CN110011215A - Replace the combination tool and method of direct current grounding pole route suspension string - Google Patents
Replace the combination tool and method of direct current grounding pole route suspension string Download PDFInfo
- Publication number
- CN110011215A CN110011215A CN201910110265.XA CN201910110265A CN110011215A CN 110011215 A CN110011215 A CN 110011215A CN 201910110265 A CN201910110265 A CN 201910110265A CN 110011215 A CN110011215 A CN 110011215A
- Authority
- CN
- China
- Prior art keywords
- suspension string
- electrician
- pedestal
- shaft tower
- ground potential
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000000725 suspension Substances 0.000 title claims abstract description 181
- 238000000034 method Methods 0.000 title claims description 10
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 110
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 53
- 239000010959 steel Substances 0.000 claims abstract description 53
- 230000005540 biological transmission Effects 0.000 claims description 36
- 239000004020 conductor Substances 0.000 claims description 13
- 238000012216 screening Methods 0.000 claims description 6
- 238000012546 transfer Methods 0.000 claims description 3
- 238000012423 maintenance Methods 0.000 abstract description 2
- 238000004519 manufacturing process Methods 0.000 description 8
- 238000006073 displacement reaction Methods 0.000 description 6
- 238000010586 diagram Methods 0.000 description 4
- 238000009413 insulation Methods 0.000 description 4
- 230000008901 benefit Effects 0.000 description 3
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
The invention discloses a kind of combination tools for replacing direct current grounding pole route suspension string, including fixture main body, pedestal and connecting screw;The pedestal is the type structure that can be installed between two suspension string hanging point angle steel, the pedestal is mounted on the bottom surface of the fixture main body by the connecting screw, the connecting screw lower end is through the pedestal and extends downwardly, the compressible clamping plate on the bottom surface of described two suspension string hanging point angle steel is set on the lower end extended segment of the connecting screw, the position that the clamping plate bottom surface is corresponded on the connecting screw is equipped with clamp nut, the both ends of the fixture main body are fitted with an anti-torsion wire bar respectively, an insulated pull rod is respectively connected on each anti-torsion wire bar, the conducting wire that one can hook suspension string side of wire is respectively connected in the every insulated pull rod mentions line suspension hook;The replacement of direct current grounding pole route suspension string can be realized using said combination tool.Suitable for line maintenance.
Description
Technical field
The present invention relates to high voltage direct current field, in particular to a kind of combination tool for replacing direct current grounding pole route suspension string
And method.
Background technique
D.C. high voltage transmission has its unique in terms of remote, high-power conveying electric energy relative to ac transmission mode
Advantage, therefore be widely used in the point-to-point power Transmission of large capacity, overlength distance, Jiangsu, Shanghai are sent in such as western water power east
Etc. ground take the mode of D.C. high voltage transmission extensively.And the livewire work of DC transmission system is concentrated mainly on high direct voltage at present
Route and converter station lack direct current grounding pole route and further investigate, therefore DC earthing line live-line work had both lacked reason
By basis, also lack practical experience.When ground electrode circuit needs replacing suspension string, power failure operation can only be generally used, at this time
The operation of direct current system can be produced bigger effect, directly reduce power supply reliability.
Moreover, direct current grounding pole route current potential is ground potential when hvdc transmission line is under bipolar mode of operation, and in list
Ground electrode circuit then has a high voltage under the operational mode of pole, be generally considered as ground electrode circuit voltage class in actual job ±
50kV.Direct current grounding pole route is because voltage class is lower, and insulation configuration is similar to distribution line, and its current-carrying capacity
Much larger than distribution line, conducting wire is again dramatically different with distribution line.Therefore, when replacing suspension string, direct current grounding pole route band
The Work tool of electric operation can not simply continue to use the Work tool and method of distribution line or hot line maintenance.
Summary of the invention
The purpose of the invention is to overcome the shortcomings of above-mentioned background technique, it is outstanding to provide a kind of replacement direct current grounding pole route
The combination tool and method of vertical string.
In order to achieve the goal above, a kind of combination tool for replacing direct current grounding pole route suspension string provided by the invention,
Including fixture main body, pedestal and connecting screw;The pedestal is the type structure that can be installed between two suspension string hanging point angle steel,
The pedestal is mounted on the bottom surface of the fixture main body by the connecting screw, and the bottom is run through in the connecting screw lower end
Seat simultaneously extends downwardly, and is set on the lower end extended segment of the connecting screw compressible in described two suspension string hanging point angle steel
Clamping plate on bottom surface, the position that the clamping plate bottom surface is corresponded on the connecting screw are equipped with clamp nut, the fixture main body
Both ends are fitted with an anti-torsion wire bar respectively, and an insulated pull rod is respectively connected on each anti-torsion wire bar, and every described exhausted
The conducting wire that one can hook suspension string side of wire is respectively connected on edge pull rod mentions line suspension hook.
Fixture main body is fixed on suspension string shaft tower side by clamping plate and pedestal, and line suspension hook will be mentioned and hooked in suspension string conducting wire
On the conducting wire of side, the tension on suspension string can be transferred to fixture main body, anti-torsion wire bar, insulated pull rod in this way and mention line suspension hook
On, so as to realize the replacement of suspension string;Meanwhile by the way that fixture main body and pedestal are designed to two components so that it is convenient to
The transport of this combination tool, also reduces production cost.
In the above scheme, the bottom surface of the fixture main body is equipped with the fixture bottom surface spiral shell for installing the connecting screw
Hole, the interior pedestal screw hole being equipped with through the pedestal of the pedestal, the pedestal is run through in the connecting screw upper end from bottom to up
Screw hole is simultaneously inserted into the tool bottom surface screw hole to be fixed on the pedestal on the bottom surface of the fixture main body.By screw thread side
Formula connects fixture main body and pedestal, simple and convenient in this way and at low cost.
In the above scheme, corresponded on the side wall of the fixture main body connecting screw upper end position be equipped with it is described
The fixture side wall screw hole of fixture bottom surface screw hole connection, is equipped with for fixing the connecting screw in the fixture side wall screw hole
Screw rod tightening pin.The screw rod tightening pin added can be effectively prevented connecting screw and get loose.
In the above scheme, the position that the connecting screw upper end corresponds to the screw rod tightening pin is equipped with tight with the screw rod
The screw rod tightening slot that rationed marketing matches.The screw rod tightening slot added can prevent from connecting in this way with screw rod tightening pin-shaped at detent
Screw rod is deviate from out of fixture bottom surface screw hole.
In the above scheme, the height h in the clamping portion of the pedestal is less than the height H of the suspension string hanging point angle steel, institute
The space D stated between the width d in the clamping portion of pedestal and described two suspension string hanging point angle steel matches.By by the card of pedestal
The height h in dress portion is designed to the height H less than suspension string hanging point angle steel, in this way, pedestal and clamping plate can tightly be clamped in two
At the upper and lower ends of suspension string hanging point angle steel;Meanwhile by the way that the width d in the clamping portion of pedestal is designed to hang with two suspension strings
Space D between point angle steel matches, and pedestal can be prevented to be subjected to displacement in this way.
In the above scheme, the length L of the clamping plate is greater than the space D between described two suspension string hanging point angle steel.It is logical
It crosses and the length L of clamping plate is designed to the space D being greater than between two suspension string hanging point angle steel so that it is convenient to clamping for clamping plate.
In the above scheme, lock washer is equipped between the clamping plate and the clamp nut.The lock washer energy added
Clamp nut is effectively prevented to get loose.
The present invention also provides a kind of methods for replacing direct current grounding pole route suspension string, comprising the following steps:
1) ground potential electrician climbs to the ground potential electric work position of shaft tower, and ground potential electrician installs shaft tower on shaft tower to be slided surely
It takes turns and puts on shaft tower side transmission rope on shaft tower fixed pulley;
2) the first ground electrician is determined insulating bar with the conducting wire for putting on side of wire transmission rope by shaft tower side transmission rope
Pulley passes to ground potential electrician, and conducting wire fixed pulley is articulated on conducting wire by ground potential electrician by insulating bar corresponds to old hang
The position for string conductor wire end of hanging down;
3) the second ground electrician fastens insulated flexible ladder end using side of wire transmission rope, and will be exhausted using side of wire transmission rope
Edge rope ladder is mounted on the conducting wire at equipotential electrician's working position;
4) it after equipotential electrician puts on screening clothing and confirms that screening clothing connection is good, is climbed by insulated flexible ladder to away from conducting wire
Greater than potential transfer is carried out at 0.2m, into equipotential, equipotential electrician working position is reached;
5) the first ground electrician is by the fixture main body, the pedestal, the connecting screw, the clamping plate, the compression
After nut, the anti-torsion wire bar and the insulated pull rod assemble, the first ground electrician will be assembled by shaft tower side transmission rope
The fixture main body, the pedestal, the connecting screw, the clamping plate, the clamp nut, the anti-torsion wire bar and described
Insulated pull rod passes to ground potential electrician, and the second ground electrician passes through side of wire transmission rope and the line suspension hook that mentions is passed to equal electricity
Position electrician;
6) after ground potential electrician first successively removes the clamp nut and the clamping plate, then by the card of the pedestal
Dress portion is installed between two suspension string hanging point angle steel, then the clamping plate is pressed on described two hang by the clamp nut
It hangs down on the bottom surface of string hanging point angle steel, then equipotential electrician cooperates with ground potential electrician and mentions the insulated pull rod with described
Line suspension hook is connected, and last equipotential electrician catches on two conducting wires for line suspension hook is mentioned described in two respectively;
7) ground potential electrician tightens the anti-torsion wire bar, and the tension on old suspension string is transferred to the fixture main body, institute
It states anti-torsion wire bar, the insulated pull rod and described mentions on line suspension hook;
8) after checking that bearing tool stress is normal, equipotential electrician takes out the locking pin of old suspension string conductor wire end, ground potential
Electrician continues to tighten the anti-torsion wire bar, until equipotential electrician disengages the connection of old suspension string conductor wire end;
9) ground potential electrician fastens shaft tower side transmission rope one end on old suspension string shaft tower end, and the first ground electrician is by bar
The tower side transmission rope other end is fastened on new suspension string shaft tower end;
10) ground potential electrician takes out the locking pin at old suspension string shaft tower end, and the first ground electrician operates shaft tower side transmission rope
Cooperation ground potential electrician disengages the connection at old suspension string shaft tower end;
11) the first ground electrician and ground potential electrician, which cooperate, reaches ground potential electric work position for new suspension string, this
When old suspension string just fall to the ground automatically, the first ground electrician and ground potential electrician cooperate and restore new suspension string shaft tower
The connection at end, and reset the locking pin at new suspension string shaft tower end;
12) ground potential electrician cooperates equipotential electrician to restore the connection of new suspension string conductor wire end, and installs new suspension string and lead
The locking pin of line end, so far, the replacement of suspension string are completed.
Fixture main body is fixed on suspension string shaft tower side by clamping plate and pedestal, and line suspension hook will be mentioned and hooked in suspension string conducting wire
On the conducting wire of side, the tension on suspension string can be transferred to fixture main body, anti-torsion wire bar, insulated pull rod in this way and mention line suspension hook
On, so as to realize the replacement of suspension string;Meanwhile by the way that fixture main body and pedestal are designed to two components so that it is convenient to
The transport of this combination tool, also reduces production cost.
Technical solution provided by the invention has the benefit that
1, fixture main body is fixed on by suspension string shaft tower side by clamping plate and pedestal, and line suspension hook hook will be mentioned and led in suspension string
On the conducting wire of line side, the tension on suspension string can be transferred to fixture main body, anti-torsion wire bar, insulated pull rod in this way and mention line suspension hook
On, so as to realize the replacement of suspension string;
2, by the way that fixture main body and pedestal be designed to two components so that it is convenient to which the transport of this combination tool, also drops
Low production cost;
3, fixture main body and pedestal are threadedly connected, it is simple and convenient in this way and at low cost;
4, the screw rod tightening pin added can be effectively prevented connecting screw and get loose;
5, the screw rod tightening slot added can prevent connecting screw from fixture bottom surface in this way with screw rod tightening pin-shaped at detent
Abjection in screw hole;
6, by the way that the height h in the clamping portion of pedestal to be designed to the height H less than suspension string hanging point angle steel, in this way, pedestal
It can be tightly clamped in clamping plate at the upper and lower ends of two suspension string hanging point angle steel;
7, matched by the space D being designed to the width d in the clamping portion of pedestal between two suspension string hanging point angle steel
It closes, pedestal can be prevented to be subjected to displacement in this way;
8, by the way that the length L of clamping plate is designed to the space D being greater than between two suspension string hanging point angle steel so that it is convenient to
Clamping plate clamps;
9, the lock washer added can be effectively prevented clamp nut and get loose.
Detailed description of the invention
Fig. 1 is the using state structure diagram of this combination tool;
Fig. 2 is the enlarged structure schematic diagram that the portion A removes after suspension string in Fig. 1;
Fig. 3 is the structural schematic diagram of the positional relationship of fixture main body and pedestal;
Fig. 4 is another viewing angle constructions schematic diagram of Fig. 3.
In figure, fixture main body 1, fixture bottom surface screw hole 1a, fixture side wall screw hole 1b, pedestal 2, pedestal screw hole 2a, connection spiral shell
Bar 3, screw rod tightening slot 3a, clamping plate 4, clamp nut 5, anti-torsion wire bar 6, insulated pull rod 7 mention line suspension hook 8, and screw rod tightening pin 9 is prevented
Loose washer 10, suspension string hanging point angle steel a, conducting wire b.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with attached drawing to embodiment party of the present invention
Formula is described in further detail.
Embodiment 1:
A kind of combination tool of replacement direct current grounding pole route suspension string as shown in Figure 1, including fixture main body 1, pedestal 2
With connecting screw 3;The pedestal 2 is the T-type structure that can be installed between two suspension string hanging point angle steel a, and the pedestal 2 passes through
The connecting screw 3 is mounted on the bottom surface of the fixture main body 1, and 3 lower end of connecting screw is simultaneously downward through the pedestal 2
Extend, is set on the lower end extended segment of the connecting screw 3 compressible on the bottom surface of described two suspension string hanging point angle steel a
Clamping plate 4, the position that 4 bottom surface of clamping plate is corresponded on the connecting screw 3 is equipped with clamp nut 5, the two of the fixture main body 1
End is fitted with an anti-torsion wire bar 6 respectively, and an insulated pull rod 7 is respectively connected on each anti-torsion wire bar 6, and every described exhausted
The conducting wire b that one can hook suspension string side of wire is respectively connected on edge pull rod 7 mentions line suspension hook 8.It will by clamping plate 4 and pedestal 2
Fixture main body 1 is fixed on suspension string shaft tower side, and will mention line suspension hook 8 and hook on the conducting wire b of suspension string side of wire, can will hang in this way
The tension to hang down on string is transferred to fixture main body 1, anti-torsion wire bar 6, insulated pull rod 7 and mentions on line suspension hook 8, so as to realize pendency
The replacement of string;Meanwhile by the way that fixture main body 1 and pedestal 2 be designed to two components so that it is convenient to the fortune of this combination tool
It is defeated, also reduce production cost.
The bottom surface of above-mentioned fixture main body 1 is equipped with the fixture bottom surface screw hole 1a for installing the connecting screw 3, the bottom
The pedestal screw hole 2a through the pedestal 2 is equipped in seat 2, the pedestal screw hole is run through in 3 upper end of connecting screw from bottom to up
2a is simultaneously inserted into the tool bottom surface screw hole 1a to be fixed on the pedestal 2 on the bottom surface of the fixture main body 1.Pass through screw thread
Mode connects fixture main body 1 and pedestal 2, simple and convenient in this way and at low cost.Described in being corresponded on the side wall of the fixture main body 1
The position of 3 upper end of connecting screw is equipped with the fixture side wall screw hole 1b being connected to the fixture bottom surface screw hole 1a, the fixture side wall
Screw rod tightening pin 9 for fixing the connecting screw 3 is installed in screw hole 1b.The screw rod tightening pin 9 added can effectively be prevented
Only connecting screw 3 is got loose.The position that 3 upper end of connecting screw corresponds to the screw rod tightening pin 9 is equipped with and the screw rod
The screw rod tightening slot 3a that tightening pin 9 matches.The screw rod tightening slot 3a added can form detent, such energy with screw rod tightening pin 9
Prevent connecting screw 3 from deviating from out of fixture bottom surface screw hole 1a.
The height h in the clamping portion of above-mentioned pedestal 2 is less than the height H of the suspension string hanging point angle steel a, the card of the pedestal 2
Space D between the width d in dress portion and described two suspension string hanging point angle steel a matches.By by the height in the clamping portion of pedestal 2
Degree h is designed to the height H less than suspension string hanging point angle steel a, in this way, pedestal 2 and clamping plate 4 can tightly be clamped in two suspension strings
At the upper and lower ends of hanging point angle steel a;Meanwhile by the way that the width d in the clamping portion of pedestal 2 is designed to and two suspension string hanging point angles
Space D between steel a matches, and pedestal 2 can be prevented to be subjected to displacement in this way.The length L of the clamping plate 4 is greater than described two pendencys
Space D between string hanging point angle steel a.By the way that the length L of clamping plate 4 is designed to be greater than between two suspension string hanging point angle steel a
Space D is so that it is convenient to the clamping of clamping plate 4.
Lock washer 10 is equipped between above-mentioned clamping plate 4 and the clamp nut 5.The lock washer 10 added can effectively be prevented
Only clamp nut 5 is got loose.
Fixture main body 1 is fixed on suspension string shaft tower side by clamping plate 4 and pedestal 2 by the present embodiment, and will be mentioned line suspension hook 8 and be hooked
On the conducting wire b of suspension string side of wire, the tension on suspension string can be transferred to fixture main body 1, anti-torsion wire bar 6, insulation in this way
It pull rod 7 and mentions on line suspension hook 8, so as to realize the replacement of suspension string;By the way that fixture main body 1 and pedestal 2 are designed to two
Component also reduces production cost so that it is convenient to the transport of this combination tool.
Meanwhile the present embodiment threadedly connects fixture main body 1 and pedestal 2, it is simple and convenient in this way and at low cost;
The screw rod tightening pin 9 added can be effectively prevented connecting screw 3 and get loose;The screw rod tightening slot 3a added can be with screw rod tightening
Pin 9 forms detent, can prevent connecting screw 3 from deviating from out of fixture bottom surface screw hole 1a in this way.
Moreover, the height h in the clamping portion of pedestal 2 by being designed to the height less than suspension string hanging point angle steel a by the present embodiment
H is spent, in this way, pedestal 2 and clamping plate 4 can be tightly clamped at the upper and lower ends of two suspension string hanging point angle steel a;By by pedestal
The width d in 2 clamping portion is designed to that the space D between two suspension string hanging point angle steel a matches, and can prevent pedestal 2 in this way
It is subjected to displacement.
Finally, the present embodiment is by the way that the length L of clamping plate 4 to be designed between being greater than between two suspension string hanging point angle steel a
Away from D so that it is convenient to the clamping of clamping plate 4;The lock washer 10 added can be effectively prevented clamp nut 5 and get loose.
Embodiment 2:
The application method of the combination tool of above-mentioned replacement direct current grounding pole route suspension string, comprising the following steps:
1) ground potential electrician climbs to the ground potential electric work position of shaft tower, and ground potential electrician installs shaft tower on shaft tower to be slided surely
It takes turns and puts on shaft tower side transmission rope on shaft tower fixed pulley;
2) the first ground electrician is determined insulating bar with the conducting wire for putting on side of wire transmission rope by shaft tower side transmission rope
Pulley passes to ground potential electrician, and conducting wire fixed pulley is articulated on conducting wire by ground potential electrician by insulating bar corresponds to old hang
The position for string conductor wire end of hanging down;
3) the second ground electrician fastens insulated flexible ladder end using side of wire transmission rope, and will be exhausted using side of wire transmission rope
Edge rope ladder is mounted on the conducting wire at equipotential electrician's working position;
4) it after equipotential electrician puts on screening clothing and confirms that screening clothing connection is good, is climbed by insulated flexible ladder to away from conducting wire
Greater than potential transfer is carried out at 0.2m, into equipotential, equipotential electrician working position is reached;
5) the first ground electrician is by the fixture main body 1, pedestal 2, the connecting screw 3, the clamping plate 4, described
After clamp nut 5, the anti-torsion wire bar 6 and the insulated pull rod 7 assemble, the first ground electrician will by shaft tower side transmission rope
It is the assembled fixture main body 1, the pedestal 2, the connecting screw 3, the clamping plate 4, the clamp nut 5, described anti-
Torsion wire bar 6 and the insulated pull rod 7 pass to ground potential electrician, and the second ground electrician mentions line for described by side of wire transmission rope
Suspension hook 8 passes to equipotential electrician;
6) after ground potential electrician first successively removes the clamp nut 5 and the clamping plate 4, then by the pedestal 2
Clamping portion be installed between two suspension string hanging point angle steel a, then the clamping plate 4 is pressed on by institute by the clamp nut 5
On the bottom surface for stating two suspension string hanging point angle steel a, then equipotential electrician and ground potential electrician, which cooperate, draws the insulation
Bar 7 is connected with the line suspension hook 8 that mentions, and last equipotential electrician catches on two conducting wire b for line suspension hook 8 is mentioned described in two respectively;
7) ground potential electrician tightens the anti-torsion wire bar 6, by the tension on old suspension string be transferred to the fixture main body 1,
It the anti-torsion wire bar 6, the insulated pull rod 7 and described mentions on line suspension hook 8;
8) after checking that bearing tool stress is normal, equipotential electrician takes out the locking pin of old suspension string conductor wire end, ground potential
Electrician continues to tighten the anti-torsion wire bar 6, until equipotential electrician disengages the connection of old suspension string conductor wire end;
9) ground potential electrician fastens shaft tower side transmission rope one end on old suspension string shaft tower end, and the first ground electrician is by bar
The tower side transmission rope other end is fastened on new suspension string shaft tower end;
10) ground potential electrician takes out the locking pin at old suspension string shaft tower end, and the first ground electrician operates shaft tower side transmission rope
Cooperation ground potential electrician disengages the connection at old suspension string shaft tower end;
11) the first ground electrician and ground potential electrician, which cooperate, reaches ground potential electric work position for new suspension string, this
When old suspension string just fall to the ground automatically, the first ground electrician and ground potential electrician cooperate and restore new suspension string shaft tower
The connection at end, and reset the locking pin at new suspension string shaft tower end;
12) ground potential electrician cooperates equipotential electrician to restore the connection of new suspension string conductor wire end, and installs new suspension string and lead
The locking pin of line end, so far, the replacement of suspension string are completed.
Fixture main body 1 is fixed on suspension string shaft tower side by clamping plate 4 and pedestal 2, and line suspension hook 8 will be mentioned and hooked in suspension string
On the conducting wire b of side of wire, the tension on suspension string can be transferred to fixture main body 1, anti-torsion wire bar 6, insulated pull rod 7 in this way and mentioned
On line suspension hook 8, so as to realize the replacement of suspension string;Meanwhile by the way that fixture main body 1 and pedestal 2 are designed to two components,
The transport for facilitating this combination tool in this way, also reduces production cost.
Said combination tool includes fixture main body 1, pedestal 2 and connecting screw 3;The pedestal 2 is that can be installed on two to hang
T-type structure between vertical string hanging point angle steel a, the pedestal 2 are mounted on the bottom of the fixture main body 1 by the connecting screw 3
On face, 3 lower end of connecting screw is through the pedestal 2 and extends downwardly, and is set on the lower end extended segment of the connecting screw 3
There is the compressible clamping plate 4 on the bottom surface of described two suspension string hanging point angle steel a, corresponds to the clamping plate 4 on the connecting screw 3
The position of bottom surface is equipped with clamp nut 5, and the both ends of the fixture main body 1 are fitted with an anti-torsion wire bar 6 respectively, each described anti-
It is respectively connected with an insulated pull rod 7 on torsion wire bar 6, is respectively connected with one in the every insulated pull rod 7 and can hook suspension string and lead
The conducting wire b's of line side mentions line suspension hook 8.Fixture main body 1 is fixed on suspension string shaft tower side by clamping plate 4 and pedestal 2, and line will be mentioned
Suspension hook 8 hooks on the conducting wire b of suspension string side of wire, and the tension on suspension string can be transferred to fixture main body 1, anti-torsion wire bar in this way
6, it insulated pull rod 7 and mentions on line suspension hook 8, so as to realize the replacement of suspension string;Meanwhile by by fixture main body 1 and pedestal 2
Two components are designed to so that it is convenient to which the transport of this combination tool, also reduces production cost.
The bottom surface of above-mentioned fixture main body 1 is equipped with the fixture bottom surface screw hole 1a for installing the connecting screw 3, the bottom
The pedestal screw hole 2a through the pedestal 2 is equipped in seat 2, the pedestal screw hole is run through in 3 upper end of connecting screw from bottom to up
2a is simultaneously inserted into the tool bottom surface screw hole 1a to be fixed on the pedestal 2 on the bottom surface of the fixture main body 1.Pass through screw thread
Mode connects fixture main body 1 and pedestal 2, simple and convenient in this way and at low cost.Described in being corresponded on the side wall of the fixture main body 1
The position of 3 upper end of connecting screw is equipped with the fixture side wall screw hole 1b being connected to the fixture bottom surface screw hole 1a, the fixture side wall
Screw rod tightening pin 9 for fixing the connecting screw 3 is installed in screw hole 1b.The screw rod tightening pin 9 added can effectively be prevented
Only connecting screw 3 is got loose.The position that 3 upper end of connecting screw corresponds to the screw rod tightening pin 9 is equipped with and the screw rod
The screw rod tightening slot 3a that tightening pin 9 matches.The screw rod tightening slot 3a added can form detent, such energy with screw rod tightening pin 9
Prevent connecting screw 3 from deviating from out of fixture bottom surface screw hole 1a.
The height h in the clamping portion of above-mentioned pedestal 2 is less than the height H of the suspension string hanging point angle steel a, the card of the pedestal 2
Space D between the width d in dress portion and described two suspension string hanging point angle steel a matches.By by the height in the clamping portion of pedestal 2
Degree h is designed to the height H less than suspension string hanging point angle steel a, in this way, pedestal 2 and clamping plate 4 can tightly be clamped in two suspension strings
At the upper and lower ends of hanging point angle steel a;Meanwhile by the way that the width d in the clamping portion of pedestal 2 is designed to and two suspension string hanging point angles
Space D between steel a matches, and pedestal 2 can be prevented to be subjected to displacement in this way.The length L of the clamping plate 4 is greater than described two pendencys
Space D between string hanging point angle steel a.By the way that the length L of clamping plate 4 is designed to be greater than between two suspension string hanging point angle steel a
Space D is so that it is convenient to the clamping of clamping plate 4.
Lock washer 10 is equipped between above-mentioned clamping plate 4 and the clamp nut 5.The lock washer 10 added can effectively be prevented
Only clamp nut 5 is got loose.
Fixture main body 1 is fixed on suspension string shaft tower side by clamping plate 4 and pedestal 2 by the present embodiment, and will be mentioned line suspension hook 8 and be hooked
On the conducting wire b of suspension string side of wire, the tension on suspension string can be transferred to fixture main body 1, anti-torsion wire bar 6, insulation in this way
It pull rod 7 and mentions on line suspension hook 8, so as to realize the replacement of suspension string;By the way that fixture main body 1 and pedestal 2 are designed to two
Component also reduces production cost so that it is convenient to the transport of this combination tool.
Meanwhile the present embodiment threadedly connects fixture main body 1 and pedestal 2, it is simple and convenient in this way and at low cost;
The screw rod tightening pin 9 added can be effectively prevented connecting screw 3 and get loose;The screw rod tightening slot 3a added can be with screw rod tightening
Pin 9 forms detent, can prevent connecting screw 3 from deviating from out of fixture bottom surface screw hole 1a in this way.
Moreover, the height h in the clamping portion of pedestal 2 by being designed to the height less than suspension string hanging point angle steel a by the present embodiment
H is spent, in this way, pedestal 2 and clamping plate 4 can be tightly clamped at the upper and lower ends of two suspension string hanging point angle steel a;By by pedestal
The width d in 2 clamping portion is designed to that the space D between two suspension string hanging point angle steel a matches, and can prevent pedestal 2 in this way
It is subjected to displacement.
Finally, the present embodiment is by the way that the length L of clamping plate 4 to be designed between being greater than between two suspension string hanging point angle steel a
Away from D so that it is convenient to the clamping of clamping plate 4;The lock washer 10 added can be effectively prevented clamp nut 5 and get loose.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all in spirit of the invention and
Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.
Claims (8)
1. a kind of combination tool for replacing direct current grounding pole route suspension string, which is characterized in that including fixture main body (1), pedestal
(2) and connecting screw (3);The pedestal (2) is the T-type structure that can be installed between two suspension string hanging point angle steel (a), described
Pedestal (2) is mounted on the bottom surface of the fixture main body (1) by the connecting screw (3), and connecting screw (3) lower end is passed through
It wears the pedestal (2) and extends downwardly, be set on the lower end extended segment of the connecting screw (3) compressible described two outstanding
The clamping plate (4) to hang down on the bottom surface of string hanging point angle steel (a), the position that the clamping plate (4) bottom surface is corresponded on the connecting screw (3) are set
Have clamp nut (5), the both ends of the fixture main body (1) are fitted with an anti-torsion wire bar (6), each anti-torsion wire bar respectively
(6) it is respectively connected with an insulated pull rod (7) on, is respectively connected with one on the every insulated pull rod (7) suspension string can be hooked and lead
The conducting wire (b) of line side mentions line suspension hook (8).
2. the combination tool of replacement direct current grounding pole route suspension string according to claim 1, which is characterized in that the card
Has the bottom surface of main body (1) equipped with the fixture bottom surface screw hole (1a) for installing the connecting screw (3), the pedestal (2) is interior
Equipped with the pedestal screw hole (2a) for running through the pedestal (2), the pedestal screw hole is run through in connecting screw (3) upper end from bottom to up
It (2a) and is inserted into tool bottom surface screw hole (1a) to be fixed on the pedestal (2) on the bottom surface of the fixture main body (1).
3. the combination tool of replacement direct current grounding pole route suspension string according to claim 2, which is characterized in that the card
The position that the connecting screw (3) upper end is corresponded on the side wall for having main body (1) is equipped with to be connected to fixture bottom surface screw hole (1a)
Fixture side wall screw hole (1b), the screw rod for fixing the connecting screw (3) is installed in the fixture side wall screw hole (1b)
Tightening pin (9).
4. the combination tool of replacement direct current grounding pole route suspension string according to claim 3, which is characterized in that the company
Screw rod (3) upper end is connect to correspond to the position of the screw rod tightening pin (9) to be equipped with the screw rod that matches with the screw rod tightening pin (9) tight
Determine slot (3a).
5. the combination tool of replacement direct current grounding pole route suspension string according to claim 1, which is characterized in that the bottom
The height h in the clamping portion of seat (2) is less than the height H of the suspension string hanging point angle steel (a), the width in the clamping portion of the pedestal (2)
Degree d is matched with the space D between described two suspension string hanging point angle steel (a).
6. the combination tool of replacement direct current grounding pole route suspension string according to claim 1, which is characterized in that the folder
The length L of plate (4) is greater than the space D between described two suspension string hanging point angle steel (a).
7. the combination tool of replacement direct current grounding pole route suspension string according to claim 1, which is characterized in that the folder
Lock washer (10) are equipped between plate (4) and the clamp nut (5).
8. replacing DC earthing polar curve using the combination tool of replacement direct current grounding pole route suspension string as described in claim 1
The method of road suspension string, which comprises the following steps:
1) ground potential electrician climbs to the ground potential electric work position of shaft tower, and ground potential electrician installs shaft tower fixed pulley simultaneously on shaft tower
Shaft tower side transmission rope is put on shaft tower fixed pulley;
2) the first ground electrician passes through shaft tower side transmission rope for insulating bar and the conducting wire fixed pulley for putting on side of wire transmission rope
Ground potential electrician is passed to, conducting wire fixed pulley is articulated on conducting wire by insulating bar and corresponds to old suspension string by ground potential electrician
The position of conductor wire end;
3) the second ground electrician fastens insulated flexible ladder end using side of wire transmission rope, and it is soft to be insulated using side of wire transmission rope
Ladder is mounted on the conducting wire at equipotential electrician's working position;
4) it after equipotential electrician puts on screening clothing and confirms that screening clothing connection is good, is climbed by insulated flexible ladder to away from conducting wire and is greater than
Potential transfer is carried out at 0.2m, into equipotential, reaches equipotential electrician working position;
5) the first ground electrician by the fixture main body (1), the pedestal (2), the connecting screw (3), the clamping plate (4),
After the clamp nut (5), the anti-torsion wire bar (6) and the insulated pull rod (7) assemble, the first ground electrician passes through shaft tower
Side transmission rope is by the assembled fixture main body (1), the pedestal (2), the connecting screw (3), the clamping plate (4), institute
It states clamp nut (5), the anti-torsion wire bar (6) and the insulated pull rod (7) and passes to ground potential electrician, the second ground electrician is logical
It crosses side of wire transmission rope and the line suspension hook (8) that mentions is passed into equipotential electrician;
6) after ground potential electrician first successively removes the clamp nut (5) and the clamping plate (4), then by the pedestal
(2) clamping portion is installed between two suspension string hanging point angle steel (a), then passes through the clamp nut (5) for the clamping plate (4)
It is pressed on the bottom surface of described two suspension string hanging point angle steel (a), then equipotential electrician and ground potential electrician mutual cooperation will
The insulated pull rod (7) is connected with the line suspension hook (8) that mentions, and last equipotential electrician will mention line suspension hook (8) respectively described in two
Catch on two conducting wires (b);
7) ground potential electrician tightens the anti-torsion wire bar (6), by the tension on old suspension string be transferred to the fixture main body (1),
It the anti-torsion wire bar (6), the insulated pull rod (7) and described mentions on line suspension hook (8);
8) after checking that bearing tool stress is normal, equipotential electrician takes out the locking pin of old suspension string conductor wire end, ground potential electrician
Continue to tighten the anti-torsion wire bar (6), until equipotential electrician disengages the connection of old suspension string conductor wire end;
9) ground potential electrician fastens shaft tower side transmission rope one end on old suspension string shaft tower end, and the first ground electrician is by shaft tower side
The transmission rope other end is fastened on new suspension string shaft tower end;
10) ground potential electrician takes out the locking pin at old suspension string shaft tower end, and the first ground electrician operates the cooperation of shaft tower side transmission rope
Ground potential electrician disengages the connection at old suspension string shaft tower end;
11) the first ground electrician and ground potential electrician, which cooperate, reaches ground potential electric work position for new suspension string, old at this time
Suspension string is just fallen to the ground automatically, and the first ground electrician and ground potential electrician cooperate and restore new suspension string shaft tower end
Connection, and reset the locking pin at new suspension string shaft tower end;
12) ground potential electrician cooperates equipotential electrician to restore the connection of new suspension string conductor wire end, and installs new suspension string conductor wire end
Locking pin, so far, the replacement of suspension string is completed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910110265.XA CN110011215A (en) | 2019-02-11 | 2019-02-11 | Replace the combination tool and method of direct current grounding pole route suspension string |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910110265.XA CN110011215A (en) | 2019-02-11 | 2019-02-11 | Replace the combination tool and method of direct current grounding pole route suspension string |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110011215A true CN110011215A (en) | 2019-07-12 |
Family
ID=67165720
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910110265.XA Pending CN110011215A (en) | 2019-02-11 | 2019-02-11 | Replace the combination tool and method of direct current grounding pole route suspension string |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110011215A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111815206A (en) * | 2020-08-26 | 2020-10-23 | 国网湖北省电力有限公司检修公司 | Direct current grounding electrode electrical variable measuring system and state evaluation method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105932599A (en) * | 2016-06-17 | 2016-09-07 | 国网湖南省电力公司带电作业中心 | Tool set capable of replacing insulator chain of ultra-high-voltage transmission line under electrified state and use method for tool set |
CN106840484A (en) * | 2017-04-11 | 2017-06-13 | 浙江维思无线网络技术有限公司 | High voltage transmission line hanging plate weighing sensor |
CN207490441U (en) * | 2017-12-06 | 2018-06-12 | 贵州电网有限责任公司 | A kind of preformed strain insulator list insulator string charged for replacement fixture |
CN207572853U (en) * | 2017-12-19 | 2018-07-03 | 国网福建省电力有限公司莆田供电公司 | A kind of shaft tower insulator chain electrification replacing tool |
CN209434754U (en) * | 2019-02-11 | 2019-09-24 | 国家电网有限公司 | Replace the combination tool of direct current grounding pole route suspension string |
-
2019
- 2019-02-11 CN CN201910110265.XA patent/CN110011215A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105932599A (en) * | 2016-06-17 | 2016-09-07 | 国网湖南省电力公司带电作业中心 | Tool set capable of replacing insulator chain of ultra-high-voltage transmission line under electrified state and use method for tool set |
CN106840484A (en) * | 2017-04-11 | 2017-06-13 | 浙江维思无线网络技术有限公司 | High voltage transmission line hanging plate weighing sensor |
CN207490441U (en) * | 2017-12-06 | 2018-06-12 | 贵州电网有限责任公司 | A kind of preformed strain insulator list insulator string charged for replacement fixture |
CN207572853U (en) * | 2017-12-19 | 2018-07-03 | 国网福建省电力有限公司莆田供电公司 | A kind of shaft tower insulator chain electrification replacing tool |
CN209434754U (en) * | 2019-02-11 | 2019-09-24 | 国家电网有限公司 | Replace the combination tool of direct current grounding pole route suspension string |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111815206A (en) * | 2020-08-26 | 2020-10-23 | 国网湖北省电力有限公司检修公司 | Direct current grounding electrode electrical variable measuring system and state evaluation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201263063Y (en) | Tool for replacing straight-line simply connected double-string overhang insulator | |
CN209344700U (en) | A kind of PVC cable protection pipe convenient for connection installation | |
CN203288783U (en) | Electricity detection type high-voltage ground wire rod | |
CN104535804A (en) | Portable current transformer test clamp | |
CN209434754U (en) | Replace the combination tool of direct current grounding pole route suspension string | |
CN110011215A (en) | Replace the combination tool and method of direct current grounding pole route suspension string | |
CN106450835A (en) | Shoe manufacturer high voltage wire landing device | |
CN209434753U (en) | For replacing the fixture component of direct current grounding pole route suspension string | |
CN201233972Y (en) | Multifunctional connecting plug | |
CN209434748U (en) | Side of wire yoke plate clamp for vertical rotary replacement direct current grounding pole line tension string | |
CN209434747U (en) | The combination tool of horizontal rotation method replacement direct current grounding pole line tension string | |
CN106877262A (en) | A kind of suspension clamp with weight hitch point | |
CN208656288U (en) | The replacement tool of ground electrode circuit insulator and fitting | |
CN209434752U (en) | The combination tool of vertical rotary method replacement direct current grounding pole line tension string | |
CN209434751U (en) | Machete card component for vertical rotary method replacement direct current grounding pole line tension string | |
CN209434749U (en) | For rotating horizontally the rotating hanger component of method replacement direct current grounding pole line tension string | |
CN211208698U (en) | Novel complete set grounding device for 220kV power transmission line | |
CN209434750U (en) | For rotating horizontally the bottle-holding rack hanger of method replacement direct current grounding pole line tension string | |
CN205863425U (en) | A kind of earth lead in scalable direction | |
CN105449612A (en) | A conductive wire insulation support plate apparatus | |
CN209119682U (en) | A kind of dedicated side's of returning device of cable conductor | |
CN202550391U (en) | High-voltage power maintenance implement | |
CN203166450U (en) | A detachable lightning arrester | |
CN109672111A (en) | The combination tool and method of horizontal rotation method replacement direct current grounding pole line tension string | |
CN109217170A (en) | The replacement tool of ground electrode circuit insulator and fitting |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190712 |