CN110002401A - Applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method - Google Patents
Applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method Download PDFInfo
- Publication number
- CN110002401A CN110002401A CN201910428586.4A CN201910428586A CN110002401A CN 110002401 A CN110002401 A CN 110002401A CN 201910428586 A CN201910428586 A CN 201910428586A CN 110002401 A CN110002401 A CN 110002401A
- Authority
- CN
- China
- Prior art keywords
- boiler tube
- reburner
- hydro carbons
- producing hydrogen
- conversion
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000006243 chemical reaction Methods 0.000 title claims abstract description 39
- 239000001257 hydrogen Substances 0.000 title claims abstract description 26
- 229910052739 hydrogen Inorganic materials 0.000 title claims abstract description 26
- UFHFLCQGNIYNRP-UHFFFAOYSA-N Hydrogen Chemical compound [H][H] UFHFLCQGNIYNRP-UHFFFAOYSA-N 0.000 title claims abstract description 24
- 238000000034 method Methods 0.000 title claims abstract description 21
- 229930195733 hydrocarbon Natural products 0.000 title claims abstract description 17
- 150000002430 hydrocarbons Chemical class 0.000 title claims abstract description 17
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 35
- 239000010959 steel Substances 0.000 claims abstract description 35
- 238000007789 sealing Methods 0.000 claims abstract description 16
- 238000010438 heat treatment Methods 0.000 claims abstract description 8
- 238000006073 displacement reaction Methods 0.000 claims abstract description 7
- 238000003466 welding Methods 0.000 claims description 14
- 239000002184 metal Substances 0.000 claims description 9
- 238000005242 forging Methods 0.000 claims description 8
- 238000009434 installation Methods 0.000 claims description 8
- 230000002035 prolonged effect Effects 0.000 claims description 6
- 239000000725 suspension Substances 0.000 claims description 5
- 238000010276 construction Methods 0.000 claims description 4
- 238000004519 manufacturing process Methods 0.000 abstract description 7
- 238000005336 cracking Methods 0.000 abstract description 6
- 230000009286 beneficial effect Effects 0.000 description 4
- ZZUFCTLCJUWOSV-UHFFFAOYSA-N furosemide Chemical compound C1=C(Cl)C(S(=O)(=O)N)=CC(C(O)=O)=C1NCC1=CC=CO1 ZZUFCTLCJUWOSV-UHFFFAOYSA-N 0.000 description 4
- UGFAIRIUMAVXCW-UHFFFAOYSA-N Carbon monoxide Chemical compound [O+]#[C-] UGFAIRIUMAVXCW-UHFFFAOYSA-N 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 230000005489 elastic deformation Effects 0.000 description 3
- 239000003546 flue gas Substances 0.000 description 3
- 230000015572 biosynthetic process Effects 0.000 description 2
- 239000007789 gas Substances 0.000 description 2
- 150000002431 hydrogen Chemical class 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000005855 radiation Effects 0.000 description 2
- 239000004215 Carbon black (E152) Substances 0.000 description 1
- 239000003054 catalyst Substances 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 230000017525 heat dissipation Effects 0.000 description 1
- 238000005984 hydrogenation reaction Methods 0.000 description 1
- 238000005504 petroleum refining Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Classifications
-
- C—CHEMISTRY; METALLURGY
- C01—INORGANIC CHEMISTRY
- C01B—NON-METALLIC ELEMENTS; COMPOUNDS THEREOF; METALLOIDS OR COMPOUNDS THEREOF NOT COVERED BY SUBCLASS C01C
- C01B3/00—Hydrogen; Gaseous mixtures containing hydrogen; Separation of hydrogen from mixtures containing it; Purification of hydrogen
- C01B3/02—Production of hydrogen or of gaseous mixtures containing a substantial proportion of hydrogen
- C01B3/32—Production of hydrogen or of gaseous mixtures containing a substantial proportion of hydrogen by reaction of gaseous or liquid organic compounds with gasifying agents, e.g. water, carbon dioxide, air
- C01B3/34—Production of hydrogen or of gaseous mixtures containing a substantial proportion of hydrogen by reaction of gaseous or liquid organic compounds with gasifying agents, e.g. water, carbon dioxide, air by reaction of hydrocarbons with gasifying agents
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P20/00—Technologies relating to chemical industry
- Y02P20/10—Process efficiency
Landscapes
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Organic Chemistry (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Engineering & Computer Science (AREA)
- Combustion & Propulsion (AREA)
- Inorganic Chemistry (AREA)
- Hydrogen, Water And Hydrids (AREA)
- Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)
Abstract
It is a kind of applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method, for the sealed connection between the more boiler tubes and conversion furnace body of multiple rows of arrangement, the boiler tube runs through vertically and stretches out the stove roof plate and drop-bottom of conversion furnace body, one end of drop-bottom is extended downwardly in boiler tube, it is provided with for preventing boiler tube expanded by heating and extends downwardly and swing laterally the securing supports being displaced, securing supports are fixedly connected with steel structure of furnace bottom.The invention avoids outlet manifold thermal expansions to extend the lateral displacement generated to boiler tube, it can guarantee the concentricity of boiler tube and stove roof plate, drop-bottom sealing structure to the maximum extent, the thermal efficiency for improving reburner, weld cracking caused by avoiding because of thermal expansion, ensure that the safety of production.
Description
Technical field
The present invention relates to technical field of petrochemical industry, are applied to hydro carbons-producing hydrogen from steam conversion more particularly, to one kind and convert
The boiler tube installing and fixing method of furnace.
Background technique
It is the master of hydrogen needed for hydrogenation plant in petroleum refining process using hydro carbons-steam conversion process hydrogen making
Source is wanted, reburner is the core equipment of such device for producing hydrogen.It is arranged in conversion furnace body in a row through stove roof plate, furnace bottom
The boiler tube of plate, conversion furnace body heat boiler tube, the effect of the catalyst in high temperature and pipe of hydro carbons-steam in boiler tube
Under be cracked into hydrogen, hydrogen is passed through in outlet manifold by boiler tube lower end and is sent out.
Use there are two types of most extensive, most common boiler tube fixed installation modes at present: the first is directly will be under boiler tube
The fixed form that end welds together with outlet manifold;Second is the setting spring fastening support boiler tube at the top of boiler tube, or
It is hung by constant force spring and draws boiler tube or hang boiler tube by the way of pulley weight-adding hammer, make boiler tube in cold conditions in suspention shape
The lower end of state, every boiler tube is connect by the down pigtail pipe mutually welded therewith with outlet manifold.
After converting furnace igniting, the constant temperature of boiler tube and outlet manifold is increased, and temperature is adopted up to 800 degrees Celsius or more
With the boiler tube of the first fixed form it is heated after will not downward prolonged expansion, can only under the traction of hanging mechanism at the top of boiler tube,
The unidirectional thermal expansion elongation of release upwards can push away at this point, generating the thermal expansion elongation in horizontal direction after outlet manifold is heated
Transverse shifting occurs for the dynamic boiler tube welded together therewith, and since outlet manifold is very long, the thermal expansion elongation after being heated is tired
Add, the transverse shifting that the boiler tube in thermal expansion extending direction outermost end generates is maximum, the transverse shifting of boiler tube make boiler tube with
The concentricity of sealing structure is destroyed between conversion furnace body, generates gap therebetween, and then is entered outside air and turned
Change in furnace, influence excess air coefficient in furnace, while radiation loss herein increases, causes to convert furnace thermal efficiency decline.Using
First expansion downwards, discharges thermal expansion portion elongation, reaches thermal expansion after bottom dead center after the boiler tube of two kinds of fixed forms is heated, then
At the top of the boiler tube under the traction of hanging mechanism, then upward prolonged expansion, discharge remaining thermal expansion elongation.And at this point, next part
Thermal expansion elongation in horizontal direction is generated to down pigtail pipe after tracheae is heated, down pigtail pipe is will push and welds therewith
Boiler tube transverse shifting together.Lateral thrust of this load on down pigtail pipe is easy to cause itself and boiler tube, outlet manifold
Weld cracking, due to being connected with high-temperature hydrogen in boiler tube, down pigtail pipe and outlet manifold pipe, there are security risks.
Obviously, all there is not the sealing structure of boiler tube and drop-bottom position in the fixed installation mode of both boiler tubes
Good influence., when cold and hot changes, lateral displacement occurs for boiler tube for the former, and coaxial sealing structure is caused to be destroyed, and influences to turn
Change furnace thermal efficiency;The latter is easy to cause down pigtail pipe and boiler tube, lower gas collection when cold and hot changes again while influencing the thermal efficiency
Pipe weld cracking, there are serious security risks.
Summary of the invention
Current hydrogen manufacturing conversion furnace boiler tube be fixedly mounted mode there are aiming at the problem that, the present invention, which provides, a kind of is applied to hydrocarbon
Class-steam hydrogen manufacturing conversion furnace boiler tube fixed structure, it is therefore an objective to constrain boiler tube and prolong in drop-bottom sealing structure position expanded by heating
The trend and direction stretched, in order to be able to effectively reliable sealing be implemented to the position, and then reduce air and enter, reduced in furnace
Excess air coefficient in flue gas is avoided to improve the thermal efficiency of reburner, while by presetting temperature compensation measure because of heat
Weld cracking caused by expanding.
For achieving the above object, the present invention adopts the following technical scheme:
A kind of more furnaces applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method, for multiple rows of arrangement
Sealed connection between pipe and conversion furnace body, the boiler tube run through vertically and stretch out the stove roof plate and furnace bottom of conversion furnace body
Plate extends downwardly one end of drop-bottom in boiler tube, is provided with the fixed support extended downwardly for preventing boiler tube expanded by heating
Part, securing supports are fixedly connected with steel structure of furnace bottom.
Preferably, comprising the following steps:
Step 1: boiler tube is hung in from top to bottom in the mounting hole of conversion furnace body, by the securing supports and furnace bottom on boiler tube
Steel construction is fixed together, and makes boiler tube can only upward prolonged expansion when heated;
Step 2: welding down pigtail pipe on the tube wall that boiler tube extends downwardly drop-bottom, and the other end and the level of down pigtail pipe are put
The outlet manifold welding set, is connected to boiler tube with outlet manifold;
Step 3: the installation sealing structure between boiler tube and conversion furnace body mounting hole.
Preferably, the securing supports are shaft forgings or are pipe type element or are sheet metal component.
Preferably, in step 1, the channel steel for being used to support boiler tube securing supports is provided on the steel structure of furnace bottom,
Channel steel is horizontally set on the two sides of boiler tube in a row, and is fixedly connected with securing supports.
Preferably, in step 1, the securing supports with welding of tubes are shaft forgings, are symmetrically welded on furnace tube outer wall
Two sides, the symmetrical shaft forgings are placed on the channel steel of boiler tube two sides, and are fixedly connected with channel steel.
Preferably, in step 1, the securing supports with welding of tubes are sheet metal component, are symmetrically welded on furnace tube outer wall
Two sides, the symmetrical sheet metal component is placed on the channel steel of boiler tube two sides, and is fixedly connected with channel steel.
Preferably, in step 1, on the outer tube wall that boiler tube stretches out stove roof plate upwards, it is outstanding to be symmetrically welded with a pair of of auxiliary
Hang lifting lug, assisted suspension lifting lug by wirerope, fixed pulley with can counterweight weight hang connect.
Preferably, in step 2, the position of down pigtail pipe and welding of tubes, setting securing supports and drop-bottom it
Between.
Preferably, in step 2, down pigtail pipe is the S-shaped pipe of elastically deformable.
Preferably, in step 2, after down pigtail pipe and boiler tube, outlet manifold welding, down pigtail pipe along outlet manifold by
The opposite direction that thermal expansion extends, which is preset with, to be extended for offsetting outlet manifold expanded by heating to down pigtail pipe generation lateral thrust
Twist angle.
Due to the adoption of the above technical scheme, background technique is compared, the invention has the following beneficial effects:
Beneficial effect one: the boiler tube for extending downwardly drop-bottom is rigidly fixed with steel structure of furnace bottom formation to be connect, and furnace is significantly reduced
Axial thermal expansion elongation of the pipe in drop-bottom sealing structure, is conducive to the sealing of reburner;
Beneficial effect two: the boiler tube for extending downwardly drop-bottom is rigidly fixed with steel structure of furnace bottom formation to be connect, and boiler tube passes through lower pig
Tail pipe is connect with outlet manifold, is avoided outlet manifold thermal expansion and is extended the lateral displacement generated to boiler tube, can be to the maximum extent
Guarantee the concentricity of boiler tube and stove roof plate, drop-bottom sealing structure, and then reduce the excess air coefficient in inner flue gas of the stove, simultaneously
Radiation loss is reduced, the thermal efficiency of reburner is improved;
Beneficial effect three: boiler tube is connect by down pigtail pipe with outlet manifold, and the good elastic deformation of down pigtail pipe itself is utilized
Amount, and by presetting temperature compensation measure, weld cracking caused by avoiding because of thermal expansion ensure that the safety of production.
Detailed description of the invention
Fig. 1 is the fixed structure schematic diagram of boiler tube;
Fig. 2 is the fixed structure schematic diagram of boiler tube in a row;
Fig. 3 is the structural schematic diagram of embodiment 2.
In figure: 1, boiler tube;1.1, securing supports;1.2, assisted suspension lifting lug;1.3, flange end cap;2, reburner;3,
Steel structure of furnace bottom;3.1, channel steel;4, down pigtail pipe;5, outlet manifold.
Specific embodiment
The preferred embodiment of the present invention described with reference to the accompanying drawings.It will be apparent to a skilled person that this
A little embodiments are used only for explaining technical principle of the invention, it is not intended that limit the scope of the invention.It needs to illustrate
, in the description of the present invention, term "front", "rear", "upper", "lower", "left", "right", "vertical", "horizontal", "inner",
The direction of instructions such as "outside", " transverse direction ", " axial direction " or the term of positional relationship are direction based on the figure or positional relationship,
This is intended merely to facilitate description, rather than indication or suggestion described device or element must have a particular orientation, with specific
Orientation construction and operation, therefore be not considered as limiting the invention.In addition it is also necessary to explanation, of the invention
In description unless specifically defined or limited otherwise, term " installation ", " connected ", " connection ", " fixation " shall be understood in a broad sense,
For example, it may be the connection of non-dismountable integraty, may be a detachable connection or integrally connected;It can be directly connected,
The connection inside two elements can be can be indirectly connected through an intermediary.It to those skilled in the art, can root
The concrete meaning of above-mentioned term in the present invention is understood according to concrete condition.
Embodiment 1:
It is a kind of applied to hydro carbons-steam hydrogen manufacturing conversion furnace boiler tube fixed structure, reburner includes conversion furnace body 2 and multiple rows of row
More boiler tubes 1 of the more boiler tubes 1 etc. of column, multiple rows of arrangement run through vertically and stretch out the stove roof plate and drop-bottom of conversion furnace body 2.
One end of drop-bottom is extended downwardly in boiler tube, on the suitable position between 1 lower port flange of boiler tube and drop-bottom, is symmetrically welded
There are the securing supports 1.1 being fixedly connected with steel structure of furnace bottom.After installation, it is in boiler tube 1 relative to steel structure of furnace bottom and fixes
State avoids the sealing structure between boiler tube 1 and drop-bottom, is generated displacement because of thermal expansion by boiler tube 1, outlet manifold 4
It influences.
In the present embodiment, securing supports 1.1 are shaft forgings, are symmetrically welded on the two sides of 1 outer wall of boiler tube.Due to conversion
It is the multiple rows of arrangement of boiler tube 1 in furnace body 2, large number of, for the ease of construction, be equipped on steel structure of furnace bottom 3 be used to support it is solid
Determine the channel steel 3.1 of supporting element 1.1, channel steel 3.1 is horizontally set on the two sides of boiler tube 1 in a row.
The fixing means the following steps are included:
Step 1: as shown in Figure 1, 2, more boiler tubes are successively hung in from top to bottom in the conversion respective mounting hole of furnace body 2, and will
Shaft forgings on each boiler tube are placed on channel steel 3.1, are fixed connection by U-bolt, are made each boiler tube can only when heated
Upward prolonged expansion.
For the ease of adjustment, the channel steel 3.1 connecting with U-bolt is equipped with long strip type connecting hole.
Since boiler tube 1 is longer also heavier, most of length, in order to keep the stress balance of boiler tube 1, subtracts on drop-bottom
Power influence caused by sealing structure is covered a while, on the outer tube wall that boiler tube 1 stretches out stove roof plate upwards, is symmetrically welded with a pair of auxiliary
Suspending hang lifting lug 1.2, assisted suspension lifting lug 1.2 by wirerope, fixed pulley with can counterweight weight hang connect.Due to weight
Flexible connection with boiler tube 1 is by wirerope, not only can be such that the stress of boiler tube is balanced, and will not make the balance by
The influence that boiler tube thermal expansion extends.
So far, one end that boiler tube 1 extends downwardly drop-bottom is in stationary state relative to steel structure of furnace bottom 3, and boiler tube 1 can only
The upward prolonged expansion of one direction, the shadow for avoiding the sealing structure between boiler tube 1 and drop-bottom from being subject to because thermal expansion generates displacement
It rings.
Step 2: on the tube wall that boiler tube 1 extends downwardly drop-bottom weld down pigtail pipe 4, the other end of down pigtail pipe 4 with
Horizontal positioned outlet manifold 5 welds, and is connected to boiler tube 1 with outlet manifold 5.
In the present embodiment, the position setting that down pigtail pipe 4 and boiler tube 1 weld securing supports 1.1 and drop-bottom it
Between, in welding procedure, not by the obstruction of channel steel 3.1.
Down pigtail pipe 4 is S-shaped pipe, and has certain elastic deformation ability.In order to guarantee under high temperature operating conditions, weld
Seam will not crack because of thermal expansion stress, and for down pigtail pipe 4 when with boiler tube 1, the welding of outlet manifold 5, down pigtail pipe 4 is along lower gas collection
The opposite direction that 5 expanded by heating of pipe extends is preset with certain twist angle, is extended with offsetting 5 expanded by heating of outlet manifold to lower pigtail
The lateral thrust of pipe 4.
Step 3: the installation sealing structure between boiler tube 1 and conversion 2 mounting hole of furnace body completes boiler tube in hydro carbons-steam
Installation on hydrogen manufacturing conversion furnace.
As a result, the present invention through the above steps, connect boiler tube 1 with steel structure of furnace bottom 3, boiler tube 1 pass through down pigtail pipe 4 and
Outlet manifold 5 connects, and avoids the thermal expansion of outlet manifold 5 and extends the lateral displacement generated to boiler tube 1, can guarantee to the maximum extent
The concentricity of boiler tube and stove roof plate, drop-bottom sealing structure, and then the excess air coefficient in inner flue gas of the stove is reduced, reduce heat dissipation
Loss, improves the thermal efficiency of reburner.And the good elastic deformation of down pigtail pipe 4 itself is utilized, default thermal expansion is passed through
Indemnifying measure, weld cracking caused by avoiding because of thermal expansion, ensure that the safety of production.
Embodiment 2:
As described in example 1 above is a kind of applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method, with reality
It applies unlike example 1, as shown in figure 3, the securing supports 1.1 are sheet metal component, is symmetrically welded on the two of 1 outer wall of boiler tube
Side.Sheet metal component on boiler tube is placed on channel steel 3.1, and is bolted to connection with channel steel 3.1.
Obviously, this connection type using sheet metal component, equally reaches using effect described in embodiment 1.It can reach
The mode of connection effect of the same race be it is various, be not repeated herein.
Part not in the detailed description of the invention is the prior art.Although an embodiment of the present invention has been shown and described, for this
For the those of ordinary skill in field, it is possible to understand that without departing from the principles and spirit of the present invention can be to these realities
It applies example and carries out a variety of change, modification, replacement and modification, the scope of the present invention is defined by the appended.
Claims (10)
1. it is a kind of applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method, more for multiple rows of arrangement
Sealed connection between boiler tube and conversion furnace body, the boiler tube run through vertically and stretch out the stove roof plate and furnace bottom of conversion furnace body
Plate, which is characterized in that extend downwardly one end of drop-bottom in boiler tube, be provided with for preventing boiler tube expanded by heating and extend downwardly
And the securing supports of horizontal swing displacement, securing supports are fixedly connected with steel structure of furnace bottom.
2. it is as described in claim 1 a kind of applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method,
It is characterized in that, comprising the following steps:
Step 1: boiler tube is hung in from top to bottom in the mounting hole of conversion furnace body, by the securing supports and furnace bottom on boiler tube
Steel construction is fixed together, and makes boiler tube can only upward prolonged expansion when heated;
Step 2: welding down pigtail pipe on the tube wall that boiler tube extends downwardly drop-bottom, and the other end and the level of down pigtail pipe are put
The outlet manifold welding set, is connected to boiler tube with outlet manifold;
Step 3: the installation sealing structure between boiler tube and conversion furnace body mounting hole.
3. it is as claimed in claim 2 a kind of applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method,
Be characterized in that: the securing supports are shaft forgings or are pipe type element or are sheet metal component.
4. a kind of as claimed in claim 2 or claim 3 install fixation side applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube
Method, it is characterised in that: in step 1, the channel steel for being used to support boiler tube securing supports is provided on the steel structure of furnace bottom,
Channel steel is horizontally set on the two sides of boiler tube in a row, and is fixedly connected with securing supports.
5. it is as claimed in claim 4 a kind of applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method,
Be characterized in that: in step 1, the securing supports with welding of tubes are shaft forgings, are symmetrically welded on the two of furnace tube outer wall
Side, the symmetrical shaft forgings are placed on the channel steel of boiler tube two sides, and are fixedly connected with channel steel.
6. it is as claimed in claim 4 a kind of applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method,
Be characterized in that: in step 1, the securing supports with welding of tubes are sheet metal component, are symmetrically welded on the two of furnace tube outer wall
Side, the symmetrical sheet metal component is placed on the channel steel of boiler tube two sides, and is fixedly connected with channel steel.
7. it is as claimed in claim 2 a kind of applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method,
It is characterized in that: in step 1, on the outer tube wall that boiler tube stretches out stove roof plate upwards, being symmetrically welded with a pair of of assisted suspension and hang
Ear, assisted suspension lifting lug by wirerope, fixed pulley with can counterweight weight hang connect.
8. it is as claimed in claim 2 a kind of applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method,
Be characterized in that: in step 2, the position of down pigtail pipe and welding of tubes is arranged between securing supports and drop-bottom.
9. it is as claimed in claim 2 a kind of applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method,
Be characterized in that: in step 2, down pigtail pipe is the S-shaped pipe of elastically deformable.
10. a kind of install applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube as described in claim 2 or 8 or 9 is fixed
Method, it is characterised in that: in step 2, after down pigtail pipe and boiler tube, outlet manifold welding, down pigtail pipe along outlet manifold by
The opposite direction that thermal expansion extends, which is preset with, to be extended for offsetting outlet manifold expanded by heating to down pigtail pipe generation lateral thrust
Twist angle.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910428586.4A CN110002401B (en) | 2019-05-22 | 2019-05-22 | Furnace tube installation and fixation method applied to hydrocarbon-steam conversion hydrogen production reformer |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910428586.4A CN110002401B (en) | 2019-05-22 | 2019-05-22 | Furnace tube installation and fixation method applied to hydrocarbon-steam conversion hydrogen production reformer |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110002401A true CN110002401A (en) | 2019-07-12 |
CN110002401B CN110002401B (en) | 2024-03-15 |
Family
ID=67177623
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910428586.4A Active CN110002401B (en) | 2019-05-22 | 2019-05-22 | Furnace tube installation and fixation method applied to hydrocarbon-steam conversion hydrogen production reformer |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110002401B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113117630A (en) * | 2019-12-31 | 2021-07-16 | 中国石油天然气股份有限公司 | Method for replacing reformer tube of chemical fertilizer synthesis reformer |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201198449Y (en) * | 2008-03-28 | 2009-02-25 | 四川亚联高科技有限责任公司 | Small-sized natural hydrogen manufacturing conversion furnace |
CN206474126U (en) * | 2016-12-26 | 2017-09-08 | 江苏天鹏石化科技股份有限公司 | A kind of boiler tube vibrator |
CN206720735U (en) * | 2017-04-14 | 2017-12-08 | 中国石油化工股份有限公司 | A kind of top burning type hydrogen manufacturing conversion furnace based on double tube reactor |
CN207102559U (en) * | 2017-04-14 | 2018-03-16 | 中国石油化工股份有限公司 | Burn formula hydrogen manufacturing conversion furnace in a kind of bottom based on double tube reactor |
CN210084939U (en) * | 2019-05-22 | 2020-02-18 | 山东齐鲁石化工程有限公司 | Furnace tube fixing structure applied to reformer of hydrocarbon-steam reforming hydrogen production device |
-
2019
- 2019-05-22 CN CN201910428586.4A patent/CN110002401B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201198449Y (en) * | 2008-03-28 | 2009-02-25 | 四川亚联高科技有限责任公司 | Small-sized natural hydrogen manufacturing conversion furnace |
CN206474126U (en) * | 2016-12-26 | 2017-09-08 | 江苏天鹏石化科技股份有限公司 | A kind of boiler tube vibrator |
CN206720735U (en) * | 2017-04-14 | 2017-12-08 | 中国石油化工股份有限公司 | A kind of top burning type hydrogen manufacturing conversion furnace based on double tube reactor |
CN207102559U (en) * | 2017-04-14 | 2018-03-16 | 中国石油化工股份有限公司 | Burn formula hydrogen manufacturing conversion furnace in a kind of bottom based on double tube reactor |
CN210084939U (en) * | 2019-05-22 | 2020-02-18 | 山东齐鲁石化工程有限公司 | Furnace tube fixing structure applied to reformer of hydrocarbon-steam reforming hydrogen production device |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113117630A (en) * | 2019-12-31 | 2021-07-16 | 中国石油天然气股份有限公司 | Method for replacing reformer tube of chemical fertilizer synthesis reformer |
Also Published As
Publication number | Publication date |
---|---|
CN110002401B (en) | 2024-03-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110002401A (en) | Applied to hydro carbons-producing hydrogen from steam conversion reburner boiler tube installing and fixing method | |
CN112680560B (en) | Waste heat boiler in converter dry dedusting system | |
CN108489273A (en) | A kind of heating furnace with pull rod | |
CN210084939U (en) | Furnace tube fixing structure applied to reformer of hydrocarbon-steam reforming hydrogen production device | |
CN106195980B (en) | A kind of pendant superheater and its multipath circulating fluidized bed boiler of application | |
CN215177009U (en) | Exhaust-heat boiler of hot stove of ferrosilicon ore | |
CN201778075U (en) | Radiant tube component | |
CN212293708U (en) | Independent passageway for connecting cold end and hot end large covers in titanium sponge distillation production | |
JP2012007836A (en) | Suspension type heat exchanger, and boiler device with the same | |
CN214148864U (en) | Vaporization cooling flue in converter waste heat boiler | |
WO2012041002A1 (en) | Large-scale steam generator | |
CN205537116U (en) | Heating furnace | |
CN221780708U (en) | Boiler supporting structure | |
CN215982502U (en) | Waste heat recovery boiler superheater structure | |
CN202081150U (en) | Soaking pit furnace with oversized blank and oversized charging amount | |
CN100458342C (en) | High temperature heat furnace | |
CN212564748U (en) | Low fixed pipe clamp of bank of tubes again | |
CN219300722U (en) | Outlet connection structure of boiler overheat screen | |
CN201614393U (en) | Novel muffle pipe hoisting clamp | |
CN110578027B (en) | Novel reformer for producing reducing gas | |
CN218238439U (en) | Self-preheating burner radiant tube device for muffle heating furnace | |
CN217875922U (en) | High-temperature energy-saving plate preheater | |
CN219328105U (en) | Novel blow-through box soot blower suspension system | |
CN213086051U (en) | Suspension furnace tube for push rod furnace | |
CN201177627Y (en) | Heating stove for charred coal reactivity and post-reaction strength test |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |