CN110056941A - A kind of gas furnace heating project intelligent management control method - Google Patents
A kind of gas furnace heating project intelligent management control method Download PDFInfo
- Publication number
- CN110056941A CN110056941A CN201910312709.8A CN201910312709A CN110056941A CN 110056941 A CN110056941 A CN 110056941A CN 201910312709 A CN201910312709 A CN 201910312709A CN 110056941 A CN110056941 A CN 110056941A
- Authority
- CN
- China
- Prior art keywords
- gas furnace
- curve
- project
- intelligent management
- control method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24D—DOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
- F24D19/00—Details
- F24D19/10—Arrangement or mounting of control or safety devices
- F24D19/1006—Arrangement or mounting of control or safety devices for water heating systems
- F24D19/1009—Arrangement or mounting of control or safety devices for water heating systems for central heating
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24H—FLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
- F24H9/00—Details
- F24H9/20—Arrangement or mounting of control or safety devices
- F24H9/2007—Arrangement or mounting of control or safety devices for water heaters
- F24H9/2035—Arrangement or mounting of control or safety devices for water heaters using fluid fuel
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Regulation And Control Of Combustion (AREA)
Abstract
The present invention relates to a kind of gas furnace heating project intelligent management control methods, comprising the following steps: control unit collection site parameter is sent to cloud;Centralized control center receives on-site parameters by cloud, and monitoring information is parsed and stored according to on-site parameters, establishes operation working curve;Establish project demands curve;Centralized control center sends work order to control unit according to on-site parameters and project demands curve negotiating cloud, the present invention is that gas furnace heating project is carried out centralized intelligence management using technology of Internet of things, user's heating system temperature is monitored and controlled automatically, it can guarantee that user's room temperature fluctuates within the set range well, not only save a large amount of man power and material, also improve the precision of the degree of automation and control, centralized control center, which realizes, monitors the unattended collection medium-long range of a large amount of heating projects, intelligent dynamic regulation, the safe operation and energy conservation of project are realized by automatic control technology and intelligent algorithm.
Description
Technical field
The present invention relates to for thermal control system field more particularly to a kind of gas furnace heating project intelligent management controlling party
Method.
Background technique
In the system of central heating, main for the control of entire heat supplying process is exactly to be opened up by the adjusting of temperature
Existing, the determinant of temperature includes many kinds, and most important one is exactly heat factor, for temperature control, control
The difficulty of system is larger, it is possible to create influence factor it is more, link is also relative complex, and the required control period is also longer.?
A series of problems, such as there are percentage of water loss height, thermal losses for the heating network of China's majority thermal substation greatly, infiltration, automatic regulating system
Controlling extent is not high, adjusts level and falls behind relatively, in control still by the way of manual adjustment valve, artificial recharge, automatically
Change is not horizontal high, and secondary pipe network water pressure difference changes greatly, and system operation has very big waste.With the development of science and technology
With the raising of environmental requirement, central heating industry is further to improve heating effect, improves heat supply efficiency, realizes that computer is automatic
Monitoring is the inexorable trend of development.
Summary of the invention
The technical problem to be solved by the present invention is to overcome the deficiencies in the prior art, a kind of gas furnace heat supply is provided
Project intelligent management control method.
The present invention is to be achieved by the following technical programs:
A kind of gas furnace heating project intelligent management control method, which comprises the following steps: control unit
Collection site parameter is sent to cloud;Centralized control center receives on-site parameters by cloud, is parsed according to on-site parameters and stores prison
Information is controlled, operation working curve is established;Establish project demands curve;Centralized control center is logical according to on-site parameters and project demands curve
It crosses cloud and sends work order to control unit.
According to the above technical scheme, it is preferable that described control unit includes PLC module and expansion module.
According to the above technical scheme, it is preferable that the on-site parameters include combustion gas furnace operating state, gas furnace operation ginseng
Number, gas furnace combustion state, gas furnace alarm module number, leaving water temperature, return water temperature, water pump state and valve state.
According to the above technical scheme, it is preferable that the monitoring information includes running state data, control feedback information, accuses
Alert data and manual operation information.
According to the above technical scheme, it is preferable that the centralized control center includes mobile phone app and webpage client.
According to the above technical scheme, it is preferable that the work order includes that gas stove switch, gas furnace leaving water temperature are set
It sets, the setting of gas furnace backwater temperature difference, water pump start and stop and valve start and stop.
According to the above technical scheme, it is preferable that further include: control unit acquires outdoor temperature, establishes environment temperature curve;
According to operation working curve and environment temperature curve, day controlling curve is made;Centralized control center sends work according to day controlling curve
Instruction.
The beneficial effects of the present invention are:
The present invention is that gas furnace heating project is carried out centralized intelligence management using technology of Internet of things, to user's heat supply system
System temperature is monitored and controlled automatically, can guarantee that user's room temperature fluctuates within the set range well, is not only saved a large amount of
Man power and material, also improve the precision of the degree of automation and control, centralized control center realize to a large amount of heating projects nobody
Collection medium-long range on duty monitoring, intelligent dynamic regulation, pass through automatic control technology and intelligent algorithm realizes the safety of project
Operation and energy conservation.
Detailed description of the invention
Fig. 1 is course of work schematic diagram of the invention.
Specific embodiment
In order to make those skilled in the art more fully understand technical solution of the present invention, with reference to the accompanying drawing and most
The present invention is described in further detail for good embodiment.
As shown, the present invention is the following steps are included: control unit collection site parameter is sent to cloud;Centralized control center is logical
It crosses cloud and receives on-site parameters, monitoring information is parsed and stored according to on-site parameters, establish operation working curve;Establishing project needs
Curve is sought, mathematics, physics and chemistry management, the in detail supply-demand curve to not same date mainly are carried out to the heat demand period of project, establish day
The project demands curve of the different demands features such as normal demand curve, festivals or holidays demand curve, boarding system, non-residential system;In collection control
The heart sends work order to control unit according to on-site parameters and project demands curve negotiating cloud.The present invention is to utilize Internet of Things
Gas furnace heating project is carried out centralized intelligence management by technology, and user's heating system temperature is monitored and controlled automatically,
It can guarantee that user's room temperature fluctuates within the set range, not only saves a large amount of man power and material well, also improve automatic
Change degree and the precision of control, centralized control center realize that the monitoring of unattended collection medium-long range, intelligence to a large amount of heating projects are dynamic
The safe operation and energy conservation of project are realized in state regulation by automatic control technology and intelligent algorithm.
According to above-described embodiment, it is preferable that described control unit includes PLC module and expansion module, general PLC module packet
Include power module, CPU and I/O module.Due to relatively more, the PLC module I/O mould of demand for control points of control unit in this example
Block is inadequate, it is necessary to increase expansion module, and expansion module is not integrated into above PLC module, to meet adopting for control unit
Collection and control require.
According to above-described embodiment, it is preferable that the on-site parameters include combustion gas furnace operating state, gas furnace operating parameter,
Gas furnace combustion state, gas furnace alarm module number, leaving water temperature, return water temperature, water pump state and valve state, control unit
It is realized and is connected to the network by 4G Internet of Things network interface card, by MQTT message server, the medium as intercommunication joins scene for centre
Number is sent to cloud, and cloud is responsible for storing data receiver, and the operation for project monitoring, project operation state analysis and project is joined
Number amendment is realized and is monitored to the unattended collection medium-long range of a large amount of heating projects.
According to above-described embodiment, it is preferable that the monitoring information includes running state data, control feedback information, alarm
Data and manual operation information, in the process of running, by 4G network and the MQTT communication server, on-site parameters upload to cloud
End after cloud receives data, decodes, parses project operation status data, control feedback information, alarm data respectively
With manual operation information etc., it is ensured that system fault diagnosis, robot control system(RCS) reliability and in terms of
It improves.
According to above-described embodiment, it is preferable that the centralized control center includes mobile phone app and webpage client, passes through mobile phone app
Or webpage client is realized and is monitored to the unattended collection medium-long ranges of a large amount of heating projects, it is convenient to user's heating system temperature into
Row is automatic to be monitored and controlled.
According to above-described embodiment, it is preferable that the work order include gas stove switch, gas furnace leaving water temperature setting,
The setting of gas furnace backwater temperature difference, water pump start and stop and valve start and stop, the present invention in automated system, by work order with
Heat is controlled, to further realize the control for temperature, centralized control center is according to on-site parameters and project need in this example
Curve is sought, work order is sent for control unit, is adjusted according to actual thermal change situation, to reach temperature control
Purpose.
According to above-described embodiment, it is preferable that further include: control unit acquires outdoor temperature, establishes environment temperature curve;Root
According to operation working curve and environment temperature curve, day controlling curve is made;Centralized control center sends work according to day controlling curve and refers to
It enables, using meteorological and heating power big data in this example, is fitted the regression relation of outdoor temperature and heating measurement, utilizes regression relation
It predicts the heating index under current outdoor temperature, demand heat is calculated according to heating index, heat and heat source instruct flow according to demand
Range determines the practical heating load of current heat source, is then modified by once confession/return water feedback information to heat source heating index,
Realize the practical automatic control for thermal output;In addition to this, in this example can also according to primary confession/return water temperature for thermal output,
Secondary confession/return water temperature is calculated, using the electric control valve of heat exchange station output end, the control valve amplitude of accommodation controls heating load,
Then secondary network circulating pump variable frequency adjustment is controlled, changes secondary water-supply flow, so that supply water temperature be made to reach theoretical calculation temperature;
Room temperature is detected simultaneously, by the acquisition to room temperature, system corrects heating coolant-temperature gage automatically, and room temperature is made to reach room
Interior design temperature value.
The present invention is that gas furnace heating project is carried out centralized intelligence management using technology of Internet of things, to user's heat supply system
System temperature is monitored and controlled automatically, can guarantee that user's room temperature fluctuates within the set range well, is not only saved a large amount of
Man power and material, also improve the precision of the degree of automation and control, centralized control center realize to a large amount of heating projects nobody
Collection medium-long range on duty monitoring, intelligent dynamic regulation, pass through automatic control technology and intelligent algorithm realizes the safety of project
Operation and energy conservation.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered
It is considered as protection scope of the present invention.
Claims (7)
1. a kind of gas furnace heating project intelligent management control method, which comprises the following steps:
A. control unit collection site parameter is sent to cloud;
B. centralized control center receives on-site parameters by cloud, and monitoring information is parsed and stored according to on-site parameters, establishes operation work
Make curve;
C. project demands curve is established;
D. centralized control center sends work order to control unit according to on-site parameters and project demands curve negotiating cloud.
2. a kind of gas furnace heating project intelligent management control method according to claim 1, which is characterized in that the control
Unit processed includes PLC module and expansion module.
3. a kind of gas furnace heating project intelligent management control method according to claim 2, which is characterized in that described existing
Field parameters include combustion gas furnace operating state, gas furnace operating parameter, gas furnace combustion state, gas furnace alarm module number, water outlet
Temperature, return water temperature, water pump state and valve state.
4. a kind of gas furnace heating project intelligent management control method according to claim 3, which is characterized in that the prison
Control information includes running state data, control feedback information, alarm data and manual operation information.
5. a kind of gas furnace heating project intelligent management control method according to claim 4, which is characterized in that the collection
Control center includes mobile phone app and webpage client.
6. a kind of gas furnace heating project intelligent management control method according to claim 5, which is characterized in that the work
Making instruction includes that gas stove switch, the setting of gas furnace leaving water temperature, the setting of gas furnace backwater temperature difference, water pump start and stop and valve open
Stop.
7. according to claim 1 to any one of 6 a kind of gas furnace heating project intelligent management control method,
It is characterized in that, further includes: control unit acquires outdoor temperature, establishes environment temperature curve;According to operation working curve and environment
Temperature curve makes day controlling curve;Centralized control center sends work order according to day controlling curve.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910312709.8A CN110056941A (en) | 2019-04-18 | 2019-04-18 | A kind of gas furnace heating project intelligent management control method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910312709.8A CN110056941A (en) | 2019-04-18 | 2019-04-18 | A kind of gas furnace heating project intelligent management control method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110056941A true CN110056941A (en) | 2019-07-26 |
Family
ID=67319524
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910312709.8A Pending CN110056941A (en) | 2019-04-18 | 2019-04-18 | A kind of gas furnace heating project intelligent management control method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110056941A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111006302A (en) * | 2019-11-29 | 2020-04-14 | 大唐东北电力试验研究院有限公司 | Secondary network intelligent regulation system based on room temperature monitoring |
CN113947308A (en) * | 2021-10-19 | 2022-01-18 | 山西英泰立达科技有限公司 | Central heating whole-network energy-saving consumption-reducing management and control system based on user demands |
CN115065710A (en) * | 2022-04-29 | 2022-09-16 | 燕山大学 | Heating furnace wisdom control by temperature change PC end and remote cloud system of observing and controling of removal end |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105180247A (en) * | 2015-08-26 | 2015-12-23 | 朱杰 | Central heating system and method with heat accumulation peak regulation function |
CN105588179A (en) * | 2016-02-15 | 2016-05-18 | 中国石化集团胜利石油管理局热电联供中心 | Heat supply network control loop based on fuzzy PID algorithm |
CN105783078A (en) * | 2016-04-14 | 2016-07-20 | 范旭强 | Heat energy area heating control system and method |
CN108679703A (en) * | 2018-05-24 | 2018-10-19 | 合肥顺昌分布式能源综合应用技术有限公司 | A kind of same space-heating system based on systems of distributed heating systems |
CN109373441A (en) * | 2018-12-20 | 2019-02-22 | 普瑞森能源科技(北京)股份有限公司 | Heat supply network energy management system and its processing method |
-
2019
- 2019-04-18 CN CN201910312709.8A patent/CN110056941A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105180247A (en) * | 2015-08-26 | 2015-12-23 | 朱杰 | Central heating system and method with heat accumulation peak regulation function |
CN105588179A (en) * | 2016-02-15 | 2016-05-18 | 中国石化集团胜利石油管理局热电联供中心 | Heat supply network control loop based on fuzzy PID algorithm |
CN105783078A (en) * | 2016-04-14 | 2016-07-20 | 范旭强 | Heat energy area heating control system and method |
CN108679703A (en) * | 2018-05-24 | 2018-10-19 | 合肥顺昌分布式能源综合应用技术有限公司 | A kind of same space-heating system based on systems of distributed heating systems |
CN109373441A (en) * | 2018-12-20 | 2019-02-22 | 普瑞森能源科技(北京)股份有限公司 | Heat supply network energy management system and its processing method |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111006302A (en) * | 2019-11-29 | 2020-04-14 | 大唐东北电力试验研究院有限公司 | Secondary network intelligent regulation system based on room temperature monitoring |
CN113947308A (en) * | 2021-10-19 | 2022-01-18 | 山西英泰立达科技有限公司 | Central heating whole-network energy-saving consumption-reducing management and control system based on user demands |
CN115065710A (en) * | 2022-04-29 | 2022-09-16 | 燕山大学 | Heating furnace wisdom control by temperature change PC end and remote cloud system of observing and controling of removal end |
CN115065710B (en) * | 2022-04-29 | 2023-07-25 | 燕山大学 | Intelligent temperature control PC end and mobile end remote cloud measurement and control system of heating furnace |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110056941A (en) | A kind of gas furnace heating project intelligent management control method | |
CN205276388U (en) | Variable -frequency and constant -pressure water supply system | |
CN103453580B (en) | Heat exchange station integrated intelligent control method | |
CN104613660A (en) | Intelligent remote control system for solar water heater | |
CN104964397A (en) | Non-intelligent air conditioning energy saving monitoring method and system of internet of things | |
CN102777974A (en) | Automatic adjustment control system for centralized heating | |
CN102916477B (en) | Multifunctional intelligent accumulator discharge device compatible with multiple voltage grades | |
CN203310003U (en) | Heat exchange station of heat supply system | |
CN104949569A (en) | Efficient energy-saving intelligent control system of heat exchanger unit | |
CN102882276A (en) | Energy efficiency monitoring method based on demand response | |
CN114134955B (en) | Ad hoc network and pressure management system and water pressure management method of self-powered water supply network | |
CN109405059B (en) | Primary pipe network dynamic load intelligent pressure difference regulating and energy saving regulating and controlling system and regulating and controlling method | |
CN213300222U (en) | Intelligent control system of heat exchange station | |
CN209181068U (en) | Energy saving regulator control system of pipe network dynamic load intelligent pressure regulating difference | |
CN208859715U (en) | A kind of heat station system with frequency converter | |
CN110593355A (en) | Water supply energy consumption reduction method based on pressure control model and PLC | |
CN215769462U (en) | Electrode boiler control system based on artificial intelligence | |
CN204611940U (en) | Heat supply secondary network supply water temperature regulation device | |
CN210425637U (en) | Distributed energy storage type cold and hot combined supply three-end integrated intelligent system | |
CN110535188B (en) | Automatic active load adjustment method and system for cascade power station group | |
CN210952495U (en) | Heat exchanger | |
CN203010761U (en) | Heating and energy-saving control system for central heating public buildings | |
CN113847643A (en) | Building heat exchange unit regulation and control method and system utilizing primary side surplus resource pressure head | |
CN208205474U (en) | A kind of solar water heater energy management platform of wireless terminal | |
CN203453027U (en) | Safe intelligent control system for air compressors |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190726 |