more than 2 hours, must by pour interrupt into The processing of row construction joint.
Above embodiments are used for illustrative purposes only, rather than limitation of the present invention, the technology people in relation to technical field Member, without departing from the spirit and scope of the present invention, can also make various transformation or modification, therefore all equivalent Technical solution also should belong to scope of the invention, should be limited by each claim.

Claims (3)

1. a kind of construction technology of tunnel trunk secondary lining, including following below scheme: preparation of construction, inverted arch construction, inverted arch filling Construction and arch wall construction;It is characterized in that,
The preparation of construction process designs concrete proportioning, coagulation the following steps are included: establish automatic gauge concrete mixing plant Soil stirring, is pumped into mould;
The inverted arch construction process is the following steps are included: inverted arch excavates basement process, and inverted arch just props up, and inverted arch trestle is in place, inverted arch Reinforcing bar binding, installs inverted arch template, pours inverted arch concrete, conserves to strong;
The inverted arch fills construction process the following steps are included: installing inverted arch filling template, pours inverted arch fill concrete, conserves To strong;
The arch wall construction process the following steps are included: preliminary bracing is laid with waterproof layer, the binding of arch wall reinforcing bar, install by built-in fitting, Arch wall template and trolley are in place, and arch wall construction joint joint part reason installs blocking plate and waterstop, pours arch wall concrete, conserves To strong, demoulding is simultaneously mobile trolley used;
Carrying out inverted arch reinforcing bar step of ligation and when arch wall reinforcing bar step of ligation, first to carry out reinforcement fabrication, meet reinforcing bar with Lower requirement:
(1) end of tension hot rolling plain bar should make 180 ° of crotches, and bending diameter cannot be less than 2.5 times of bar diameter, Hook end should there are the straightways for being not less than 3 times of bar diameter;
(2) the round end with Ribbed Bar of tension hot calendering, when using square crotch, the bending diameter of straight hook cannot be less than steel 5 times of muscle diameter, hook end should there are the straightways for being not less than 3 times of bar diameter;
(3) bent-up bar should curve smooth curve, and for plain bar, bending radius cannot be less than 10 times of bar diameter, For Ribbed Bar, bending radius cannot be less than 12 times of bar diameter;
(4) stirrup made of plain bar, end should make the crotch not less than 90 °, have the structure of shockproof requirements that should make 135 ° or 180 ° of crotch;
(5) bending diameter of crotch should be greater than steel bar stress diameter, and cannot be less than 7.5 times of stirrup diameter;Crotch end straight line The length of section, cannot be less than 5 times of stirrup diameter, there is the structure of shockproof requirements, cannot be less than 10 times of stirrup diameter;
(6) splice: when overlap joint arc welding, the length of double welded joint is not less than 5d, and the length of inconel weld is not less than 10d, d For bar diameter;Binding lap of splice tensile region is 35d, and compressive region 25d, d are bar diameter;Steel bar stress welding or binding Connector is arranged in internal force smaller part, and is staggeredly arranged, and connector spacing is not less than 1.3 times of laps of splice;
When carrying out the inverted arch and inverted arch filling construction process, constructed using self-propelled hydraulic inverted arch trestle;Inverted arch template uses Set shaped steel formwork on-site consolidation, and prop up vertical secured;It is symmetrically poured, is used to two sides from intermediate using chute when pouring inverted arch concrete Poker vibrator vibration compacting;Inverted arch filling construction is carried out after inverted arch intensity final set immediately, inverted arch concrete strength reaches Allow walk after 5MPa, inverted arch concrete strength reach design strength 100% after allow vehicle pass-through;
Carry out the sequence of the arch wall reinforcing bar step of ligation of the arch wall construction process are as follows: the reinforcing bar processed is transported in hole → is made Industry rack in place → longitudinally connected reinforcing bar is installed on the outside of the main reinforcement → installation of outside with welding manner and adjust outside main reinforcement spacing → Longitudinally connected reinforcing bar on the inside of inside main reinforcement → installation is installed with welding manner and adjusts inside main reinforcement spacing → installation stirrup;
The built-in fitting for carrying out the arch wall construction process installs, template and trolley step in place: according to design document, in reinforcing steel bar frame Embedded box, pipeline etc. are installed in rack slot, accurately releases tunnel middle line and elevation with total station and level, by track by trolley Lining cutting position is moved to, absolute altitude is mixed up, by the support lever arm of the good template of tunnel-liner inner outline size adjusting, starts the liquid of trolley Pressure system makes arch wall Template Location, guarantees that trolley middle line is consistent with tunnel middle line, fixed after the molding of arch wall template, and installs stifled Head template, reconnects delivery pump pipeline, and preparation pours arch wall concrete;
When pouring arch wall concrete step of the arch wall construction process is carried out, is constructed using tunneling boring once moulding method;Using The attached vibrator two ways hung on poker vibrator and trolley is vibrated;The mobile spacing of poker vibrator is not Greater than 1.5 times of its operating radius, and the depth being inserted into lower-layer concrete is 5~10cm, when vibrating lasting of each vibration point Between, it is no longer sunk with concrete, bubble no longer occurs, surface laitance occurs obviously for degree;The running time of attached vibrator With concrete pour full attached vibrator vibrate range when unlatching, each time of vibration be 1~2 minute.
2. the construction technology of tunnel trunk secondary lining according to claim 1, which is characterized in that carry out the arch wall and apply Before template and the trolley step in place of work process, first trolley track is laid with according to tunnel middle line and elevation, trolley track uses Standard sleeper and fish platee;Gauge is consistent with the wheelspan of trolley, and the height difference < 10mm of left and right rail level, restarting motor makes trolley In place, the brushing release agent and in template.
3. the construction technology of tunnel trunk secondary lining according to claim 1, which is characterized in that carry out the arch wall and apply When pouring arch wall concrete step of work process, prevents concrete surface from defect occur using following measures:
A, window is divided to be poured, pump concrete, which puts in storage, to be layered from bottom to top from placing section joint to non-placing direction It is symmetrical to pour, prevent bias from making template deformation;When lower-layer concrete is perfused, trolley middle layer window is opened, with benefit exhaust;Perfusion When middle layer concrete, trolley top-level windows are opened, with benefit exhaust;
B, when concrete perfusion, several meters of hose is lengthened in pump line front end, should be protruded into window when into window and uses up nozzle Amount vertically downward, directly pumps to scar to avoid concrete, corner and abutment wall is caused voids and pits occur;
C, the drop height degree that freely inclines when concreting, when being more than, using utensils such as sliding slot, tumbling barrels, or passes through no more than 2 meters The aperture reserved in template pours;
D, guarantee the ratio of mud of concrete;
E, concrete bind the inward end mould direction Shi Yingcong perfusion, exclude air, with guarantee vault be perfused full and compactness;
F, guarantee continuous concreting, avoid the intermittent time too long, if more than 2 hours work must be carried out by pouring to interrupt Make seam processing.
CN201910379864.1A 2019-05-05 2019-05-05 A kind of construction technology of tunnel trunk secondary lining Pending CN110080806A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910379864.1A CN110080806A (en) 2019-05-05 2019-05-05 A kind of construction technology of tunnel trunk secondary lining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910379864.1A CN110080806A (en) 2019-05-05 2019-05-05 A kind of construction technology of tunnel trunk secondary lining

Publications (1)

Publication Number Publication Date
CN110080806A true CN110080806A (en) 2019-08-02

Family

ID=67419252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910379864.1A Pending CN110080806A (en) 2019-05-05 2019-05-05 A kind of construction technology of tunnel trunk secondary lining

Country Status (1)

Country Link
CN (1) CN110080806A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374641A (en) * 2019-08-21 2019-10-25 中建空列(北京)工程设计研究院有限公司 The construction method of tunnel-liner
CN110497923A (en) * 2019-08-21 2019-11-26 中建空列(北京)工程设计研究院有限公司 Empty rail pipeline transportation system
CN110497924A (en) * 2019-08-21 2019-11-26 中建空列(北京)工程设计研究院有限公司 A kind of empty rail pipeline transportation system for tunnel
CN110685719A (en) * 2019-10-31 2020-01-14 中铁建大桥工程局集团第五工程有限公司 Quick construction method for double-span simply-supported inverted arch trestle
CN111188633A (en) * 2020-01-08 2020-05-22 中建三局基础设施建设投资有限公司 Rapid construction method for secondary lining of small-section tunnel
CN111396083A (en) * 2019-09-29 2020-07-10 中铁隧道局集团有限公司 Tunnel lining strip pressing mold pouring process and monitoring method for lining concrete pressure and full state thereof
CN111411977A (en) * 2020-03-26 2020-07-14 中铁十二局集团有限公司 Construction method for connecting diaphragm in single-hole double-layer tunnel by mould building
CN112610240A (en) * 2020-12-19 2021-04-06 中交二公局萌兴工程有限公司 Secondary lining construction process for mountain tunnel
CN113417668A (en) * 2021-07-29 2021-09-21 中铁隧道集团一处有限公司 Pouring construction method for high cantilever tunnel side wall
CN114738000A (en) * 2022-04-23 2022-07-12 石家庄铁源工程咨询有限公司 Pouring construction method for secondary lining concrete of railway tunnel arch wall
WO2022193200A1 (en) * 2021-03-18 2022-09-22 中建三局基础设施建设投资有限公司 Rapid construction method for secondary lining of small-section tunnel
CN115288740A (en) * 2022-08-11 2022-11-04 山东水总有限公司 Lining construction process for small-section tunnel

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108194136A (en) * 2017-12-31 2018-06-22 中铁十九局集团第二工程有限公司 Lining construction method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108194136A (en) * 2017-12-31 2018-06-22 中铁十九局集团第二工程有限公司 Lining construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
孟维军: "《高速铁路隧道工程施工技术》", 31 August 2014 *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110497923A (en) * 2019-08-21 2019-11-26 中建空列(北京)工程设计研究院有限公司 Empty rail pipeline transportation system
CN110497924A (en) * 2019-08-21 2019-11-26 中建空列(北京)工程设计研究院有限公司 A kind of empty rail pipeline transportation system for tunnel
CN110374641A (en) * 2019-08-21 2019-10-25 中建空列(北京)工程设计研究院有限公司 The construction method of tunnel-liner
CN110374641B (en) * 2019-08-21 2021-03-16 中建空列(北京)工程设计研究院有限公司 Construction method of tunnel lining
CN111396083B (en) * 2019-09-29 2021-12-10 中铁隧道局集团有限公司 Tunnel lining strip pressing mold pouring process and monitoring method for lining concrete pressure and full state thereof
CN111396083A (en) * 2019-09-29 2020-07-10 中铁隧道局集团有限公司 Tunnel lining strip pressing mold pouring process and monitoring method for lining concrete pressure and full state thereof
CN110685719A (en) * 2019-10-31 2020-01-14 中铁建大桥工程局集团第五工程有限公司 Quick construction method for double-span simply-supported inverted arch trestle
CN111188633A (en) * 2020-01-08 2020-05-22 中建三局基础设施建设投资有限公司 Rapid construction method for secondary lining of small-section tunnel
CN111411977A (en) * 2020-03-26 2020-07-14 中铁十二局集团有限公司 Construction method for connecting diaphragm in single-hole double-layer tunnel by mould building
CN112610240A (en) * 2020-12-19 2021-04-06 中交二公局萌兴工程有限公司 Secondary lining construction process for mountain tunnel
WO2022193200A1 (en) * 2021-03-18 2022-09-22 中建三局基础设施建设投资有限公司 Rapid construction method for secondary lining of small-section tunnel
CN113417668A (en) * 2021-07-29 2021-09-21 中铁隧道集团一处有限公司 Pouring construction method for high cantilever tunnel side wall
CN113417668B (en) * 2021-07-29 2023-12-15 中铁隧道集团一处有限公司 Pouring construction method of high cantilever tunnel side wall
CN114738000A (en) * 2022-04-23 2022-07-12 石家庄铁源工程咨询有限公司 Pouring construction method for secondary lining concrete of railway tunnel arch wall
CN115288740A (en) * 2022-08-11 2022-11-04 山东水总有限公司 Lining construction process for small-section tunnel

Similar Documents

Publication Publication Date Title
CN110080806A (en) A kind of construction technology of tunnel trunk secondary lining
CN105386778B (en) Tunnel excavation lining construction chassis and tunnel excavation lining construction method
CN103939114B (en) A kind of outstanding rail chassis lining construction method
CN104060629B (en) The superimposed wall construction method in covered back-digging subway station and portable side wall formwork jumbo
CN104453946B (en) Advanced reinforcing construction method for building tunnel in soft surrounding rock
CN108397200B (en) Back-fabricated construction method for tunnel connection section structure of subway station
CN102619522A (en) Construction method for subway contact passage
CN101725149B (en) Construction method of long open-cut tunnel
CN110185457B (en) TBM (Tunnel boring machine) horizontal pilot tunnel construction method
CN211038657U (en) Cover encircles based deeply buries loess tunnel deformation control construction structures
CN101818645B (en) Construction method for newly increasing arched open cut tunnel at railway operating line tunnel portal
CN110331992A (en) A kind of hole daguanpeng construction method
CN102031736A (en) Construction technology for under-passing existing line under complicated geological condition
CN107152292A (en) Tunnel descending inclined shaft contrary sequence method two serves as a contrast construction method
CN110671131A (en) Loess tunnel substrate reinforcing structure and method based on high-pressure jet grouting pile
CN109611102A (en) Construction of the flyover method is worn under a kind of cold excavation
CN112879037A (en) Safe construction method for mine tunnel
CN109209389A (en) Hazy tunnel construction method
CN110984999A (en) Tunnel shaft construction method
CN110656959A (en) Large-section loess tunnel primary support limit-invasion arch-changing construction method
CN204983669U (en) Constructional column be connected with collar tie beam pour device
CN110761808A (en) Large-section loess tunnel supporting system and supporting construction method
CN108691552A (en) Large-section horseshoe-shaped shield cutting receiving construction method
CN110195604A (en) A kind of threaded list road main tunnel TBM driving section constructing method
CN114876515A (en) Two lining platform trucks in tunnel are pour fast

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190802