CN109987555A - The construction method of pneumatic enhanced demister - Google Patents

The construction method of pneumatic enhanced demister Download PDF

Info

Publication number
CN109987555A
CN109987555A CN201910198331.3A CN201910198331A CN109987555A CN 109987555 A CN109987555 A CN 109987555A CN 201910198331 A CN201910198331 A CN 201910198331A CN 109987555 A CN109987555 A CN 109987555A
Authority
CN
China
Prior art keywords
absorption tower
enhanced
pneumatic
demister
hydraulic lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910198331.3A
Other languages
Chinese (zh)
Inventor
阮启祎
聂中员
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electric Construction Group Jiangxi Electric Power Construction Co Ltd
Original Assignee
China Electric Construction Group Jiangxi Electric Power Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Electric Construction Group Jiangxi Electric Power Construction Co Ltd filed Critical China Electric Construction Group Jiangxi Electric Power Construction Co Ltd
Priority to CN201910198331.3A priority Critical patent/CN109987555A/en
Publication of CN109987555A publication Critical patent/CN109987555A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D53/00Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols
    • B01D53/14Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols by absorption
    • B01D53/18Absorbing units; Liquid distributors therefor
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F11/00Lifting devices specially adapted for particular uses not otherwise provided for

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Analytical Chemistry (AREA)
  • General Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Vaporization, Distillation, Condensation, Sublimation, And Cold Traps (AREA)

Abstract

The invention discloses a kind of construction methods of pneumatic enhanced demister, absorption tower is divide into upper part and lower part first, platform is built at the buttress of the spray piping on absorption tower and the supporting beam of spray piping, column and hydraulic lifting apparatus are installed on platform, packing is installed in upper absorption inner wall of tower, upper absorption tower is raised to required height using hydraulic lifting apparatus.Compared to traditional absorption tower remodeling method, construction method of the invention cuts absorption tower, absorption tower is divided into upper absorption tower and lower absorption tower two parts, lifting operation only is carried out to upper absorption tower, more than ten meters of upper absorption tower whole height, weight are more than 100 tons, greatly reduce absorption tower transformation project amount, can save the cost can also reduce construction risk.

Description

The construction method of pneumatic enhanced demister
Technical field
The present invention relates to project installation field more particularly to a kind of construction methods for starting enhanced demister.
Background technique
Pneumatic enhanced demister is mainly used in the absorption tower of wet desulphurization industry, and effect is to remove in air-flow Mist, this mist not only contain moisture, also dissolved with substances such as sulfuric acid, sulfate, sulfur dioxide, to blower, heat exchanger and flue It is stained, corrosion very capable, it is therefore desirable to remove.
What is generally installed in traditional absorption tower is a kind of old demister, with new pneumatic enhanced demister in shape It is different in size, if replacing the height that old demister needs to increase absorption tower with pneumatic enhanced demister.The prior art Way is that entire absorption tower is lifted since the bottom on absorption tower, and entire absorption tower height degree about 50m, weight are more than 400 tons, not only Height is required to the hydraulic lifting apparatus of lifting, and needs to modify the spray piping on absorption tower, project amount is big.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of construction methods of new pneumatic enhanced demister, to absorption Tower is cut, and absorption tower is divided into upper absorption tower and lower absorption tower two parts, and only to upper absorption tower, (upper absorption tower refers to suction The part of the high 30m or more of tower beacon is received, demister is mounted in absorption tower) it is lifted, it reduces and pneumatic enhanced demisting is installed The difficulty of construction of device, while the spray piping that former absorption tower is transformed is avoided, reduce whole project amount.
In order to solve the above technical problems, the technical solution adopted by the present invention are as follows: a kind of construction of pneumatic enhanced demister Method includes the following steps:
Step 1: platform and scaffold are built below the cutting line of absorption tower, cutting line is located at below old demister (cutting The absolute altitude of line is 30m or so), the hard point of platform and scaffold is located at the buttress and spray piping of the spray piping on absorption tower Supporting beam;
Step 2: the expansion joint for removing the net flue in absorption tower and associated conduit, the cable testing bridge etc. that influence construction are set It is standby;
Step 3: column being installed on platform, hydraulic lifting apparatus is installed on column, is installed more than the cutting line of absorption tower Packing;Then hydraulic lifting apparatus is tentatively promoted, increase the lift lever of hydraulic lifting apparatus and gib head, gib head holds out against packing;
Step 4: being cut at cutting line, absorption tower is split as two parts up and down;
Step 5: starting hydraulic lifting apparatus, absorption tower in lifting;
Step 6: new siding is welded in the bottom on upper absorption tower;
Step 7: packing being installed on new siding;
Step 8: step 5-7 is repeated, until upper absorption tower is promoted to required height;
Step 9: removing old demister, new pneumatic enhanced demister is installed.
Further, the packing is the channel steel after curved arc, and the internal diameter of packing and the internal diameter on absorption tower are equal, swollen Circle is generally divided into three sections, and insertion is welded in the door shape snap-gauge for absorbing inner wall of tower;In order to improve the intensity of packing and avoid sliding It moves, reinforcing rib can be set inside channel steel, and welding is used for anti-skidding angle steel between channel steel and the inner wall on upper absorption tower.
Further, diagonal brace is provided between the column and platform.
Further, the erosion resistant coating that inner wall of tower corresponds to packing position is absorbed in the preparation stage removal of construction, it is ensured that door Shape snap-gauge firm welding, while reducing packing and the upper sliding absorbed between inner wall of tower.
Further, in the step 5, the process on absorption tower is gradually to carry out in lifting, is lifted upper absorption tower every time Suspend after setting height, observes and check whether column, packing and hydraulic lifting apparatus are normal;Check all hydraulic lifting device Hoisting depth, if the maximum height difference of hydraulic lifting apparatus be more than setting value, all hydraulic lifting device is adjusted It is flat;In leveling, a hoisting depth of single hydraulic lifting apparatus is no more than 3mm.
The utility model has the advantages that construction method of the invention cuts absorption tower, absorption tower is divided into upper absorption tower under Absorption tower two parts, only carry out lifting operation to upper absorption tower, and more than ten meters of upper absorption tower whole height, weight are more than 100 Ton, greatly reduce absorption tower transformation project amount, can save the cost can also reduce construction risk.
Detailed description of the invention
Fig. 1 is the construction schematic diagram of the pneumatic enhanced demister of embodiment 1.
Wherein: 1, upper absorption tower;2, lower absorption tower;3, packing;4, door shape snap-gauge;5, platform;6, column;7, diagonal brace;8, Hydraulic lifting apparatus;9, reinforcing rib;10, angle steel;11, lift lever;12, gib head;13, cutting line.
Specific embodiment
Invention is further described in detail With reference to embodiment.
Embodiment 1
As shown in Figure 1, the construction method of the pneumatic enhanced demister of the present embodiment, includes the following steps:
Step 1: 1 inner wall of absorption tower corresponds to the erosion resistant coating of 3 position of packing in removal, welds multiple shape snap-gauges in the position 4;
Step 2: building platform 5 and scaffold in 13 or less absorption tower cutting line, (scaffold is used to provide for construction worker It is convenient, be not shown in the figure), cutting line 13 is located at below old demister (absolute altitude of cutting line 13 is 30m or so), 5 He of platform The hard point of scaffold is located at the buttress of the spray piping on absorption tower and the supporting beam of spray piping;
Step 3: the expansion joint for removing the net flue in absorption tower and associated conduit, the cable testing bridge etc. that influence construction are set It is standby;
Step 4: column 6 being installed on platform 5, diagonal brace 7 is provided between column 6 and platform 5, is installed on column 6 hydraulic Lifting device 8, on absorption tower, 13 or more cutting line installs packing 3, and packing 3 is the #25 channel steel after curved arc, packing 3 Internal diameter is equal with the internal diameter on absorption tower, and it is three sections that packing 3, which divides, and insertion is welded in the door shape snap-gauge 4 for absorbing inner wall of tower;In channel steel Inside setting reinforcing rib 9, and welding is used for anti-skidding angle steel 10 between channel steel and the inner wall on upper absorption tower 1;Then it tentatively mentions Hydraulic lifting apparatus 8 is risen, increase the lift lever 11 of hydraulic lifting apparatus 8 and gib head 12, gib head 12 holds out against packing 3;
Step 5: being cut at cutting line 13, absorption tower is split as upper absorption tower 1 and lower 2 two parts of absorption tower;
Step 6: starting hydraulic lifting apparatus 8, absorption tower 1 in lifting;
Step 7: welding new siding in the bottom on upper absorption tower 1;
Step 8: packing 3 is installed on new siding;
Step 9: step 6-8 is repeated, until upper absorption tower 1 is promoted to required height;
Step 9: removing old demister, new pneumatic enhanced demister is installed;
Step 10: removing platform 5, hydraulic lifting apparatus 8, column 6 etc.;
Step 11: the ending such as the attachmentes such as installation nozzle, polishing examination, sandblasting, spraying corrosion resistant coating, examination, dismounting scaffold Work.
In above-mentioned steps 6, the process on absorption tower 1 is gradually to carry out in lifting, is lifted upper absorption tower 1 every time about Suspend 10 minutes after 100mm, observes and check whether column 6, packing 3 and hydraulic lifting apparatus 8 are normal;Check that all hydraulic mentions The hoisting depth of device 8 is risen, if the maximum height difference of hydraulic lifting apparatus 8 is more than setting value, all hydraulic is promoted and is filled 8 are set to be leveled;In leveling, a hoisting depth of single hydraulic lifting apparatus 8 is no more than 3mm.
Although embodiments of the present invention are illustrated in specification, these embodiments are intended only as prompting, It should not limit protection scope of the present invention.It is equal that various omission, substitution, and alteration are carried out without departing from the spirit and scope of the present invention It should be included within the scope of the present invention.

Claims (8)

1. a kind of construction method of pneumatic enhanced demister, it is characterised in that include the following steps:
Step 1: platform and scaffold are built below the cutting line of absorption tower, cutting line is located at below old demister, platform and foot The hard point of hand cradle is located at the buttress of the spray piping on absorption tower and the supporting beam of spray piping;
Step 2: the equipment for removing the influence construction in absorption tower;
Step 3: column being installed on platform, hydraulic lifting apparatus is installed on column, packing is installed more than the cutting line of absorption tower;
Step 4: being cut at cutting line, absorption tower is split as two parts up and down;
Step 5: starting hydraulic lifting apparatus, absorption tower in lifting;
Step 6: new siding is welded in the bottom on upper absorption tower;
Step 7: packing being installed on new siding;
Step 8: step 5-7 is repeated, until upper absorption tower is promoted to required height;
Step 9: removing old demister, new pneumatic enhanced demister is installed.
2. the construction method of pneumatic enhanced demister according to claim 1, it is characterised in that: the packing is to pass through Channel steel after curved arc.
3. the construction method of pneumatic enhanced demister according to claim 2, it is characterised in that: set inside the channel steel It is equipped with reinforcing rib.
4. the construction method of pneumatic enhanced demister according to claim 3, it is characterised in that: in channel steel and upper absorption Welding is used for anti-skidding angle steel between the inner wall of tower.
5. the construction method of pneumatic enhanced demister according to claim 1, it is characterised in that: the column and platform Between be provided with diagonal brace.
6. the construction method of pneumatic enhanced demister according to claim 1, it is characterised in that: in the preparation rank of construction The erosion resistant coating that inner wall of tower corresponds to packing position is absorbed in section removal.
7. the construction method of pneumatic enhanced demister according to claim 1, it is characterised in that: in the step 5, The process on absorption tower is gradually to carry out in lifting, is suspended after being lifted upper absorption tower setting height every time, observes and check column, swollen Whether circle and hydraulic lifting apparatus are normal;The hoisting depth for checking all hydraulic lifting device, if hydraulic lifting apparatus is most Big height difference is more than setting value, then levels to all hydraulic lifting device.
8. the construction method of pneumatic enhanced demister according to claim 7, it is characterised in that: in leveling, individually Hoisting depth of hydraulic lifting apparatus is no more than 3mm.
CN201910198331.3A 2019-03-15 2019-03-15 The construction method of pneumatic enhanced demister Pending CN109987555A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910198331.3A CN109987555A (en) 2019-03-15 2019-03-15 The construction method of pneumatic enhanced demister

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910198331.3A CN109987555A (en) 2019-03-15 2019-03-15 The construction method of pneumatic enhanced demister

Publications (1)

Publication Number Publication Date
CN109987555A true CN109987555A (en) 2019-07-09

Family

ID=67129588

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910198331.3A Pending CN109987555A (en) 2019-03-15 2019-03-15 The construction method of pneumatic enhanced demister

Country Status (1)

Country Link
CN (1) CN109987555A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101879407A (en) * 2010-07-30 2010-11-10 广东火电工程总公司 Structure and method for jacking absorption tower from middle segment
CN101879399A (en) * 2010-07-30 2010-11-10 广东火电工程总公司 Structure and method for jacking absorption tower from middle segment
CN105776067A (en) * 2016-05-25 2016-07-20 中国能源建设集团湖南火电建设有限公司 Lifting device and inverted installing method for reducing absorption tower
CN105836678A (en) * 2016-05-25 2016-08-10 中国能源建设集团湖南火电建设有限公司 Lifting device and lifting method for large tank
CN106731517A (en) * 2016-12-22 2017-05-31 华润电力(菏泽)有限公司 A kind of cylinder tower cutting jacking turns to technique
CN106836836A (en) * 2017-01-23 2017-06-13 山东国舜建设集团有限公司 A kind of Flue Gas Desulphurization for Coal-burning Power Plant tower transforms secondary hydraulic lifting installation method
CN108502774A (en) * 2018-06-06 2018-09-07 中国能源建设集团广东火电工程有限公司 A kind of absorption tower tower top steering structure and forward method
CN108756441A (en) * 2018-08-11 2018-11-06 中国电建集团贵州电力设计研究院有限公司 A kind of hydraulic lifting flipped device and its hanging method for reducing tower

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101879407A (en) * 2010-07-30 2010-11-10 广东火电工程总公司 Structure and method for jacking absorption tower from middle segment
CN101879399A (en) * 2010-07-30 2010-11-10 广东火电工程总公司 Structure and method for jacking absorption tower from middle segment
CN105776067A (en) * 2016-05-25 2016-07-20 中国能源建设集团湖南火电建设有限公司 Lifting device and inverted installing method for reducing absorption tower
CN105836678A (en) * 2016-05-25 2016-08-10 中国能源建设集团湖南火电建设有限公司 Lifting device and lifting method for large tank
CN106731517A (en) * 2016-12-22 2017-05-31 华润电力(菏泽)有限公司 A kind of cylinder tower cutting jacking turns to technique
CN106836836A (en) * 2017-01-23 2017-06-13 山东国舜建设集团有限公司 A kind of Flue Gas Desulphurization for Coal-burning Power Plant tower transforms secondary hydraulic lifting installation method
CN108502774A (en) * 2018-06-06 2018-09-07 中国能源建设集团广东火电工程有限公司 A kind of absorption tower tower top steering structure and forward method
CN108756441A (en) * 2018-08-11 2018-11-06 中国电建集团贵州电力设计研究院有限公司 A kind of hydraulic lifting flipped device and its hanging method for reducing tower

Similar Documents

Publication Publication Date Title
CN108756441A (en) A kind of hydraulic lifting flipped device and its hanging method for reducing tower
CN108775081A (en) A kind of hydraulic lifting inverted structure and its application method
CN102936962A (en) Construction method of slanting cantilever steel structure supported by temporary steel frame
CN102121273A (en) Hydraulic lifting inversion method for reinforced concrete chimney steel inner cylinder
CN102626850A (en) Installation process for metal oil tank in cave storage
CN103590648A (en) Chimney sliding lifting platform construction method and construction device
CN106836836B (en) A kind of secondary hydraulic lifting installation method of Flue Gas Desulphurization for Coal-burning Power Plant tower transformation
CN209457425U (en) A kind of ancient architecture wall recovery support
CN108590147A (en) Assembling the shaped steel suspension scaffolding and its construction method
CN210659228U (en) Movable single-side formwork system for subway construction
CN204386608U (en) A kind of tunnel invert construction tool
CN109987555A (en) The construction method of pneumatic enhanced demister
CN208686187U (en) A kind of hydraulic lifting flipped device for variable diameter tower
CN102587676B (en) Method for mounting internal girder structure of nuclear island at nuclear power station
CN205558915U (en) Portable operation device
CN101818563A (en) Jack-up integral lifting mobile platform and using method
CN203497150U (en) Scaffold for hatch coaming of ship
CN106284989A (en) The sliding form bracing system of double track and complete construction method
CN208685808U (en) A kind of hydraulic lifting inverted structure
CN201864018U (en) Temporary scaffold device used in cross bulkhead subsection closure
CN106224755B (en) The remodeling method of the rubber diaphragm sealed gas holder of two-part
CN104018657A (en) Method for constructing high and large cornice through horizontal sliding platform
CN205346719U (en) Hoisting device is used in casing installation of desulphurization unit absorption tower
CN210508326U (en) Liftable well operation platform
CN208734345U (en) A kind of shield tunnel secondary grouting rack

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190709

RJ01 Rejection of invention patent application after publication