CN110006507A CN201910149668.5A CN201910149668A CN110006507A CN 110006507 A CN110006507 A CN 110006507A CN 201910149668 A CN201910149668 A CN 201910149668A CN 110006507 A CN110006507 A CN 110006507A
Authority
CN
China
Prior art keywords
water level
anshi
vertical shaft
level observation
boring method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910149668.5A
Other languages
Chinese (zh)
Inventor
翁益松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhoushan Water Resources Survey And Design Institute
Original Assignee
Zhoushan Water Resources Survey And Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhoushan Water Resources Survey And Design Institute filed Critical Zhoushan Water Resources Survey And Design Institute
Priority to CN201910149668.5A priority Critical patent/CN110006507A/en
Publication of CN110006507A publication Critical patent/CN110006507A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01FMEASURING VOLUME, VOLUME FLOW, MASS FLOW OR LIQUID LEVEL; METERING BY VOLUME
    • G01F23/00Indicating or measuring liquid level or level of fluent solid material, e.g. indicating in terms of volume or indicating by means of an alarm
    • G01F23/30Indicating or measuring liquid level or level of fluent solid material, e.g. indicating in terms of volume or indicating by means of an alarm by floats
    • G01F23/64Indicating or measuring liquid level or level of fluent solid material, e.g. indicating in terms of volume or indicating by means of an alarm by floats of the free float type without mechanical transmission elements

Landscapes

  • Physics & Mathematics (AREA)
  • Fluid Mechanics (AREA)
  • General Physics & Mathematics (AREA)
  • Earth Drilling (AREA)

Abstract

Boring method Jian Anshi water level observation well mechanism, it leads the way including controller, sensor, vertical shaft, floating ball, diversion tunnel, auxiliary and decontamination mechanism, the vertical shaft top is equipped with sensor, sensor is connected by conducting wire with controller, floating ball is placed in vertical shaft, it is connected below vertical shaft with diversion tunnel, diversion tunnel right part is equipped with decontamination mechanism, is equipped with auxiliary below diversion tunnel 5 and leads the way;The invention has the advantages that establishing boring method builds bank formula water level observation well, in such a way that Vertical Well and diversion channel combine, changing tradition to build tower is that drill mode without building trestle substantially reduces engineering construction difficulty and construction investment.

Description

Boring method Jian Anshi water level observation well mechanism
Technical field
The present invention relates to boring method Jian Anshi water level observation well mechanisms, belong to hydrotechnics field.
Background technique
In recent years, increasing with global harsh weather, local extra torrential rain, the burst mountain torrents and Super Typhoon etc. in China The frequency of occurrences of extreme weather increased significantly, intensity increased, coverage is in increase tendency, will be especially in the presence of to reservoir The safety of the reservoir of sick danger hidden danger, which constitutes, to be seriously threatened.Often there is reservoir to break down accident, cause huge personnel's wound It dies and economic loss, lesson is deep.Therefore, accurate measurements reservoir level information understands reservoir level dynamic, it has also become each in time Grade hydraulic department urgent problem to be solved, meanwhile, in order to reach rational management and the management of flood control, in addition to will be in work of building water conservancy projects Journey is made great efforts outside raising with whole people's water-disaster-conscience etc. is improved, it is often more important that accurate, the safe and reliable property of one kind is selected to pass through again by force The practical water level monitoring system that helps to grasp Hydrologic Information in time.Therefore, reservoir level monitoring becomes the hydrology, hydraulic department Important research direction, the water level logging system built at present have it is following several, emphasis reservoir based on vertical shaft, water level platform be island or Excavation builds bank formula, and general reservoir is based on inclined shaft.Its defect is as follows: the 1 vertical inspection well for building island platform will build trestle waterborne And pier, investment is high, difficulty of construction is big, day-to-day operation maintenance cost is high;The 2 vertical inspection wells for building bank slope platform want generous Earth and stone digging is measured, investment is high, construction risk is big, generous amount excavates the landfill cubic metre of earth and stone and easily causes soil erosion, and environment influences Greatly;3 inclined inspection wells are because well logging pipe linking is difficult to theoretic straight line, and water level wheel machining accuracy is not high enough, tiltedly The reasons such as well pedestal sedimentation easily cause water level monitoring data inaccurate.
Summary of the invention
The object of the present invention is to provide boring method Jian Anshi water level observation well mechanisms.
The problem to be solved in the present invention is the defect of existing water level logging system in design.
To achieve the purpose of the present invention, the technical solution adopted by the present invention is that:
Boring method Jian Anshi water level observation well mechanism, including controller, sensor, vertical shaft, floating ball, diversion tunnel, auxiliary are drawn Road and decontamination mechanism, the vertical shaft top are equipped with sensor, and sensor is connected by conducting wire with controller, vertical shaft It is inside placed with floating ball, is connected below vertical shaft with diversion tunnel, diversion tunnel right part is equipped with decontamination mechanism, is equipped with below diversion tunnel 5 Auxiliary is led the way.
The vertical shaft and diversion tunnel are located in hillside.
The auxiliary is led the way L-shaped.
It being equipped in PE pipe and turns in one's mind in the vertical shaft and diversion tunnel, bore mode is first to be bored to beat vertical shaft with hammering, after Diversion tunnel is beaten with hidden hole drilling.
The sensor is laser ranging module or ultrasonic distance measuring module.
The controller is single-chip microcontroller or plc structure, and interior equipped with GPRS locating module.
The decontamination mechanism includes fixed link, water-proof electric telescopic rod, spiral spinner, blade, waterproof machine, water-proof electric Telescopic rod left end is fixed with fixed link, and right end is fixed with waterproof machine, spiral spinner, propeller are equipped in waterproof machine shaft Blade is installed, water-proof electric telescopic rod and waterproof machine are connected with controller on cap.
The propeller cap portion is hollow, global density 1g/cm.
The invention has the advantages that establishing boring method builds bank formula water level observation well, combined using Vertical Well and diversion channel Mode, changing tradition to build tower is that drill mode without building trestle substantially reduces engineering construction difficulty and construction investment, simultaneously It is also convenient for operation and maintenance and management in the future.It is compared with the traditional method compared with new boring method Jian Anshi water level observation well mechanism is more Economy, safer, effect is more preferable, has good market prospects.
Detailed description of the invention
Fig. 1 is boring method Jian Anshi water level observation well mechanism main view;
Fig. 2 is the enlarged diagram of decontamination mechanism 7;
In figure: 1, controller 2, sensor 3, vertical shaft 4, floating ball 5, diversion tunnel 6, auxiliary lead the way 7, decontamination Mechanism.
Specific embodiment
The present invention is further illustrated with reference to the accompanying drawings and embodiments.
Boring method Jian Anshi water level observation well mechanism, including controller 1, sensor 2, vertical shaft 3, floating ball 4, diversion tunnel 5,6, decontamination mechanism 7 of leading the way is assisted, it is characterised in that: 3 top of vertical shaft is equipped with sensor 2, and sensor 2 passes through conducting wire It is connected with controller 1, floating ball 4 is placed in vertical shaft 3, for incuding water level, 3 lower section of vertical shaft is connected with diversion tunnel 5 It is logical, it realizes that reservoir Quick water-inducing, 5 right part of diversion tunnel are equipped with decontamination mechanism 7, prevent from blocking, auxiliary is equipped with below diversion tunnel 5 and is led the way 6, reach double-layer safety, allows the water to normally flow into diversion tunnel 5.
The vertical shaft 3 and diversion tunnel 5 are located in hillside, build simple, and 5 mouthfuls of diversion tunnel are additionally provided with and rotatably enclose Column.
The auxiliary is led the way 6 L-shaped.
It is equipped in PE pipe and turns in one's mind in the vertical shaft 3 and diversion tunnel 5, external casting concrete makes it have good knot Structure intensity, bore mode are first to be bored to beat vertical shaft 3 with hammering, after with hidden hole drilling beat diversion tunnel 5, guarantee the precision pierced, really It protects Vertical Well and diversion channel is effectively docked, reduce error, reduce the blindness of construction, save the duration, improve construction efficiency, tool There is very high economic benefit, while can accomplish that soft, hard stratum, basement rock etc. effectively pierce using the bore mode.
The sensor 2 is laser ranging module or ultrasonic distance measuring module, laser ranging module model LOG18071501。
The controller 1 is single-chip microcontroller or plc structure, and interior equipped with GPRS locating module, can adopt C51 series monolithic The signal of collection is sent to monitoring personnel.
The decontamination mechanism 7 includes fixed link 8, water-proof electric telescopic rod 9, spiral spinner 10, blade 11, waterproof machine 12,9 left end of water-proof electric telescopic rod is fixed with fixed link 8, and right end is fixed with waterproof machine 12, installs in 12 shaft of waterproof machine There is spiral spinner 10, blade 11, water-proof electric telescopic rod 9 and waterproof machine 12 and 1 phase of controller are installed on spiral spinner 10 Connection.
10 part of spiral spinner is hollow, global density 1g/cm, and the such service life of equipment length of density close to water is not easy Generate weight power.
Application method: when wanting to understand water level, the water in diversion tunnel 5 reaches vertical shaft 3, is incuded by sensor 2 floating The position of ball 4 passes information to controller 1, and controller 1 is sent to human observer, when there is sundries to block water inlet, can lead to It crosses the control movement of decontamination mechanism 7 of controller 1 to be excluded, therefore there is good reliability.
Electric telescopic rod, waterproof machine, propeller these do not need.Bigger material is not had under water, submersible machine is also easy It is bad.As long as conducting oneself the decontamination mechanism that work can dismantle in water inlet openning.

Claims (8)

1. boring method Jian Anshi water level observation well mechanism, including controller (1), sensor (2), vertical shaft (3), floating ball (4), Diversion tunnel (5), auxiliary lead the way (6), decontamination mechanism (7), it is characterised in that: vertical shaft (3) top be equipped with sensor (2), sensor (2) is connected by conducting wire with controller (1), is placed with floating ball (4) in vertical shaft (3), under vertical shaft (3) Side is connected with diversion tunnel (5), and diversion tunnel (5) right part is equipped with decontamination mechanism (7), and auxiliary is equipped with below diversion tunnel (5) and is led the way (6).
2. boring method Jian Anshi water level observation well mechanism according to claim 1, it is characterized in that: the vertical shaft (3) It is located in hillside with diversion tunnel (5).
3. boring method Jian Anshi water level observation well mechanism according to claim 1, it is characterized in that: the auxiliary leads the way (6) It is L-shaped.
4. boring method Jian Anshi water level observation well mechanism according to claim 1, it is characterized in that: the vertical shaft (3) Turn in one's mind with being equipped in PE pipe in diversion tunnel (5), bore mode is first to be bored to beat vertical shaft (3) with hammering, after with hidden hole drilling play diversion Hole (5).
5. boring method Jian Anshi water level observation well mechanism according to claim 1, it is characterized in that: the sensor (2) is Laser ranging module or ultrasonic distance measuring module.
6. boring method Jian Anshi water level observation well mechanism according to claim 1, it is characterized in that: the controller (1) is Single-chip microcontroller or plc structure, and it is interior equipped with GPRS locating module.
7. boring method Jian Anshi water level observation well mechanism according to claim 1, it is characterized in that: the decontamination mechanism (7) Including fixed link (8), water-proof electric telescopic rod (9), spiral spinner (10), blade (11), waterproof machine (12), water-proof electric is stretched Contracting bar (9) left end is fixed with fixed link (8), and right end is fixed with waterproof machine (12), is equipped with spiral shell in waterproof machine (12) shaft Revolve spinner (10), be equipped with blade (11) on spiral spinner (10), water-proof electric telescopic rod (9) and waterproof machine (12) with control Device (1) is connected.
8. boring method Jian Anshi water level observation well mechanism according to claim 1, it is characterized in that: the spiral spinner (10) Part is hollow, global density 1g/cm.
CN201910149668.5A 2019-02-28 2019-02-28 Boring method Jian Anshi water level observation well mechanism Pending CN110006507A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910149668.5A CN110006507A (en) 2019-02-28 2019-02-28 Boring method Jian Anshi water level observation well mechanism

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910149668.5A CN110006507A (en) 2019-02-28 2019-02-28 Boring method Jian Anshi water level observation well mechanism

Publications (1)

Publication Number Publication Date
CN110006507A true CN110006507A (en) 2019-07-12

Family

ID=67166147

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910149668.5A Pending CN110006507A (en) 2019-02-28 2019-02-28 Boring method Jian Anshi water level observation well mechanism

Country Status (1)

Country Link
CN (1) CN110006507A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114183126A (en) * 2021-12-16 2022-03-15 上海长凯岩土工程有限公司 Implementation method for ectopic water level observation of dewatering well

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130289878A1 (en) * 2012-04-26 2013-10-31 Korea Institute Of Geoscience And Mineral Resources System for monitoring coastal underground water
CN106092251A (en) * 2016-06-23 2016-11-09 舟山市水利勘测设计院 A kind of water level observation well monitoring system
CN205719177U (en) * 2016-06-23 2016-11-23 舟山市水利勘测设计院 One builds bank formula water level observation well
CN108871506A (en) * 2018-07-18 2018-11-23 黑龙江省林业科学研究所 A kind of hydrologic monitoring device
CN109204758A (en) * 2018-10-06 2019-01-15 江苏新韩通船舶重工有限公司 A kind of propeller for preventing sundries from winding

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130289878A1 (en) * 2012-04-26 2013-10-31 Korea Institute Of Geoscience And Mineral Resources System for monitoring coastal underground water
CN106092251A (en) * 2016-06-23 2016-11-09 舟山市水利勘测设计院 A kind of water level observation well monitoring system
CN205719177U (en) * 2016-06-23 2016-11-23 舟山市水利勘测设计院 One builds bank formula water level observation well
CN108871506A (en) * 2018-07-18 2018-11-23 黑龙江省林业科学研究所 A kind of hydrologic monitoring device
CN109204758A (en) * 2018-10-06 2019-01-15 江苏新韩通船舶重工有限公司 A kind of propeller for preventing sundries from winding

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114183126A (en) * 2021-12-16 2022-03-15 上海长凯岩土工程有限公司 Implementation method for ectopic water level observation of dewatering well
CN114183126B (en) * 2021-12-16 2023-09-19 上海长凯岩土工程有限公司 Implementation method for abnormal observation water level of precipitation well

Similar Documents

Publication Publication Date Title
CN102758430B (en) Large-diameter rotary digging pile construction technology for ultra-deep dumped unconsolidated soil bodies
CN101922302A (en) Fault processing method of high pressure water enrichment area
CN1831250A (en) Construction technology of dry soil taking hole forming method of rotary digging drilling machine
CN102226340B (en) Construction method for rock-entering cast-in-situ bored piles with diameter of less than 1.5m
CN108590706A (en) One kind being used for speciality single-track railway tunnel drifter with booms Construction Techniques of Grouting in Heavy Curtain
CN110093912A (en) A kind of surface subsidence deformation monitoring device and its construction method
CN205719868U (en) Contaminated soil and subsoil water inject in situ repairs the pilot system that dilation angle determines
CN203066913U (en) Hole drilling construction equipment of reverse circulation drill
CN111691397A (en) Karst tunnel bottom filling bead string type karst cave steel pipe pile grouting hole forming method
CN110630325B (en) Draining method for long-distance tunnel by utilizing horizontal directional drilling
CN106761674B (en) It is a kind of integrate draw water and the ground of unrestrained water test lead directly to down-hole drilling device
CN110006507A (en) Boring method Jian Anshi water level observation well mechanism
CN208506279U (en) A kind of auger underground water level detecting device
CN109083181A (en) Collapsible loess super long large diameter pile foundation churning driven half bore mud wet process pore-forming technique
CN207988946U (en) A kind of drilling follow pile pile drilling machine with reamer
CN208310757U (en) A kind of rich water weak soil, the artificial bore detecting device of thin silt ultra-deep pipeline
CN105275389A (en) Double-rod well drilling machine
CN111005379A (en) Construction method for removing pile body of reinforced concrete cast-in-place pile
CN113417644B (en) Karst cave detection method in shield construction process
CN213539092U (en) Foundation pile bores core and detects auxiliary device
CN210887222U (en) Grouting pipe for hydrologic special test recharge well
CN109681119B (en) Full-blade spiral drilling machine and PHC tubular pile foundation construction method
CN201747260U (en) Double-drill pipe well drill rig
CN206815303U (en) Observation of groundwater levels bores into well
CN202832330U (en) Sand mechanism and drilling tool

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination