CN110070283A - A kind of chemical project safe design management method - Google Patents

A kind of chemical project safe design management method Download PDF

Info

Publication number
CN110070283A
CN110070283A CN201910307557.2A CN201910307557A CN110070283A CN 110070283 A CN110070283 A CN 110070283A CN 201910307557 A CN201910307557 A CN 201910307557A CN 110070283 A CN110070283 A CN 110070283A
Authority
CN
China
Prior art keywords
project
situation
design
wages
management
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910307557.2A
Other languages
Chinese (zh)
Inventor
王晶晶
丁训凯
文晓梅
杨金席
张大亮
谷庭宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Zhongjian Engineering Design And Research Institute Co Ltd
Original Assignee
Jiangsu Zhongjian Engineering Design And Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Zhongjian Engineering Design And Research Institute Co Ltd filed Critical Jiangsu Zhongjian Engineering Design And Research Institute Co Ltd
Priority to CN201910307557.2A priority Critical patent/CN110070283A/en
Publication of CN110070283A publication Critical patent/CN110070283A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/21Design, administration or maintenance of databases
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • Economics (AREA)
  • Databases & Information Systems (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Data Mining & Analysis (AREA)
  • General Engineering & Computer Science (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of chemical project safe design management methods, and this method includes S1: the first step carries out project statistics by each program member, and establishment designs a set of Microsoft Excel;S2: classification adjustment disparity items different designs personnel's situation;Beneficial effects of the present invention: it is used as a system to be managed multiple projects itself, design a set of project management, evaluation system, solve the data collection needed in each project complete process, data sharing, data check that data quantization, professional coordination, progress chasing, progress adjustment, quality risk control, project feedback summarize problem.

Description

A kind of chemical project safe design management method
Technical field:
The invention belongs to chemical project security technology area, in particular to a kind of chemical project safe design management method.
Background technique:
Chemical Engineering Design is divided into basic engineering, detailed design.Chemical industry safe design belongs to basic engineering, according to enterprise/design The fundamental technology packet that institute provides makes project according to safety devices design is carried out on the basis of safety evaluation report risk analysis It is able to satisfy the requirement of state's laws, regulation, standard, specification.
Chemical project safe design, working contents include:
1. drawing band control point pid stream journey on the basis of a pair existing technique packet carries out HAZOP assay, SIL deciding grade and level The graph makings such as figure, the layout of equipment, equipment list.
2. technology major design finishes, downstream professional building, structure, plumbing, electrical, instrument are successively tentatively set Meter.
3. safe design content summarizes in pair each professional Preliminary design, text is worked out, retribution urgency management board examines, examines Cha Hou, text, each technical document accordingly modify, are perfect.
Increasingly attention with country to Safe production of chemical industry, chemical project safe design project is increasing, due to Chemical project safe design itself has strongly professional, and safe design is long with respect to the design cycle, while each professional's body is past Toward multiple projects are designed simultaneously, situations such as each profession needs frequent communication and coordination, each profession to be clearly present upstream and downstream design relation, The safe design management of most designing units is more chaotic, and at present most designing institutees to chemical project safe design management, I.e. the quality of project, progress, risk control, summary, wage and salary administration etc. be only limitted to particular leader using existing experience, knowledge into Capable simple, extensive management, management is unable to do what one wishes, and prior art defect is as follows:
1, Project quality management, which is relied on, has project experiences to relevant design personnel, dictates part designing points, no data (typical hazard analysis, exemplary secure design, typical accidents, project situation, module is completed in such as dangerization material data in library Change design), as flow of personnel, experience are different, working efficiency is not high, and project quality fluctuation is larger;
2, project scheduling management by designer scene feed back, each project leader, which urges, to be wanted, can not real-time item into Degree tracking, feedback, adjustment, upstream and downstream professional coordination are easy to disconnect;
3, wages can only be estimated roughly generally using fixed plus deduction, can not accurately consider project cost, can not accurately make Fixed more reasonable wages excitation, employee motivation are unable to fully transfer.
Summary of the invention:
The object of the invention is that a kind of chemical project safe design management method is provided to solve the above-mentioned problems, It solves the problems, such as existing at present.
To solve the above-mentioned problems, the present invention provides a kind of technical solutions:
A kind of chemical project safe design management method, including chemical project safe design management, comprising the following steps:
S1, the first step carry out project statistics by each program member, and establishment designs a set of Microsoft Excel;
S2, the file of each designer is placed on a file by project management member, then creates an EXCEL text Part, with "=[filename .xls] tag name!$ row $ column " call each designer's situation, arrange and sort by A~G, respectively set Meter personnel, school examine personnel's name, project number, want seeking time number of days, past time, project performance, remaining work Make scheduled time, member's wages.
Preferably, the step S1 is specifically included:
S11, project essential information:
Contract situation: contract title, task amount is clear, and job schedule requires etc., specifies the Project design/check/audit Personal expenditures ratio;Project decomposition: each Specialty Design expense accounting is specified in each professional's distribution, progress cooperation;Difficulty or ease point Class: clearly general industry and trade class has the simple class of template, general harmful influence project, especially complex project report expense accounting generally to want It asks, this project accounting situation.
Database input/inquiry/extraction: database input: S12 when project starts, the important information of previous project is existed By column A~H input in Microsoft Excel: project number, project seating position, is related to dangerization material data, emphasis at project name Process names, emphasis storage tank, peril data, exemplary secure facilities design are supervised, it, will be in the project of completion at the end of project The unified management of project management department, biography company;Data query: it is used in EXCEL and inputs name of material, emphasis supervises danger process names, again Point storage tank substance title quickly finds the similar project security risk analysis of this design object by searching for function, safety is set Count situation;Data are extracted: according to the project number inquired, being applied calling the project data for extracting and needing to project management department, be carried out Design.
S13, quality management: personnel's situation: design, examines personnel's title, the same title, expense accounting at school;Quality risk feelings Condition: emphasis supervision hazardous chemical, emphasis supervision technique, emphasis storage tank, emphasis storage situation are filled in item by item;Project difficulty is completed Situation: difficult situation explanation, design, school, the opinion signature for examining personnel, client feedback situation are completed to project;After comprehensively considering Weight assignment is examined to this project complexity and project quality situation.
S14, progress control: real-time progress situation: list A~G is by column input: contract No. of the project wants seeking time number of days, Through past time, project performance, residue work scheduled time;The special performance of project: each profession exchange information and Whether special circumstances illustrate, examine to this project project process performance;This project project process performance is examined, power Reassignment.
S15, cost management: program member's wages calculate: calculating the wages situation of member;Wages in project ratio calculate and Payment: calculating according to project ratio and wages calculation formula is used to pay member's wages.
Preferably, wages calculation formula in the step S15 are as follows: personal expenditures ratio is examined in wages=contract amount * design/school Example * project complexity weight ratio * report quality situation weight ratio * progress performance weight ratio.
Beneficial effects of the present invention:
1. convenient for unified setting permission, process (such as transmitting/receiving file, transmitting, the update, modification) stream of chemical industry safe design Cheng Hua, standardization, transparence, centralized management reduce human factor bring risk.It is basic to realize office workflow automation, together Shi Suoyou operation process recording all has trackability;
2. Database vendors, modularized design, each professional to existing data be not repeated inquiry, editor (such as Corresponding harmful influence title, dangerous process names are searched in input, and relevant design personnel can find related accidents case, material The project situation that matter, exemplary secure designing points, correlated knowledge point are explained, done) improve working efficiency;
3. real-time item, professional's progress queries, project administrator is to project process real-time query and tracking, coordination pair Each profession progress;Each professional designer simultaneously, understands the project process situation in time, obtains upstream and downstream technical document money in time Material, professional problem upstream and downstream feedback;
4. convenient for evaluation, quantization project situation, to project complexity, progress performance, customer evaluation situation etc. into Row quantization marking, and proportionate relationship is formed with wages.
Detailed description of the invention:
Detailed description will be given by the following detailed implementation and drawings by the present invention for ease of explanation,.
Fig. 1 is composition block diagram of the invention;
Fig. 2 is project essential information composition block diagram of the invention;
Fig. 3 is database input/inquiry/extraction composition block diagram of the invention;
Fig. 4 is quality management composition block diagram of the invention;
Fig. 5 is progress control composition block diagram of the invention;
Fig. 6 is cost management composition block diagram of the invention.
Specific embodiment:
As shown in figures 1 to 6, present embodiment uses a kind of following technical scheme: chemical project safe design manager Method, including chemical project safe design management, it is characterised in that: the following steps are included:
S1, the first step carry out project statistics by each program member, and establishment designs a set of Microsoft Excel;
S2, the file of each designer is placed on a file by project management member, then creates an EXCEL text Part, with "=[filename .xls] tag name!$ row $ column " call each designer's situation, arrange and sort by A~G, respectively set Meter personnel, school examine personnel's name, project number, want seeking time number of days, past time, project performance, remaining work Make scheduled time, member's wages.
Wherein, the step S1 is specifically included:
S11, project essential information:
Contract situation: contract title, task amount is clear, and job schedule requires etc., specifies the Project design/check/audit Personal expenditures ratio;
Project decomposition: each Specialty Design expense accounting is specified in each professional's distribution, progress cooperation;
Difficulty or ease classification: clearly general industry and trade class has the simple class of template, general harmful influence project, especially complex project report Expense accounting generally requires, this project accounting situation, management process procedure, relies on personal experience's extensive management for original, Become to monitor in real time, adjust in real time, retrospective precision management mode.
S12, database input/inquiry/extraction:
Database input: when project starts, by the important information of previous project by column A~H input in Microsoft Excel: Project number, project seating position, is related to dangerization material data, emphasis supervision process names, emphasis storage tank, danger at project name Dangerous casualty data, exemplary secure facilities design.At the end of project, the project of completion is uploaded into the unified management of project management department, company;
Data query: with input name of material, emphasis supervision danger process names, emphasis storage tank substance name in EXCEL Claim, the similar project security risk analysis of this design object, safe design situation are quickly found by searching for function;
Data are extracted: according to the project number inquired, being applied calling the project data for extracting and needing to project management department, be carried out Design.
S13, quality management:
Personnel's situation: design, examines personnel's title, the same title, expense accounting at school;
Quality risk situation: emphasis supervision hazardous chemical, emphasis supervision technique, emphasis storage tank, emphasis storehouse are filled in item by item Store up situation;
Project difficulty performance: difficult situation explanation, design, school, the opinion signature for examining personnel, client are completed to project Feedback;
Weight assignment is examined to this project complexity and project quality situation after comprehensively considering, by common harmful influence Data, risk analysis, exemplary secure design, accident case etc. summarize and link and timely update, and improve working efficiency, subtract Few mistake, leakage item.
S14, progress control:
Real-time progress situation: list A~G is by column input: contract No. of the project wants seeking time number of days, past time, Project performance, residue work scheduled time;
The special performance of project: each profession is exchanged information and whether special circumstances illustrate, complete to this project project process It is examined at situation;
This project project process performance is examined, weight assignment, projects, each professional's progress situation have Can real-time tracking, inquiry, coordination, communication, and record traceable.
S15, cost management:
Program member's wages calculate: calculating the wages situation of member;
Wages are calculated and are paid in project ratio: calculating according to project ratio and wages calculation formula is used to pay member's firewood Money quantifies project situation, is allowed to motivate to form adjustable proportionate relationship with wages.
Wherein, wages calculation formula in the step S15 are as follows: personal expenditures ratio * is examined in wages=contract amount * design/school Project complexity weight ratio * report quality situation weight ratio * progress performance weight ratio.
Database, quality management, progress control in this management, cost management, PDCA cyclic process, belong to chemical industry item Mesh safe design difference is implemented aspect and is required, and needs to continuously improve in implementation process perfect.
Beneficial effects of the present invention:
1. convenient for unified setting permission, process (such as transmitting/receiving file, transmitting, the update, modification) stream of chemical industry safe design Cheng Hua, standardization, transparence, centralized management reduce human factor bring risk.It is basic to realize office workflow automation, together Shi Suoyou operation process recording all has trackability;
2. Database vendors, modularized design, each professional to existing data be not repeated inquiry, editor (such as Corresponding harmful influence title, dangerous process names are searched in input, and relevant design personnel can find related accidents case, material The project situation that matter, exemplary secure designing points, correlated knowledge point are explained, done) improve working efficiency;
3. real-time item, professional's progress queries, project administrator is to project process real-time query and tracking, coordination pair Each profession progress;Each professional designer simultaneously, understands the project process situation in time, obtains upstream and downstream technical document money in time Material, professional problem upstream and downstream feedback;
4. convenient for evaluation, quantization project situation, to project complexity, progress performance, customer evaluation situation etc. into Row quantization marking, and proportionate relationship is formed with wages.
The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention, the technology of the industry Personnel are it should be appreciated that the present invention is not limited to the above embodiments, and the above embodiments and description only describe this The principle of invention, without departing from the spirit and scope of the present invention, various changes and improvements may be made to the invention, these changes Change and improvement all fall within the protetion scope of the claimed invention, the claimed scope of the invention by appended claims and its Equivalent thereof.

Claims (3)

1. a kind of chemical project safe design management method, it is characterised in that: the following steps are included:
S1, the first step carry out project statistics by each program member, and establishment designs a set of Microsoft Excel;
S2, the file of each designer is placed on a file by project management member, then creates an EXCEL file, With "=[filename .xls] tag name!$ row $ column " call each designer's situation, arrange and sort by A~G, respectively designer Member, school examine personnel's name, project number, want seeking time number of days, past time, and project performance, residue work is in advance Between timing, member's wages.
2. a kind of chemical project safe design management method according to claim 1, it is characterised in that: the step S1 tool Body includes:
S11, project essential information: contract situation: contract title, task amount is clear, and job schedule requires etc., specifies the project and sets Meter/check/auditor's cost ratio;Project decomposition: each Specialty Design expense is specified in each professional's distribution, progress cooperation Accounting;Difficulty or ease classification: clearly general industry and trade class has the simple class of template, general harmful influence project, especially complex project report expense Accounting generally requires, this project accounting situation;
Database input/inquiry/extraction: database input: S12 when project starts, the important information of previous project is existed By column A~H input in Microsoft Excel: project number, project seating position, is related to dangerization material data, emphasis at project name Process names, emphasis storage tank, peril data, exemplary secure facilities design are supervised, it, will be in the project of completion at the end of project The unified management of project management department, biography company;Data query: it is used in EXCEL and inputs name of material, emphasis supervises danger process names, again Point storage tank substance title quickly finds the similar project security risk analysis of this design object by searching for function, safety is set Count situation;Data are extracted: according to the project number inquired, being applied calling the project data for extracting and needing to project management department, be carried out Design;
S13, quality management: personnel's situation: design, examines personnel's title, the same title, expense accounting at school;Quality risk situation: Emphasis supervision hazardous chemical, emphasis supervision technique, emphasis storage tank, emphasis storage situation are filled in item by item;Project difficulty completes feelings Condition: difficult situation explanation, design, school, the opinion signature for examining personnel, client feedback situation are completed to project;It is right after comprehensively considering This project complexity and project quality situation examine weight assignment;
S14, progress control: real-time progress situation: list A~G is by column input: contract No. of the project wants seeking time number of days, has been subjected to The time gone, project performance, residue work scheduled time;The special performance of project: each profession exchange information and whether Special circumstances explanation, examines this project project process performance;This project project process performance is examined, weight is assigned Value;
S15, cost management: program member's wages calculate: calculating the wages situation of member;Wages are calculated and are given in project ratio It pays: being calculated according to project ratio and wages calculation formula is used to pay member's wages.
3. a kind of chemical project safe design management method according to claim 2, it is characterised in that: the step S15 Middle wages calculation formula are as follows: personal expenditures ratio * project complexity weight ratio * report is examined in wages=contract amount * design/school Quality condition weight ratio * progress performance weight ratio.
CN201910307557.2A 2019-04-17 2019-04-17 A kind of chemical project safe design management method Pending CN110070283A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910307557.2A CN110070283A (en) 2019-04-17 2019-04-17 A kind of chemical project safe design management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910307557.2A CN110070283A (en) 2019-04-17 2019-04-17 A kind of chemical project safe design management method

Publications (1)

Publication Number Publication Date
CN110070283A true CN110070283A (en) 2019-07-30

Family

ID=67367989

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910307557.2A Pending CN110070283A (en) 2019-04-17 2019-04-17 A kind of chemical project safe design management method

Country Status (1)

Country Link
CN (1) CN110070283A (en)

Similar Documents

Publication Publication Date Title
CN108960627A (en) A kind of full Schedule monitoring management system and method based on scientific research project
CN106548324A (en) A kind of IT system O&M service management system
CN106327068A (en) Intelligent LIMS system based on monitoring of marine environment and fishery resources
CN108335041A (en) A kind of control system of business data performance appraisal
CN104408575A (en) Enterprise operation data management system and method
Rackow et al. Green Cockpit: Transparency on energy consumption in manufacturing companies
CN110555675A (en) Method for realizing real-time online supervision
CN114186955A (en) Standardized management system for safety production
CN112200547A (en) Laboratory science data management system
CN110070283A (en) A kind of chemical project safe design management method
CN109360291A (en) A kind of construction machinery equipment inspection service system
CN114445090A (en) Tracking management system for enterprise pollution discharge permission
Aksyonov et al. Development of an automated system for analysis, modeling, and decision-making for metallurgical enterprise
CN113407161A (en) Complex equipment-oriented collaborative research and development management system
CN112269360A (en) Intelligent data analysis system based on alumina production
Abudayyeh et al. The design and implementation of a maintenance information model for rural municipalities
CN102890795A (en) System and method for accounting production working hours of workshop
Hossain et al. Assembly line balancing and sensitivity analysis of a single-model stochastic sewing line using arena simulation modelling.
deSpautz Quantifying the benefits of automation
Yan et al. Promote intelligent manufacturing with lean six sigma management concept
US20020178188A1 (en) Productivity recovery and improvement software
CN115983809B (en) Enterprise office management method and system based on intelligent portal platform
Belousov et al. System Development for Generating Reports on Production Activities on the Platform SAP
RU62720U1 (en) INFORMATION AND ANALYTICAL SYSTEM FOR MONITORING FISHING OBJECTS
Hadi et al. University of Kufa unified laboratories management system using computer application

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190730