CN112227341B - Applicable to the treatment method of piles first scattered and then rigid for filling works on under-consolidated soft soil foundations - Google Patents

Applicable to the treatment method of piles first scattered and then rigid for filling works on under-consolidated soft soil foundations Download PDF

Info

Publication number
CN112227341B
CN112227341B CN202011195496.4A CN202011195496A CN112227341B CN 112227341 B CN112227341 B CN 112227341B CN 202011195496 A CN202011195496 A CN 202011195496A CN 112227341 B CN112227341 B CN 112227341B
Authority
CN
China
Prior art keywords
pile
soft soil
grouting
foundation
piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011195496.4A
Other languages
Chinese (zh)
Other versions
CN112227341A (en
Inventor
章荣军
黄悦
郑俊杰
董超强
蒋达飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huazhong University of Science and Technology
Original Assignee
Huazhong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huazhong University of Science and Technology filed Critical Huazhong University of Science and Technology
Priority to CN202011195496.4A priority Critical patent/CN112227341B/en
Publication of CN112227341A publication Critical patent/CN112227341A/en
Application granted granted Critical
Publication of CN112227341B publication Critical patent/CN112227341B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/08Improving by compacting by inserting stones or lost bodies, e.g. compaction piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明属于软土地基处理技术领域,公开了一种适用于欠固结软土地基上填方工程的先散后刚桩处理方法,先散后刚桩是一种变刚度桩。欠固结软土地基上施工堆填土堆载之前,在软土地基中先施工碎石桩,并同时插入注浆管但不注浆,然后再进行堆填土施工。堆填土施工后,软土在堆填土自重作用下产生超孔隙水压并开始排水固结,此时碎石桩渗透系数较大,可作为排水通道,加速软土的固结沉降。待地基软土固结沉降大致完成时,再往预留的注浆管中注入水泥浆液,水泥浆液渗入碎石桩,使碎石桩的骨料凝结成为刚度较大的刚性桩;刚性桩则能分担更多荷载,以提高欠固结软土地基的承载力以及减小地基的工后沉降。

Figure 202011195496

The invention belongs to the technical field of soft soil foundation treatment, and discloses a method for treating piles that are first scattered and then rigid, which are suitable for filling works on under-consolidated soft soil foundations. Before the construction of the landfill on the under-consolidated soft soil foundation, the gravel pile shall be constructed in the soft soil foundation, and the grouting pipe shall be inserted at the same time without grouting, and then the landfill construction shall be carried out. After the construction of the landfill, the soft soil generates excess pore water pressure under the action of the self-weight of the landfill and begins to drain and consolidate. At this time, the permeability coefficient of the gravel pile is large, which can be used as a drainage channel to accelerate the consolidation and settlement of the soft soil. When the consolidation and settlement of the soft soil of the foundation is substantially completed, the cement slurry is injected into the reserved grouting pipe, and the cement slurry penetrates into the gravel pile, so that the aggregate of the gravel pile is condensed into a rigid pile with greater rigidity; It can share more load to improve the bearing capacity of under-consolidated soft soil foundation and reduce the post-construction settlement of the foundation.

Figure 202011195496

Description

First-dispersing and then-reinforcing pile treatment method suitable for filling engineering on under-consolidated soft soil foundation
Technical Field
The invention belongs to the technical field of soft soil foundation treatment, and particularly relates to a method for treating piles which are scattered first and then reinforced, and are suitable for filling projects on an under-consolidated soft soil foundation.
Background
At present, a soft soil foundation treatment method of under-consolidation generally adopts a surcharge or vacuum preloading drainage consolidation method or a surcharge and vacuum preloading drainage consolidation method, and then adopts cement mixing piles and the like to form a composite foundation. For filling projects on an under-consolidated soft soil foundation, the preloading is carried out by only utilizing the dead weight of filled soil, so that the method has great limitation, and is mainly characterized in that (1) the preloading treatment depth is limited; (2) the permeability coefficient of the soft soil is small, the drainage path is long, the dissipation of the ultra-static pore water pressure is very slow, and the construction period required by the stacking is long; (3) the ultra-static pore pressure in the unconsolidated soil is not completely dissipated, and consolidation settlement still occurs subsequently, so that the post-construction settlement is larger.
When a composite foundation is formed by constructing discrete material piles in soft soil and then performing filling construction and prepressing, the lifting range of the foundation bearing capacity of the soft soil foundation is limited; when a rigid pile is constructed in soft soil to form a composite foundation and then the soil filling construction is carried out for prepressing, the consolidation of the under-consolidated soft soil still needs a longer time, and the construction period of the preloading is longer. In view of the defects of the above treatment methods, a foundation treatment method for an under-consolidated soft soil foundation upper filling project, which has a short construction period and can greatly improve the bearing capacity of the foundation and control post-construction settlement, is to be developed.
Through the above analysis, the problems and defects of the prior art are as follows:
in the prior art, consolidation settlement of the under-consolidated soft soil foundation is slow, and the required construction period is long.
In the prior art, the consolidation settlement of the under-consolidated soft soil foundation is not thorough, so that the post-construction settlement is caused.
The composite foundation formed by the prior art can not meet the requirements of bearing capacity, construction period and post-construction settlement of the foundation at the same time.
The difficulty in solving the above problems and defects is: at present, a pile body in a composite foundation often cannot have drainage capacity and vertical rigidity, so that the requirements of foundation bearing capacity, construction period and post-construction settlement are met at the same time, certain difficulty is achieved, and improper treatment of construction cost can be improved more.
The significance of solving the problems and the defects is as follows: the drainage capacity and the vertical rigidity of the pile body in the composite foundation are exerted in different time periods, so that the construction period can be shortened, the construction progress is accelerated, the cost is saved, the post-construction settlement is reduced, and the bearing capacity requirement of the foundation is met.
Disclosure of Invention
Aiming at the problems in the prior art, the invention provides a method for treating piles which are firstly scattered and then reinforced and are suitable for filling projects on an under-consolidated soft soil foundation.
The invention is realized in this way, a method for treating the pile after the first scattering suitable for the filling engineering on the under-consolidated soft soil foundation comprises the following steps:
s1, flattening a soft soil foundation, measuring and lofting and fixing piles;
s2, forming holes by using a double-sleeve method, vibrating a steel grouting pipe together with the double sleeves to sink into soft soil, and checking whether the grouting pipe is smooth or not by injecting clear water after the grouting pipe is inserted;
s3, after hole forming, putting gravel into the pile to form a pile, and tamping the gravel pile after constructing the gravel pile at a certain height in the pile forming process;
s4, constructing a mattress layer after the gravel pile is formed, then performing pile filling construction to a preset height, and enabling a grouting pipe to penetrate through the pile filling soil to ensure that the grouting opening is above the surface of the pile filling soil, so that subsequent grouting is facilitated;
s5, after the soil filling construction is finished, preloading is carried out on the soft soil foundation under the action of soil filling gravity, hyperstatic pore water pressure is generated in the soft soil, and gravel piles in the soft soil can be used as drainage channels to accelerate consolidation settlement of the soft soil;
s6, after the pile is loaded for a period of time, checking a reserved grouting pipe, and injecting cement slurry into the pile by using a pressure pump after the grouting pipe is ensured to be smooth;
s7, the cement slurry permeates into the broken stones, and after a period of time, broken stone aggregate is condensed, so that the pile body becomes a rigid pile with higher rigidity.
Further, in step S2, the inner sleeve of the double sleeve is provided with a groove, and the inner wall of the outer sleeve is ribbed, so that the steel grouting pipe can be conveniently inserted and fixed between the gaps of the inner and outer sleeves, and can be simultaneously vibrated and sunk into the soft soil along with the double sleeve when the pipe is vibrated and sunk.
Further, in step S2, the steel grouting pipes are open-bottomed pipes, and two steel grouting pipes are provided for each pile, and are divided to be located on both sides of the pile body.
Further, in step S4, the grouting pipe may be lengthened by welding or the like to penetrate the fill, with the grouting opening being located above the fill.
Further, in steps S5 and S6, grouting is not performed immediately after completion of gravel pile construction, but in the first place, filling construction is performed, and grouting is performed when consolidation settlement of the soft soil foundation by preloading reaches 80% or more of the estimated total settlement.
Further, in step S6, cement grout is injected into the two steel grouting pipes simultaneously by the pressure pump, and sectional lifting grouting is adopted, and the grouting pipes are pulled out after grouting; grouting must be continuously carried out, and if interruption occurs due to reasons, grouting should be immediately processed, and grouting is resumed as soon as possible to ensure grouting quality. During grouting, the grouting amount and the grouting pressure are controlled well, and the relationship between the grouting amount and the grouting pressure is considered comprehensively to determine the basis for finishing grouting, and carefully do the grouting shielding work to avoid grouting return.
Further, in step S7, after a period of time after grouting, the pile bodies are coagulated into rigid piles, and the composite foundation is changed from a discrete material pile composite foundation to a rigid pile composite foundation. And (4) soft soil drainage consolidation at the discrete material pile composite foundation stage.
Another object of the present invention is to provide a pile-after-scattering processing apparatus suitable for a filling project on an under-consolidated soft soil foundation, comprising a soft soil foundation, the soft soil foundation comprising a plurality of piles; a steel grouting pipe is inserted in the pile; the steel grouting pipes are inserted into the double-sleeve interlayer; the bottom of the steel grouting pipe is provided with a grouting hole;
the pile is filled with a gravel pile; a mattress layer is laid on the upper part of the gravel pile; the upper part of the mattress layer is paved with stacking soil.
Further, the double-sleeve comprises an outer sleeve, an inner sleeve groove and an outer sleeve pipe rib;
the steel grouting pipe is positioned at the groove of the inner sleeve;
the outer sleeve ribs are positioned on two sides of the steel grouting pipe, and the outer sleeve ribs are positioned between the outer sleeve and the inner sleeve.
Further, the gravel pile is grouted to form a rigid pile.
By combining all the technical schemes, the invention has the advantages and positive effects that:
the pile is firstly scattered and then is rigid, namely a gravel pile is firstly constructed in a soft soil foundation, a grouting pipe is reserved but is not grouted immediately, the pile is grouted after the foundation is pre-pressed for a period of time by using the self weight of the filling soil or other methods, and the pile body forms a rigid pile after grouting. In the soil filling and pre-pressing stage, the gravel pile can play a role in draining water, so that the consolidation of the unconsolidated soil is accelerated, and the construction period is shortened; after the consolidation and settlement of the soft soil are approximately completed, cement slurry is injected, and the pile body becomes a rigid pile, so that more loads can be shared. The method has the advantages that the consolidation settlement of the under-consolidated soft soil foundation is quickly completed, the construction period is shortened, and the settlement after construction is reduced; and after consolidation and settlement are basically completed, a rigid pile composite foundation is formed, and the bearing capacity of the foundation is obviously improved.
Technical effect or experimental effect of comparison. The method comprises the following steps:
when only filling is adopted for carrying out preloading, the required construction period is long and is often as long as one year, and the settlement after construction is difficult to control; when a composite foundation is formed by constructing discrete material piles in soft soil and then performing filling construction and prepressing, the lifting range of the foundation bearing capacity of the soft soil foundation is limited; when a rigid pile is constructed in soft soil to form a composite foundation and then the filling construction is carried out for prepressing, the consolidation of the under-consolidated soft soil still needs a long time, and large negative friction resistance on the pile side, which is unfavorable for the foundation, can be generated.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings needed to be used in the embodiments of the present application will be briefly described below, and it is obvious that the drawings described below are only some embodiments of the present application, and it is obvious for those skilled in the art that other drawings can be obtained from the drawings without creative efforts.
Fig. 1 is a flowchart of a method for processing a pile after first scattering, which is suitable for a filling project on an under-consolidated soft soil foundation according to an embodiment of the present invention.
Fig. 2 is a top view of a double cannula provided by an embodiment of the present invention.
Fig. 3 is a schematic view of a gravel pile composite foundation before grouting according to an embodiment of the invention.
Fig. 4 is a schematic diagram of a post-grouting rigid pile composite foundation provided by an embodiment of the invention.
In fig. 2-4: 1. soft soil foundation; 2. double-casing; 2-1, outer sleeve; 2-2, inner sleeve; 2-3, inner sleeve groove; 2-4, outer sleeve pipe ribs; 3. steel grouting pipes; 4. gravel piles; 5. a mattress layer; 6. filling soil in a pile; 7. a rigid pile.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail with reference to the following embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Aiming at the problems in the prior art, the invention provides a method for treating piles which are firstly scattered and then reinforced and are suitable for filling engineering on an under-consolidated soft soil foundation, and the invention is described in detail by combining the attached drawings.
As shown in fig. 1, the method for treating the first-scattered and second-rigid piles, which is suitable for the filling engineering on the under-consolidated soft soil foundation, provided by the invention comprises the following steps:
s101, flattening the soft soil foundation 1, measuring and lofting, and fixing piles, wherein the pile distance can be 4-6 times of the pile diameter, and the pile distance can be selected according to the actual situation of the foundation.
S102, selecting the length and the diameter of a pile according to engineering geological conditions, generally drilling through a soft soil layer to enable the end of the pile to enter a hard soil layer, forming a hole by using a double-casing method, sinking a steel grouting pipe 3 into soft soil along with a double-casing pipe 2 through vibration of mechanical equipment such as a vibration hammer, a crane and the like, inserting the steel grouting pipe 3 into the soft soil, and then injecting clear water through a grouting pump to check whether the grouting pipe is unblocked; as shown in fig. 2, the double sleeve 2 is provided with two grooves in the inner sleeve, and the inner wall of the outer sleeve is provided with ribs at the corresponding positions of the grooves of the inner sleeve, so that the steel grouting pipe 3 can be conveniently inserted into the gap between the inner sleeve and the outer sleeve and fixed at the grooves, and can be simultaneously vibrated along with the double sleeve to sink into soft soil during vibration pipe sinking; the steel grouting pipes 3 are steel pipes with holes at the bottom pipe bodies, and each pile is provided with two steel grouting pipes which are respectively positioned at two sides of the pile body.
S103, after hole forming, gravel is thrown in to form a pile, in the pile forming process, the gravel pile 4 is tamped after being constructed at a certain height, grouting is not performed immediately after the gravel pile is constructed, and only a grouting pipe is reserved for subsequent grouting.
S104, constructing a mattress layer 5 after the gravel pile is formed, and then performing pile filling 6 construction to a preset height; the grouting pipe 3 should reserve a sufficient length (capable of being lengthened by welding) on the surface of the foundation to penetrate through the filling soil, so as to ensure that the grouting opening is above the filling soil surface, and facilitate subsequent grouting work.
And S105, after the filling construction is finished, preloading is carried out for a period of time, hyperstatic pore water pressure is generated in the soft soil under the filling effect, the permeability coefficient of the gravel pile in the soft soil is large, the gravel pile can be used as a drainage channel, the drainage path is shortened, and the consolidation settlement of the soft soil can be accelerated remarkably.
S106, after a period of stacking, when the consolidation settlement of the soft soil reaches 80% or more of the estimated total settlement, grouting is started. And (3) checking the reserved grouting pipes, injecting cement slurry into the grouting pipes by using a grouting pump after the grouting pipes are ensured to be unblocked, grouting two grouting pipes 3 simultaneously during grouting, and adopting a grouting mode of sectional lifting. Because the grouting pipe is a bottom perforated pipe, cement slurry seeps out of the bottom of the grouting pipe, and the cement slurry gradually rises from the bottom of the gravel pile 4 in the sectional lifting process. During grouting, the recording work of grouting pressure, grouting amount, grouting time and other abnormal conditions is well done, the grouting amount and the grouting pressure are convenient to control, and the grouting amount of each pile is basically consistent. Grouting must be continuously carried out, and if interruption occurs due to reasons, grouting should be immediately processed, and grouting is resumed as soon as possible to ensure grouting quality. And after grouting, carefully performing slurry shielding work to avoid slurry return. And pulling out the grouting pipe after grouting.
S107, cement slurry permeates broken stones, and after a period of time, broken stone aggregate is solidified, the pile body becomes a rigid pile 7 with higher rigidity; at the moment, a rigid pile composite foundation is formed, and the bearing capacity of the foundation is obviously improved.
The invention provides a first-dispersing and second-reinforcing pile processing device suitable for filling engineering on an under-consolidated soft soil foundation, which comprises: the pile foundation comprises a soft soil foundation 1, a double-sleeve 2, an outer sleeve 2-1, an inner sleeve 2-2, an inner sleeve groove 2-3, an outer sleeve pipe rib 2-4, a steel grouting pipe 3, a gravel pile 4, a mattress layer 5, a pile filling 6 and a rigid pile 7.
Fig. 2 is a top view of a double cannula according to an embodiment of the present invention.
Fig. 3 is a schematic view of a gravel pile composite foundation before grouting according to an embodiment of the invention.
Fig. 4 is a schematic diagram of a post-grouting rigid pile composite foundation provided by an embodiment of the invention.
In the description of the present invention, "a plurality" means two or more unless otherwise specified; the terms "upper", "lower", "left", "right", "inner", "outer", "front", "rear", "head", "tail", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, are only for convenience in describing and simplifying the description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed in a particular orientation, and be operated, and thus, should not be construed as limiting the invention. Furthermore, the terms "first," "second," "third," and the like are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
The above description is only for the purpose of illustrating the present invention and the appended claims are not to be construed as limiting the scope of the invention, which is intended to cover all modifications, equivalents and improvements that are within the spirit and scope of the invention as defined by the appended claims.

Claims (2)

1.一种适用于欠固结软土地基上填方工程的先散后刚桩处理方法,其特征在于,所述适用于欠固结软土地基上填方工程的先散后刚桩处理方法包括:1. a method for the treatment of piles after first dispersing and then just piles that is applicable to filling works on under-consolidated soft soil foundations, it is characterized in that, the described method for treating firstly dispersing and then rigid piles that are applicable to filling works on under-consolidated soft soil foundations Methods include: 在软土地基中先施工碎石桩,并同时插入注浆管但不注浆,然后再进行堆填土施工;In the soft soil foundation, the gravel piles are constructed first, and the grouting pipe is inserted at the same time without grouting, and then the landfill construction is carried out; 堆填土施工后,软土在堆填土自重作用下产生超孔隙水压并排水固结;After the construction of the landfill, the soft soil will generate excess pore water pressure under the action of the self-weight of the landfill and drain and consolidate; 地基软土固结沉降完成时,再往预留的注浆管中注入水泥浆液,水泥浆液渗入碎石桩,使碎石桩的骨料凝结成为刚度较大的刚性桩;When the consolidation and settlement of the soft soil of the foundation is completed, the cement slurry is injected into the reserved grouting pipe, and the cement slurry penetrates into the gravel pile, so that the aggregate of the gravel pile is condensed into a rigid pile with high rigidity; 所述适用于欠固结软土地基上填方工程的先散后刚桩处理方法进一步包括:The method for treating the piles first and then rigid, which is suitable for filling works on under-consolidated soft soil foundations, further includes: S1,平整软土地基,测量放样并定桩;S1, level the soft soil foundation, measure the stake out and fix the pile; S2,用双套管法成孔,并将钢质注浆管随双套管一起振动沉入软土,插入注浆管后通过注入清水检查注浆管是否畅通;S2, use the double casing method to form a hole, vibrate the steel grouting pipe together with the double casing and sink it into the soft soil, insert the grouting pipe and inject clean water to check whether the grouting pipe is unobstructed; S3,成孔后投入碎石成桩,成桩过程中碎石桩每施工一定高度后进行夯实;S3, after the hole is formed, put in the gravel to form a pile, and in the process of forming the pile, the gravel pile is tamped after a certain height is constructed; S4,碎石桩成桩后施工褥垫层,然后再进行堆填土施工至预定高度,注浆管穿过堆填土;S4, after the gravel piles are formed into piles, the mattress layer is constructed, and then the landfill construction is carried out to the predetermined height, and the grouting pipe passes through the landfill; S5,填土施工完毕后,软土地基在填土重力作用下进行堆载预压,软土中产生超静孔隙水压,软土中的碎石桩作为排水通道,加快软土固结沉降;S5. After the filling construction is completed, the soft soil foundation is preloaded under the action of the filling gravity, and excess pore water pressure is generated in the soft soil. The gravel piles in the soft soil are used as drainage channels to accelerate the consolidation and settlement of the soft soil. ; S6,堆载一段时间后,检查预留的注浆管,畅通后用压力泵注入水泥浆液;S6, after stacking for a period of time, check the reserved grouting pipe, and inject cement slurry with a pressure pump after it is unblocked; S7,水泥浆液渗入碎石中,经过一段时间碎石骨料凝结,桩体成为刚度较大的刚性桩;S7, the cement slurry penetrates into the crushed stone, and after a period of time, the aggregate of the crushed stone coagulates, and the pile body becomes a rigid pile with high rigidity; 在步骤S2中,双套管的内套管设有凹槽,且外套管内壁带肋,钢质注浆管插入并固定在内外套管的空隙之间,并在振动沉管时随双套管同时振动沉入软土;In step S2, the inner casing of the double casing is provided with grooves, and the inner wall of the outer casing is ribbed, and the steel grouting pipe is inserted and fixed between the gaps of the inner and outer casings, and when the immersed pipe is vibrated, it is accompanied by the double casing. The pipe vibrates and sinks into the soft soil at the same time; 在步骤S2中,钢质注浆管为底部开口管,对于每根桩设有两根钢质注浆管,分别位于桩体的两侧;In step S2, the steel grouting pipe is an open bottom pipe, and each pile is provided with two steel grouting pipes, which are respectively located on both sides of the pile body; 在步骤S4中,通过焊接技术加长注浆管,穿过填土层,注浆口位于填土上部;In step S4, the grouting pipe is lengthened by welding technology, passes through the filling layer, and the grouting port is located on the upper part of the filling; 在步骤S5及步骤S6中,碎石桩施工完毕后并不立即注浆,先进行堆填土施工,待堆载预压至软土地基的固结沉降达到预估总沉降的高于80%时再进行注浆;In step S5 and step S6, the gravel piles are not grouted immediately after the construction is completed, and the landfill construction is carried out first, and the consolidation settlement of the soft soil foundation is preloaded until the consolidation settlement reaches more than 80% of the estimated total settlement. grouting when 在步骤S6中,通过压力泵同时向两根钢质注浆管注入水泥浆液,并采用分段提升式注浆,注浆完毕后拔出注浆管;注浆连续进行;In step S6, the two steel grouting pipes are simultaneously injected with cement grout by a pressure pump, and a segmented lift grouting is used. After the grouting is completed, the grouting pipes are pulled out; the grouting is performed continuously; 在步骤S7中,注浆后一段时间,桩体凝结成刚性桩,复合地基由散体材料桩复合地基变为刚性桩复合地基。In step S7, after grouting for a period of time, the pile body is solidified into a rigid pile, and the composite foundation is changed from a composite foundation of a bulk material pile to a composite foundation of a rigid pile. 2.一种用于权利要求1所述适用于欠固结软土地基上填方工程的先散后刚桩处理方法的装置,包括软土地基,其特征在于,所述软土地基包括多个桩;所述桩内插装有钢质注浆管;所述钢质注浆管穿插在双套管夹层中;所述钢质注浆管底部开有注浆孔;2. A device used for the method of claim 1, which is applicable to the method for treating piles first and then rigid, which is suitable for filling works on under-consolidated soft soil foundations, comprising a soft soil foundation, wherein the soft soil foundation comprises a plurality of a pile; a steel grouting pipe is inserted into the pile; the steel grouting pipe is inserted into the double casing interlayer; the bottom of the steel grouting pipe is provided with a grouting hole; 所述桩内填充有碎石桩;所述碎石桩上部铺设有褥垫层;所述褥垫层上部铺设有堆填土;The pile is filled with gravel piles; the upper part of the gravel pile is laid with a mattress; the upper part of the mattress is covered with landfill; 所述双套管包括外套管、内套管、内套管凹槽、外套管管肋;The double casing includes an outer casing, an inner casing, an inner casing groove, and an outer casing pipe rib; 所述钢质注浆管位于内套管凹槽处;The steel grouting pipe is located at the groove of the inner casing; 所述外套管管肋位于所述钢质注浆管两侧,同时所述外套管管肋位于外套管、内套管之间;The outer casing pipe rib is located on both sides of the steel grouting pipe, and the outer casing pipe rib is located between the outer casing and the inner casing; 所述碎石桩注浆后形成刚性桩。The crushed stone pile forms a rigid pile after grouting.
CN202011195496.4A 2020-10-30 2020-10-30 Applicable to the treatment method of piles first scattered and then rigid for filling works on under-consolidated soft soil foundations Active CN112227341B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011195496.4A CN112227341B (en) 2020-10-30 2020-10-30 Applicable to the treatment method of piles first scattered and then rigid for filling works on under-consolidated soft soil foundations

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011195496.4A CN112227341B (en) 2020-10-30 2020-10-30 Applicable to the treatment method of piles first scattered and then rigid for filling works on under-consolidated soft soil foundations

Publications (2)

Publication Number Publication Date
CN112227341A CN112227341A (en) 2021-01-15
CN112227341B true CN112227341B (en) 2021-07-23

Family

ID=74122631

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011195496.4A Active CN112227341B (en) 2020-10-30 2020-10-30 Applicable to the treatment method of piles first scattered and then rigid for filling works on under-consolidated soft soil foundations

Country Status (1)

Country Link
CN (1) CN112227341B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113293754B (en) * 2021-06-04 2022-09-20 华中科技大学 Slurry-solidified gravel-soil pile suitable for under-solidified soft soil foundation and reinforcing method
CN115221595B (en) * 2022-08-08 2024-07-30 建研地基基础工程有限责任公司 Method for calculating bearing capacity of gravel pellet pile based on composite foundation

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101591904A (en) * 2008-05-28 2009-12-02 徐立新 The reinforcement means of grouting following drainage prepressing type drainage body composite pile foundation
CN202039771U (en) * 2011-03-31 2011-11-16 威海建设集团股份有限公司 Long-spiral grouting and guncreting multifunctional drilling tool

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101591904A (en) * 2008-05-28 2009-12-02 徐立新 The reinforcement means of grouting following drainage prepressing type drainage body composite pile foundation
CN202039771U (en) * 2011-03-31 2011-11-16 威海建设集团股份有限公司 Long-spiral grouting and guncreting multifunctional drilling tool

Also Published As

Publication number Publication date
CN112227341A (en) 2021-01-15

Similar Documents

Publication Publication Date Title
CN103233454B (en) Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation
CN101781888B (en) Vibration sinking tube compacted gravel-concrete combined pile and construction method thereof
CN104131546B (en) A kind of processing method of collapsible loess foundation
CN108086343A (en) Overhanging type unilateral side wall mixed reinforcement and replacing structure and its construction method
CN104988815A (en) Method for treating post-construction settlement disease of railroad bed
CN112227341B (en) Applicable to the treatment method of piles first scattered and then rigid for filling works on under-consolidated soft soil foundations
CN107513994A (en) One kind segmentation becomes supporting rotary digging stake and its construction method without leave
CN105113478A (en) Dynamic compaction treatment method of deep foundation displacement
CN112081158B (en) Construction method for forming reinforced composite pile foundation by advanced grouting of high-rise building
CN117211321A (en) Construction method of integrated swirl shaft wall caisson and reverse working
CN112081155B (en) Reinforcing and lifting method for bar-shaped or box-shaped foundation building
CN112281799B (en) First-dispersing and later-reinforcing pile construction method and construction device suitable for ultra-soft soil
CN112144559B (en) Well construction method in high-water-rich loess sand pebble stratum pressure-variable pipe well
CN107012861A (en) A kind of discrete material core expansive concrete stake and its construction method
CN110453699B (en) Drainage and anti-sliding pile structure with "meter" type pile core and construction method thereof
JP2016041893A (en) Pile foundation and pile foundation construction method
CN110055845B (en) Construction method for soft soil roadbed on two sides of highway bridge and culvert
CN112942341A (en) Construction method for implanting prefabricated pipe pile into complex geology
CN106906816A (en) A kind of method for improving soft soil foundation prefabricated pile effect of driving pile
CN110144871A (en) A kind of dark bank treatment construction method
JP6431193B2 (en) C. capable of seismic reinforcement and quality control G. S method
CN114934511A (en) Post-grouting method and device for slurry wall protection pore-forming cast-in-place pile
CN211340744U (en) Soft soil foundation treatment structure
CN110106869A (en) A construction method of gravel grouting pile adjacent to business line
JP3874734B2 (en) Impermeable wall construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant