CN110042830A - A kind of concrete fills out the stake of core perforated pipe and construction method - Google Patents

A kind of concrete fills out the stake of core perforated pipe and construction method Download PDF

Info

Publication number
CN110042830A
CN110042830A CN201910372162.0A CN201910372162A CN110042830A CN 110042830 A CN110042830 A CN 110042830A CN 201910372162 A CN201910372162 A CN 201910372162A CN 110042830 A CN110042830 A CN 110042830A
Authority
CN
China
Prior art keywords
pile
perforated pipe
concrete
stake
core
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910372162.0A
Other languages
Chinese (zh)
Inventor
邹永强
雷金波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanchang Hangkong University
Original Assignee
Nanchang Hangkong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanchang Hangkong University filed Critical Nanchang Hangkong University
Priority to CN201910372162.0A priority Critical patent/CN110042830A/en
Publication of CN110042830A publication Critical patent/CN110042830A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/50Piles comprising both precast concrete portions and concrete portions cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of concrete to fill out the stake of core perforated pipe and construction method, in the perforated pipe stake static pressure pile-sinking construction time, forms concrete core to the perforated pipe pile pipe intra-bladder instillation concrete that draining finishes, technical key point is to include the following steps: to lay out pile;Positioning;Static pressure pile-sinking;Soil body discharging consolidation: in the perforated pipe stake static pressure pile-sinking construction time, the pore water being completed in the foundation soil body in pile sinking region is discharged into tubular pole lumen by pile body drainage hole, accelerates dissipation of excess pore-water pressure;Lumen draws water;Core is filled out in lumen.The solution have the advantages that: the defects of overcoming the reduction of prefabricated concrete pipe pile bearing capacity caused by pile body aperture and unbearable horizontal loading, dissipation of excess pore-water pressure can effectively be accelerated in the perforated pipe stake static pressure pile-sinking construction time, after draining substantially, concrete core is formed from the inside concrete perfusion of tubular pole mouth, it is ensured that perforated pipe stake there are enough bearing capacities in the carrying stage and can undertake part of horizontal load.

Description

A kind of concrete fills out the stake of core perforated pipe and construction method
Technical field
The present invention relates to technical field of building construction, specially a kind of concrete fills out the stake of core perforated pipe and construction method.
Background technique
Prefabricated concrete pipe pile is widely used in all kinds of foundation treatments at present, but effect of driving pile is always This aspect yet unresolved issue, especially handle moisture content is high, intensity is low, poor permeability soft soil foundation when, static pressure Excess pore water pressure caused by pile sinking easily causes a series of harm such as adjacent stake offset, broken pile.According to related engineering practice and Theoretical data shows to design by reasonable pile body and construction technology can effectively mitigate pile sinking effect, therefore perforated pipe stake Technology is come into being, and by reasonably opening up permeable hole in pile body, accelerates the dissipation of excess pore-water pressure of tubular pole piling construction phase, Mitigate soil compaction during pile driving harm.
But pile body aperture certainly will will cause the reduction of bearing capacity, and in the prior art, Authorization Notice No. is A kind of perforated pipe stake for deep soft soil treatment is disclosed in a Chinese invention patent file of CN201620410U, according to Perforated pipe stake related research result may indicate that perforated pipe stake can effectively mitigate effect of driving pile, but pile body aperture certainly will cause The reduction of tubular pole bearing capacity destroys the defects of pile body globality, unbearable horizontal loading and tapping stress concentration phenomenon.For This, it is proposed that a kind of concrete fills out the stake of core perforated pipe and construction method.
Summary of the invention
The purpose of the present invention is to provide a kind of concrete to fill out the stake of core perforated pipe and construction method, it is intended to solve perforated pipe stake Adverse effect caused by pile body aperture.
To achieve the above object, the present invention provides a kind of concrete and fills out core perforated pipe pile construction method, including the following steps:
(1) it lays out pile: laying stake position on soft foundation;
(2) it positions: perforated pipe stake is lifted into default stake position;
(3) static pressure pile-sinking: after pile press machine is in place, static pressure pile-sinking is carried out to perforated pipe stake and reaches designated depth;
(4) in the perforated pipe stake static pressure pile-sinking construction time, the hole in the foundation soil body in pile sinking region soil body discharging consolidation: is completed Water is discharged into tubular pole lumen by pile body drainage hole, accelerates dissipation of excess pore-water pressure;
(5) lumen draws water: being completely drawn out intraluminal pore water by suction pump;
(6) core is filled out in lumen: after drawing water, filling out core to perforated pipe pile pipe intra-bladder instillation concrete, sufficiently vibrate in the process;
(7) it shifts: repeating step (1) to step (6) and carry out next perforated pipe pile driving construction.
The present invention provides a kind of concrete and fills out core perforated pipe stake, fills out core perforated pipe pile driving construction side using comprising above-mentioned concrete Method, including the stake of precast concrete perforated pipe and concrete core, it is characterised in that: the cylindrical tubular pole of precast concrete perforated pipe stake Several pairs of through holes are offered on wall, concrete perfusion fill out core at mixed into lumen after pile peripheral earth draining finishes substantially Solidifying core.
Compared with prior art, the beneficial effects of the present invention are:
In original perforated pipe pile foundation, lumen and pile body hole are filled by rear concrete perfusion, both ensure that The advantages of original acceleration foundation soil body dissipation of excess pore-water pressure of perforated pipe stake mitigates effect of driving pile, and compensate for aperture and lead Tubular pole bearing capacity is caused to be reduced this defect, while improving the globality of tubular pole and rigidity to undertake horizontal loading, and energy Effectively avoid the appearance of pile body tapping stress concentration phenomenon.
Detailed description of the invention
Fig. 1 is lateral Structure of cross section schematic diagram of the invention;
Fig. 2 is Specific construction process flow diagram of the present invention;
In figure: 1, cylindrical tube pile lining;2, through hole;3, concrete core;4, precast concrete perforated pipe stake;5, piling is mechanical; 6, pore water;7, suction pump;8, concrete mixer.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear-complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
As shown in Fig. 2, precast concrete perforated pipe stake 4 is lifted into default stake position, piling machinery 5 at engineering construction scene It is consistent with conventional tubular pole static pressure pile-sinking process that 4 pile sinking of precast concrete perforated pipe stake is reached into designated depth after in place, due to heavy Stake soil compaction effect, the pore water meeting in the 4 static pressure pile-sinking construction time of precast concrete perforated pipe stake, in the foundation soil body in pile sinking region It is discharged into 4 lumen of concrete perforated pipe stake by pile body through hole 2, accelerates 6 pressure dissipation of pore water;It will by suction pump 7 The intraluminal pore water 6 of concrete perforated pipe stake 4 is completely drawn out, and after drawing water, has hole to concrete by concrete mixer 8 Concrete perfusion 3 carries out filling out core in 4 official jargon of tubular pole, sufficiently vibrates in the process, is to fill out the concrete perforated pipe after core shown in Fig. 1 4 Structure of cross section schematic diagrames of stake, concrete are filled into concrete core 3 to lumen and 1 through hole of cylindrical tube pile lining, 2 hole, So that cylindrical tube pile lining 1 restores completely, ensure that the acceleration foundation soil body excess pore water of precast concrete perforated pipe stake 4 again On the basis of 6 pressure dissipations mitigate the advantages of effect of driving pile, compensating for aperture causes precast concrete perforated pipe stake 4 to carry Power is reduced this defect, while the through hole 2 for filling up cylindrical tube pile lining 1 improves the entirety of precast concrete perforated pipe stake 4 Property with rigidity can undertake horizontal loading, and can effectively avoid stress concentration phenomenon at the through hole 2 of cylindrical tube pile lining 1 Occur, to meet different design requirements.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that including that process-method-article of a series of elements or equipment are not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process-method-article or equipment Intrinsic element.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variation-modification-replacements can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (2)

1. a kind of concrete fills out core perforated pipe pile construction method, it is characterised in that: successively include the following steps:
(1) it lays out pile: laying stake position on soft foundation;
(2) it positions: perforated pipe stake is lifted into default stake position;
(3) static pressure pile-sinking: after pile press machine is in place, static pressure pile-sinking is carried out to perforated pipe stake and reaches designated depth;
(4) in the perforated pipe stake static pressure pile-sinking construction time, the hole in the foundation soil body in pile sinking region soil body discharging consolidation: is completed Water is discharged into tubular pole lumen by pile body drainage hole, accelerates dissipation of excess pore-water pressure;
(5) lumen draws water: being completely drawn out intraluminal pore water by suction pump;
(6) core is filled out in lumen: after drawing water, filling out core to perforated pipe pile pipe intra-bladder instillation concrete, sufficiently vibrate in the process;
(7) it shifts: repeating step (1) to step (6) and carry out next perforated pipe pile driving construction.
2. a kind of concrete fills out core perforated pipe stake, core perforated pipe is filled out using comprising a kind of concrete as described in claim 1 Pile construction method, including the stake of precast concrete perforated pipe and concrete core, it is characterised in that: precast concrete perforated pipe pile pipe wall Several pairs of through holes are offered, concrete perfusion fill out core into concrete into lumen after pile peripheral earth draining finishes substantially Core.
CN201910372162.0A 2019-05-06 2019-05-06 A kind of concrete fills out the stake of core perforated pipe and construction method Pending CN110042830A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910372162.0A CN110042830A (en) 2019-05-06 2019-05-06 A kind of concrete fills out the stake of core perforated pipe and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910372162.0A CN110042830A (en) 2019-05-06 2019-05-06 A kind of concrete fills out the stake of core perforated pipe and construction method

Publications (1)

Publication Number Publication Date
CN110042830A true CN110042830A (en) 2019-07-23

Family

ID=67280925

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910372162.0A Pending CN110042830A (en) 2019-05-06 2019-05-06 A kind of concrete fills out the stake of core perforated pipe and construction method

Country Status (1)

Country Link
CN (1) CN110042830A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111485547A (en) * 2020-06-03 2020-08-04 山东大学 Prefabricated horizontal bearing type high-toughness concrete permeable pile and preparation method thereof
CN114319319A (en) * 2021-12-03 2022-04-12 上海建工集团股份有限公司 High-bearing core-filling steel pipe pile and construction method thereof
CN114855770A (en) * 2022-03-28 2022-08-05 中铁时代建筑设计院有限公司 Device and method for dissipating excess pore water pressure generated by pile sinking of precast tubular pile

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104179174A (en) * 2014-08-13 2014-12-03 山东科技大学 Porous grouted pipe special-shaped pile and pile-forming method
JP2016037715A (en) * 2014-08-06 2016-03-22 新日鐵住金株式会社 Ground improvement pile and ground improvement method
CN106436684A (en) * 2016-11-21 2017-02-22 中铁上海设计院集团有限公司 Water drainage reinforcing device for prepressing treatment of deep soft soil roadbed and application method of water drainage reinforcing device
CN107012857A (en) * 2017-05-12 2017-08-04 上海建工二建集团有限公司 One kind is prefabricated with the tapered screw thread combination pile tube in hole and its construction method
CN206941568U (en) * 2017-05-19 2018-01-30 青岛瑞源工程集团有限公司 A kind of draining end-bearing pile for muck foundation
CN108396728A (en) * 2018-04-16 2018-08-14 浙江大学 Constructing device and construction method for the multi-functional pile pile that the islands Tian Haizhu can drain

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016037715A (en) * 2014-08-06 2016-03-22 新日鐵住金株式会社 Ground improvement pile and ground improvement method
CN104179174A (en) * 2014-08-13 2014-12-03 山东科技大学 Porous grouted pipe special-shaped pile and pile-forming method
CN106436684A (en) * 2016-11-21 2017-02-22 中铁上海设计院集团有限公司 Water drainage reinforcing device for prepressing treatment of deep soft soil roadbed and application method of water drainage reinforcing device
CN107012857A (en) * 2017-05-12 2017-08-04 上海建工二建集团有限公司 One kind is prefabricated with the tapered screw thread combination pile tube in hole and its construction method
CN206941568U (en) * 2017-05-19 2018-01-30 青岛瑞源工程集团有限公司 A kind of draining end-bearing pile for muck foundation
CN108396728A (en) * 2018-04-16 2018-08-14 浙江大学 Constructing device and construction method for the multi-functional pile pile that the islands Tian Haizhu can drain

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111485547A (en) * 2020-06-03 2020-08-04 山东大学 Prefabricated horizontal bearing type high-toughness concrete permeable pile and preparation method thereof
CN114319319A (en) * 2021-12-03 2022-04-12 上海建工集团股份有限公司 High-bearing core-filling steel pipe pile and construction method thereof
CN114855770A (en) * 2022-03-28 2022-08-05 中铁时代建筑设计院有限公司 Device and method for dissipating excess pore water pressure generated by pile sinking of precast tubular pile
CN114855770B (en) * 2022-03-28 2024-04-26 中铁时代建筑设计院有限公司 Device and method for dissipating excess pore water pressure generated by pile sinking of prefabricated pipe pile

Similar Documents

Publication Publication Date Title
CN101182709B (en) Method of composite electroosmosis, vacuum precipitation and vacuum preload reinforcement foundation and device thereof
CN110042830A (en) A kind of concrete fills out the stake of core perforated pipe and construction method
CN206385531U (en) A kind of pile tube device of reinforcing soft ground
KR100679601B1 (en) Method of suction drain for water drainage in soft ground
CN103233454A (en) Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation
CN103243703B (en) A kind of method adopting side-wall hole hard hollow section process soft soil consolidation
WO2021027025A1 (en) High-rise building settling reinforcing and lifting correcting construction method
CN101634139B (en) Dynamic compaction method for backfill foundation with drainage layer
CN104060601A (en) Construction method utilizing pile foundations of precast construction piles for ground treatment
CN108797578A (en) Crushed stone grouting pile and its construction method with classification enlarged footing
CN201436323U (en) Drainage structure of dynamic compaction foundation
CN208201874U (en) A kind of open-cell cloth bag grouting structure
CN205591212U (en) Multi -functional precast tubular pile
CN102444115A (en) Net sling-coated gravel pile
CN205242391U (en) Back slip casting precast pile that permeates water
CN101182708B (en) Covering type composite vacuum electroosmosis, method for forced ramming reinforcing foundation and device thereof
CN112281799A (en) First-dispersing and later-reinforcing pile construction method and construction device suitable for ultra-soft soil
CN104110024A (en) Drainage consolidation method for reinforcement treatment of hydraulic filling soft clay
CN109914392A (en) Upper section draining is lower to save not drain combination type prefabricated tubular pile and construction method
WO2020240779A1 (en) Ground improvement method
CN103741682B (en) The construction method of a kind of carbon fiber cloth bag cast-in-place antiarch surface composition shaped pile
CN112227341B (en) First-dispersing and then-reinforcing pile treatment method suitable for filling engineering on under-consolidated soft soil foundation
CN212001021U (en) Soft soil foundation reinforcing structure in dredger fill area
CN205501991U (en) Prevent blockking up multi -functional precast tubular pile
CN105908695B (en) A kind of barged-in fill drain consolidation system and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190723

WD01 Invention patent application deemed withdrawn after publication