CN109990951A - A kind of product protective capacities test equipment and test method - Google Patents

A kind of product protective capacities test equipment and test method Download PDF

Info

Publication number
CN109990951A
CN109990951A CN201711484783.5A CN201711484783A CN109990951A CN 109990951 A CN109990951 A CN 109990951A CN 201711484783 A CN201711484783 A CN 201711484783A CN 109990951 A CN109990951 A CN 109990951A
Authority
CN
China
Prior art keywords
relay
test
switch
time
water tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711484783.5A
Other languages
Chinese (zh)
Inventor
丁丁
秦建旭
孙强明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WEIFANG PAITELAI ELECTRIC Co Ltd
Prestolite Electric Beijing Ltd
Original Assignee
WEIFANG PAITELAI ELECTRIC Co Ltd
Prestolite Electric Beijing Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WEIFANG PAITELAI ELECTRIC Co Ltd, Prestolite Electric Beijing Ltd filed Critical WEIFANG PAITELAI ELECTRIC Co Ltd
Priority to CN201711484783.5A priority Critical patent/CN109990951A/en
Publication of CN109990951A publication Critical patent/CN109990951A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01MTESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G01M3/00Investigating fluid-tightness of structures
    • G01M3/02Investigating fluid-tightness of structures by using fluid or vacuum
    • G01M3/04Investigating fluid-tightness of structures by using fluid or vacuum by detecting the presence of fluid at the leakage point
    • G01M3/06Investigating fluid-tightness of structures by using fluid or vacuum by detecting the presence of fluid at the leakage point by observing bubbles in a liquid pool

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Examining Or Testing Airtightness (AREA)

Abstract

The invention discloses a kind of product protective capacities test equipment and test methods, product protective capacities test equipment includes support device, the sealing device for accommodating test product is provided in support device, sealing device includes water tank and tank lid, water tank and tank lid are tightly connected by gripping mechanism, water tank is provided with that exhaust valve is gentle to connect mouth, and gas connects mouth and is connected with for providing air pressure into water tank and generating inside and outside test product the compressed air source unit of pressure difference, and compressed air source unit is electrically connected electric control gear.The present invention is based on electric control gears to realize automatic test, and at low cost, occupied space is few, and test method is simple and test effect is obvious.It need to only can be realized simultaneously for the test of different protective capacities requirement products by adjusting part or parameter, test equipment has very strong flexibility.

Description

A kind of product protective capacities test equipment and test method
Technical field
The present invention relates to the product test fields for having protective capacities to require, and are related specifically to a kind of for starter and its zero The test equipment and test method of component protective capacities test.
Background technique
The product that requires with protective capacities, equipment are generally required to the degree of protection of their shell according to country The relevant regulations of standard carry out experiment test, are wanted with ensuring that the degree of protection of the product, equipment meets or exceeds national standard It asks.
Starter and its components are frequently encountered dust in application environment, muddy, water, machine oil, diesel oil and some corruption The presence of corrosion solution;If most solid substance and liquid solution will cause machinery into inside starter or its components Clamping stagnation, corrosion of metal, the mechanical disorders such as circuit damage.Therefore starter and its components belong to the production required with protective capacities Product need to carry out experiment test to its degree of protection,
The test mode and requirement being usually taken are completed based on electrical equipment degree of protection as defined in GB 4208.Foundation The typical starter and its assembly degree of protection such as IPX6 of the requirement, it is desirable that as follows:
It is sprayed water, and met to the shell of subject product in all possible direction using the code test nozzle of standard requirements Following condition:
1. nozzle inside diameter: 12.5mm;
2. water flow: (100 ± 5) L/min;
3. hydraulic pressure: being adjusted according to regulation water flow;
4. the central part of main water flow: the circle for being about 120mm from diameter at nozzle 2.5m;
5. every square metre of water spraying time of case surface: more 1min;
6. test period: minimum 3min;
7. nozzle is to case surface distance: 2.5m~3m.
If protection level requirements are IPX7, need to meet claimed below:
Using standard requirements caisson, subject product shell submerges by installation condition as defined in factory, and Meet following condition:
1. the minimum point of shell of the height less than 850mm, should be lower than water surface 1000mm;
2. height is equal to or more than the shell highest point of 850mm, water surface 150mm should be lower than;
3. duration of test runs 30min;
4. water temperature and the style temperature difference are not more than 5k.
In addition to this kind of Soft pack experiments of sealing performance method is also given in GBT 15171:
1. being put into suitable distilled water in vacuum chamber, sample is fixed on specimen holder, then is dipped in water.This When, the top of sample must not be lower than 25mm at a distance from the water surface.
2. covering the sealing cover of vacuum chamber, exhaust valve is closed, then open vacuum tube valves to vacuum chamber.
3. the leakage situation of observation sample when vacuumizing and during vacuum is kept, depending on it, whether there is or not continuous bubbles to generate.It is single A discrete bubble is not intended as sample leakage.
4. opening air inlet pipe valve, communicate vacuum chamber with atmosphere, open sealing cover, sample is taken out, by the water on its surface It cleans, Kaifeng checks inside sample whether there is test water infiltration.
Thus it sees, the test mode being usually taken is needed according to different degree of protection using different test equipments, right Test equipment requires high.Existing test equipment is flexible poor, and the degree of automation is low, and test method operation difficulty is big, the test period It is long;And test effect is difficult to intuitive judgment, it is necessary to observe internal state after disassembling to product.Thus it is more suitable for very The exemplar of limited quantity carries out in the laboratory of test analysis;It is not particularly suited for test beat, Flexible Equipment, test automation Degree, testing cost, the batch production scene that test validity has higher requirements;Poor universality.
Summary of the invention
In order to overcome above-mentioned the deficiencies in the prior art, it is to propose that the present invention, which solves its first technical problem, A kind of product protective capacities test equipment, high degree of automation is easy to operate, versatile, and test effect is more intuitive.
As the same technical concept, another technical problem solved by the invention is to provide a kind of above-mentioned production of use The low protective capacities test method of product protective capacities test equipment.
In order to solve the first technical problem mentioned above, the technical scheme adopted by the invention is that: a kind of product protective capacities is surveyed Try equipment, comprising: support device, the support device are provided with the sealing device for accommodating test product, the sealing device packet Water tank and tank lid are included, the water tank and the tank lid are tightly connected by gripping mechanism, and the water tank is provided with exhaust valve Gentle to connect mouth, the gas connects mouth and is connected with for providing air pressure into the water tank and generating pressure difference inside and outside the test product Compressed air source unit, the compressed air source unit is electrically connected electric control gear.
Further, the compressed air source unit includes the air pump being driven by motor.
Further, the electric control gear includes main circuit and logic control circuit;
The main circuit includes: power supply adaptor, with the relay normally open switch of the motor joining for driving the air pump and The relay for controlling the relay normally open switch, is serially connected with the first relay between the power supply adaptor and the relay Normal open switch;
The logic control circuit include: the change-over switch being serially connected with the power supply adaptor, position switch and Master control circuit;The master control circuit includes the first circuit parallel with one another, second servo loop, tertiary circuit, the 4th circuit, Five circuits and the 6th circuit;
First circuit include the second relay normally closed switch and concatenated with the second relay normally closed switch two Parallel branch, wherein a branch connects first time relay, another branch connects to be controlled by the first time relay First time relay normally closed switch and the first relay;
The second servo loop includes the first pressure control switch being serially connected, the first relay normally closed switch and third Relay, the first relay normally closed switch are controlled by first relay;
The tertiary circuit includes second pressure control switch and first the second relay normally open switch, second pressure After power control switch and first the second relay normally open switch in parallel with third relay normally closed switch and the second relay Device concatenation, the third relay normally closed switch are controlled by the third relay, the second relay control described second Relay normally open switch;
4th circuit includes that second the second relay normally open switch and the 4th relay normally open switch, and second A second relay normally open switch with after the 4th relay normally open switch in parallel with third relay described in another Normally closed switch concatenation, the third relay normally closed switch concatenate three three branches in parallel, and first article of branch connects the 4th relay Device, Article 2 branch connect second time relay, and Article 3 branch connects the third time relay;
5th circuit includes the second time relay normal open switch being serially connected, the first LED pipe, and described second Time relay normal open switch is controlled by second time relay;
6th circuit includes the second time relay normally closed switch, second time relay normally closed switch concatenation There are two parallel branches, a branch connects the second LED pipe, and another branch connects third time relay normal open switch and third LED pipe.
Further, the first time relay normally closed switch is that on-delay disconnects switch, second time relay Device normally closed switch is that on-delay disconnects switch, and second time relay normal open switch is on off delay closure switch, institute It states third time relay normal open switch on-delay closure and power cut off delay disconnects switch.
Further, the exhaust valve is electric-controlled type exhaust valve, and the master control circuit further includes the 7th circuit, the described 7th Circuit include be serially connected the 5th relay normally open switch and the electric-controlled type exhaust valve, the 5th circuit further include with 5th relay of the first LED pipe concatenation, the 5th relay control the 5th relay normally open switch.
Further, the electric control gear includes the display box for showing automatically controlled information, and the electric control gear is relay Control circuit device or programmable integrated circuit device.
Further, the support device includes cabinet, and the electric control gear is set in the cabinet.
Further, switching mechanism is provided between the tank lid and the cabinet, the switching mechanism includes being fixed on The bracket of the cabinet, and the rocker arm hinged with the bracket, the one end are connect with the tank lid, the other end with put Set mass configuration support is connected, the tank lid or the rocker arm be connected with handle.
Further, the product protective capacities test equipment further includes cleaning system, and the cleaning system includes control water platform And air gun.
To solve above-mentioned second technical problem, the technical scheme adopted by the invention is that:
A kind of product protective capacities test method, using product protective capacities test equipment described above, including it is following Step:
A, the tank lid in the sealing device is opened, product to be measured is directly placed into or is put into mobile bracket In the water tank, and liquid is injected to predetermined altitude H into the water tank;
B, the tank lid is closely connect with the water tank by the gripping mechanism, starting electric control gear switch, prison Measuring pressure in the water tank, in predetermined pressure domain P1, the compressed air source unit operation is to adjust the pressure in the water tank;
C, when monitoring that pressure reaches predetermined pressure P2 in the water tank in preset time T 1, the compressed air source unit stops Operation;During P2 pressure maintaining continues, until reaching the electric control gear after predetermined dwell time T2 gives " test is completed " warning, and benefit Restore the pressure in the water tank with the exhaust valve being connected with the water tank, until reaching predetermined pressure domain P1;
When monitoring that pressure is not up to predetermined pressure P2 in the water tank in preset time T 1, if at this time the time without departing from Preset time T 1, the compressed air source unit continue to run the pressure adjusted in the water tank, until the water in preset time T 1 Pressure reaches predetermined pressure P2 in case, and test continues;Monitor that pressure is not up to predetermined in the water tank in preset time T 1 When pressure P2, if the time, the compressed air source unit was out of service, terminates in advance test beyond preset time T 1 at this time;
D, as needed, can one wheel test continue pressure maintaining P2 during or just at the end of, by manually controlling The non-self-holding switch stated in circuit device resets, and the dwell time is recalculated, the extended testing system dwell time;
E, when during the test, the protective capacities of test product is not up to preset requirement, test product protects bad place Significant performance is had, test effect is intuitively shown;
F, test terminates, and closes system, takes out test product, and test product surface is cleared up in cleaning system;
G, the input information for switching or changing the electric control gear by manually controlling the electric control gear enters a new round Test.
After above-mentioned technical proposal, the beneficial effects of the present invention are:
The protective capacities test equipment structure is simple, and wherein support device, sealing device, compressed air source unit mention for product testing The testing conditions of high request high standard are supplied.
And the test of product protective capacities is realized based on electric control gear, and entire test process can be realized automatically, It operates simpler.And in the short time can intuitive judgment go out whether product meets preassigned requirement, be greatly improved Test beat;And it is at low cost, occupied space is few, and operation is simple, while only needing to pass through tune for different protective capacities demands Whole part or parameter can be realized, so that equipment be enabled to have very strong flexibility.The equipment is especially suitable for test beat There is rigors production scene with test condition.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of product of the present invention protective capacities test equipment;
Fig. 2 is the test method flow chart using Fig. 1 test equipment;
Fig. 3 is the circuit diagram for realizing the electric control gear of Fig. 2 test method;
In figure: 1- sealing device, 11- water tank, 12- display box, 13- tank lid, 131- handle, 14- switching mechanism, 141- Bracket, 142- rocker arm, 15- gripping mechanism, 16- are supported with object, 2- support device, 21- cabinet, 22- mobile bracket, 3- cleaning System, 31- control water platform, and 4- gas connects mouth, 51- knife switch, 52- knife switch, 53- relay, 53a- relay normally open switch, 54- air pump, 55- power supply adaptor, 56- position switch, the second relay of 57-, 57a- the second relay normally closed switch 57b- Two relay normally opens switch, the second relay normally open of 57c- switch, 58- first time relay, 58a- first time relay Normally closed switch, 59- first pressure control switch, 60- second pressure control switch, the 4th relay of 61-, the 4th relay of 61a- Normal open switch, the first relay of 62-, 62a- the first relay normally closed switch, the first relay normally open of 62b- switch, 63- third Relay, 63a- third relay normally closed switch, second time relay of 64-, 64a- second time relay normal open switch, 64b- second time relay normally closed switch, the 65- third time relay, 65a- third time relay normal open switch, 66- Five relays, the 5th relay normally open of 66a- switch, the first LED pipe of 67-, the second LED pipe of 68-, 69- third LED pipe, 70- row Air valve, 71- change-over switch.
Specific embodiment
In conjunction with attached drawing, the present invention is described in further detail with its specific embodiment.
In description of the invention, it is to be understood that "left", "right", etc. the orientation or positional relationships of descriptions be based on attached drawing Orientation and positional relationship, it is only for convenient for simplify description, be not considered as limiting the invention.
As shown in Figure 1, product protective capacities test equipment mainly include accommodate test product sealing device 1, support it is close The support device 2 of seal apparatus 1, support device 2 include cabinet 21 and the mobile bracket 22 for consigning product to be measured, sealing device 1 Including be fixed on cabinet 21 water tank 11,11 upper cover of water tank be equipped with tank lid 13, be provided with water between water tank 11 and cabinet 21 Case pad.Water tank 11 is tightly connected with tank lid 13 by gripping mechanism 15, i.e., by the clamping screw on gripping mechanism 15 with spiral shell Tank lid 13 is pressed on water tank 11 by the mode that bolt screws, and guarantees to be confined space inside water tank 11.Tank lid 13 and cabinet Switching mechanism 14 is provided between 21.The switching mechanism 14 includes the bracket 141 that is fixed on cabinet 21, and with the bracket 141 Hinged rocker arm 142,142 one end of rocker arm are connect with tank lid 13,142 other end of rocker arm and the configuration support 16 for placing mass Be connected, tank lid 13 or rocker arm 142 be connected with handle 131.
Water tank 11 is additionally provided with that exhaust valve is gentle to connect mouth 4, and gas connects mouth 4 and is connected in the water tank 11 to sealing device 1 Air pressure is provided and generates the compressed air source unit of pressure difference inside and outside test product, which includes the air pump 54 being driven by motor, The motor of air pump 54 is electrically connected with electric control gear, which is set in cabinet 21, and the display box 12 in electric control gear is set It is placed on cabinet 21.Electric control gear is control relay circuit device or programmable integrated circuit device, such as PLC, monolithic Machine realizes logic control;The external tester of electric control gear and actuator, such as sensor, pump, valve, LED, buzzer etc..
The product protective capacities test equipment further includes cleaning system 3, and cleaning system 3 includes control water platform 31 and air gun.
The present embodiment with air pump 54 be vacuum pump when, the specifically used process of the equipment is described below:
As shown in Fig. 2, equipment is in use, product to be measured is placed on mobile bracket 22, by the lock on gripping mechanism 15 Tight bolt is unscrewed, and opens gripping mechanism 15, and tank lid 13 is connected the right side of rocker arm 142 and 141 hinged support of bracket, rocker arm 142 It is placed with mass in connected counterweight support 16 on the left of hinged support, in this way when gripping mechanism 15 is opened, in mass 2 The right side of effect lower shake-changing arm 142 drives the tank lid 13 of water tank 11 that can rise to after certain altitude and is limited part limit (limit Part is not shown in the figure), so that tank lid 13 be made to keep nature opening state.
Mobile bracket 22 is held, product to be measured is placed in water tank 11 (or product to be measured is directly put into water tank In 11), to water tank 11 inside inject selected liquid to predetermined altitude H, it is water, predetermined altitude H that liquid is selected in the present embodiment It is set to the height until when product to be measured is covered with the liquid completely;Tank lid 13 is closed later, engages gripping mechanism 15, and will card Clamping screw on tight device 15 is tightened, and tank lid 13 and water tank 11 is tightly connected, it is ensured that sealing effect.
Start electric control gear switch, can voluntarily be carried out according to process shown in Fig. 2 inside water tank 11.Monitor that pressure exists When the P1 of predetermined pressure domain, air pump 54 (being selected as vacuum pump) is run to adjust pressure in water tank 11;If supervised in preset time T 1 When measuring pressure and reaching predetermined pressure P2, vacuum pump is out of service, during P2 pressure maintaining continues, completes automatically controlled after predetermined dwell time T2 Device, which is given, warns " test is completed ", and (pressure maintaining test will be continued until when completing setting pressure maintaining by not completing dwell time T2 Between after T2 system give warn " test is completed "), and the pressure in water tank is restored to predetermined pressure domain P1, is done for lower whorl test Prepare;
If monitor that pressure is not up to predetermined pressure P2 in preset time T 1, vacuum pump runing time is judged at this time Whether more than T1, when being less than T1, vacuum pump continues to run pressure regulation, until it is laggard to reach predetermined pressure P2 in preset time T 1 Enter next step process;If when more than T1, it is possible to which there are line faults, and control vacuum pump is out of service, cannot be introduced into down at this time One step process, test terminate in advance;
As needed, can one wheel test continue pressure maintaining P2 during or just at the end of, pass through manual control circuit Non- self-holding switch (normally closed push button switch) in device resets, and the dwell time resets, and recalculates, i.e., artificially freely extends again Test the dwell time.
Find that product surface part there are continuous air bubbles to emerge, that is, shows that product protective capacities does not reach and want in test process It asks, if instead product surface is without continuous air bubbles after testing process, then product protective capacities is qualified.In test process Duration, atmospheric pressure value, the information such as alarm may be displayed on display box 12.
Test is completed 11 internal pressure of rear water box and is restored, and opens tank lid 13, mobile bracket 22 is taken out, control is placed on On water platform 31, product surface then is quickly cleaned with equipment such as air guns, cleaning object is flowed out by 31 drain outlet of control water platform.
Test can manually control electric control gear switch or change input information and carry out follow-on test or change batch test.Such as Fruit has particular demands to preset time therein, pressure set domain, by adjusting control relay circuit setup time relay, Pressure transducer achieves the goal;Or the setting of certain logic is completed based on programmable integrated circuit device.The thus set equipment There is very strong flexibility, equipment cost can be saved under a variety of demands.
A kind of situation of the concrete application in reality:
Sealing space absolute pressure value is set into P2=0.06MPa (60KPa), while inside starter or relay product Atmospheric pressure value is a standard atmospheric pressure, and P0=0.1MPa (100KPa) generates draught head in starter or relay both ends in this way For P0-P2=0.04MPa;The numerical value can show that absolute pressure is shown in common air gauge by equipment such as such as air gauges And the difference of atmospheric pressure, air gauge shows that numerical value is P2-P0=-0.04Mpa under above-mentioned case.It is equivalent to and the water of 4m depth is provided Pressure has greatly saved the test space without the 4m depth of water is provided at the scene.
Fluid flow rate in product hole is directly proportional to hole both ends pressure, when product is wrapped up by liquid completely, passes through system The pressure higher than level of protection is made, product protection weakness can be aggravated and generate more significant fluid flow phenomena, tested It, so in a short time can intuitive judgment it can be seen that the undesirable product vulnerable area of protection continuously overflows a large amount of bubbles in journey Whether product meets preassigned requirement out, and the pressure maintaining testing time, T2 can be reduced within 1 minute, is greatly improved test Beat.
The present embodiment is based on testing procedure process shown in Fig. 2 with the relay of the switch controlled using a variety of relays with it Its control principle is specifically described for control circuit device:
As shown in figure 3, control relay circuit corresponding with this testing process includes main circuit and logic control circuit. After knife switch 51,52 on main circuit is closed, AC power source accesses circuit.It is converted alternating current to by power supply adaptor 55 The DC voltage needed using power supply adaptor 55 is S-50-24 Switching Power Supply in this example, converts alternating current to 24V direct current Voltage, the direct-flow voltage regulation source as logic control circuit.
For operator, testing process can be completed by a change-over switch 71.When change-over switch 71 is switched on, water Case lid 13 is not switched on, and position switch 56 (determining on off operating mode according to 13 position of tank lid of sealing device 1) is now in closure State, after the completion of last round of test, when the pressure in water tank 11 does not restore, second relay normally open switch 57b, 57c is still set to In closed state, the second relay 57 must be electric, and the second relay 57 is the control relay of second relay normally open switch 57b, 57c Device, by self-sustaining enable the second relay 57 and the 4th relay 61 persistently it is electric, and make the second relay normal Make and break is closed 57a and is in an off state, and the second relay normally closed switch 57a is disconnected prevent the first relay 62 is electric from obtaining, so First relay normally open switch 62b is remained open, and relay 53 cannot obtain electric, and relay normally open switch 53a is remained open, vacuum Air pump inoperative.After second time relay, 64 preset time T 2, the switch of control is made a response, the second time relay Device normal open switch 64a closure, the second time relay normally closed switch 64b are disconnected, and the 5th relay 66 must be electric, and the 5th relay is normal Switch 66a closure, exhaust valve 70 (for electric-controlled type exhaust valve) work.
When exhaust valve 70 acts on 11 internal pressure of lower header and reverts to predetermined pressure domain P1, the first pressure under the pressure Control switch 591 enters closed state, and second pressure control switch 60 is in an off state, the first relay normally closed switch 62a For closed state, thus third relay 63 it is electric;Third relay 63 is the control relay of third relay normally closed switch 63a Therefore device, third relay normally closed switch 63a are disconnected, lead to 57 power loss of the second relay, the second relay 57 described above Self-sustaining be released from, the second relay normally closed switch 57a closure, thus first time relay 58 and the first relay 62 must Electricity, vacuum pump operation pressure regulation, first time relay 58 are connected after predetermined time T1, and the pressure in water tank 11 is within the T1 time Reach predetermined pressure P2 value, (in addition, if beyond the T1 time because certain failures cause 11 internal pressure of water tank to be unable to adjust to predetermined When pressure P2 value, vacuum pump out of service itself can will not be worked long hours with protecting.) second pressure is controlled and opened under the pressure It closes 60 and enters closed state, first pressure control switch 59 is in an off state, and the second relay 57 must be electric, and the second relay is normal Make and break is closed 57a and is disconnected, and 62 power loss of first time relay 58 and the first relay, vacuum pump is out of service, tests into pressure maintaining Stage.At the same time, the second relay 57 obtains cable order the second relay normally open switch 57b closure and is in circuit self-locking state, Another the second relay normally open switch 57c closure causes the 4th relay switch 61a and the 4th relay 61 to be in shape of controlling oneself State, while second time relay 64 and the third time relay 65 start timing.When the second 64 predetermined pressure maintaining of the time relay Between be T2, before reaching dwell time T2, second time relay 64 control the second time relay normally closed switch 64b still locate It in on-state, gives the second LED pipe 68 electric signal, shows " in test " signal in display box 12.When second time relay After 64 preset time Ts 2, the switch of control is made a response, the second time relay normal open switch 64a closure, when second Between relay normally closed switch 64b disconnect, the first LED pipe 67 and the 5th relay 66 electric, display " test completion ".
The 5th relay normally open switch 66a is closed at this time, and exhaust valve 70 starts to be vented, and system, which is in, restores pressure process, It prepares for next round test.
The setting of the third time relay 65 is in order to extend the dwell time;65 preset time of the third time relay be greater than etc. Be in the characteristics of T2, third time relay normal open switch 65a the third time relay 65 it is electric after time-delay closing, and The third time relay 65 is delayed after powering off and disconnects;In described in the upper section, the second time relay normally closed switch 64b disconnect after the Three time relay normal open switch 65a closure, a wheel test process is completed at this time.When exhaust valve 70 does not have started exhaust, Change-over switch 71 (in the case where non-self maintained push button switch) in operator's trigger circuit resets, and second time relay is normally closed Switch 64b can be closed again, but exhaust valve 70 no longer works at this time, and the third time relay 44 powers off, but third time relay Device normal open switch 65a needs could disconnect after a certain time, and third LED pipe 69 can react under this state, prompt behaviour It is interrupted, pressing inside water tank 11 at this time still is by force P2, and testing process can be again introduced into test completion shape after running a period of time State, can be taking human as the lengthening dwell time by increasing this mode of the third time relay 65;It in addition can be by accessing timing The mode of device records break time.
When pressure restores to preset pressure domain P1, first pressure control switch 59 is closed, third relay 63 it is electric, lead Cause third relay normally closed switch 63a disconnect, final result is that exhaust valve 70 stops working, and vacuum pump is run again, system into Enter next round working condition.Or tank lid 13 is opened by operator, whole system is placed in original state by position switch 56, This batch of tested product is taken out, tank lid 13 is closed after next group product is put into water tank 11, into new round test process.
Thus the follow-on test that may be implemented that product is surveyed to a batch is seen;If necessary to be surveyed to successive batches product Examination, then can be by closing change-over switch 71;Or change-over switch 71 is kept to be closed, by opening tank lid 13, control position Switch 56 disconnects;Whole system is enabled to restPose.
The non-self-holding normally closed switch disconnected when change-over switch 71 is set as only in pressing, and position switch 56 is set as having When having the switch of on-off two states, the automation of testing process equally can be preferably realized, it is similar with process above, herein It is not added and repeats.
In water tank 11 monitoring of pressure can by water tank 11 be arranged pressure sensor come to pressure in water tank 11 into Row real-time monitoring.
Certainly, the invention may also have other embodiments, without deviating from the spirit and substance of the present invention, ripe Various corresponding changes and modifications, but these corresponding changes and modifications can be made according to the present invention by knowing those skilled in the art Belong to the protection scope of the appended claims of the present invention.

Claims (10)

1. a kind of product protective capacities test equipment, comprising: support device, which is characterized in that
The sealing device for accommodating test product is provided in the support device, the sealing device includes water tank and tank lid, By gripping mechanism sealed connection, the water tank is provided with that exhaust valve is gentle to connect mouth, the gas for the water tank and the tank lid It connects mouth and is connected with the compressed air source unit for generating pressure difference for the offer air pressure into the water tank and inside and outside the test product, it is described Compressed air source unit is electrically connected electric control gear.
2. product protective capacities test equipment according to claim 1, which is characterized in that the compressed air source unit includes by electricity The air pump of machine driving.
3. product protective capacities test equipment according to claim 2, which is characterized in that the electric control gear includes main electricity Road and logic control circuit;
The main circuit includes: power supply adaptor, with the relay normally open switch for the motor joining for driving the air pump and control The relay of the relay normally open switch, is serially connected with the first relay normally open between the power supply adaptor and the relay Switch;
The logic control circuit includes: the change-over switch, position switch and master control being serially connected with the power supply adaptor Circuit processed;The master control circuit includes the first circuit parallel with one another, second servo loop, tertiary circuit, the 4th circuit, the 5th time Road and the 6th circuit;
First circuit include the second relay normally closed switch and concatenated with the second relay normally closed switch two simultaneously Join branch, wherein a branch connects first time relay, another article of branch is connect by the of first time relay control One time relay normally closed switch and the first relay;
The second servo loop includes the first pressure control switch being serially connected, the first relay normally closed switch and third relay Device, the first relay normally closed switch are controlled by first relay;
The tertiary circuit includes second pressure control switch and first the second relay normally open switch, the second pressure control System switch and first the second relay normally open switch in parallel after with third relay normally closed switch and the second relay string It connects, the third relay normally closed switch is controlled by the third relay, and second relay controls second relay Device normal open switch;
4th circuit includes second the second relay normally open switch and the 4th relay normally open switch, second institute State the second relay normally open switch with it is normally closed with third relay described in another after the 4th relay normally open switch in parallel Switch concatenation, the third relay normally closed switch concatenate three three branches in parallel, and first article of branch connects the 4th relay, the Two branches connect second time relay, and Article 3 branch connects the third time relay;
5th circuit includes the second time relay normal open switch being serially connected, the first LED pipe, second time Relay normally open switch is controlled by second time relay;
6th circuit includes the second time relay normally closed switch, and second time relay normally closed switch is serially connected with two Parallel branch, a branch connect the second LED pipe, and another branch connects third time relay normal open switch and third LED pipe.
4. product protective capacities test equipment as claimed in claim 3, which is characterized in that the first time relay is normally closed Switch disconnects switch for on-delay, and second time relay normally closed switch is disconnected for on-delay and being switched, and described second Time relay normal open switch is on off delay closure switch, third time relay normal open switch on-delay closure and Power cut off delay disconnects switch.
5. product protective capacities test equipment as claimed in claim 4, which is characterized in that the exhaust valve is electric-controlled type exhaust Valve, the master control circuit further include the 7th circuit, and the 7th circuit includes that the 5th relay normally open being serially connected is opened It closes and the electric-controlled type exhaust valve, the 5th circuit further includes the 5th relay concatenated with first LED pipe, and described the Five relays control the 5th relay normally open switch.
6. product protective capacities test equipment according to claim 5, which is characterized in that the electric control gear includes being used for Show that the display box of automatically controlled information, the electric control gear are control relay circuit device or programmable integrated circuit device.
7. product protective capacities test equipment according to claim 1, which is characterized in that the support device includes machine Cabinet, the electric control gear are set in the cabinet.
8. product protective capacities test equipment according to claim 7, which is characterized in that the tank lid and the cabinet Between be provided with switching mechanism, the switching mechanism includes the bracket for being fixed on the cabinet, and with the bracket is hinged shakes Arm, the one end are connect with the tank lid, and the other end is connected with the configuration support for placing mass, the tank lid Or the rocker arm be connected with handle.
9. product protective capacities test equipment as described in claim 1, which is characterized in that the product protective capacities test is set Standby further includes cleaning system, and the cleaning system includes control water platform and air gun.
10. a kind of product protective capacities test method, which is characterized in that surveyed using product protective capacities described in claim 1 Try equipment, comprising the following steps:
A, the tank lid in the sealing device is opened, product to be measured is directly placed into or is put into mobile bracket described In water tank, and liquid is injected to predetermined altitude H into the water tank;
B, the tank lid is closely connect with the water tank by the gripping mechanism, starting electric control gear switch monitors For pressure in predetermined pressure domain P1, the compressed air source unit operation is to adjust the pressure in the water tank in the water tank;
C, when monitoring that pressure reaches predetermined pressure P2 in the water tank in preset time T 1, the compressed air source unit stops fortune Row during P2 pressure maintaining continues, until reaching the electric control gear after predetermined dwell time T2 gives " test is completed " warning, and utilizes The exhaust valve being connected with the water tank restores the pressure in the water tank, until reaching predetermined pressure domain P1;
When monitoring that pressure is not up to predetermined pressure P2 in the water tank in preset time T 1, if at this time the time without departing from default Time T1, the compressed air source unit continue to run the pressure adjusted in the water tank, until in preset time T 1 in the water tank Pressure reaches predetermined pressure P2, and test continues;Monitor that pressure is not up to predetermined pressure in the water tank in preset time T 1 When P2, if the time, the compressed air source unit was out of service, terminates in advance test beyond preset time T 1 at this time;
D, as needed, can one wheel test continue pressure maintaining P2 during or just at the end of, by manually controlling the electricity Non- self-holding switch in the device of road resets, and the dwell time is recalculated, the extended testing system dwell time;
E, when during the test, the protective capacities of test product is not up to preset requirement, test product protects bad place to have Significant performance, intuitively shows test effect;
F, test terminates, and closes system, takes out test product, and test product surface is cleared up in cleaning system;
G, the input information for switching or changing the electric control gear by manually controlling the electric control gear enters new round test.
CN201711484783.5A 2017-12-29 2017-12-29 A kind of product protective capacities test equipment and test method Pending CN109990951A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711484783.5A CN109990951A (en) 2017-12-29 2017-12-29 A kind of product protective capacities test equipment and test method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711484783.5A CN109990951A (en) 2017-12-29 2017-12-29 A kind of product protective capacities test equipment and test method

Publications (1)

Publication Number Publication Date
CN109990951A true CN109990951A (en) 2019-07-09

Family

ID=67110354

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711484783.5A Pending CN109990951A (en) 2017-12-29 2017-12-29 A kind of product protective capacities test equipment and test method

Country Status (1)

Country Link
CN (1) CN109990951A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1338318A (en) * 1971-11-18 1973-11-21 Cross Co Leak detector unit
GB1426556A (en) * 1972-05-05 1976-03-03 British Gas Corp Vacuum proving apparatus for plant using gaseous fuel and plant having such arrangement
CN203465064U (en) * 2013-09-11 2014-03-05 浙江茗熔电器保护系统有限公司 Circuit control system of sealing performance detection equipment
CN204065361U (en) * 2014-08-04 2014-12-31 北京佩特来电器有限公司 Starter wet type bell housing stand durability test apparatus
CN204330246U (en) * 2015-01-13 2015-05-13 四川新健康成生物股份有限公司 A kind of movable type general-purpose device automatically detected for impermeability
CN204373858U (en) * 2015-02-02 2015-06-03 深圳市中孚能电气设备有限公司 A kind of automatic shutter waterproof tester
CN106840526A (en) * 2017-01-03 2017-06-13 歌尔股份有限公司 Electronic product waterproof tester
CN206387543U (en) * 2016-12-06 2017-08-08 群光电子(苏州)有限公司 Waterproof test tool
CN207717298U (en) * 2017-12-29 2018-08-10 北京佩特来电器有限公司 A kind of product protective capacities test equipment

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1338318A (en) * 1971-11-18 1973-11-21 Cross Co Leak detector unit
GB1426556A (en) * 1972-05-05 1976-03-03 British Gas Corp Vacuum proving apparatus for plant using gaseous fuel and plant having such arrangement
CN203465064U (en) * 2013-09-11 2014-03-05 浙江茗熔电器保护系统有限公司 Circuit control system of sealing performance detection equipment
CN204065361U (en) * 2014-08-04 2014-12-31 北京佩特来电器有限公司 Starter wet type bell housing stand durability test apparatus
CN204330246U (en) * 2015-01-13 2015-05-13 四川新健康成生物股份有限公司 A kind of movable type general-purpose device automatically detected for impermeability
CN204373858U (en) * 2015-02-02 2015-06-03 深圳市中孚能电气设备有限公司 A kind of automatic shutter waterproof tester
CN206387543U (en) * 2016-12-06 2017-08-08 群光电子(苏州)有限公司 Waterproof test tool
CN106840526A (en) * 2017-01-03 2017-06-13 歌尔股份有限公司 Electronic product waterproof tester
CN207717298U (en) * 2017-12-29 2018-08-10 北京佩特来电器有限公司 A kind of product protective capacities test equipment

Similar Documents

Publication Publication Date Title
CN207717298U (en) A kind of product protective capacities test equipment
KR101928034B1 (en) Bottom sealed and top cover connector type chamber test device used the water pressure test of the ocean equipment
CN209178483U (en) Cathodic protection potential measuring device
JPH11264499A (en) Oil mist generating system and method
CN109990951A (en) A kind of product protective capacities test equipment and test method
CN111749922A (en) Molecular pump fault diagnosis prediction system
CN104438199B (en) Aircraft engine starter flushing equipment and control system thereof
US5671135A (en) Programmable controller module
CN110426306B (en) Device for testing heat shock resistance of glass panel of indoor heater
CN112728317A (en) Garden hazardous chemical substance monitoring system based on industrial internet and implementation method thereof
CN202851518U (en) Digital display hydraulic cylinder
CN110440994A (en) A kind of waterproof performance detection method of plated film LED light strip
CN106353140A (en) Vacuum sampling system
CN207623455U (en) Industrial frequency withstand voltage testing equipment in a kind of automation insulation seed oil
CN205554149U (en) Self -service vehicle washing machine
CN210120328U (en) Control room and monitored control system for it is underground or under water
CN211425793U (en) Transformer conservator sealing detection device
CN110411680B (en) Liquid injection and drainage and pressure detection device for closed liquid cooling system
JP2000241288A (en) Seal inspection equipment
CN106225990B (en) Method for monitoring by using vacuum dew point intelligent monitoring device
CN108916020B (en) Automatic detection equipment for pressure maintaining of hydraulic pump
CN205330910U (en) Compressor system
CN219799729U (en) Cable identification device
CN206056875U (en) For the flushing of hydraulic tube piece inwall and the device of weld seam pressure-bearing detection
CN110702341A (en) Transformer conservator sealing detection device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination