CN109989780A - A kind of plateau tunnel ventilation pressurizing device - Google Patents

A kind of plateau tunnel ventilation pressurizing device Download PDF

Info

Publication number
CN109989780A
CN109989780A CN201910375269.0A CN201910375269A CN109989780A CN 109989780 A CN109989780 A CN 109989780A CN 201910375269 A CN201910375269 A CN 201910375269A CN 109989780 A CN109989780 A CN 109989780A
Authority
CN
China
Prior art keywords
ante
chamber
hole
pressure
back cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910375269.0A
Other languages
Chinese (zh)
Other versions
CN109989780B (en
Inventor
张凯
李建斌
王杜娟
李光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Engineering Equipment Group Co Ltd CREG
Original Assignee
China Railway Engineering Equipment Group Co Ltd CREG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Engineering Equipment Group Co Ltd CREG filed Critical China Railway Engineering Equipment Group Co Ltd CREG
Priority to CN201910375269.0A priority Critical patent/CN109989780B/en
Publication of CN109989780A publication Critical patent/CN109989780A/en
Application granted granted Critical
Publication of CN109989780B publication Critical patent/CN109989780B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • E21F1/006Ventilation at the working face of galleries or tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F11/00Rescue devices or other safety devices, e.g. safety chambers or escape ways
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Emergency Management (AREA)
  • Pulmonology (AREA)
  • Control Of Fluid Pressure (AREA)
  • Ventilation (AREA)

Abstract

The present invention proposes a kind of plateau tunnel ventilation pressurizing device, including sealing system in hole, sealing system includes ante-chamber partition panel in the hole, ante-chamber partition panel is equipped with ante-chamber telescopic device, ante-chamber telescopic device and ante-chamber are tightly connected, and ante-chamber sealing cooperates with tunnel, and the front of ante-chamber partition panel forms ante-chamber, pressurization dynamical system is connected to pressure regulating system, and pressure regulating system and wind-exchanging system extend in ante-chamber.Advantages of the present invention: guarantee that ante-chamber constructing tunnel work surface environmental pressure is stabilized to the Plain 1bar(pressure in hole);Marshaling and personnel, which can be convenient, navigates within ante-chamber in hole, adapter cavity, back cavity in hole;PM2.5 detection device monitors hole endoparticle object concentration in real time in hole, and carries out early warning ventilation operation, guarantees that air is suitble to construction personnel's operation in hole;Ante-chamber in hole, adapter cavity, back cavity is equipped with sound-powered phone, anti-explosion telephone facilitates in hole in hole dispatches.

Description

A kind of plateau tunnel ventilation pressurizing device
Technical field
The present invention relates to constructing tunnel equipment, particularly relate to a kind of plateau tunnel ventilation pressurizing device.
Background technique
Sichuan-Tibet railway will start to build on a large scale, since Sichuan-Tibet railroad elevation is normally at 4000 meters or so, atmospheric pressure About 0.5bar or so is probably the half of Plain atmospheric pressure, and personnel generally have altitude sickness in this height above sea level in-cavity construction, out The situations such as existing headache, dizziness, dim eyesight, tinnitus, malaise, difficulty in walking, if not being aerated pressurization to construction tunnel, it will Extreme influence normal construction.
Using plateau tunnel ventilation pressurizing device, the pressure of construction environment in tunnel can be stabilized to the Plain 1bar(pressure Power), to efficiently construct.
Plateau tunnel ventilation pressurizing device includes back cavity sealing system in ante-chamber and hole in hole, before guarantee is sealed in hole Chamber;Ante-chamber pressure regulating system in hole guarantees that preceding cavity pressure is 1bar or so in hole;Adapter cavity adds depressurized system, guarantees marshalling Train and personnel shuttle;Ante-chamber wind-exchanging system in hole, according to PM2.5 concentration and oxygen content in hole, air in real-time update hole; Communication and lighting system, communication can be convenient in hole and dispatch in time.
Summary of the invention
The problem of present invention proposes a kind of plateau tunnel ventilation pressurizing device, and it is severe to solve altitude environment, influences construction.
The technical scheme of the present invention is realized as follows: sealing system in a kind of plateau tunnel ventilation pressurizing device, including hole It unites, sealing system includes ante-chamber partition panel in the hole, and ante-chamber partition panel is equipped with ante-chamber telescopic device, ante-chamber telescopic device It is tightly connected with ante-chamber, ante-chamber sealing cooperates with tunnel, and the front of ante-chamber partition panel forms ante-chamber, dynamical system of pressurizeing and pressure Regulating system connection, pressure regulating system and wind-exchanging system extend in ante-chamber.
The pressurization dynamical system includes pressure duct, pressure duct by air compressor machine, air accumulator, back cavity air accumulator with Pressure regulating system connection.
The pressure duct is equipped with cooling driers and filter between air compressor machine and air accumulator.
The pressure duct is equipped with relay air accumulator and relay pneumatics between air accumulator and back cavity air accumulator Machine.
The pressure regulating system includes ante-chamber channel, and ante-chamber channel is divided into two-way, stretches all the way by single-seat adjusting valve To ante-chamber, another way is divided into two-way by Pneumatic decompression part, is connected to all the way with single-seat adjusting valve, and another way passes through pressure reducing valve I It is divided into two-way, is connected to all the way with PI controller, another way is connected to pressure transmitter, and PI controller is connected to single-seat adjusting valve, PI controller is connected to pressure transmitter, pressure transmitter and the pipeline connection for being located at single-seat adjusting valve rear end part.
The ante-chamber is connected to by safety line with back cavity, and safety line is equipped with safety valve.
The ante-chamber telescopic device is ante-chamber telescopic cylinder.
The wind-exchanging system includes two ventilation ducts, and a ventilation duct is connected to outside ante-chamber and hole by ventilation blower, another ventilation Pipe is connected to ante-chamber and back cavity.
Detection of Air Quality equipment and hedging storehouse are equipped in the ante-chamber.
Sealing system further includes back cavity partition panel in the hole, and back cavity partition panel is equipped with back cavity telescopic device, back cavity Telescopic device and back cavity are tightly connected, and back cavity sealing cooperates with tunnel, form transition between ante-chamber partition panel and back cavity partition panel Chamber, the rear portion of back cavity partition panel form back cavity, pressurization dynamical system and plus-minus pressure system connectivity, depressurized system are added to extend to adapter cavity It is interior.
Described plus depressurized system includes adapter cavity pipeline, and adapter cavity is extended back by pressure relief assembly to adapter cavity.
The adapter cavity is extended back by two groups of pressure relief assemblies to adapter cavity.
The pressure relief assembly includes check valve, pressure reducing valve and pressure gauge.
The adapter cavity pipeline is after pressure relief assembly using flowmeter.
The adapter cavity is connected to by safety line with back cavity, and safety line is equipped with safety valve.
Threeway balance pipe is equipped in the adapter cavity, pipe one end extends to ante-chamber by ball valve I, and the pipe other end is located at transition Intracavitary and be equipped with ball valve I, the pipe other end extends to back cavity by ball valve I, the pressure gauge in adapter cavity, the pressure gauge in back cavity.
The back cavity telescopic device is back cavity telescopic cylinder.
Advantages of the present invention: guarantee that ante-chamber constructing tunnel work surface environmental pressure is stabilized to the Plain 1bar(pressure in hole); Marshaling and personnel, which can be convenient, navigates within ante-chamber in hole, adapter cavity, back cavity in hole;PM2.5 detection device is supervised in real time in hole Hole endoparticle object concentration is controlled, and carries out early warning ventilation operation, guarantees that air is suitble to construction personnel's operation in hole;Ante-chamber, mistake in hole Cross that chamber, back cavity is equipped with sound-powered phone, anti-explosion telephone facilitates in hole in hole dispatches.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with It obtains other drawings based on these drawings.
Fig. 1 is schematic structural view of the invention.
Fig. 2 is that sealing system overhangs schematic diagram in hole of the present invention.
Fig. 3 is the side view of Fig. 2.
Fig. 4 is that sealing system recycles schematic diagram in hole of the present invention.
Fig. 5 is the side view of Fig. 4.
In figure: 1- ante-chamber partition panel, 2- ante-chamber telescopic cylinder, the sealing of 3- ante-chamber, 4- back cavity partition panel, 5- back cavity stretch gas Cylinder, 6- back cavity seal, 7- air compressor machine, 8- air accumulator, 9- pressure duct, 10- relay air accumulator, 11- relay air compressor machine, after 12- Cavity gas storage tank, 13- ball valve I, 14- Pneumatic decompression part, 15- pressure reducing valve I, 16-PI controller, 17- pressure transmitter, 18- single seat Regulating valve, 19- ball valve II, 20- ball valve III, 21- check valve, 22- pressure reducing valve II, 23- pressure gauge, 24- pressure reducing valve III, 25- Flowmeter, 26- gate valve, 27- anti-explosion telephone, 28- muffler, 29- ventilation blower, 30- ventilation duct, 31- butterfly valve I, 32- butterfly valve II, 33- safety valve, the compensation environmental pressure table of 34-, the explosion-proof clock and watch of 35-, 36- Hygrothermograph, 37- sound-powered phone, 38- emergency lighting Lamp, 39- back cavity hermatic door, 40- ante-chamber hermatic door, 41- ante-chamber, 42- adapter cavity, 43- back cavity, 44- Detection of Air Quality equipment, 45- ball valve IV, 46- hedging storehouse, 47- pressure sensor, 48- prior-warning device, 49- cooling driers, 50- filter.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other under that premise of not paying creative labor Embodiment shall fall within the protection scope of the present invention.
As shown in Figure 1, sealing system, pressurization dynamical system, pressure in a kind of plateau tunnel ventilation pressurizing device, including hole Regulating system plus depressurized system and wind-exchanging system.
Sealing system includes ante-chamber partition panel 1 and back cavity partition panel 4 in hole, and ante-chamber partition panel 1 is equipped with the flexible gas of ante-chamber Cylinder 2, ante-chamber telescopic cylinder 2 are connect with ante-chamber sealing 3, and ante-chamber sealing 3 cooperates with tunnel, and back cavity partition panel 4 is stretched equipped with back cavity Contracting cylinder 5, back cavity telescopic cylinder 5 are connect with back cavity sealing 6, and back cavity sealing 6 cooperates with tunnel, the front shape of ante-chamber partition panel 1 At ante-chamber 41, adapter cavity 42 is formed between ante-chamber partition panel 1 and back cavity partition panel 4, the rear portion of back cavity partition panel 4 forms back cavity 43, ante-chamber partition panel 1 is equipped with ante-chamber hermatic door 40, and back cavity partition panel 4 is equipped with back cavity hermatic door 39.
Pressurization dynamical system includes pressure duct 9, and pressure duct 9 passes through air compressor machine 7, ball valve III20, cooling driers 49, ball Divide after valve III20, filter 50, ball valve III20, air accumulator 8, relay air accumulator 10, relay air compressor machine 11, back cavity air accumulator 12 It for two-way, is connected to all the way with pressure regulating system, another way and plus-minus pressure system connectivity.
Pressure regulating system includes ante-chamber channel, pressure duct 9 after back cavity air accumulator 12 all the way with ante-chamber channel Connection, ante-chamber channel are divided into two-way after ball valve IV45, are divided into two after single-seat adjusting valve 18 extends in ante-chamber 41 all the way Road, another way after ball valve IV45 are divided by ball valve I13, Pneumatic decompression part 14 for two-way, all the way with single-seat adjusting valve 18 Connection, another way are two-way by pressure reducing valve I15 points, are connected to all the way with PI controller 16, and another way and pressure transmitter 17 connect Logical, PI controller 16 is connected to single-seat adjusting valve 18, and PI controller 16 is connected to pressure transmitter 17, pressure transmitter 17 and position Ball valve III20 is equipped on pipeline before and after the pipeline connection of 18 rear end part of single-seat adjusting valve, this connectivity part.
Adding depressurized system includes adapter cavity pipeline, another way and adapter cavity of the pressure duct 9 after back cavity air accumulator 12 Pipeline connection, adapter cavity pipeline pass through check valve 21, pressure reducing valve II22, pressure gauge 23, check valve 21, pressure reducing valve III24, pressure Table 23, spinner flowmeter 25 divide for two-way, and the gate valve 26 passed through in back cavity all the way is extended back to adapter cavity, then pass through check valve 21, muffler 28, another way directly extend to adapter cavity, then pass through check valve, gate valve 26 and muffler 28.
Wind-exchanging system includes two ventilation ducts 30, a ventilation duct 30 by hole outside ventilation blower 29, back cavity butterfly valve I31, preceding The butterfly valve I31 of chamber, to be connected to outside ante-chamber 41 and hole, another ventilation duct 30 is by the butterfly valve II32 of back cavity, the butterfly valve of ante-chamber II32, to be connected to ante-chamber 41 and back cavity 43.
Ante-chamber 41 and adapter cavity 42 are connected to by safety line with back cavity 43, and safety line is equipped with safety valve 33.
Threeway balance pipe is equipped in adapter cavity 42, pipe one end extends to ante-chamber 41 by ball valve I13, and the pipe other end is located at transition In chamber 42 and it is equipped with ball valve I13, the pipe other end passes through ball valve I13, the pressure gauge 23 in adapter cavity 42, the pressure gauge in back cavity 43 23 extend to back cavity 43.
It was equipped with for two communicating pipes between adapter cavity 42 and back cavity 43, a connecting pipe is equipped with the gate valve 26 and muffler of back cavity 28, another communicating pipe is equipped with the gate valve 26 of adapter cavity and the muffler 28 of back cavity.
Detection of Air Quality equipment 44, hedging storehouse 46, pressure sensor 47, prior-warning device are equipped in the ante-chamber 41 48.Compensation environmental pressure table 34, explosion-proof clock and watch 35, Hygrothermograph 36 and emergency light 38 are equipped in adapter cavity 42.Ante-chamber 41, anti-explosion telephone 27 and sound-powered phone 37 are communicated between adapter cavity 42, back cavity 43.
Sealing system in a kind of plateau tunnel ventilation pressurizing device, including hole, pressurization dynamical system, pressure regulating system, Add depressurized system and wind-exchanging system.
Form of construction work of the present invention: being divided into three chambers for tunnel by ante-chamber partition panel, back cavity partition panel and tunnel wall, according to Secondary is respectively ante-chamber, adapter cavity and back cavity, controls ante-chamber sealing by ante-chamber telescopic cylinder, it is close that back cavity telescopic cylinder controls back cavity Envelope, realizes the sealing or opening of each chamber.It is close that ante-chamber hermatic door, back cavity are installed respectively on ante-chamber partition panel, back cavity partition panel Closure door shuttles for marshaling and personnel.Tunnel is needed in hole wall when constantly tunneling forward using the side such as swage slip casting The tunnel of formula, interval production high-flatness seals section, is used to constantly move forward, guarantees the gas leakage that ante-chamber is small as far as possible in hole Amount.
Pressurization dynamical system includes the air compressor machine outside hole, and air compressor machine delivers compressed air to air accumulator, then passes through high pressure Pipeline delivers compressed air to relay air accumulator (with the extension of tunnel distance, according to pipeline crushing and pipeline compressive resistance Increase relay air compressor machine and relay air accumulator), then the back cavity air accumulator in hole is transported to by relay air compressor machine relay pressurizing, point It Jin Ru not pressure regulating system and plus depressurized system.
Pressure regulating system includes ante-chamber channel, and the compressed air from back cavity air accumulator enters ante-chamber channel, is passed through all the way Ball valve IV points are crossed as two-way, is directly protruding into ante-chamber by unidirectional regulating valve all the way, cavity pressure is stablized before guaranteeing, another way is passed through Ball valve I reduces to 4bar into Pneumatic decompression three linked piece pressure, and 4bar compressed air is divided into two-way, and 4bar compressed air is all the way Single-seat adjusting valve provides power source, and another way 4bar compressed air is further depressurized to 1.4bar, 1.4bar by pressure reducing valve I Compressed air is divided into two-way, and 1.4bar compressed air provides power source, another way 1.4bar compressed air for PI controller all the way Power source is provided for pressure transmitter.PI controller compared with setting pressure 1bar, controls X mouthfuls by Y mouthfuls of compressed airs The opening size of single-seat adjusting valve, ante-chamber working region pressure is 1bar normal pressure in the hole Lai Wending.
Adding depressurized system includes adapter cavity pipeline, and the compressed air from back cavity air accumulator enters adapter cavity pipeline, then By check valve, pressure reducing valve II is adjusted by observation pressure gauge and is depressurized to 4bar, enters back into check valve, again by observation pressure Table adjusts pressure reducing valve III and is depressurized to 1bar, the flow of compressed air is observed by spinner flowmeter, and control by manual gate valve The flow of air, silencer can reduce the noise of air.
The safety valve of 1bar is installed, cavity pressure is no more than 1bar before guaranteeing between ante-chamber and back cavity.After in adapter cavity and hole The safety valve that 1bar is installed between chamber guarantees that transition cavity pressure in hole is no more than 1bar.
Wind-exchanging system conveys fresh air into hole by ventilation blower, ventilation duct, there is PM2.5 and oxygen content detection in hole Equipment, ante-chamber air quality in real-time detection hole, if air quality is poor, air replacement early-warning lamp and alarm are rung first in hole It rises, ante-chamber construction personnel enters danger avoidance cabin pressure maintaining and hides in hole, the pneumatic ball valve IV phase down of pressure regulating system, two gas Dynamic butterfly valve I, two Pneumatic butterfly valve II are opened, and hole separate ventilation machine starting, tunnel uses forced ventilation, until PM2.5 is examined in hole It is qualified to survey air, separate ventilation machine in hole stops, and two Pneumatic butterfly valve I, two Pneumatic butterfly valve II are closed, pressure regulating system it is pneumatic Ball valve IV is opened, and air replacement early-warning lamp and alarm stop in hole, and construction personnel is by ante-chamber intercommunication balance pressure in danger avoidance cabin and hole Power comes out from danger avoidance cabin and continues to construct.
It is connected between ante-chamber and adapter cavity by threeway balance pipe in hole, when marshaling and personnel will enter ante-chamber in hole When, the pressure between ante-chamber and adapter cavity is balanced by manual ball valve I.
The systems such as back cavity communication are ante-chamber in hole, adapter cavity in hole, back cavity provides Communications service in hole, can be efficient complete At the scheduling in tunnel.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (10)

1. sealing system in a kind of plateau tunnel ventilation pressurizing device, including hole, it is characterised in that: sealing system in the hole Including ante-chamber partition panel (1), ante-chamber partition panel (1) is equipped with ante-chamber telescopic device, and ante-chamber telescopic device and ante-chamber sealing (3) are even It connects, ante-chamber seals (3) and tunnel cooperates, and the front of ante-chamber partition panel (1) forms ante-chamber (41), pressurization dynamical system and pressure tune System connectivity is saved, pressure regulating system and wind-exchanging system extend in ante-chamber (41).
The pressurizing device 2. plateau tunnel according to claim 1 is divulged information, it is characterised in that: the pressurization dynamical system packet It includes pressure duct (9), pressure duct (9) is by air compressor machine (7), air accumulator (8), back cavity air accumulator (12) and pressure regulating system Connection.
The pressurizing device 3. plateau tunnel according to claim 2 is divulged information, it is characterised in that: on the pressure duct (9) Equipped with the cooling driers (49) and filter (50) between air compressor machine (7) and air accumulator (8).
The pressurizing device 4. plateau tunnel according to claim 2 is divulged information, it is characterised in that: on the pressure duct (9) Equipped with the relay air accumulator (10) and relay air compressor machine (11) between air accumulator (8) and back cavity air accumulator (12).
The pressurizing device 5. plateau tunnel according to claim 1 is divulged information, it is characterised in that: the pressure regulating system packet Ante-chamber channel is included, ante-chamber channel is divided into two-way, extends in ante-chamber (41) by single-seat adjusting valve (18) all the way, and another way passes through gas Dynamic decompression part (14) is divided into two-way, is connected to all the way with single-seat adjusting valve (18), and another way passes through pressure reducing valve I(15) it is divided into two-way, It is connected to all the way with PI controller (16), another way is connected to pressure transmitter (17), PI controller (16) and single-seat adjusting valve (18) it is connected to, PI controller (16) be connected to pressure transmitter (17), pressure transmitter (17) and positioned at single-seat adjusting valve (18) The pipeline connection of rear end part.
The pressurizing device 6. plateau tunnel according to claim 1 is divulged information, it is characterised in that: the wind-exchanging system includes two Ventilation duct (30), a ventilation duct (30) are connected to outside ante-chamber (41) and hole by ventilation blower (29), and another ventilation duct is connected to ante-chamber (41) and back cavity (43).
The pressurizing device 7. plateau tunnel according to claim 1 is divulged information, it is characterised in that: be equipped in the ante-chamber (41) Detection of Air Quality equipment (44) and hedging storehouse (46).
The pressurizing device 8. plateau tunnel according to claim 1 is divulged information, it is characterised in that: sealing system is also in the hole Including back cavity partition panel (4), back cavity partition panel (4) is equipped with back cavity telescopic device, and back cavity telescopic device and back cavity sealing (6) are even It connects, back cavity seals (6) and tunnel cooperates, and forms adapter cavity (42) between ante-chamber partition panel (1) and back cavity partition panel (4), back cavity The rear portion of partition panel (4) forms back cavity (43), and pressurization dynamical system and plus-minus pressure system connectivity add depressurized system to extend to adapter cavity (42) in.
The pressurizing device 9. plateau tunnel according to claim 8 is divulged information, it is characterised in that: described plus depressurized system includes Adapter cavity pipeline, adapter cavity are extended back by pressure relief assembly to adapter cavity (42).
The pressurizing device 10. plateau tunnel according to claim 8 is divulged information, it is characterised in that: in the adapter cavity (42) Equipped with threeway balance pipe, ball valve I(13 is passed through in pipe one end) it extends to ante-chamber (41), the pipe other end is located in adapter cavity (42) and is equipped with Ball valve I(13), the pipe other end is by ball valve I(13), the pressure gauge (23) in adapter cavity (42), the pressure gauge in back cavity (43) (23) back cavity (43) are extended to.
CN201910375269.0A 2019-05-07 2019-05-07 Plateau tunnel ventilation pressurizing device Active CN109989780B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910375269.0A CN109989780B (en) 2019-05-07 2019-05-07 Plateau tunnel ventilation pressurizing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910375269.0A CN109989780B (en) 2019-05-07 2019-05-07 Plateau tunnel ventilation pressurizing device

Publications (2)

Publication Number Publication Date
CN109989780A true CN109989780A (en) 2019-07-09
CN109989780B CN109989780B (en) 2024-04-19

Family

ID=67135957

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910375269.0A Active CN109989780B (en) 2019-05-07 2019-05-07 Plateau tunnel ventilation pressurizing device

Country Status (1)

Country Link
CN (1) CN109989780B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101095972A (en) * 2007-07-05 2008-01-02 北京科技大学 Tunnel face dispersion oxygen supplying system and oxygen supplying method in high altitude area
CN201334909Y (en) * 2008-12-18 2009-10-28 中铁隧道集团隧道设备制造有限公司 Airlock of shield machine
CN102429778A (en) * 2011-12-26 2012-05-02 中国人民武装警察部队后勤学院附属医院 Medical security car capable of realizing highland pressurization
CN102635397A (en) * 2012-03-30 2012-08-15 长治清华机械厂 Air supply device of mining rescue capsule
CN104265042A (en) * 2014-09-12 2015-01-07 北京新立机械有限责任公司 Emergency capsule
CN204754987U (en) * 2015-05-19 2015-11-11 中交二公局第三工程有限公司 Tunnel internally -powered wind pressure pressure device under high and cold condition in plateau
CN205277471U (en) * 2015-12-15 2016-06-01 西南交通大学 High and cold construction ventilation of tunnel system in plateau
CN208502769U (en) * 2018-06-13 2019-02-15 中铁十四局集团大盾构工程有限公司 A kind of gas ventilator for fire operation with pressure in shield cabin
CN209818097U (en) * 2019-05-07 2019-12-20 中铁工程装备集团有限公司 Plateau tunnel ventilation pressure device

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101095972A (en) * 2007-07-05 2008-01-02 北京科技大学 Tunnel face dispersion oxygen supplying system and oxygen supplying method in high altitude area
CN201334909Y (en) * 2008-12-18 2009-10-28 中铁隧道集团隧道设备制造有限公司 Airlock of shield machine
CN102429778A (en) * 2011-12-26 2012-05-02 中国人民武装警察部队后勤学院附属医院 Medical security car capable of realizing highland pressurization
CN102635397A (en) * 2012-03-30 2012-08-15 长治清华机械厂 Air supply device of mining rescue capsule
CN104265042A (en) * 2014-09-12 2015-01-07 北京新立机械有限责任公司 Emergency capsule
CN204754987U (en) * 2015-05-19 2015-11-11 中交二公局第三工程有限公司 Tunnel internally -powered wind pressure pressure device under high and cold condition in plateau
CN205277471U (en) * 2015-12-15 2016-06-01 西南交通大学 High and cold construction ventilation of tunnel system in plateau
CN208502769U (en) * 2018-06-13 2019-02-15 中铁十四局集团大盾构工程有限公司 A kind of gas ventilator for fire operation with pressure in shield cabin
CN209818097U (en) * 2019-05-07 2019-12-20 中铁工程装备集团有限公司 Plateau tunnel ventilation pressure device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王瑜敏等: "《金属矿山》", 28 February 2022, pages: 194 - 198 *

Also Published As

Publication number Publication date
CN109989780B (en) 2024-04-19

Similar Documents

Publication Publication Date Title
CN102198321A (en) Normal-pressure hypoxic cabin for interval hypoxic training and method for regulating oxygen concentration in hypoxic cabin
CN109989780A (en) A kind of plateau tunnel ventilation pressurizing device
CN209818097U (en) Plateau tunnel ventilation pressure device
CN107420109A (en) A kind of automatic pressure-maintaining system and shield machine for slurry balance shield machine
CN208277865U (en) A kind of bullet train denoising device
CN101426554A (en) Breathing apparatus for an aircrew member
CN207420573U (en) A kind of automatic pressure-maintaining system and shield machine for slurry balance shield machine
CN208331787U (en) Continuous gas supply superpressure pressure protective device
CN103982223B (en) Compressed-air supply system
CN114279651A (en) Airtightness testing system using diaphragm compressor and operation method
GB1264560A (en)
CN206086284U (en) Automobile -used oxygen suppliment pressure regulating system in plateau
CN211315770U (en) Pressure-maintaining air supply device for breathing air of temporary refuge
CN210278013U (en) Intelligent mine compressed air self-rescue device
CN209415038U (en) A kind of hydrogen air supply system
CN203879539U (en) Oxygen supplying device for coal mine refuge chamber
CN207416085U (en) A kind of wind pressure automatic control system
CN108279134A (en) Universal on-board oxygen equipment simulating experimental rig
CN217462238U (en) Drilling/rescuing dual-purpose safe self-rescuing air and oxygen supply system
CN209505396U (en) A kind of driving cab of fire fighting truck and the safe breathing equipment of crew department
CN104747490A (en) Bearing-oil-sealed buffer gas pressure control method
CN210567566U (en) Oxygen gas supply explosion-proof structure
CN104763664B (en) Bearing oil-tightening buffering air pressure Force control system
CN217875336U (en) Control valve block of emergency system for underground coal mine
CN219208286U (en) Vacuum pressure reducing device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant