CN110056402A - Steam surplus energy utility for coal-fired thermal power unit power peak regulation couples extraction for heat supply system and adjusting method - Google Patents

Steam surplus energy utility for coal-fired thermal power unit power peak regulation couples extraction for heat supply system and adjusting method Download PDF

Info

Publication number
CN110056402A
CN110056402A CN201910229910.XA CN201910229910A CN110056402A CN 110056402 A CN110056402 A CN 110056402A CN 201910229910 A CN201910229910 A CN 201910229910A CN 110056402 A CN110056402 A CN 110056402A
Authority
CN
China
Prior art keywords
steam
pipe
pressure
extraction
heat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910229910.XA
Other languages
Chinese (zh)
Other versions
CN110056402B (en
Inventor
高新勇
常浩
何晓红
李成磊
夏明�
洪纯珩
黄平平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huadian Electric Power Research Institute Co Ltd
Original Assignee
Huadian Electric Power Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huadian Electric Power Research Institute Co Ltd filed Critical Huadian Electric Power Research Institute Co Ltd
Priority to CN201910229910.XA priority Critical patent/CN110056402B/en
Publication of CN110056402A publication Critical patent/CN110056402A/en
Application granted granted Critical
Publication of CN110056402B publication Critical patent/CN110056402B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01KSTEAM ENGINE PLANTS; STEAM ACCUMULATORS; ENGINE PLANTS NOT OTHERWISE PROVIDED FOR; ENGINES USING SPECIAL WORKING FLUIDS OR CYCLES
    • F01K7/00Steam engine plants characterised by the use of specific types of engine; Plants or engines characterised by their use of special steam systems, cycles or processes; Control means specially adapted for such systems, cycles or processes; Use of withdrawn or exhaust steam for feed-water heating
    • F01K7/34Steam engine plants characterised by the use of specific types of engine; Plants or engines characterised by their use of special steam systems, cycles or processes; Control means specially adapted for such systems, cycles or processes; Use of withdrawn or exhaust steam for feed-water heating the engines being of extraction or non-condensing type; Use of steam for feed-water heating
    • F01K7/38Steam engine plants characterised by the use of specific types of engine; Plants or engines characterised by their use of special steam systems, cycles or processes; Control means specially adapted for such systems, cycles or processes; Use of withdrawn or exhaust steam for feed-water heating the engines being of extraction or non-condensing type; Use of steam for feed-water heating the engines being of turbine type
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01KSTEAM ENGINE PLANTS; STEAM ACCUMULATORS; ENGINE PLANTS NOT OTHERWISE PROVIDED FOR; ENGINES USING SPECIAL WORKING FLUIDS OR CYCLES
    • F01K13/00General layout or general methods of operation of complete plants
    • F01K13/02Controlling, e.g. stopping or starting
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01KSTEAM ENGINE PLANTS; STEAM ACCUMULATORS; ENGINE PLANTS NOT OTHERWISE PROVIDED FOR; ENGINES USING SPECIAL WORKING FLUIDS OR CYCLES
    • F01K17/00Using steam or condensate extracted or exhausted from steam engine plant
    • F01K17/02Using steam or condensate extracted or exhausted from steam engine plant for heating purposes, e.g. industrial, domestic
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01KSTEAM ENGINE PLANTS; STEAM ACCUMULATORS; ENGINE PLANTS NOT OTHERWISE PROVIDED FOR; ENGINES USING SPECIAL WORKING FLUIDS OR CYCLES
    • F01K7/00Steam engine plants characterised by the use of specific types of engine; Plants or engines characterised by their use of special steam systems, cycles or processes; Control means specially adapted for such systems, cycles or processes; Use of withdrawn or exhaust steam for feed-water heating
    • F01K7/34Steam engine plants characterised by the use of specific types of engine; Plants or engines characterised by their use of special steam systems, cycles or processes; Control means specially adapted for such systems, cycles or processes; Use of withdrawn or exhaust steam for feed-water heating the engines being of extraction or non-condensing type; Use of steam for feed-water heating
    • F01K7/44Use of steam for feed-water heating and another purpose
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E20/00Combustion technologies with mitigation potential
    • Y02E20/14Combined heat and power generation [CHP]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P80/00Climate change mitigation technologies for sector-wide applications
    • Y02P80/10Efficient use of energy, e.g. using compressed air or pressurized fluid as energy carrier
    • Y02P80/15On-site combined power, heat or cool generation or distribution, e.g. combined heat and power [CHP] supply

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Engine Equipment That Uses Special Cycles (AREA)
  • Control Of Turbines (AREA)

Abstract

The invention discloses a kind of steam surplus energy utilities for coal-fired thermal power unit power peak regulation to couple extraction for heat supply system and adjusting method, belongs to cogeneration of heat and power technical field.The system includes: steam turbine high-pressure cylinder, reheater, Steam Turbine Through IP Admission, turbine low pressure cylinder, steam generator, pressure matcher, oxygen-eliminating device, No. two feed pumps and industrial heat user;Steam generator is using the hot steam again from reheater as heat source, the low temperature feedwater from oxygen-eliminating device is heated to produce high steam, as the high-pressure steam source of pressure matcher, the extraction steam for factories from Steam Turbine Through IP Admission is driven, produces steam required for industrial heat user.The present invention realizes the power peak regulation of coal-fired thermal power unit so that coal-fired thermal power unit effectively meets extraneous steam supply demand in high and low load operation Shi Junneng by the coupling of pressure matcher and steam generator and original extraction steam for factories mode.It can be seen that the present invention is worth with biggish practice.

Description

Steam surplus energy utility for coal-fired thermal power unit power peak regulation couples extraction for heat supply system System and adjusting method
Technical field
The invention belongs to cogeneration of heat and power technical fields, and in particular to a kind of steam for coal-fired thermal power unit power peak regulation Surplus energy utility couples extraction for heat supply system and adjusting method.
Background technique
Currently, for having been carried out the steam power plant of extraction steam for factories central heating in early days, since heat supply process is simply extensive, energy Amount loss is serious, so that the comprehensive energy utilization efficiency of steam power plant can not further increase, many has carried out industrial heating Steam power plant does not realize profit, or even the case where lose.Causing this phenomenon main cause is exactly unit heat supply design It is all by operating condition design, and in actual operation, unit load fluctuation frequently, when especially unit is in underrun, is Meet steam parameter needed for industrial heating, usually all using modes such as throttlings, caused energy loss is extremely serious, thus Causing thermoelectricity unit cannot achieve profit.
Currently, the main patented technology in the field: (1) mesolow connection butterfly valve adjusts joint hot press mesolow industry steam supply Method and system " patent No. 201610320911.1 " and (2) novel heat-power cogeneration steam turbine " patent No. 200810013170.8 ", there is following technical limitations, first is that the degree of superheat of high parameter steam is underutilized, two Be the high and low pressure steam of hot press or pressure matcher temperature parameter it is non-adjustable, hot press or pressure matcher can not be promoted Efficiency numbers.Therefore, which throws away in terms of improving efficiency has some limitations.
Summary of the invention
It is an object of the invention to overcome the above deficiencies in the existing technologies, and provide it is a kind of design rationally, performance Reliably, the steam surplus energy utility coupling extraction for heat supply system and adjusting method of coal-fired thermal power unit power peak regulation are advantageously implemented.
Technical solution used by the present invention solves the above problems is: a kind of steaming for coal-fired thermal power unit power peak regulation Vapour surplus energy utility couples extraction for heat supply system, which is characterized in that it includes: steam turbine high-pressure cylinder, reheater, presses in steam turbine Cylinder, turbine low pressure cylinder, steam generator, pressure matcher, oxygen-eliminating device, No. two feed pumps and industrial heat user, the steamer The steam drain of machine high pressure cylinder and the air intake of reheater connect, and the venthole of the reheater passes through hot steam pipe and steam turbine again The air intake of intermediate pressure cylinder connects, and No.1 valve is equipped in heat again steam pipe, and the steam drain of the Steam Turbine Through IP Admission is logical The air intake for spending mesolow communicating pipe and turbine low pressure cylinder connects, and is equipped with hydraulic pressure butterfly valve on mesolow communicating pipe, institute The venthole for stating reheater also passes through the heat high temperature air intake of steam branch pipe and steam generator connection again, and in hot steam branch again No. two valves are installed on pipe, the low temperature venthole of the steam generator is connect by the first steam pipe with industrial steam supply pipe, And No. five valves are installed on the first steam pipe, the low temperature water inlet of the steam generator passes through feed pipe and oxygen-eliminating device Water outlet connection, and No. three valves and No. two feed pumps, the steam are sequentially installed with along water flowing direction on feed pipe The high pressure venthole of generator is connected by the high-pressure admission mouth of high-pressure steam pipe and pressure matcher, and on high-pressure steam pipe No. four valves are installed, the extraction steam for factories mouth of the Steam Turbine Through IP Admission is connect by extraction steam for factories pipe with industrial steam supply pipe, and No. six valves are installed on extraction steam for factories pipe, the extraction steam for factories mouth of the Steam Turbine Through IP Admission also pass through extraction steam for factories branch pipe with The low pressure admission mouth of pressure matcher connects, and No. seven valves are equipped on extraction steam for factories branch pipe, the pressure matcher Middle extrusion steam ports is connect by the second steam pipe with industrial steam supply pipe, and No. eight valves are equipped on the second steam pipe, described The steam output end of industrial steam supply pipe is connect with industrial heat user.
Furthermore, oxygen-eliminating device of the low temperature feedwater from coal-fired thermal power unit needed for the steam generator utilizes The boiler feedwater of low pressure regenerative steam heating in oxygen-eliminating device Jing Guo Steam Turbine Through IP Admission reduces steam generation as low temperature feedwater The high parameter steam energy consumed in device.
Furthermore, the steam generator using the heat from reheater again steam as heat source, by heat come High steam is produced from the low temperature feedwater of oxygen-eliminating device.
Furthermore, the pressure matcher is using the high steam driving from steam generator in steam turbine The extraction steam for factories of cylinder pressure, middle pressure steam needed for producing industrial heat user.
Furthermore, extraction steam for factories of the steam needed for the industrial heat user from Steam Turbine Through IP Admission, pressure The middle pressure steam of orchestration production and the hot steam again after steam generator desuperheat.
The adjusting side of the steam surplus energy utility coupling extraction for heat supply system for coal-fired thermal power unit power peak regulation Method is as follows:
When coal-fired thermal power unit heavy-duty service, at this time:
No.1 valve and hydraulic pressure butterfly valve are opened, opens and adjusts No. six valves, the extraction steam for factories of Steam Turbine Through IP Admission passes sequentially through Extraction steam for factories pipe and industrial steam supply pipe are delivered to industrial heat user;
When coal-fired thermal power performing low-load running of machine set, at this time:
Close No. six valves, open hydraulic pressure butterfly valve, open and adjust No.1 valve, No. two valves, No. three valves, No. four valves, No. five valves, No. seven valves and No. eight valves, by heat, steam branch pipe is delivered to steam hair to steam to the heat from reheater again again Raw device, heats the low temperature feedwater from oxygen-eliminating device to produce high steam, the heat after steam generator desuperheat again steam according to Secondary the first steam pipe and the industrial steam supply pipe of passing through is delivered to industrial heat user, and the high steam that steam generator generates passes through high pressure Steam pipe enters pressure matcher, and the extraction steam for factories from Steam Turbine Through IP Admission is driven to produce middle pressure steam, pressure matcher The middle pressure steam of generation passes sequentially through the second steam pipe and industrial steam supply pipe is delivered to industrial heat user.
The adjusting side of the above-mentioned steam surplus energy utility coupling extraction for heat supply system for coal-fired thermal power unit power peak regulation In method:
During coal-fired thermal power unit participates in power peak regulation, when coal-fired thermal power unit heavy-duty service, merely with steam turbine The extraction steam for factories of intermediate pressure cylinder is as steam needed for industrial heat user, when coal-fired thermal power performing low-load running of machine set, merely with pressure The middle pressure steam that power adaptation produces and the hot steam again after steam generator desuperheat are as steaming needed for industrial heat user Vapour.
Compared with prior art, the present invention having the following advantages that and effect: rationally, structure is simple, reliable performance for design, closes Reason couples extraction for heat supply system designed for the steam surplus energy utility of coal-fired thermal power unit power peak regulation, to realize: (1) utilizing Steam produces high steam to heat from reheater again, sufficiently recycles the degree of superheat of hot steam again;(2) using in oxygen-eliminating device The boiler feedwater of low pressure regenerative steam heating by Steam Turbine Through IP Admission is reduced and is consumed in steam generator as low temperature feedwater High parameter steam energy;(3) by adjusting the high steam parameter of steam generator production, the parameter with pressure matcher is realized Matching, further increases the performance of pressure matcher;(4) pass through pressure matcher and steam generator and original extraction steam for factories side The coupling of formula is realized coal-fired so that coal-fired thermal power unit effectively meets extraneous steam supply demand in high and low load operation Shi Junneng The power peak regulation of thermoelectricity unit.It can be seen that the present invention is worth with biggish practice.
Detailed description of the invention
Fig. 1 is the overall structure diagram of the embodiment of the present invention.
Fig. 2 is the heat regenerative system structural schematic diagram of coal-fired thermal power unit in the embodiment of the present invention.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawing and by embodiment, and following embodiment is to this hair Bright explanation and the invention is not limited to following embodiments.
Embodiment.
Referring to Fig. 1 to Fig. 2, the steam surplus energy utility for coal-fired thermal power unit power peak regulation in the present embodiment, which couples, to be taken out Vapour heating system, it includes: steam turbine high-pressure cylinder 1, reheater 2, Steam Turbine Through IP Admission 3, turbine low pressure cylinder 4, steam generation Device 5, pressure matcher 6,7, No. two feed pumps 8 of oxygen-eliminating device and industrial heat user 9, the steam drain and reheating of steam turbine high-pressure cylinder 1 The air intake of device 2 connects, and by heat, steam pipe 22 is connect the venthole of reheater 2 with the air intake of Steam Turbine Through IP Admission 3 again, and No.1 valve 11 is installed in heat again steam pipe 22, the steam drain of Steam Turbine Through IP Admission 3 passes through mesolow communicating pipe 21 and vapour The air intake of turbine low pressure (LP) cylinder 4 connects, and hydraulic pressure butterfly valve 12 is equipped on mesolow communicating pipe 21, the venthole of reheater 2 Also by heat, steam branch pipe 23 is connect with the high temperature air intake of steam generator 5 again, and is equipped in heat again steam branch pipe 23 The low temperature venthole of No. two valves 13, steam generator 5 is connect by the first steam pipe 26 with industrial steam supply pipe 30, and first No. five valves 16 are installed, the low temperature water inlet of steam generator 5 passes through the water outlet of feed pipe 24 and oxygen-eliminating device 7 on steam pipe 26 Mouth connection, and No. three valves 14 and No. two feed pumps 8, steam generation are sequentially installed with along water flowing direction on feed pipe 24 The high pressure venthole of device 5 is connect by high-pressure steam pipe 25 with the high-pressure admission mouth of pressure matcher 6, and in high-pressure steam pipe 25 On No. four valves 15 are installed, the extraction steam for factories mouth of Steam Turbine Through IP Admission 3 is connected by extraction steam for factories pipe 27 and industrial steam supply pipe 30 It connects, and No. six valves 17 is installed on extraction steam for factories pipe 27, the extraction steam for factories mouth of Steam Turbine Through IP Admission 3 also passes through extraction steam for factories Branch pipe 28 is connect with the low pressure admission mouth of pressure matcher 6, and No. seven valves 18, pressure are equipped on extraction steam for factories branch pipe 28 The middle extrusion steam ports of adaptation 6 is connect by the second steam pipe 29 with industrial steam supply pipe 30, and is installed on the second steam pipe 29 There are No. eight valves 19, the steam output end of industrial steam supply pipe 30 is connect with industrial heat user 9.
In the present embodiment, oxygen-eliminating device 7 of the low temperature feedwater needed for steam generator 5 from coal-fired thermal power unit utilizes The boiler feedwater of low pressure regenerative steam heating in oxygen-eliminating device 7 Jing Guo Steam Turbine Through IP Admission 3 reduces steam hair as low temperature feedwater The high parameter steam energy consumed in raw device 5;Steam is as heat source again using the heat from reheater 2 for steam generator 5, by adding Low temperature feedwater of the heat from oxygen-eliminating device 7 produces high steam.
In the present embodiment, pressure matcher 6 is using the high steam driving from steam generator 5 in steam turbine The extraction steam for factories of cylinder pressure 3, middle pressure steam needed for producing industrial heat user 9.This is because coal-fired thermal power performing low-load running of machine set When Steam Turbine Through IP Admission 3 extraction steam for factories pressure lower than coal-fired thermal power unit declared working condition run when Steam Turbine Through IP Admission 3 work Industry extraction pressure is unable to satisfy the demand of industrial heat user 9.
In the present embodiment, extraction steam for factories of the steam needed for industrial heat user 9 from Steam Turbine Through IP Admission 3, pressure The middle pressure steam that orchestration 6 produces and the hot steam again after 5 desuperheat of steam generator.
The adjusting method that the present embodiment is related to is as follows:
When coal-fired thermal power unit heavy-duty service, at this time: opening No.1 valve 11 and hydraulic pressure butterfly valve 12, open and adjust No. six Valve 17, the extraction steam for factories of Steam Turbine Through IP Admission 3 passes sequentially through extraction steam for factories pipe 27 and industrial steam supply pipe 30 is delivered to industrial heat User 9;
When coal-fired thermal power performing low-load running of machine set, at this time: closing No. six valves 17, open hydraulic pressure butterfly valve 12, open and adjust The valve 14, four of valve 13, three 16, No. seven valves 18 of the valve of valve 15, five of No.1 valve 11, two and No. eight valves 19, by heat, steam branch pipe 23 is delivered to steam generator 5 to steam to the heat from reheater 2 again again, heats from oxygen-eliminating device 7 Low temperature feedwater produces high steam, and steam passes sequentially through 26 He of the first steam pipe to the heat after 5 desuperheat of steam generator again Industrial steam supply pipe 30 is delivered to industrial heat user 9, and the high steam that steam generator 5 generates enters pressure by high-pressure steam pipe 25 Power adaptation 6 drives the extraction steam for factories from Steam Turbine Through IP Admission 3 to produce middle pressure steam, the middle pressure that pressure matcher 6 generates Steam passes sequentially through the second steam pipe 29 and industrial steam supply pipe 30 is delivered to industrial heat user 9.
In the carrying out practically method of the present embodiment, during coal-fired thermal power unit participates in power peak regulation, work as coal fuel heating When motor group heavy-duty service, merely with the extraction steam for factories of Steam Turbine Through IP Admission 3 as steam needed for industrial heat user 9, when When coal-fired thermal power performing low-load running of machine set, merely with the middle pressure steam of the production of pressure matcher 6 and by 5 desuperheat of steam generator Hot steam again afterwards is as steam needed for industrial heat user 9.
It is any to be familiar with although the present invention is disclosed as above with embodiment, its protection scope being not intended to limit the invention The technical staff of this technology changes and retouches made without departing from the spirit and scope of the invention, should belong to this hair Bright protection scope.

Claims (7)

1. a kind of steam surplus energy utility for coal-fired thermal power unit power peak regulation couples extraction for heat supply system, which is characterized in that It includes: steam turbine high-pressure cylinder (1), reheater (2), Steam Turbine Through IP Admission (3), turbine low pressure cylinder (4), steam generator (5), pressure matcher (6), oxygen-eliminating device (7), No. two feed pumps (8) and industrial heat user (9), the steam turbine high-pressure cylinder (1) Steam drain connect with the air intake of reheater (2), the venthole of the reheater (2) passes through heat steam pipe (22) and steamer again The air intake of machine intermediate pressure cylinder (3) connects, and is equipped with No.1 valve (11) in heat again steam pipe (22), presses in the steam turbine The steam drain of cylinder (3) is connect by mesolow communicating pipe (21) with the air intake of turbine low pressure cylinder (4), and is connected in mesolow It is equipped with hydraulic pressure butterfly valve (12) on pipe (21), the venthole of the reheater (2) also passes through heat steam branch pipe (23) and steam again The high temperature air intake of generator (5) connects, and No. two valves (13) are equipped in heat again steam branch pipe (23), the steam hair The low temperature venthole of raw device (5) is connect by the first steam pipe (26) with industrial steam supply pipe (30), and in the first steam pipe (26) On No. five valves (16) are installed, the low temperature water inlet of the steam generator (5) passes through feed pipe (24) and oxygen-eliminating device (7) Water outlet connection, and No. three valves (14) and No. two feed pumps are sequentially installed with along water flowing direction on feed pipe (24) (8), the high pressure venthole of the steam generator (5) passes through the high-pressure admission of high-pressure steam pipe (25) and pressure matcher (6) Mouth connection, and No. four valves (15) are installed on high-pressure steam pipe (25), the extraction steam for factories mouth of the Steam Turbine Through IP Admission (3) It is connect by extraction steam for factories pipe (27) with industrial steam supply pipe (30), and No. six valves is installed on extraction steam for factories pipe (27) (17), it is low with pressure matcher (6) also to pass through extraction steam for factories branch pipe (28) for the extraction steam for factories mouth of the Steam Turbine Through IP Admission (3) It is pressed into steam ports connection, and No. seven valves (18) are installed on extraction steam for factories branch pipe (28), the middle pressure of the pressure matcher (6) Venthole is connect by the second steam pipe (29) with industrial steam supply pipe (30), and No. eight valves are equipped on the second steam pipe (29) The steam output end of door (19), the industry steam supply pipe (30) is connect with industrial heat user (9).
2. the steam surplus energy utility according to claim 1 for coal-fired thermal power unit power peak regulation couples extraction for heat supply system System, which is characterized in that oxygen-eliminating device (7) of the low temperature feedwater needed for the steam generator (5) from coal-fired thermal power unit.
3. the steam surplus energy utility according to claim 2 for coal-fired thermal power unit power peak regulation couples extraction for heat supply system System, which is characterized in that the steam generator (5) using the hot steam again from reheater (2) as heat source, by heat come High steam is produced from the low temperature feedwater of oxygen-eliminating device (7).
4. the steam surplus energy utility according to claim 1 for coal-fired thermal power unit power peak regulation couples extraction for heat supply system System, which is characterized in that the pressure matcher (6) comes from steam turbine using the high steam driving from steam generator (5) The extraction steam for factories of intermediate pressure cylinder (3), middle pressure steam needed for production industrial heat user (9).
5. the steam surplus energy utility according to claim 1 for coal-fired thermal power unit power peak regulation couples extraction for heat supply system System, which is characterized in that steam needed for the industrial heat user (9) comes from the extraction steam for factories of Steam Turbine Through IP Admission (3), pressure The middle pressure steam of orchestration (6) production and the hot steam again after steam generator (5) desuperheat.
6. a kind of steam surplus energy utility coupling according to any one of claims 1 to 5 for coal-fired thermal power unit power peak regulation Close the adjusting method of extraction for heat supply system, which is characterized in that its adjusting method is as follows:
When coal-fired thermal power unit heavy-duty service, at this time:
No.1 valve (11) and hydraulic pressure butterfly valve (12) are opened, opens and adjusts No. six valves (17), the work of Steam Turbine Through IP Admission (3) Industry steam extraction passes sequentially through extraction steam for factories pipe (27) and industrial steam supply pipe (30) is delivered to industrial heat user (9);
When coal-fired thermal power performing low-load running of machine set, at this time:
No. six valves (17) are closed, opens hydraulic pressure butterfly valve (12), opens and adjust No.1 valve (11), No. two valves (13), three Number valve (14), No. four valves (15), No. five valves (16), No. seven valves (18) and No. eight valves (19) come from reheater (2) Heat again steam by heat again steam branch pipe (23) be delivered to steam generator (5), heating come from oxygen-eliminating device (7) low temperature feedwater High steam is produced, steam passes sequentially through the first steam pipe (26) and industry to the heat after steam generator (5) desuperheat again Steam supply pipe (30) is delivered to industrial heat user (9), steam generator (5) generate high steam by high-pressure steam pipe (25) into Enter pressure matcher (6), driving comes from the extraction steam for factories of Steam Turbine Through IP Admission (3) to produce middle pressure steam, pressure matcher (6) The middle pressure steam of generation passes sequentially through the second steam pipe (29) and industrial steam supply pipe (30) is delivered to industrial heat user (9).
7. the steam surplus energy utility according to claim 6 for coal-fired thermal power unit power peak regulation couples extraction for heat supply system The adjusting method of system, it is characterised in that:
During coal-fired thermal power unit participates in power peak regulation, when coal-fired thermal power unit heavy-duty service, merely with steam turbine The extraction steam for factories of intermediate pressure cylinder (3) is as steam needed for industrial heat user (9), when coal-fired thermal power performing low-load running of machine set, only Using the middle pressure steam of pressure matcher (6) production and the heat after steam generator (5) desuperheat, steam is warm as industry again Steam needed for user (9).
CN201910229910.XA 2019-03-26 2019-03-26 Steam complementary energy utilization coupling steam extraction heat supply system and adjusting method Active CN110056402B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910229910.XA CN110056402B (en) 2019-03-26 2019-03-26 Steam complementary energy utilization coupling steam extraction heat supply system and adjusting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910229910.XA CN110056402B (en) 2019-03-26 2019-03-26 Steam complementary energy utilization coupling steam extraction heat supply system and adjusting method

Publications (2)

Publication Number Publication Date
CN110056402A true CN110056402A (en) 2019-07-26
CN110056402B CN110056402B (en) 2023-11-28

Family

ID=67315943

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910229910.XA Active CN110056402B (en) 2019-03-26 2019-03-26 Steam complementary energy utilization coupling steam extraction heat supply system and adjusting method

Country Status (1)

Country Link
CN (1) CN110056402B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110631112A (en) * 2019-09-11 2019-12-31 上海发电设备成套设计研究院有限责任公司 Steam energy storage peak shaving system and method for heat supply unit

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01285606A (en) * 1988-05-10 1989-11-16 Toshiba Corp Method and device of starting 2-stage reheat type steam turbine plant
JP2011027036A (en) * 2009-07-27 2011-02-10 Hitachi Ltd Combined power generation plant and method for controlling the same
JP2013064372A (en) * 2011-09-20 2013-04-11 Hitachi Ltd Low pressure turbine bypass control device, and power plant
JP2013151876A (en) * 2012-01-24 2013-08-08 Toshiba Corp Carbon dioxide separation recovery device, carbon dioxide recovery type steam power generation system, and method for operating the same
WO2013132994A1 (en) * 2012-03-09 2013-09-12 株式会社日立製作所 Coal-fired thermal power plant
CN104775860A (en) * 2015-04-09 2015-07-15 中国东方电气集团有限公司 System for improving reliability of heat supply network of subcritical coal-fired unit
CN204591384U (en) * 2015-04-09 2015-08-26 中国东方电气集团有限公司 A kind of system improving subcritical coal unit reliability of heating network
CN107120147A (en) * 2017-04-17 2017-09-01 华电电力科学研究院 A kind of varying duty thermal power plant heating energy-saving structure and its adjusting method
CN107270383A (en) * 2017-07-06 2017-10-20 国网山东省电力公司电力科学研究院 A kind of thermoelectricity peak load regulation heating system
CN109356677A (en) * 2018-10-17 2019-02-19 华电电力科学研究院有限公司 A kind of novel solidifying pumping back heating system and operation method for more low pressure (LP) cylinder steam turbines
CN109404073A (en) * 2018-11-20 2019-03-01 华电电力科学研究院有限公司 A kind of solidifying pumping back heating system and operation method for variable working condition unit

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01285606A (en) * 1988-05-10 1989-11-16 Toshiba Corp Method and device of starting 2-stage reheat type steam turbine plant
JP2011027036A (en) * 2009-07-27 2011-02-10 Hitachi Ltd Combined power generation plant and method for controlling the same
JP2013064372A (en) * 2011-09-20 2013-04-11 Hitachi Ltd Low pressure turbine bypass control device, and power plant
JP2013151876A (en) * 2012-01-24 2013-08-08 Toshiba Corp Carbon dioxide separation recovery device, carbon dioxide recovery type steam power generation system, and method for operating the same
WO2013132994A1 (en) * 2012-03-09 2013-09-12 株式会社日立製作所 Coal-fired thermal power plant
CN104775860A (en) * 2015-04-09 2015-07-15 中国东方电气集团有限公司 System for improving reliability of heat supply network of subcritical coal-fired unit
CN204591384U (en) * 2015-04-09 2015-08-26 中国东方电气集团有限公司 A kind of system improving subcritical coal unit reliability of heating network
CN107120147A (en) * 2017-04-17 2017-09-01 华电电力科学研究院 A kind of varying duty thermal power plant heating energy-saving structure and its adjusting method
CN107270383A (en) * 2017-07-06 2017-10-20 国网山东省电力公司电力科学研究院 A kind of thermoelectricity peak load regulation heating system
CN109356677A (en) * 2018-10-17 2019-02-19 华电电力科学研究院有限公司 A kind of novel solidifying pumping back heating system and operation method for more low pressure (LP) cylinder steam turbines
CN109404073A (en) * 2018-11-20 2019-03-01 华电电力科学研究院有限公司 A kind of solidifying pumping back heating system and operation method for variable working condition unit

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
春健;: "300 MW纯凝机组再热蒸汽系统供热改造方案研究", 应用能源技术, no. 12 *
蔡缪云;: "华鑫电厂抽汽供热改造方案", 科学中国人, no. 35 *
黎林村;: "纯凝机组工业供热改造设计", 南方能源建设, no. 01 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110631112A (en) * 2019-09-11 2019-12-31 上海发电设备成套设计研究院有限责任公司 Steam energy storage peak shaving system and method for heat supply unit
CN110631112B (en) * 2019-09-11 2023-11-28 上海发电设备成套设计研究院有限责任公司 Steam energy storage peak shaving system and method for heat supply unit

Also Published As

Publication number Publication date
CN110056402B (en) 2023-11-28

Similar Documents

Publication Publication Date Title
CN109826681B (en) Industrial heating system for gas-steam combined cycle unit steam extraction integration and operation method thereof
CN109855147B (en) Combined cycle device based on heat supply and power peak regulation coupling and operation method thereof
CN109798157A (en) A kind of solidifying pumping back coupling steam extraction integrated system and its operation method for thermoelectricity unit power peak regulation
CN110344899A (en) The system and method for high pressure industry steam supply ability is mentioned under a kind of power plant underload
CN109854315B (en) Heating system for gas-steam combined cycle unit steam extraction integration and operation method thereof
CN109869204A (en) A kind of heat supply for Combined cycle gas-steam turbine unit and power peak regulation coupled system and its operation method
CN109356677A (en) A kind of novel solidifying pumping back heating system and operation method for more low pressure (LP) cylinder steam turbines
CN210509309U (en) Steam complementary energy utilization coupling steam extraction heat supply system for thermoelectric unit electric power peak regulation
CN109854316A (en) A kind of combined cycle heat supply based on energy cascade utilization and power peak regulation coupled system and its operation method
CN110185510A (en) A kind of thermoelectricity unit cuts off low pressure (LP) cylinder and couples back pressure machine step heating system and adjusting method into vapour
CN106437875A (en) Thermal power generating unit working medium shunting circulation peak shaving system
CN114046186A (en) High-flexibility high-thermoelectric-ratio composite thermal mass bypass heating system
CN112833378B (en) Reheating system capable of improving heat supply capacity
CN110056402A (en) Steam surplus energy utility for coal-fired thermal power unit power peak regulation couples extraction for heat supply system and adjusting method
CN112145244B (en) System and method for improving water supply temperature and steam supply capacity of coal-fired power generating unit
CN206694081U (en) A kind of heat regenerative system for thermal power plant
CN209724435U (en) A kind of solidifying pumping back coupling steam extraction integrated system for thermoelectricity unit power peak regulation
CN210179723U (en) Combined cycle device based on heat supply and electric power peak regulation coupling
CN209621420U (en) A kind of heat supply for Combined cycle gas-steam turbine unit and power peak regulation coupled system
CN209726304U (en) A kind of extraction for heat supply integrated system for combined cycle unit power peak regulation
CN109611166A (en) A kind of solidifying pumping back heating system and operation method for more low pressure (LP) cylinder Variable Conditions of Steam Turbine
CN214840728U (en) Double-extraction steam supply system based on ejector
CN109763869A (en) A kind of accumulation of heat coupling steam extraction integrated system and its operation method for combined cycle energy cascade utilization
CN111706898B (en) Method for improving heat supply capacity of unit after high-back-pressure heat supply transformation
CN209621419U (en) A kind of matched combined cycle extraction for heat supply integrated system of coupling pressure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant