CN110059448A - A kind of shield tunneling face Ground surface settlement method considering the deformation of cutterhead Squeezing Ground - Google Patents
A kind of shield tunneling face Ground surface settlement method considering the deformation of cutterhead Squeezing Ground Download PDFInfo
- Publication number
- CN110059448A CN110059448A CN201910427363.6A CN201910427363A CN110059448A CN 110059448 A CN110059448 A CN 110059448A CN 201910427363 A CN201910427363 A CN 201910427363A CN 110059448 A CN110059448 A CN 110059448A
- Authority
- CN
- China
- Prior art keywords
- cutterhead
- shield
- annulus
- spoke
- infinitesimal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- Theoretical Computer Science (AREA)
- Computer Hardware Design (AREA)
- General Physics & Mathematics (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The invention discloses a kind of shield tunneling face Ground surface settlement methods of consideration cutterhead Squeezing Ground deformation, by carrying out model simplification and annulus differential process to shield cutter, soil deformation volume caused by any position soil body extrusion time suffered in the normal tunneling process of shield, extrusion and displacement and cutterhead squeeze in front of cutterhead is able to by boring parameters quantitative expressions such as cutterhead revolving speed, shield tunneling speed.The extrusion deformation as a key factor for influencing ground settlement, it is uneven into casting with shield caused by together with out break Stratum Loss, improve the ability of classical Peck formula ground settlement at excavation face in prediction shield tunneling process.The present invention is suitable for the circular beater plate of any pattern, and implementation process is clearly simple, the precision of prediction that shield tunneling causes ground settlement can be further increased under existing Computational frame, and provide foundation for the Precise control of shield.
Description
Technical field
The invention belongs to shield tunnel project field more particularly to a kind of shield tunnelings for considering the deformation of cutterhead Squeezing Ground
Face Ground surface settlement method.
Background technique
Shield is economical quick thus extensive due to its comparatively safe environmental protection of constructing as a kind of professional tunnel digging equipment
Applied in urban tunnel construction.However, the hydrogeological encountered while shield tunnel fast development and periphery
Environment more sophisticated, accident caused by shield-tunneling construction are commonplace.Wherein, the deformation of earth's surface caused by tunnel excavation is applied as shield
The key problem controlled needed for work is widely noticed for a long time but seldom comes to a conclusion.
It can be three parts from the ground settlement first and last, occurred in shield tunneling process, comprising: (1) when arrival
The deformation of excavation face earth's surface: when excavation face is closer apart from observation point, since excavation face soil body off-load (stress release) makes ground
Sedimentation or support pressure occur for layer and thrust is excessive so that excavation face stratum is swelled, mainly by shield into casting boring parameter
Matching and native storehouse In-pit dumping state cause;(2) shield by when the ground settlement that occurs: refer to since cutterhead until shield tail is logical
Generated sedimentation during crossing observation point, comprising: shield shell generates shearing to the fricting shearing disturbance of soil and becomes during shield driving
Shape, shield rectifies a deviation, turns, kowtowing etc. cause snakelike posture, soil layer disturbance, relaxation after fall to excavate in space stratum caused to be damaged
The pre-large post-small conical design of shield machine of becoming estranged to generate gap between stratum and shield shell;(3) shield tail gap settles: shield tail abjection
Afterwards, synchronous grouting and secondary grouting slurries fail to fill out shrinks full of shield tail gap and the condensation of later period slurries in time, and soil body slump is filled out
It fills gap and causes stratum settlement.In this three parts stratum settlement, straightway shield when passing through generated stratum settlement (2) compared with
It is few;The stratum settlement (3) that shield tail gap generates is affected by formation properties and synchronous grouting level, and filling mud jacking is timely,
Under mud jacking amount abundance or pressure situation appropriate, sedimentation caused by shield tail gap is also limited.In entire tunneling process, shield is arrived
Up to when excavation face cause ground settlement (1) to be the main source and core control object of whole earth's surface deformation.
Ground settlement caused by excavation face front, is mainly derived from two parts: during (A) shield-tunneling construction when arrival
Into casting it is uneven caused by Stratum Loss amount, i.e., as into the Stratum Loss amount for not considering stratum deformation caused by casting;(B) by
The formation volume compression caused by cutterhead squeezes and support pressure is excessive, or since support pressure is too small, reservoir stress release
Caused volume is bulk.
Chinese invention patent 201610707226.4 discloses a kind of earth pressure balanced shield, EPBS Tu Cang into earth's surface caused by casting
Settlement prediction method, the patent establish shield into casting boring parameter and do not consider to determine between the Stratum Loss of stratum deformation
Magnitude relation by that can calculate the Stratum Loss amount of the every driving ring of shield into casting relevant parameter, and is estimated by Peck formula
Ground settlement caused by corresponding Stratum Loss, above-mentioned (A) problem of very good solution.But the patent fails to consider above-mentioned (B)
Partial influence fails to consider the influence that deforms to earth's surface of soil body stereomutation during shield tunneling.
Summary of the invention
The application aims to solve at least one of problems of the prior art.For this purpose, it is an object of the present invention to
A kind of shield tunneling face Ground surface settlement method of consideration cutterhead Squeezing Ground deformation is provided.
In order to solve the above technical problems, the application adopts the following technical scheme that
A kind of shield tunneling face Ground surface settlement method considering the deformation of cutterhead Squeezing Ground, includes the following steps:
(1) cutterhead model foundation;
(2) cutterhead model is radially discrete for a series of sequentially connected annulus infinitesimals;
(3) classification and marking is carried out to annulus infinitesimal
The region that panel or spoke are corresponded on annulus infinitesimal is defined as Pij;PijRepresent jth on i-th of annulus infinitesimal
Block panel or spoke region;The width of jth block panel or spoke region is defined as W on i-th of annulus infinitesimalij;
(4) cutterhead rotates compression time suffered by the soil body of front in weekly during calculating shield tunneling
For cutter head center region, the cutterhead front soil body is by jth block panel or spoke region P on i-th of annulus infinitesimalij
The time t of extrudingijIt is equal to:
For the soil body other than cutter head center region, in front of cutterhead the soil body by jth block panel on i-th of annulus infinitesimal or
Spoke region PijThe time t of extrudingijIt is equal to:
Wherein, w is cutterhead revolving speed, and R is the radius of cutterhead, R1For cutter head center zone radius, r is i-th of annulus infinitesimal
Internal diameter, π is pi;
(5) compression displacement suffered by the soil body of cutterhead front during calculating shield tunneling
For cutter head center region, the cutterhead front soil body is by jth block panel or spoke region P on i-th of annulus infinitesimalij
Maximum compression caused by compressing is displaced dijAre as follows:
For the soil body other than cutter head center region, in front of cutterhead the soil body by jth block panel on i-th of annulus infinitesimal or
Spoke region PijMaximum displacement d caused by compressingijAre as follows:
Wherein, v is shield driving speed;
(6) during calculating shield tunneling, the soil body is because of volume compression amount caused by squeezing in front of cutterhead:
The soil body is by jth block panel or spoke region P on i-th of annulus differential in front of cutterheadijVolume pressure caused by squeezing
Contracting amount calculation formula is as follows:
Volume compression amount caused by then the soil body is squeezed by all panels on i-th of annulus differential or spoke in front of cutterhead is total
It is as follows with calculation formula:
Wherein: dr is the width of annulus infinitesimal;J is the total quantity of i-th annulus differential top panel and spoke;
By calculating soil body volume compression caused by all annulus differential top panels or spoke region extruding in front of cutterhead
The sum of amount, namely volume compression amount caused by annulus differential is integrated in radius, entire cutterhead extrusion soil can be obtained and drawn
The volume compression amount V risenpAre as follows:
(7) total Stratum Loss V caused by shield tunneling is calculatedL;
(8) inverse ground settlement groove width
In conjunction with Stratum Loss value and actual measurement ground settlement value is calculated, pass through formula (8) inverse ground settlement groove width i:
Wherein: SmaxFor earth's surface maximum settlement value;I is ground settlement groove width;
(9) ground settlement occurred at excavation face in shield tunneling process is calculated
When establishing shield lower ring driving by formula (9), it is contemplated that under cutterhead extrusion soil deformation, driving ginseng
Ground surface settlement formula caused by number:
Wherein, x is the horizontal distance on cross section (section vertical with shield driving direction) apart from tunnel central axis,
S (x) is that apart from tunnel, central axis horizontal distance is the ground settlement value of x position on cross section.
Further, Stratum Loss V caused by shield tunnelingL=Vloss+VP, soil body Volume Loss VlossBy the patent No.
201610707226.4 formula (4) in is calculated.
Further, it in a new P. drechsleri, computes repeatedly step (4) to step (9), iteration updates spiral transferring
It send machine to be unearthed the boring parameters such as efficiency and ground settlement groove width, obtains new Ground surface settlement formula.
Further, the principle simplified during cutterhead model foundation are as follows: cutter of the removal other than shield central area,
Retain cutter head panel, spoke and central cutter.
Compared with prior art, the beneficial effects of the present invention are: (1) this method be suitable for any pattern circular knife
Disk;(2) quantitative relationship of cutterhead extrusion soil volume Yu the important boring parameter such as shield driving speed and cutterhead revolving speed is provided,
Further foundation is provided for the Precise control of shield;(3) Stratum Loss amount caused by both having taken into account casting imbalance is provided,
It is contemplated that the Stratum Loss calculation method deformed caused by cutterhead extrusion soil stratum;(4) classical Peck formula is improved to exist
Predict the Ground surface settlement precision occurred at excavation face in shield tunneling process.
In conclusion the present invention is a kind of applied widely, the shield that computational accuracy is high, implementing procedure is clear and simple and practical
Ground surface settlement method at excavation face in structure tunneling process.
Detailed description of the invention
Fig. 1 is the shield cutter rough schematic view;
Fig. 2 is the cutter head center region annulus differential expanded view;
Fig. 3 is the cutter head center with exterior domain annulus differential expanded view;
Fig. 4 is the cutter head center region soil body compression displacement schematic diagram;
Fig. 5 is the cutter head center with exterior domain soil body compression displacement schematic diagram;
Fig. 6 is spoke type shield cutter schematic diagram used in described No. 14 line running tunnels of Beijing Metro;
Fig. 7 is plate spoke shield cutter schematic diagram used in the Tunnel Engineering over strait of the Guangdong.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
Referring to figures 1-4, a kind of shield tunneling face Ground surface settlement method considering the deformation of cutterhead Squeezing Ground, including
Following steps:
Step (1): cutterhead model foundation
As shown in Figure 1, the cutterhead pattern to specific shield engineering project carries out model simplification, cutterhead model is established, is simplified
Principle are as follows: scraper of the removal other than shield central area, hobboing cutter, cutter, the cutters such as imitation-shaped knife retain panel, spoke and
Central cutter (large scale fish tail knife, hobboing cutter etc.).
Step (2): annulus differential is taken to cutterhead model
Circular beater plate is divided into annulus infinitesimal, for each infinitesimal with a thickness of dr, annulus infinitesimal radius is r;If annulus infinitesimal
Width dr is infinitely small, can be approximately length for 2 π r, width is the rectangle infinitesimal of dr after the expansion of infinitesimal annulus;
Step (3): classification and marking is carried out to annulus differential
As shown in Figure 1, being defined as P if annulus infinitesimal corresponding position on cutterhead is panel and spoke region;Each company
Continuous panel or spoke domain is defined as Pij, represent jth block panel or spoke region on i-th of rectangle infinitesimal;Panel or
The width of spoke region is defined as Wij, represent the continuous width of jth block panel or spoke region on i-th of rectangle infinitesimal.
If annulus infinitesimal corresponding position on cutterhead is opening, it is defined as O;Each continuous panel or spoke domain are defined as Oik, generation
Kth block is open on i-th of rectangle infinitesimal of table.
Note: for cutter head center region, it is assumed that large scale center fish tail knife or central hob group can be effectively by surroundings
The soil body is scraped to be open into cutterhead, therefore the annulus differential in cutter head center region is as shown in Fig. 2, cutter head center is micro- with the annulus of exterior domain
Divide as shown in Figure 3.
Step (4): cutterhead rotates compression time suffered by the soil body of front in weekly during calculating shield tunneling
When soil particle is located in front of panel or spoke, cutterhead starts the extruding of soil particle, until soil particle again
Compression terminates when positioned at opening front;When soil particle just enters cutterhead opening in front of spoke or panel, original panel
Or spoke can make soil particle quickly flow the pressure difference occurred rapidly between the extruding force and opening support pressure of soil particle
It buries in storehouse.If shield driving speed is v, soil particle compression speed is equal to shield driving speed v.
For cutter head center region, the soil particle in front of cutterhead at cutter head center r (corresponds to i-th of annulus on cutterhead
Infinitesimal), by jth block panel or spoke region (Pij) squeeze time tijIt is equal to:
Wherein, w is cutterhead revolving speed, and cutter head center zone radius is R1。
For the soil body other than cutter head center region, the soil particle in front of cutterhead at cutter head center r is (on corresponding cutterhead
I-th of annulus infinitesimal), by jth block panel or spoke region (Pij) squeeze time tijIt is equal to:
Step (5): compression displacement suffered by the soil body in front of cutterhead during calculating shield tunneling.When shield is normally tunneled, circle
The amount of compression of the Zhou Qianfang soil body can be indicated that the amount of compression of panel or spoke is as shown in figure intermediate cam shape, opening portion circular arc by Fig. 4
Straight line in corresponding diagram.For cutter head center region, the cutterhead front soil body is by jth block panel or spoke on i-th of annulus infinitesimal
Region (Pij) compress caused maximum compression displacement dijAre as follows:
As shown in figure 5, for the soil body other than cutter head center region, if cutter head center arrangement large scale fish tail knife or rolling
Knife, the cutterhead front soil body is by jth block panel or spoke region (P on i-th of annulus infinitesimalij) compress caused maximum displacement
dijAre as follows:
Step (6): during calculating shield tunneling, the soil body is because of volume compression amount caused by squeezing in front of cutterhead.Cutterhead
Radius is R, then the cutterhead front soil body is by jth block panel or spoke (P on i-th of annulus differentialij) squeeze caused volume pressure
Contracting amount can be calculated by the triangle in figure:
The then volume that the soil body is squeezed by i-th of annulus differential top panel or spoke region in front of cutterhead are as follows:
By calculate volume compression amount caused by the soil body is squeezed by all annulus differential top panels or spoke in front of cutterhead it
With, namely volume compression amount caused by annulus differential is integrated in radius, volume caused by cutterhead extrusion soil can be obtained
Decrement VpAre as follows:
Step (7): Stratum Loss caused by shield tunneling is calculated.According to Chinese invention patent (application number:
201610707226.4, patent name: a kind of earth pressure balanced shield, EPBS Tu Cang is into Ground surface settlement method caused by casting) it calculates
Shield into casting it is uneven caused by soil body Volume Loss be Vloss;If VlossSo that earth's surface has Subsidence trend, it is believed that VlossFor
Just;If VlossSo that earth's surface has protuberance trend, it is believed that VlossIt is negative.Then total Stratum Loss V caused by shield tunnelingLAre as follows:
VL=Vloss+VP (8)
Step (8): inverse ground settlement groove width.In the case where not generating cavity in stratum, caused by shield tunneling
Stratum Loss is equal with earth's surface Stratum Loss.Therefore, corresponding ground settlement can be based on caused by shield tunneling as Peck formula
Total Stratum Loss is VLIt calculates.In conjunction with Stratum Loss value and actual measurement ground settlement value is calculated, pass through formula (9) inverse ground settlement
Groove width i:
Wherein: SmaxFor earth's surface maximum settlement value;I is ground settlement groove width (i.e. ground settlement curve symmetric axis to recurvation
Horizontal distance between point);
Step (9): the ground settlement occurred at excavation face in shield tunneling process is calculated.Shield is established by formula (10)
When the lower ring of structure tunnels, it is contemplated that under cutterhead extrusion soil deformation, Ground surface settlement formula caused by boring parameter:
Wherein, x is the horizontal distance on cross section (section vertical with shield driving direction) apart from tunnel central axis,
S (x) is that apart from tunnel, central axis horizontal distance is the ground settlement value of x position on cross section.
Stratum Loss caused by step (7) described shield tunneling, both included during shield tunneling due into casting not
The Stratum Loss for not including stratum deformation caused by balance, also includes the cubic deformation due to caused by cutterhead extrusion soil.
Step (8) the earth's surface Stratum Loss, refers under not drainage situation, the final settlement that earth's surface is formed after tunnel excavation
Sump volume.
The Ground surface settlement formula occurred at excavation face in shield tunneling process described in step (9), shield is in every pick
Into after a ring, because of formation parameter, buried depth and sediment improvement Parameters variation, calculating need to be re-started according to above-mentioned process, to protect
Card Ground surface settlement formula has degree of precision.
The application is further described below in conjunction with specific embodiment.
Embodiment 1
The present embodiment is illustrated with spoke type shield cutter used in No. 14 line running tunnels of Beijing Metro.
A kind of shield tunneling face Ground surface settlement method considering the deformation of cutterhead Squeezing Ground, includes the following steps:
Step (1): simplify cutterhead model.For the Project Shield cutterhead actual disposition, removal shield central area with
Outer scraper, hobboing cutter, cutter, the cutters such as imitation-shaped knife retain panel, spoke and center large scale fish tail knife, form cutterhead and calculate
Schematic diagram is as shown in Figure 6.
Step (2): annulus differential is taken to cutterhead model.Circular beater plate is divided into annulus infinitesimal, each infinitesimal with a thickness of
Dr, annulus infinitesimal radius are r;If annulus infinitesimal width dr is infinitely small, by infinitesimal annulus expansion after, can be approximately length be 2 π r,
Width is the rectangle infinitesimal of dr.
Step (3): classification and marking is carried out to annulus differential.If annulus infinitesimal on cutterhead corresponding position be panel and
Spoke region is defined as P;Each continuous panel or spoke domain are defined as Pij, represent jth block face on i-th of rectangle infinitesimal
Plate or spoke;The length of panel or spoke is defined as Wij, represent jth block panel or spoke on i-th of rectangle infinitesimal
Continuous length.If annulus infinitesimal corresponding position on cutterhead is opening, it is defined as O;Each continuous panel or spoke domain
It is defined as Oik, represent kth block on i-th of rectangle infinitesimal and be open.
Step (4): during calculating shield tunneling, compression time suffered by the soil body in front of cutterhead.Before cutter head panel and spoke
Necromancer body is unavoidably squeezed in digging process.When soil particle has just been located in front of panel or spoke, cutterhead is to soil particle
Extruding start, until soil particle again be located at opening front when compression terminate;If shield forward speed is v, soil particle compression
Speed is equal to shield forward speed v.If cutterhead revolving speed is w, spoke width perseverance is Ws, cutter head center zone radius is R1, because of cutterhead
Center arrangement large scale fish tail knife, soil particle of the cutter head center region fore at cutter head center r is (i-th on corresponding cutterhead
Annulus infinitesimal), by jth block panel or spoke (Pij) squeeze time tijIt is equal to:
For the soil body other than cutter head center region, the soil particle at cutter head center r (corresponds to i-th of circle on cutterhead
Ring infinitesimal), by jth block panel or spoke (Pij) squeeze time tijIt is equal to:
Wherein, Ws1It is located at R for the radius of annulus infinitesimal1With R2Between when spoke width,
Ws2It is located at R for the radius of annulus infinitesimal2The width of spoke when between cutter radius R.
Step (5): during calculating shield tunneling, compression displacement suffered by the soil body in front of cutterhead.When shield is normally tunneled, because
Cutter head center arranges large scale fish tail knife, and for cutter head center region, the cutterhead front soil body is by jth block on i-th of annulus infinitesimal
Panel or spoke (Pij) compress caused maximum displacement dijAre as follows:
For the soil body other than cutter head center region, in front of cutterhead the soil body by jth block panel on i-th of annulus infinitesimal or
Spoke (Pij) squeeze caused maximum displacement dijAre as follows:
Step (6): during calculating shield tunneling, the soil body is because of volume compression amount caused by squeezing in front of cutterhead.In cutterhead
Heart zone radius is R1, it is R that spoke, which widens position radius,2, cutter radius R.Because cutter head center arranges large scale fish tail knife, then
When shield is normally tunneled, volume compression amount V caused by cutterhead extrusion soilpAre as follows:
Step (7): Stratum Loss caused by shield tunneling is calculated.According to Chinese invention patent (application number:
201610707226.4, patent name: a kind of earth pressure balanced shield, EPBS Tu Cang is into Ground surface settlement method caused by casting) it calculates
Shield into casting it is uneven caused by soil body Volume Loss be Vloss;If VlossSo that earth's surface has Subsidence trend, it is believed that VlossFor
Just;If VlossSo that earth's surface has protuberance trend, it is believed that VlossIt is negative.Then Stratum Loss V caused by shield tunnelingLAre as follows:
VL=Vloss+VP (6)
Step (8): inverse ground settlement groove width.In the case where not generating cavity in stratum, caused by shield tunneling
Stratum Loss is equal with earth's surface Stratum Loss.Therefore, corresponding ground settlement can be based on caused by shield tunneling as Peck formula
Total Stratum Loss is VLIt calculates.In conjunction with Stratum Loss value and actual measurement ground settlement value is calculated, pass through formula (7) inverse ground settlement
Groove width i:
Wherein: SmaxFor earth's surface maximum settlement value;I is ground settlement groove width (i.e. ground settlement curve symmetric axis to recurvation
Horizontal distance between point);
Step (9): the ground settlement occurred at excavation face in shield tunneling process is calculated.It can be established by formula (8)
When the lower ring of shield tunnels, it is contemplated that under cutterhead extrusion soil deformation, Ground surface settlement formula caused by boring parameter:
Wherein, x is the horizontal distance on cross section apart from tunnel central axis, and S (x) is on cross section apart from tunnel center
Axis horizontal distance is the ground settlement value of x position.
Embodiment 2
Plate spoke shield cutter used illustrates when being built with Guangdong Tunnel Engineering over strait.
A kind of shield tunneling face Ground surface settlement method considering the deformation of cutterhead Squeezing Ground, includes the following steps:
Step (1): simplify cutterhead model.For the Project Shield cutterhead actual disposition, removal shield central area with
Outer scraper, hobboing cutter, cutter, the cutters such as imitation-shaped knife retain panel, spoke and cutter head center hobboing cutter, form cutterhead calculation diagram
As shown in Figure 7.
Step (2): annulus infinitesimal is taken to cutterhead, each infinitesimal is with a thickness of dr, and annulus is apart from center of circle r;By infinitesimal annulus exhibition
It opens, is approximately length for 2 π r, width is the rectangle infinitesimal of dr.
Step (3): if annulus infinitesimal corresponding position on cutterhead is panel and spoke region, it is defined as P;It is each continuous
Panel or spoke domain be defined as Pij, represent jth block panel or spoke on i-th of rectangle infinitesimal;Length is defined as Wij,
Represent the continuous length of jth block panel or spoke on i-th of rectangle infinitesimal.If annulus infinitesimal corresponding position on cutterhead
For opening, it is defined as O;Each continuous panel or spoke domain are defined as Oik, represent kth block on i-th of rectangle infinitesimal and be open.
Step (4): the soil body in cutterhead opening front, it is believed that soil pressure is equal to support pressure;In front of cutter head panel and spoke
The soil body is unavoidably squeezed in digging process.When soil particle has just been located in front of panel, compression starts.The speed if shield is advanced
Degree is v, and cutterhead revolving speed is w, and spoke width perseverance is Ws, cutter head center zone radius is R1, before soil particle compression speed is equal to shield
Into speed v;The extrusion time of the cutter head center region soil body is calculated by formula (1).
For cutter head center position with exterior domain, the soil particle at cutter head center r (corresponds to i-th of annulus on cutterhead
Infinitesimal), being divided to by the time that jth block panel or spoke squeeze to be two regions, according to the range of cutter radius, respectively by public affairs
Formula (2) and formula (3) calculate.
Wherein, θ is to fan the corresponding central angle of annular panel as shown in Figure 5.
Step (5): when shield is normally tunneled, for the soil body in cutter head center region, by i-th of annulus infinitesimal on cutterhead,
Maximum displacement d caused by jth block panel or spoke squeezeijAre as follows:
For cutter head center position with exterior domain, the soil particle at cutter head center r (corresponds to i-th of annulus on cutterhead
Infinitesimal), it can be calculated by the displacement point that jth block panel or spoke squeeze for two parts, according to the range of cutter radius, press respectively
Formula (5) and formula (6) calculate:
Step (6): during calculating shield tunneling, the soil body is because of volume compression amount caused by squeezing in front of cutterhead.If cutterhead
Radius be R, when shield is normally tunneled, volume compression amount V caused by cutterhead extrusion soilpAre as follows:
Step (7): Stratum Loss caused by shield tunneling is calculated.According to Chinese invention patent (application number:
201610707226.4, patent name: a kind of earth pressure balanced shield, EPBS Tu Cang is into Ground surface settlement method caused by casting) it calculates
Shield into casting it is uneven caused by soil body Volume Loss be Vloss;If VlossSo that earth's surface has Subsidence trend, it is believed that VlossFor
Just;If VlossSo that earth's surface has protuberance trend, it is believed that VlossIt is negative.Total Stratum Loss V caused by shield tunneling can be calculatedLAre as follows:
VL=Vloss+VP (8)
Step (8): inverse ground settlement groove width.In the case where not generating cavity in stratum, caused by shield tunneling
Stratum Loss is equal with earth's surface Stratum Loss.Therefore, corresponding ground settlement can be based on caused by shield tunneling as Peck formula
Total Stratum Loss is VLIt calculates.In conjunction with Stratum Loss value and actual measurement ground settlement value is calculated, pass through formula (9) inverse ground settlement
Groove width i:
Wherein: SmaxFor earth's surface maximum settlement value;I is ground settlement groove width (i.e. ground settlement curve symmetric axis to recurvation
Horizontal distance between point);
Step (9): the ground settlement occurred at excavation face in shield tunneling process is calculated.It can be established by formula (10)
When the lower ring of shield tunnels, it is contemplated that under cutterhead extrusion soil deformation, Ground surface settlement formula caused by boring parameter:
Wherein, x is the horizontal distance on cross section apart from tunnel central axis, and S (x) is on cross section apart from tunnel center
Axis horizontal distance is the ground settlement value of x position.
Above-described embodiment is only to clearly demonstrate examples made by the present invention, rather than the restriction to embodiment.For
For those of ordinary skill in the art, other various forms of variations or change can also be made on the basis of the above description
It is dynamic.Here without can not be also exhaustive to all embodiments.And the obvious variation or change thus amplified out
It is dynamic to be still in the protection scope of this invention.
Claims (4)
1. a kind of shield tunneling face Ground surface settlement method for considering the deformation of cutterhead Squeezing Ground, which is characterized in that including such as
Lower step:
(1) cutterhead model foundation
(2) cutterhead model is radially discrete for a series of sequentially connected annulus infinitesimals
(3) classification and marking is carried out to annulus infinitesimal
The region that panel or spoke are corresponded on annulus infinitesimal is defined as Pij;PijRepresent jth block panel on i-th of annulus infinitesimal
Or spoke region;The width of jth block panel or spoke region is defined as W on i-th of annulus infinitesimalij;
(4) cutterhead rotates compression time suffered by the soil body of front in weekly during calculating shield tunneling
For cutter head center region, the cutterhead front soil body is by jth block panel or spoke region P on i-th of annulus infinitesimalijIt squeezes
Time tijIt is equal to:
For the soil body other than cutter head center region, the cutterhead front soil body is by jth block panel or spoke on i-th of annulus infinitesimal
Region PijThe time t of extrudingijIt is equal to:
Wherein, w is cutterhead revolving speed, and R is the radius of cutterhead, R1For cutter head center zone radius, r is the interior of i-th of annulus infinitesimal
Diameter, WijThe width of jth block panel or spoke on i-th of annulus infinitesimal is represented, π is pi;
(5) compression displacement suffered by the soil body of cutterhead front during calculating shield tunneling
For cutter head center region, the cutterhead front soil body is by jth block panel or spoke region P on i-th of annulus infinitesimalijCompression
Caused maximum compression is displaced dijAre as follows:
For the soil body other than cutter head center region, the cutterhead front soil body is by jth block panel or spoke on i-th of annulus infinitesimal
Region PijMaximum displacement d caused by compressingijAre as follows:
Wherein, v is shield driving speed;
(6) during calculating shield tunneling, the soil body is because of volume compression amount caused by squeezing in front of cutterhead
The soil body is by jth block panel or spoke region P on i-th of annulus differential in front of cutterheadijVolume compression amount caused by squeezing
Calculation formula is as follows:
Volume compression amount caused by then the soil body is squeezed by all panels on i-th of annulus differential or spoke region in front of cutterhead is total
It is as follows with calculation formula:
Wherein: dr is the width of annulus infinitesimal;J is the total quantity of i-th annulus differential top panel and spoke;
By calculate volume compression amount caused by the soil body is squeezed by all annulus differential top panels or spoke region in front of cutterhead it
With, namely volume compression amount caused by annulus differential is integrated in radius, caused by entire cutterhead extrusion soil can be obtained
Volume compression amount VpAre as follows:
(7) total Stratum Loss V caused by shield tunneling is calculatedL=Vloss+VP, VlossFor soil body Volume Loss;
(8) inverse ground settlement groove width
In conjunction with Stratum Loss value and actual measurement ground settlement value is calculated, pass through formula (8) inverse ground settlement groove width i:
Wherein: SmaxFor earth's surface maximum settlement value;I is ground settlement groove width;
(9) ground settlement occurred at excavation face in shield tunneling process is calculated
When establishing shield lower ring driving by formula (9), it is contemplated that under cutterhead extrusion soil deformation, boring parameter draws
The Ground surface settlement formula risen:
Wherein, x is horizontal distance apart from tunnel central axis on the section vertical with shield driving direction, and S (x) is and shield
On the vertical cross section of tunneling direction apart from tunnel central axis horizontal distance be x position ground settlement value.
2. prediction technique according to claim 1, which is characterized in that soil body Volume Loss VlossBy the patent No.
201610707226.4 formula (4) in is calculated.
3. prediction technique according to claim 2, it is characterised in that: in a new P. drechsleri, according to real-time
Boring parameter repeats above-mentioned calculating step (4) and arrives step (9), obtains new Ground surface settlement formula.
4. prediction technique according to claim 1, it is characterised in that: the principle simplified during cutterhead model foundation are as follows:
The cutter other than shield central area is removed, cutter head panel, spoke and central cutter are retained.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910427363.6A CN110059448B (en) | 2019-05-22 | 2019-05-22 | Shield excavation surface settlement prediction method considering cutter head extrusion stratum deformation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910427363.6A CN110059448B (en) | 2019-05-22 | 2019-05-22 | Shield excavation surface settlement prediction method considering cutter head extrusion stratum deformation |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110059448A true CN110059448A (en) | 2019-07-26 |
CN110059448B CN110059448B (en) | 2021-08-27 |
Family
ID=67324051
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910427363.6A Active CN110059448B (en) | 2019-05-22 | 2019-05-22 | Shield excavation surface settlement prediction method considering cutter head extrusion stratum deformation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110059448B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112379082A (en) * | 2020-11-13 | 2021-02-19 | 中铁二十局集团有限公司 | Method for determining influence factors of shield construction surface deformation based on MIC |
CN114236092A (en) * | 2021-11-11 | 2022-03-25 | 北京交通大学 | Tunnel excavation face stability experiment equipment and method considering shield cutter head influence |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6082930A (en) * | 1997-11-27 | 2000-07-04 | Obayashi Corporation | Shield driving machine |
CN106126775A (en) * | 2016-06-13 | 2016-11-16 | 暨南大学 | Method is analyzed in the land movement that double track tunnel shield-tunneling construction causes |
CN106295057A (en) * | 2016-08-23 | 2017-01-04 | 中南大学 | A kind of earth pressure balanced shield, EPBS Tu Cang enters the Ground surface settlement method that casting causes |
CN106934251A (en) * | 2017-04-25 | 2017-07-07 | 浙江大学城市学院 | A kind of calculation of ground surface settlement method in class rectangle shield tunnel construction |
-
2019
- 2019-05-22 CN CN201910427363.6A patent/CN110059448B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6082930A (en) * | 1997-11-27 | 2000-07-04 | Obayashi Corporation | Shield driving machine |
CN106126775A (en) * | 2016-06-13 | 2016-11-16 | 暨南大学 | Method is analyzed in the land movement that double track tunnel shield-tunneling construction causes |
CN106295057A (en) * | 2016-08-23 | 2017-01-04 | 中南大学 | A kind of earth pressure balanced shield, EPBS Tu Cang enters the Ground surface settlement method that casting causes |
CN106934251A (en) * | 2017-04-25 | 2017-07-07 | 浙江大学城市学院 | A kind of calculation of ground surface settlement method in class rectangle shield tunnel construction |
Non-Patent Citations (1)
Title |
---|
瞿同明 等: "基于离散元分析盾构动态掘进引起的无粘性地层主应力特征", 《中南大学学报(自然科学版)》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112379082A (en) * | 2020-11-13 | 2021-02-19 | 中铁二十局集团有限公司 | Method for determining influence factors of shield construction surface deformation based on MIC |
CN112379082B (en) * | 2020-11-13 | 2022-09-13 | 中铁二十局集团有限公司 | MIC-based method for determining influence factors of shield construction surface deformation |
CN114236092A (en) * | 2021-11-11 | 2022-03-25 | 北京交通大学 | Tunnel excavation face stability experiment equipment and method considering shield cutter head influence |
Also Published As
Publication number | Publication date |
---|---|
CN110059448B (en) | 2021-08-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103924602B (en) | Deep Thick Soft Ground foundation ditch construction method | |
CN108560541A (en) | A kind of full casing follow-up scar drilling construction method of churning driven | |
CN102561404B (en) | Steel reinforced concrete column type joint and construction method of underground diaphragm wall using same | |
CN102852121B (en) | Artificial composite foundation for building clay core rock-fill dam on deep overburden and construction method for artificial composite foundation | |
CN107590357A (en) | A kind of different construction stage Tunnel Stabilities sentence method for distinguishing | |
CN110059448A (en) | A kind of shield tunneling face Ground surface settlement method considering the deformation of cutterhead Squeezing Ground | |
CN210086275U (en) | Double-wall hollow open caisson foundation | |
CN105625293A (en) | Dissolution rock strong-development construction site filling-type geological processing structure and construction method thereof | |
CN110110489A (en) | A kind of lithostratigraphy shield tunnel pressure from surrounding rock calculation method | |
CN106096162A (en) | A kind of method determining shield support pressure and mathematical model thereof and construction method | |
CN203834468U (en) | Internal expansion type miniature concrete pile | |
CN107313430A (en) | The deep big foundation pit subregion construction method of three face Nearby Structures | |
CN202559363U (en) | Foundation pit supporting structure for underground diaphragm wall with steel structure | |
CN105200994A (en) | Construction method for reserved shield crossing composite foundation pit support device | |
CN106703059A (en) | Construction method of cross-shaped pull trough of open caisson | |
CN109469066A (en) | Earthmoving machinery combines excavation construction method and system with hydraulic tunneling boring solid | |
CN104727325B (en) | A kind of method of construction of polder sea wall | |
CN208293573U (en) | A kind of fixed frame can be used for different-diameter steel pile casting | |
CN107794927B (en) | Deep foundation pit earthwork excavation method with hard rock geology | |
CN105672334B (en) | Sectional type roadbed water retaining construction method for low-lying terrain area by adopting water retaining plates | |
CN105625435B (en) | Sea product island multi-section, multi-level special-shaped equipment deep basal pit quick molding method | |
CN110390140B (en) | Method for calculating stratum settlement of existing line penetrating through double-hole tunnel | |
CN204753671U (en) | Power shovel is used to soil property irrigation canals and ditches excavation | |
CN210597398U (en) | Dog-ear type two-phase underground continuous wall cold joint waterproof construction | |
CN209429054U (en) | Seepage prevention of dam founda structure in ultra-deep thick-covering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |