CN110003671A - The comprehensive ice melting system of snow melt anti-rut agent and road surface - Google Patents

The comprehensive ice melting system of snow melt anti-rut agent and road surface Download PDF

Info

Publication number
CN110003671A
CN110003671A CN201910267400.1A CN201910267400A CN110003671A CN 110003671 A CN110003671 A CN 110003671A CN 201910267400 A CN201910267400 A CN 201910267400A CN 110003671 A CN110003671 A CN 110003671A
Authority
CN
China
Prior art keywords
road
asphalt
snow melt
carbon fiber
course
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910267400.1A
Other languages
Chinese (zh)
Other versions
CN110003671B (en
Inventor
秦怡懈
肖衡林
郑紫园
郭高强
李智奇
王柳叶
马强
陈智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei University of Technology
Original Assignee
Hubei University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei University of Technology filed Critical Hubei University of Technology
Priority to CN201910267400.1A priority Critical patent/CN110003671B/en
Publication of CN110003671A publication Critical patent/CN110003671A/en
Application granted granted Critical
Publication of CN110003671B publication Critical patent/CN110003671B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C08ORGANIC MACROMOLECULAR COMPOUNDS; THEIR PREPARATION OR CHEMICAL WORKING-UP; COMPOSITIONS BASED THEREON
    • C08KUse of inorganic or non-macromolecular organic substances as compounding ingredients
    • C08K13/00Use of mixtures of ingredients not covered by one single of the preceding main groups, each of these compounds being essential
    • C08K13/02Organic and inorganic ingredients
    • CCHEMISTRY; METALLURGY
    • C08ORGANIC MACROMOLECULAR COMPOUNDS; THEIR PREPARATION OR CHEMICAL WORKING-UP; COMPOSITIONS BASED THEREON
    • C08KUse of inorganic or non-macromolecular organic substances as compounding ingredients
    • C08K3/00Use of inorganic substances as compounding ingredients
    • C08K3/16Halogen-containing compounds
    • CCHEMISTRY; METALLURGY
    • C08ORGANIC MACROMOLECULAR COMPOUNDS; THEIR PREPARATION OR CHEMICAL WORKING-UP; COMPOSITIONS BASED THEREON
    • C08KUse of inorganic or non-macromolecular organic substances as compounding ingredients
    • C08K5/00Use of organic ingredients
    • C08K5/04Oxygen-containing compounds
    • C08K5/09Carboxylic acids; Metal salts thereof; Anhydrides thereof
    • C08K5/098Metal salts of carboxylic acids
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/24Methods or arrangements for preventing slipperiness or protecting against influences of the weather
    • E01C11/26Permanently installed heating or blowing devices ; Mounting thereof
    • E01C11/265Embedded electrical heating elements ; Mounting thereof
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/18Coherent pavings made in situ made of road-metal and binders of road-metal and bituminous binders
    • E01C7/26Coherent pavings made in situ made of road-metal and binders of road-metal and bituminous binders mixed with other materials, e.g. cement, rubber, leather, fibre
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/32Coherent pavings made in situ made of road-metal and binders of courses of different kind made in situ
    • CCHEMISTRY; METALLURGY
    • C08ORGANIC MACROMOLECULAR COMPOUNDS; THEIR PREPARATION OR CHEMICAL WORKING-UP; COMPOSITIONS BASED THEREON
    • C08KUse of inorganic or non-macromolecular organic substances as compounding ingredients
    • C08K3/00Use of inorganic substances as compounding ingredients
    • C08K3/16Halogen-containing compounds
    • C08K2003/162Calcium, strontium or barium halides, e.g. calcium, strontium or barium chloride
    • CCHEMISTRY; METALLURGY
    • C08ORGANIC MACROMOLECULAR COMPOUNDS; THEIR PREPARATION OR CHEMICAL WORKING-UP; COMPOSITIONS BASED THEREON
    • C08KUse of inorganic or non-macromolecular organic substances as compounding ingredients
    • C08K3/00Use of inorganic substances as compounding ingredients
    • C08K3/16Halogen-containing compounds
    • C08K2003/166Magnesium halide, e.g. magnesium chloride
    • CCHEMISTRY; METALLURGY
    • C08ORGANIC MACROMOLECULAR COMPOUNDS; THEIR PREPARATION OR CHEMICAL WORKING-UP; COMPOSITIONS BASED THEREON
    • C08KUse of inorganic or non-macromolecular organic substances as compounding ingredients
    • C08K2201/00Specific properties of additives
    • C08K2201/014Additives containing two or more different additives of the same subgroup in C08K

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Medicinal Chemistry (AREA)
  • Polymers & Plastics (AREA)
  • Organic Chemistry (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention belongs to the current technical fields of road safety, it is related to the comprehensive ice melting system of a kind of snow melt anti-rut agent and road surface, the comprehensive ice melting system in road surface includes asphalt concrete road structure, carbon fiber electrically hot systems and is formed by snow melt asphalt uplayer based on snow melt pitch;Snow melt asphalt uplayer is laid on the upper surface of asphalt concrete road structure;Carbon fiber electrically hot systems are placed between snow melt asphalt uplayer and asphalt concrete road structure.The present invention provides one kind can effectively ensure deicing or snow melting effect, the comprehensive ice melting system of the snow melt anti-rut agent of corrosion resistant degree of corrosion height and environmental protection and saving and road surface.

Description

The comprehensive ice melting system of snow melt anti-rut agent and road surface
Technical field
The invention belongs to the current technical field of road safety, it is related to a kind of deicing salt and road surface deicing device, more particularly to The comprehensive ice melting system of a kind of snow melt anti-rut agent and road surface.
Background technique
China is vast in territory, and northern winter often faces the ice and snow accumulation of serious ice and snow problem, especially pavement of road Traffic management departments at different levels are annoying always with removing problem, it is direct indirect caused by being frozen every year due to pavement of road accumulated snow Economic loss reaches several hundred million members.The processing problem of pavement of road accumulated snow icing is paid much attention in countries in the world for a long time, carries out The technical methods that a variety of improvement road snows freeze are explored in a large amount of correlation test research.In summary, Road is administered Area snow icing method mainly has removing method and melts method two major classes: 1) removing method can be divided into artificial removing and mechanical removal;2) Melt rule and is divided into chemical method and hot thawing method.Wherein, common deicing salt is that cost is most cheap using being, and application is the most A kind of extensive method of deicing or snow melting.However, shedding for deicing salt needs biggish cost of labor, and for constructing in winter Personnel for, personal safety is a major challenge again.And chloride salt snow melt, ice melting agent large-scale use brought by it is negative Effect is increasingly becoming emphasis concerned by people.But road after villaumite is handled service life can reduce 50%, this to warp Ji causes huge loss.Traditional Environmental-protection type deicing salt MG-104, calcium acetate magnesium salt, acetic acid sylvite and urea etc. are to peripheral ring Border, the corrosion of road accessory structure and influence are relatively small, but its snow melt higher cost, inefficiency.But it just depends merely on and melts The use for avenging agent, in severe cold weather, but seems and proves definitely inferior, it is necessary to comprehensively utilize other forms method snow melt Ice.With the development of science and technology having developed a kind of mode snow-removing and ice-thawing that electric heating system is combined with deicing salt.But in plain asphalt In road surface, due to the characteristic of asphalt roads, if being laid with heating cable like that with traditional cement concrete pavement for another example, it is easy to Since the uneven load, differential settlement and unreasonable use on road surface lead to the destruction of heating cable, in addition, if single The use of heat-generating system in a large amount of uses of non-severe cold weather is that can generate a large amount of waste of energy.
Summary of the invention
In order to solve the above technical problems in background technology, the present invention provides one kind can effectively ensure snow melt Ice effect, the comprehensive ice melting system of the snow melt anti-rut agent of corrosion resistant degree of corrosion height and environmental protection and saving and road surface.
To achieve the goals above, the present invention adopts the following technical scheme:
A kind of snow melt anti-rut agent, it is characterised in that: the snow melt anti-rut agent is by calcium chloride, potassium acetate, calcium acetate And four kinds of raw materials of magnesium chloride are made, the weight percent of four kinds of components is as follows in the snow melt anti-rut agent:
Preferably, the present invention used by calcium chloride, potassium acetate, calcium acetate and magnesium chloride weight ratio be 1: 3:2:3.
Preferably, the method applied in the present invention the following steps are included:
1) prepare raw material calcium chloride, potassium acetate, calcium acetate and magnesium chloride;
2) raw material prepared respectively step 1) is dried, is ground and screening process;The mode of the drying is It is dried using the vibrated fluidized bed of ZLG3 × 0.30;70~140 DEG C of the inlet air temperature of the vibrated fluidized bed, leaving air temp 40~70 DEG C, evaporation water ability is 20~35kg/h;The mode of the grinding is ground with flour mill;The screening is to filter out partial size Range is the powder of 2 ± 1mm, is ready for use on step 3);
3) calcium chloride, potassium acetate, calcium acetate and magnesium chloride are obtained after mixing according to foregoing component proportion To finished product.
It is a kind of that the snow melt pitch to be formed is prepared based on foregoing snow melt anti-rut agent, it is characterised in that: the snow melt Pitch includes AC-13 type pitch and adds the foregoing snow melt anti-rut agent in AC-13 type pitch, and the snow melt is anti- The additive amount of rut agent is the 5%-10% of AC-13 type asphalt quality.
A kind of comprehensive ice melting system in road surface, it is characterised in that: the comprehensive ice melting system in the road surface includes bituminous concrete road Line structure, carbon fiber electrically hot systems and foregoing snow melt pitch are formed by snow melt asphalt uplayer;The snow melt drip Green upper layer is laid on the upper surface of asphalt concrete road structure;The carbon fiber electrically hot systems are placed in snow melt asphalt uplayer Between asphalt concrete road structure.
Preferably, carbon fiber electrically hot systems used by present invention institute include carbon fiber grille, distribution control box, synthesis Measurement and control instrument, temperature sensor, electric valve and alternating current incoming end;The carbon fiber grille is laid on snow melt asphalt uplayer and drip Between green concrete road line structure;The electric valve being connected with alternating current incoming end is provided in the distribution control box;The distribution Control cabinet, temperature sensor, carbon fiber grille and comprehensive control instrument are sequentially connected composition closed circuit;The comprehensive control instrument It is the electric integrated measurement and control instrument of PMW2000 series.
Preferably, carbon fiber grille used by present invention institute is tied up by carbon fiber line and glass dimension grid grid It forms;The carbon fiber line is the heater wire being composed of carbon fiber, Teflon and stainless steel cloth;Adjacent two carbon fibers The spacing tieed up between line is 7.5mm;The size of the glass dimension grid grid is 75mm × 75mm;The glass ties up grid grid Shape be square, glass dimension grid grid through being not less than 80kN/m, the glass dimension to broadwise breaking strength Grid grid through being not less than 3% to broadwise elongation at break.
Preferably, asphalt concrete road structure used by present invention institute includes being successively set on road from top to bottom The Sub-course Asphalt Concrete, Sub-sealing Course, roadbase, road subbase course and road cushion on soil matrix layer;The carbon fiber Electric heating system is placed between snow melt asphalt uplayer and the Sub-course Asphalt Concrete.
Preferably, road cushion used by present invention institute is dense structure of skeleton, the compacting of the road cushion Degree is not less than 80% not less than 96%, CBR value;0.075mm percent of pass does not surpass in gradation composition used by the road cushion Cross 5%;The road subbase course is identical as the thickness of roadbase;The road subbase course and roadbase are all made of cement Stabilization gravel is laid with;Cement stabilized macadam 7d unconfined compressive strength is not less than 2.5MPa in the road subbase course;The road Cement stabilized macadam 7d unconfined compressive strength is not less than 3.5MPa in base course;By heavy compaction standard, the road base The compactness of layer is not less than 97%, and the compactness of the roadbase is not less than 98%;The Sub-sealing Course uses single layer pitch table Face disposition;The Sub-course Asphalt Concrete uses close-graded Coarse Graded Bituminous Concrete, and the close-graded coarse grain formula pitch is mixed The model for coagulating soil is AC-25C, and the Sub-course Asphalt Concrete thickness is not less than 45mm.
A kind of construction method of the comprehensive ice melting system in road surface, it is characterised in that: the construction method the following steps are included:
1) according to highway asphalt concrete pavement construction technique normalizing and construction process requirement, in the upper table of the earth base of road layer Face successively laying road bed course, road subbase course, roadbase, Sub-sealing Course and the Sub-course Asphalt Concrete from bottom to top, shape At asphalt concrete road structure;The road cushion is dense structure of skeleton, and the compactness of the road cushion is not less than 96%, CBR value are not less than 80%;0.075mm percent of pass is no more than 5% in gradation composition used by the road cushion;Institute It is identical as the thickness of roadbase to state road subbase course;The road subbase course and roadbase are all made of cement stabilized macadam It is laid with;Cement stabilized macadam 7d unconfined compressive strength is not less than 2.5MPa in the road subbase course;In the roadbase Cement stabilized macadam 7d unconfined compressive strength is not less than 3.5MPa;By heavy compaction standard, the compacting of the road subbase course Degree is not less than 97%, and the compactness of the roadbase is not less than 98%;The Sub-sealing Course uses single layer asphalt topping;Institute The Sub-course Asphalt Concrete is stated using close-graded Coarse Graded Bituminous Concrete, the model of the close-graded Coarse Graded Bituminous Concrete It is AC-25C, the Sub-course Asphalt Concrete thickness is not less than 45mm;
2) it is laid with carbon fiber grille in the upper surface of the Sub-course Asphalt Concrete, and drip is fixed on by line card and cement nail The upper surface of green concrete cutting optimal;The carbon fiber grille is tied up by carbon fiber line and glass dimension grid grid; The carbon fiber line is the heater wire being composed of carbon fiber, Teflon and stainless steel cloth;Adjacent two carbon fiber lines Between spacing be 7.5mm;The size of the glass dimension grid grid is 75mm × 75mm;The shape of the glass dimension grid grid Shape is square, glass dimension grid grid through being not less than 80kN/m, the glass fiber grid to broadwise breaking strength Grid through being not less than 3% to broadwise elongation at break;Carbon fiber grille is laid with size requirement: being along track line arrangement width 0.6~0.9m, the carbon fiber grille of a length of 8~10m are arranged in the bicycle road of outside;It is installed again outside road structure with automatically controlled Case, electric valve, comprehensive controller and connection control route processed and and temperature sensor formation loop;Work as temperature sensor When detecting road environment temperature lower than -2 DEG C, starts electric heating system, close electric heating system when higher than -2 DEG C;The comprehensive control instrument is The electric integrated measurement and control instrument of PMW2000 series;
3) PC-3 emulsified asphalt sticking layer oil is dispensed in the upper surface of the Sub-course Asphalt Concrete, the PC-3 emulsified asphalt is viscous The dosage of layer oil is 0.5~0.7L/m2;The PC-3 emulsified asphalt sticking layer oil Asphalt Content 50%;
4) in the upper surface of PC-3 emulsified asphalt sticking layer oil laying snow melt asphalt uplayer and to design standard, road surface is completed The final maintenance of structure obtains the comprehensive ice melting system in road surface;The snow melt asphalt uplayer is obtained by snow melt asphalt paving;Institute Stating snow melt pitch includes the snow melt anti-rut agent of AC-13 type pitch and addition in AC-13 type pitch, the snow melt Rut resistance The additive amount of agent is the 5%-10% of AC-13 type asphalt quality;The snow melt anti-rut agent is by calcium chloride, potassium acetate, acetic acid Four kinds of raw materials of calcium and magnesium chloride are made;The weight percent of four kinds of components is as follows in the snow melt anti-rut agent:
Preferably, the calcium chloride, potassium acetate, calcium acetate and magnesium chloride weight ratio be 1:3:2:3.
The invention has the advantages that
The present invention snow melt scarce capacity and electric heating system under conventional ice and snow weather under severe cold weather for novel snow melting pitch Unite energy waste the problem of, propose the comprehensive ice melting system in a kind of snow melt anti-rut agent, snow melt pitch and road surface;The anti-vehicle of the snow melt Rut agent uses the composite snow-melting agent of the acetate production containing the villaumites such as calcium, magnesium and calcium, potassium, effectively reduces the harm to environment, It is a kind of efficient snow melting material, and a kind of anti-rut agent best in quality.In ice and snow weather deicing salt from being precipitated, road is realized Road is from ice-melt function;The comprehensive ice melting system in the road surface is conventional pitch concrete road line structure, novel snow melting asphalt surface course and carbon Fiber-electric heating system three parts composition.Novel snow melting asphalt surface course is mixed on the basis of traditional road asphalt material and be joined NEW TYPE OF COMPOSITE deicing salt.Electric heating system utilizes external electric power, thermal energy is provided to road surface by inbuilt carbon fiber grille, with reality The function of existing severe cold weather system deicing or snow melting.The system utilizes snow melt agent material and electric energy, general ice and snow day air flue well Realize that deicing or snow melting, severe cold weather are opened electric heating system and melted simultaneously using electric heating deicing or snow melting from snow melt agent material is precipitated in road Snow pitch can provide booster action when pavement temperature does not rise, delay to freeze.The present invention is using inexpensive environmentally friendly snow melt Agent material, efficient electric heating utilization rate and the good pressure resistance of carbon fiber, fold resistance, corrosion resistance, it is more environmentally-friendly to save durable, symbol It is practical to close engineering.In construction method, is completely spread using snow melt asphalt surface course but electric heating system is only laid with one-lane novel construction Cost is greatly lowered while guaranteeing deicing or snow melting efficiency in method.With the technology phase of single use electrothermal way deicing or snow melting Than, the present invention takes full advantage of a kind of novel snow melting pitch, power consumption is reduced, and liberated manpower, support personnel's safety, simultaneously Environmental protection and saving;And the snow melt pitch completely to pave makes the heating wire for only needing to be laid with a lane two-wheel line is i.e. certifiable to melt Snowization ice effect.So the technology with single use deicing salt, it is insufficient that the invention avoids severe cold weather deicing salt ice melting capabilities The problem of, while environmental protection and saving, both reduced costs and in turn ensured deicing or snow melting efficiency.
Detailed description of the invention
Fig. 1 is that carbon fiber grille of the invention buries schematic diagram;
Fig. 2 is that carbon fiber of the invention buries diagrammatic cross-section;
Fig. 3 is the embedded schematic diagram of carbon fiber grille of the invention in asphalt surface course;
Figure label:
1- snow melt asphalt uplayer;2- pitch the Sub-course Asphalt Concrete;3- Sub-sealing Course;4- roadbase;Under 5- road Base;6- road cushion;8- carbon fiber grille;10- distribution control box;11- comprehensive control instrument;12- temperature sensor;13- electricity Valve.
Specific embodiment
Firstly, the snow melt anti-rut agent is by calcium chloride, potassium acetate, vinegar the present invention provides a kind of snow melt anti-rut agent Four kinds of raw materials of sour calcium and magnesium chloride are made, and the weight percent of four kinds of components is as follows in the snow melt anti-rut agent:
The preparation flow of snow melt anti-rut agent: this deicing salt raw material is calcium chloride, potassium acetate, calcium acetate and magnesium chloride.Chlorine Change calcium and magnesium chloride suffers from good deicing or snow melting ability, calcium acetate and potassium acetate compare traditional salt deicing salt environment-friendly type more By force, the corrosion of road pavement is smaller.Through testing, preferred ingredient mass percent is calcium chloride 8% to 14%, and potassium acetate is 30% to 35%, calcium acetate is 20% to 25% and magnesium chloride is 30% to 35%.The specific match ratio of this programme selects chlorination Calcium: potassium acetate: calcium acetate: magnesium chloride=1:3:2:3, by raw material stoving, grinding, screening, (wherein, drying uses ZLG3 × 0.30 Vibrated fluidized bed drying, 70~140 DEG C of the inlet air temperature of vibrated fluidized bed, 40~70 DEG C of leaving air temp, evaporation water ability is 20~35kg/h;Grinding is ground with flour mill, is sieved to filter out the powder that particle size range is 2 ± 1mm) after, match according to this Composition and division in a proportion produces New Kind of Solvent of Snow-melted, has lower freezing point, can effectively prevent and prevent bituminous pavement under cryogenic It freezes.The adaptive temperature range of deicing salt is wider, and road pavement properties influence smaller.It is demonstrated experimentally that it be not only it is a kind of high The snow melting material of effect, and a kind of anti-rut agent best in quality.
In addition, the snow melt pitch to be formed is prepared based on snow melt anti-rut agent the present invention also provides a kind of, the snow melt pitch Including AC-13 type pitch and add in AC-13 type pitch as preceding record snow melt anti-rut agent, snow melt anti-rut agent Additive amount is the 5%-10% of AC-13 type asphalt quality.While the ratio can have the effect of preferable deicing or snow melting, manufacture is melted Snow pitch properties evidence meets national regulation.
Referring to Fig. 1, Fig. 2 and Fig. 3, the present invention provides a kind of comprehensive ice melting system in road surface, the comprehensive ice melting systems in road surface Snow melt asphalt uplayer 1 is formed by including asphalt concrete road structure, carbon fiber electrically hot systems and based on snow melt pitch; Snow melt asphalt uplayer 1 is laid on the upper surface of asphalt concrete road structure;Carbon fiber electrically hot systems are placed on snow melt pitch Between surface layer 1 and asphalt concrete road structure.
Wherein: carbon fiber electrically hot systems include carbon fiber grille 8, distribution control box 10, comprehensive control instrument 11, temperature sensing Device 12, electric valve 13 and alternating current incoming end;Carbon fiber grille 8 is laid on snow melt asphalt uplayer and asphalt concrete road knot Between structure;The electric valve 13 being connected with alternating current incoming end is provided in distribution control box 10;Distribution control box 10, temperature sensor 12, carbon fiber grille 8 and comprehensive control instrument 11 are sequentially connected composition closed circuit, and comprehensive control instrument 11 is PMW2000 series Electric integrated measurement and control instrument.Carbon fiber grille 8 is tied up by carbon fiber line and glass dimension grid grid;Carbon fiber line be by The heater wire that carbon fiber, Teflon and stainless steel cloth are composed;Spacing between adjacent two carbon fiber lines is 7.5mm;The size that glass ties up grid grid is 75mm × 75mm;The shape of glass dimension grid grid is square, and glass ties up lattice Aperture plate lattice through being not less than 80kN/m to broadwise breaking strength, glass tie up grid grid through to equal with broadwise elongation at break Not less than 3%.
Asphalt concrete road structure includes below the bituminous concrete being successively set on the earth base of road layer from top to bottom Layer 2, Sub-sealing Course 3, roadbase 4, road subbase course 5 and road cushion 6;Carbon fiber electrically hot systems are placed in above snow melt pitch Between layer 1 and the Sub-course Asphalt Concrete 2.Road cushion 6 is dense structure of skeleton, and the compactness of road cushion 6 is not less than 96%, CBR value are not less than 80%;0.075mm percent of pass is no more than 5% in gradation composition used by road cushion 6;Road bottom Base 5 is identical as the thickness of roadbase 4;Road subbase course 5 and roadbase 4 are all made of cement stabilized macadam laying;Road Cement stabilized macadam 7d unconfined compressive strength is not less than 2.5MPa in sub-base road 5;Cement stabilized macadam 7d in roadbase 4 Unconfined compressive strength is not less than 3.5MPa;By heavy compaction standard, the compactness of road subbase course 5 is not less than 97%, road The compactness of base 4 is not less than 98%;Sub-sealing Course 3 uses single layer asphalt topping;In Sub-sealing Course include emulsified asphalt and Gather materials;Wherein the content of the emulsified asphalt in Sub-sealing Course is not less than 60%;The usage amount of emulsified asphalt is 1.0~1.2kg/m3; Gathering materials using ES-3 type in Sub-sealing Course, the dosage gathered materials are 5m3/1000m2, the thickness to gather materials is not less than 1cm;Bituminous concrete Cutting optimal 2 uses close-graded Coarse Graded Bituminous Concrete, and the model of close-graded Coarse Graded Bituminous Concrete is AC-25C, and pitch is mixed Solidifying soil 2 thickness of cutting optimal is not less than 45mm.
A kind of construction method of the comprehensive ice melting system in road surface, construction method the following steps are included:
1) according to highway asphalt concrete pavement construction technique normalizing and construction process requirement, in the upper table of the earth base of road layer Face successively laying road bed course 6, road subbase course 5, roadbase 4, Sub-sealing Course 3 and the Sub-course Asphalt Concrete from bottom to top 2, form asphalt concrete road structure;Road cushion 6 is dense structure of skeleton, and the compactness of road cushion 6 is not less than 96%, CBR value are not less than 80%;0.075mm percent of pass is no more than 5% in gradation composition used by road cushion 6;Road bottom Base 5 is identical as the thickness of roadbase 4;Road subbase course 5 and roadbase 4 are all made of cement stabilized macadam laying;Road Cement stabilized macadam 7d unconfined compressive strength is not less than 2.5MPa in sub-base road 5;Cement stabilized macadam 7d in roadbase 4 Unconfined compressive strength is not less than 3.5MPa;By heavy compaction standard, the compactness of road subbase course 5 is not less than 97%, road The compactness of base 4 is not less than 98%;Sub-sealing Course 3 uses single layer asphalt topping;The content of emulsified asphalt is not less than 60%; The usage amount of emulsified asphalt is 1.0~1.2kg/m3;Gather materials using ES-3 type, dosage 5m3/1000m2, the thickness to gather materials is low In 1cm;The Sub-course Asphalt Concrete 2 uses close-graded Coarse Graded Bituminous Concrete, the type of close-graded Coarse Graded Bituminous Concrete It number is AC-25C, 2 thickness of the Sub-course Asphalt Concrete is not less than 45mm;
2) it is laid with carbon fiber grille 8 in the upper surface of the Sub-course Asphalt Concrete 2, and is fixed on by line card and cement nail The upper surface of the Sub-course Asphalt Concrete 2;Carbon fiber grille 8 is tied up by carbon fiber line and glass dimension grid grid; Carbon fiber line is the heater wire being composed of carbon fiber, Teflon and stainless steel cloth;Between adjacent two carbon fiber lines Spacing be 7.5mm;The size that glass ties up grid grid is 75mm × 75mm;The shape of glass dimension grid grid is square, Glass tie up grid grid through to broadwise breaking strength be not less than 80kN/m, glass tie up grid grid through being broken to broadwise Elongation is not less than 3%;It is laid with temperature sensor 12, temperature sensor 12 is placed among two carbon fiber heating wires and keeps Level, apart from heating cable about 25~35mm;Construction road module be laid with size requirement: along track line arrangement width be 0.6~ 0.9m, the heating module of a length of 8~10m are arranged in the bicycle road of outside;Installed again outside road structure distribution control box 10, Electric valve 13, comprehensive controller 11 and connection control route and and the formation loop of temperature sensor 12;Comprehensive controller 11 be the electric integrated measurement and control instrument of PMW2000 series, and the functions such as energy monitor, analysis, control are focused on an easy economy by it Device in, conventional analog electromagnetic equipment can be replaced completely, instead of a large amount of single transmitters and instrument.
3) PC-3 emulsified asphalt sticking layer oil, PC-3 emulsified asphalt adhesion coating are dispensed in the upper surface of the Sub-course Asphalt Concrete 2 The dosage of oil is 0.5~0.7L/m2;PC-3 emulsified asphalt sticking layer oil Asphalt Content 50%;
4) in the upper surface of PC-3 emulsified asphalt sticking layer oil laying snow melt asphalt uplayer 1 and to design standard, road is completed The final maintenance of face structure obtains the comprehensive ice melting system in road surface;Snow melt asphalt uplayer 1 is obtained by snow melt asphalt paving;Melt Snow pitch includes the snow melt anti-rut agent of AC-13 type pitch and addition in AC-13 type pitch, the addition of snow melt anti-rut agent Amount is the 5%-10% of AC-13 type asphalt quality;Snow melt anti-rut agent is grouped as by four kinds of following groups of weight percent:
Specifically, calcium chloride, potassium acetate, calcium acetate and magnesium chloride weight ratio be 1:3:2:3.
The course of work of the invention: after Winter Snow starts, asphalt concrete pavement temperature is begun to decline.Work as pavement temperature Near 0 DEG C, there is icing trend on road surface, and under wheel impacts effect, the deicing salt in pitch starts to be precipitated.Water in air Divide and absorbed rapidly by solid matter deliquescent in deicing salt and generate deliquescence phenomenon, so that ice and snow surface is formed a small amount of water, melt Snow agent particle, which gradually dissolves, forms snow melt agent solution.Because solid phase (ice and snow) vapour pressure is greater than liquid phase (snow melt agent solution), at this time Solid phase starts to melt to liquid phase, i.e. ice and snow.If weather further deteriorates, when deicing salt is not enough to deicing or snow melting everywhere. It opens carbon fiber-electric heating system and tides over warm-up phase under the auxiliary of deicing salt, transmit heat to asphalt concrete pavement.Make Asphalt concrete pavement temperature is maintained at 0 DEG C or more, to realize the function of road deicing or snow melting.
Snow melt pitch realizes the function of snow-ice melting system using the vapour pressure principle that seif-citing rate and soluble-salt reduce water, Carbon fiber electrically hot systems transfer heat to covering by transferring heat to asphalt concrete pavement, asphalt concrete pavement again Ice and snow layer on it melts its heat, Lai Shixian road deicing or snow melting.Novel snow melting pitch be a kind of NEW TYPE OF COMPOSITE deicing salt with AC-13 asphalt mixing is made.It realizes snow-ice melting system using the vapour pressure principle that seif-citing rate and soluble-salt reduce water Function.Since carbon fiber and glass fibre all have the advantages that tensile strength is high, both fibrages are pacified at grid It is placed in asphalt surface course.Road surface cracking resistance and the thorough ability of anti-vehicle can effectively be enhanced;Spy strong using the electric conductivity of carbon fiber simultaneously Point can quickly generate heat road surface by electric heating, so that ice and snow on road surfaces fast melt, realizes the snow melt being simple and efficient Change ice.
The present invention is applied in bituminous concrete using a kind of novel carbon fiber grid, as a kind of heat-generating system.In conjunction with NEW TYPE OF COMPOSITE deicing salt before ensure that the road deicing or snow melting of general rain and snow weather, start carbon fiber in severe cold weather Electric heating system is tieed up, the use of NEW TYPE OF COMPOSITE deicing salt is aided with.The efficient utilization rate for guaranteeing the energy, is reduced environmental pollution.To sum up, It comprehensively utilizes novel snow melting pitch and carbon fiber electrically hot systems and can be used as a kind of new grind to the process of deicing or snow melting Study carefully direction and application field, there is an urgent need to a kind of ice melting system that can be used for asphalt concrete road road surface and its matched applies Work method.
Carbon fiber electrically hot systems are using external electric power, by the carbon fiber grille 8 of laying to snow melt asphalt uplayer 1 The functional system of thermal energy is provided, is arranged on asphalt roads the Sub-course Asphalt Concrete 2, including control route, outside is furnished with Distribution control box 10, comprehensive control instrument 11, electric valve 13, placement temperature sensor 12, consolidation nail.Distribution control box 10, synthesis Measurement and control instrument 11, control route, the connection of carbon fiber grille 8 form closed circuit, control electric valve 13 by distribution control box 10, then By 13 switch control line of electric valve, distribution control box 10 can also control the size of electric current, can be with by comprehensive control instrument 11 When detect current conditions, an emergency situation is encountered, can immediately by distribution control box 10 disconnect electric valve 13.Temperature sensor 12 is Surface temperature is measured, comprehensive control instrument 11 can the temperature signal that is transmitted by temperature sensor 12 of real-time reception.Pavement temperature is detected, Control electric heating conversion rate.
Below in conjunction with specific embodiments and its attached drawing is to comprehensive utilization novel snow melting pitch provided by the invention and carbon The technical solution of fiber+electric heating asphalt concrete pavement ice melting system and construction method is described further.
Embodiment 1
Specific step is as follows for implementation:
1) according to highway asphalt concrete pavement construction technique normalizing and construction process requirement, on the earth base of road layer 7 according to The secondary road cushion 6 for being laid with 20mm thickness, bed course 6 are dense structure of skeleton, and compactness >=96%, CBR value is no less than 80%; As antifreeze bedding course, 0.075mm percent of pass is no more than 5% in gradation composition.Then 19mm thickness is laid with cement stabilized macadam Underlayment 5 is equally laid with the base 4 of 19mm thickness with cement stabilized macadam.Cement stabilized macadam 7d unconfined compressive strength is not small In 3.5MPa, underlayment is not less than 2.5MPa;Compactness of subbase is not less than 98%, and base roadbed (is not less than 97% Heavy compaction standard).
2) pave the saturating oil reservoir of spread PC-2 emulsified asphalt before Sub-sealing Course, dosage 1.0L/m2(bitumen content 50%).
3) it is laid with Sub-sealing Course 3, using single layer asphalt topping;The content of emulsified asphalt is not less than 60% in Sub-sealing Course; The usage amount of emulsified asphalt is 1.0~1.2kg/m in Sub-sealing Course3;Gather materials using ES-3 type, dosage 5m3/1000m2, with a thickness of 1cm。
4) asphalt concrete cutting optimal 2, using close-graded Coarse Graded Bituminous Concrete (AC-25C), with a thickness of 45mm。
5) carbon fiber lattice made of being tied up as carbon fiber line and glass dimension grid grid on the Sub-course Asphalt Concrete 2 Grid 8 are fixed with line card and cement nail, and carbon fiber line is the heater wire being composed of carbon fiber+Teflon+stainless steel cloth, Spacing is 7.5mm, and glass ties up grid grid having a size of 75mm × 75mm, and shape is square, through to broadwise breaking strength not Less than 80kn/m, through being not less than 3% to broadwise elongation at break.It is laid with control route 9 and temperature sensor 12, temperature sensing Device 12 is placed in holding level among two carbon fiber heating wires, apart from heating cable about 25mm.Construction road module is laid with size It is required that: it is 0.6m along track line arrangement width, the heating module of a length of 8m is arranged in the bicycle road of outside.Melted according to practical section Snowization ice demand determines to be laid with total length.
6) spread PC-3 emulsified asphalt sticking layer oil between asphalt concrete pavement, dosage 0.5L/m2(bitumen content 50%).
7) it is laid with novel snow melting pitch and is laid with upper layer, bituminous concrete upper layer is made to reach designed elevation 60mm, it is complete At the final maintenance of pavement structure, and then the pitch for completing to be equipped with entire novel snow melting pitch and carbon fiber electric heating ice melting system is mixed Solidifying dirt road line structure.
8) distribution control box 10, electric valve 13, comprehensive controller 11, connection control route 9 are installed again outside road structure Closed circuit is formed with temperature sensor 12.Complete the drip of entire comprehensive utilization novel snow melting pitch and carbon fiber electrically hot systems The debugging of green concrete road surface ice melting system is checked and accepted.
9) after Winter Snow starts, asphalt concrete pavement temperature is begun to decline.Near pavement temperature is lower than 0 DEG C, road There is icing trend in face, and under wheel impacts effect, the deicing salt in pitch starts to be precipitated, and gradually melts from part as the time increases Change is extended to comprehensive thawing, completes deicing or snow melting work.If weather further deteriorates, deicing salt is not enough to deicing or snow melting everywhere When.It opens carbon fiber-electric heating system and tides over warm-up phase under the auxiliary of deicing salt, transmit heat to asphalt concrete pavement Amount.Asphalt concrete pavement temperature is set to be maintained at 0 DEG C or more, to realize the function of road deicing or snow melting.

Claims (10)

1. a kind of snow melt anti-rut agent, it is characterised in that: the snow melt anti-rut agent be by calcium chloride, potassium acetate, calcium acetate with And four kinds of raw materials of magnesium chloride are made, the weight percent of four kinds of components is as follows in the snow melt anti-rut agent:
Weight percentages of components (%)
Calcium chloride 8-14;
Potassium acetate 30-35;
Calcium acetate 20-25;
Magnesium chloride 30-35.
2. snow melt anti-rut agent according to claim 1, it is characterised in that: the calcium chloride, potassium acetate, calcium acetate and The weight ratio of magnesium chloride is 1:3:2:3.
3. the preparation method of snow melt anti-rut agent as claimed in claim 1 or 2, it is characterised in that: the method includes following Step:
1) prepare raw material calcium chloride, potassium acetate, calcium acetate and magnesium chloride;
2) raw material prepared respectively step 1) is dried, is ground and screening process;The mode of the drying is to use The drying of the vibrated fluidized bed of ZLG3 × 0.30;70 ~ 140 DEG C of the inlet air temperature of the vibrated fluidized bed, is steamed by 40 ~ 70 DEG C of leaving air temp Shampoo divides ability to be 20 ~ 35kg/h;The mode of the grinding is ground with flour mill;The screening is to filter out particle size range to be The powder of 2 ± 1mm, is ready for use on step 3);
3) calcium chloride, potassium acetate, calcium acetate and magnesium chloride are mixed according to component proportion described in claims 1 or 2 equal Finished product is obtained after even.
4. a kind of prepare the snow melt pitch to be formed based on snow melt anti-rut agent of any of claims 1 or 2, it is characterised in that: institute Stating snow melt pitch includes that AC-13 type pitch and the snow melt as claimed in claim 1 or 2 added in AC-13 type pitch are anti- The additive amount of rut agent, the snow melt anti-rut agent is the 5%-10% of AC-13 type asphalt quality.
5. a kind of comprehensive ice melting system in road surface, it is characterised in that: the comprehensive ice melting system in the road surface includes asphalt concrete road Structure, carbon fiber electrically hot systems and snow melt asphalt uplayer (1) is formed by based on snow melt pitch as claimed in claim 4; The snow melt asphalt uplayer (1) is laid on the upper surface of asphalt concrete road structure;The carbon fiber electrically hot systems are placed in Between snow melt asphalt uplayer (1) and asphalt concrete road structure.
6. the comprehensive ice melting system in road surface according to claim 5, it is characterised in that: the carbon fiber electrically hot systems include carbon Fiber grid (8), distribution control box (10), comprehensive control instrument (11), temperature sensor (12), electric valve (13) and alternating current connect Enter end;The carbon fiber grille (8) is laid between snow melt asphalt uplayer and asphalt concrete road structure;It is described with automatically controlled The electric valve (13) being connected with alternating current incoming end is provided in case (10) processed;The distribution control box (10), temperature sensor (12), carbon fiber grille (8) and comprehensive control instrument (11) are sequentially connected composition closed circuit;The comprehensive control instrument (11) is The electric integrated measurement and control instrument of PMW2000 series.
7. the comprehensive ice melting system in road surface according to claim 6, it is characterised in that: the carbon fiber grille (8) is by carbon Fiber line and glass dimension grid grid are tied up;The carbon fiber line is by carbon fiber, Teflon and stainless steel cloth The heater wire being composed;Spacing between adjacent two carbon fiber lines is 7.5mm;The size of glass dimension grid grid is 75mm×75mm;The shape of glass dimension grid grid is square, the glass dimension grid grid through to disconnected with broadwise Resistance to spalling is not less than 80kN/m, glass dimension grid grid through being not less than 3% to broadwise elongation at break.
8. according to the comprehensive ice melting system in road surface described in claim 5 or 6 or 7, it is characterised in that: the asphalt concrete road Structure includes the Sub-course Asphalt Concrete (2) being successively set on the earth base of road layer from top to bottom, Sub-sealing Course (3), Road Base Layer (4), road subbase course (5) and road cushion (6);The carbon fiber electrically hot systems be placed in snow melt asphalt uplayer (1) with Between the Sub-course Asphalt Concrete (2).
9. the comprehensive ice melting system in road surface according to claim 8, it is characterised in that: the road cushion (6) is that skeleton is close The compactness of full mold structure, the road cushion (6) is not less than 80% not less than 96%, CBR value;The road cushion (6) is adopted 0.075mm percent of pass is no more than 5% in gradation composition;The road subbase course (5) is identical as the thickness of roadbase (4); The road subbase course (5) and roadbase (4) are all made of cement stabilized macadam laying;Water in the road subbase course (5) Cement-stabilizing broken stone 7d unconfined compressive strength is not less than 2.5MPa;Cement stabilized macadam 7d is without lateral confinement in the roadbase (4) Compression strength is not less than 3.5MPa;By heavy compaction standard, the compactness of the road subbase course (5) is not less than 97%, the road The compactness of base course (4) is not less than 98%;The Sub-sealing Course (3) uses single layer asphalt topping;Under the bituminous concrete Surface layer (2) uses close-graded Coarse Graded Bituminous Concrete, and the model of the close-graded Coarse Graded Bituminous Concrete is AC-25C, institute The Sub-course Asphalt Concrete (2) thickness is stated not less than 45mm.
10. a kind of construction method of the comprehensive ice melting system in road surface, it is characterised in that: the construction method the following steps are included:
1) according to highway asphalt concrete pavement construction technique normalizing and construction process requirement, the upper surface of the earth base of road layer from It is lower and on successively under laying road bed course (6), road subbase course (5), roadbase (4), Sub-sealing Course (3) and bituminous concrete Surface layer (2) forms asphalt concrete road structure;The road cushion (6) is dense structure of skeleton, the road cushion (6) compactness is not less than 80% not less than 96%, CBR value;0.075mm in gradation composition used by the road cushion (6) Percent of pass is no more than 5%;The road subbase course (5) is identical as the thickness of roadbase (4);The road subbase course (5) and Roadbase (4) is all made of cement stabilized macadam laying;Cement stabilized macadam 7d is without lateral confinement resistance to compression in the road subbase course (5) Intensity is not less than 2.5MPa;Cement stabilized macadam 7d unconfined compressive strength is not less than 3.5MPa in the roadbase (4);It presses The compactness of heavy compaction standard, the road subbase course (5) is not less than 97%, and the compactness of the roadbase (4) is not less than 98%;The Sub-sealing Course (3) uses single layer asphalt topping;The Sub-course Asphalt Concrete (2) uses close-graded coarse grain formula The model of bituminous concrete, the close-graded Coarse Graded Bituminous Concrete is AC-25C, and the Sub-course Asphalt Concrete (2) is thick Degree is not less than 45mm;
2) carbon fiber grille (8) are laid in the upper surface of the Sub-course Asphalt Concrete (2), and are fixed on by line card and cement nail The upper surface of the Sub-course Asphalt Concrete (2);The carbon fiber grille (8) is by carbon fiber line and glass dimension grid grid bundle It pricks;The carbon fiber line is the heater wire being composed of carbon fiber, Teflon and stainless steel cloth;Adjacent two carbon Spacing between fiber line is 7.5mm;The size of the glass dimension grid grid is 75mm × 75mm;The glass ties up grid The shape of lattice is square, glass dimension grid grid through being not less than 80kN/m, the glass to broadwise breaking strength Tie up grid grid through being not less than 3% to broadwise elongation at break;Carbon fiber grille (8) is laid with size requirement: along track line Arrangement width is 0.6 ~ 0.9m, and the carbon fiber grille (8) of a length of 8 ~ 10m is arranged in the bicycle road of outside;Pacify again outside road structure Assemble electric control box (10), electric valve (13), comprehensive controller (11) and connection control route and and temperature sensor (12) Form loop;When temperature sensor (12) detection road environment temperature is lower than -2 DEG C, start electric heating system, when being higher than -2 DEG C Close electric heating system;The comprehensive control instrument (11) is the electric integrated measurement and control instrument of PMW2000 series;
3) PC-3 emulsified asphalt sticking layer oil is dispensed in the upper surface of the Sub-course Asphalt Concrete (2), the PC-3 emulsified asphalt is viscous The dosage of layer oil is 0.5 ~ 0.7L/m2;The PC-3 emulsified asphalt sticking layer oil Asphalt Content 50%;
4) in the upper surface of PC-3 emulsified asphalt sticking layer oil laying snow melt asphalt uplayer (1) and to design standard, road surface is completed The final maintenance of structure obtains the comprehensive ice melting system in road surface;The snow melt asphalt uplayer (1) is obtained by snow melt asphalt paving It arrives;The snow melt pitch includes the snow melt anti-rut agent of AC-13 type pitch and addition in AC-13 type pitch, the snow melt The additive amount of anti-rut agent is the 5%-10% of AC-13 type asphalt quality;The snow melt anti-rut agent be by calcium chloride, potassium acetate, Four kinds of raw materials of calcium acetate and magnesium chloride are made;The weight percent of four kinds of components is as follows in the snow melt anti-rut agent:
Weight percentages of components (%)
Calcium chloride 8-14;
Potassium acetate 30-35;
Calcium acetate 20-25;
Magnesium chloride 30-35.
CN201910267400.1A 2019-04-03 2019-04-03 Snow-melting and anti-rut agent and pavement comprehensive ice-melting system Active CN110003671B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910267400.1A CN110003671B (en) 2019-04-03 2019-04-03 Snow-melting and anti-rut agent and pavement comprehensive ice-melting system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910267400.1A CN110003671B (en) 2019-04-03 2019-04-03 Snow-melting and anti-rut agent and pavement comprehensive ice-melting system

Publications (2)

Publication Number Publication Date
CN110003671A true CN110003671A (en) 2019-07-12
CN110003671B CN110003671B (en) 2020-12-22

Family

ID=67169730

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910267400.1A Active CN110003671B (en) 2019-04-03 2019-04-03 Snow-melting and anti-rut agent and pavement comprehensive ice-melting system

Country Status (1)

Country Link
CN (1) CN110003671B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111041935A (en) * 2019-12-11 2020-04-21 郑州第二市政建设集团有限公司 Asphalt concrete road with heating function and construction method thereof
CN111366093A (en) * 2020-03-02 2020-07-03 哈尔滨工业大学 Multifunctional distributed optical fiber sensor for road strain test and heat conduction snow melting
CN115369717A (en) * 2022-08-12 2022-11-22 同济大学 System and method for melting ice and snow on asphalt pavement of expressway

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010003347A (en) * 1999-06-22 2001-01-15 유헌형 Construction method on Hi-porous concrete pavement functioning snow melting and thawing by using Electro Conduction Concrete
CN101671539A (en) * 2008-09-11 2010-03-17 上海市长宁区少年科技指导站 Snowmelt agent
CN102092978A (en) * 2010-12-15 2011-06-15 长安大学 Environmental-protection self-snow-melting asphalt pavement admixture and preparation method thereof
CN103342988A (en) * 2013-07-04 2013-10-09 沈阳工业大学 Environment-friendly snow melting agent and preparation method thereof
CN105484322A (en) * 2015-12-23 2016-04-13 武汉广益交通科技股份有限公司 Anti-freezing preservative for cold region tunnel fire protection and use method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010003347A (en) * 1999-06-22 2001-01-15 유헌형 Construction method on Hi-porous concrete pavement functioning snow melting and thawing by using Electro Conduction Concrete
CN101671539A (en) * 2008-09-11 2010-03-17 上海市长宁区少年科技指导站 Snowmelt agent
CN102092978A (en) * 2010-12-15 2011-06-15 长安大学 Environmental-protection self-snow-melting asphalt pavement admixture and preparation method thereof
CN103342988A (en) * 2013-07-04 2013-10-09 沈阳工业大学 Environment-friendly snow melting agent and preparation method thereof
CN105484322A (en) * 2015-12-23 2016-04-13 武汉广益交通科技股份有限公司 Anti-freezing preservative for cold region tunnel fire protection and use method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111041935A (en) * 2019-12-11 2020-04-21 郑州第二市政建设集团有限公司 Asphalt concrete road with heating function and construction method thereof
CN111366093A (en) * 2020-03-02 2020-07-03 哈尔滨工业大学 Multifunctional distributed optical fiber sensor for road strain test and heat conduction snow melting
CN115369717A (en) * 2022-08-12 2022-11-22 同济大学 System and method for melting ice and snow on asphalt pavement of expressway

Also Published As

Publication number Publication date
CN110003671B (en) 2020-12-22

Similar Documents

Publication Publication Date Title
CN101806028B (en) Layered steel fiber conductive bituminous concrete
CN102815893B (en) Asphalt mixture with ice and snow removing function and preparation method thereof
CN110003671A (en) The comprehensive ice melting system of snow melt anti-rut agent and road surface
CN107489080B (en) A kind of anti-freeze road and its construction method
CN101353239B (en) Conductive concrete, preparing method, heating system and method for melting ice and snow
CN103015316B (en) Asphalt concrete steel bridge pavement structure and pavement method thereof
CN102704366A (en) High-performance rubberized asphalt composite seal coat and construction method thereof
CN205276085U (en) Novel preventative maintenance bituminous pavement structure layer
CN204690575U (en) A kind of electrical heating type paving structure for bridge floor deicing or snow melting
CN111287084B (en) Intelligent anti-freezing bridge deck structure and construction method
CN205617181U (en) Slag bituminous mixture road surface structure convenient to microwave heating snow melt
CN110055856A (en) Seif-citing rate road surface and heating cable mixing road surface ice melting system and its construction method
CN207619764U (en) A kind of ultra-thin anti-freezing ice maintenance of surface structure
CN114481747A (en) Pavement structure based on phase-change temperature-regulating material and construction method
CN107524066B (en) A kind of anti-freeze asphalt concrete layer and its construction method
CN102182133A (en) Electromagnetic deicing and snow melting method
CN202509361U (en) High-performance rubber asphalt composite seal coat
CN108360327A (en) A kind of permanent seal cooling advanced composite material (ACM) road structure and construction method
CN104652269A (en) Bridge deck pavement structure for orthotropic steel bridge
CN205874971U (en) Functional type bridge deck pavement structure
CN110158407B (en) Graphene conductive anti-sliding wear-resistant pavement and construction method thereof
Shi et al. Pavement treatments for sustainable winter road maintenance
CN207003179U (en) Road surface with dewatering type bituminous epoxy open gradation long-life Friction Surface
CN207672357U (en) A kind of transition slab at bridge head and asphalt concrete pavement changeover portion composite pavement structure
CN206858986U (en) Town road bituminous paving

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant