CN108590147A - Assembling the shaped steel suspension scaffolding and its construction method - Google Patents

Assembling the shaped steel suspension scaffolding and its construction method Download PDF

Info

Publication number
CN108590147A
CN108590147A CN201810588066.5A CN201810588066A CN108590147A CN 108590147 A CN108590147 A CN 108590147A CN 201810588066 A CN201810588066 A CN 201810588066A CN 108590147 A CN108590147 A CN 108590147A
Authority
CN
China
Prior art keywords
steel
cantilevered
plate
flange plate
tie rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810588066.5A
Other languages
Chinese (zh)
Inventor
王卫国
徐之彬
张科迪
胡怡彬
程旭凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Jiangong Engineering Group Co Ltd
Original Assignee
Ningbo Jiangong Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Jiangong Engineering Group Co Ltd filed Critical Ningbo Jiangong Engineering Group Co Ltd
Priority to CN201810588066.5A priority Critical patent/CN108590147A/en
Publication of CN108590147A publication Critical patent/CN108590147A/en
Pending legal-status Critical Current

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/20—Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by walls
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00—Component parts or accessories for scaffolds
    • E04G5/04—Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/046—Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Movable Scaffolding (AREA)

Abstract

本发明涉及一种装配化型钢悬挑脚手架及其施工方法,该悬挑脚手架包括悬挑型钢部分和拉杆组件,悬挑型钢部分包括工字钢、端板、槽钢调节梁,槽钢调节梁由两根平行的槽钢构成,且两根槽钢分别与工字钢的工字型两侧凹口呈滑动配合,两根槽钢各一端均焊接固定于端板,工字钢的上翼缘板、下翼缘板、腹板与槽钢调节梁的上翼缘板、下翼缘板、腹板之间分别设有对位的螺栓固定孔和螺栓孔,并通过螺栓、螺母锁紧固定。施工时,将所述端板与建筑结构之间通过对拉螺栓、螺母锁紧固定,将拉杆组件一端与工字钢上翼缘板连接,另一端与建筑结构锁紧固定,最后将脚手架固定于工字钢,即完成施工,施工过程简单,脚手架悬挑长度可调,适用范围广。

The invention relates to an assembled shaped steel cantilevered scaffold and a construction method thereof. The cantilevered scaffold includes a cantilevered steel part and a tie rod assembly. The cantilevered steel part includes I-beams, end plates, channel steel adjustment beams, and channel steel adjustment beams. It is composed of two parallel channel steels, and the two channel steels are slidingly matched with the notches on both sides of the I-shaped steel. Each end of the two channel steels is welded and fixed to the end plate. The upper wing of the I-shaped steel Between the flange plate, the lower flange plate, the web plate and the upper flange plate, the lower flange plate, and the web plate of the channel steel adjusting beam, there are corresponding bolt fixing holes and bolt holes respectively, and are locked by bolts and nuts fixed. During construction, the end plate and the building structure are locked and fixed by means of pull bolts and nuts, one end of the tie rod assembly is connected to the upper flange plate of the I-beam, the other end is locked and fixed to the building structure, and finally the scaffolding is fixed For I-beams, the construction is completed, the construction process is simple, the length of the scaffold cantilever is adjustable, and the scope of application is wide.

Description

装配化型钢悬挑脚手架及其施工方法Assembled steel cantilevered scaffold and its construction method

技术领域technical field

本发明涉及建筑领域的脚手架,是一种装配化型钢悬挑脚手架及其施工方法。The invention relates to a scaffold in the construction field, and relates to an assembled section steel cantilevered scaffold and a construction method thereof.

背景技术Background technique

在多层和高层建筑工程中,悬挑脚手架是一项必不可少的安全防护措施和操作台,直接影响工人的人身安全,以及工程施工质量、效率。传统的型钢悬挑脚手架都是通过U形拉环或锚固螺栓将型钢锚固在楼板上,且依据规范锚固长度不得小于1.25倍的悬挑长度,型钢使用总量大。在悬挑型钢铺设层,由于悬挑型钢对使用空间的需求较大,建筑物内部空间可能无法直接满足铺设要求,需要额外预留孔洞或采取其他加强锚固措施保证锚固的安全性,从而导致铺设层施工复杂,而且楼面存在工字型钢会影响后续内墙和楼面的施工。悬挑型钢由于是从建筑内部向外延伸悬挑,导致必须在墙体上预留孔洞,施工完毕后悬挑型钢拆卸时,都是将型钢由外向内抽到建筑物内部,然后统一吊装拆卸。如果建筑物内部空间不足,则需要将型钢切断,不仅分段拆运造成大量损耗,且导致型钢重复使用率低。悬挑型钢拆卸后,会在建筑物外部墙体上留下较大孔洞,即使通过填补使孔洞消失,但由于填补材料和孔周材料的时间及性质差异,填补孔处会存在较大的渗漏隐患。除此以外,现有悬挑脚手架悬挑长度较难调节。为此,有待对现有的悬挑脚手架施工结构进行改进。In multi-storey and high-rise construction projects, cantilevered scaffolding is an essential safety protection measure and operating platform, which directly affects the personal safety of workers, as well as the quality and efficiency of project construction. The traditional section steel cantilevered scaffolds anchor the section steel on the floor through U-shaped pull rings or anchor bolts, and according to the specification, the anchorage length should not be less than 1.25 times the cantilever length, and the total amount of section steel used is large. In the cantilevered steel laying layer, due to the large demand for the use of space for the cantilevered steel, the interior space of the building may not directly meet the laying requirements, and it is necessary to reserve additional holes or take other strengthening anchorage measures to ensure the safety of the anchorage, resulting in laying The construction of the first floor is complicated, and the existence of I-shaped steel on the floor will affect the subsequent construction of the inner wall and floor. Since the cantilevered steel is extended from the inside of the building, holes must be reserved on the wall. After the construction is completed, when the cantilevered steel is disassembled, the steel is drawn from the outside to the inside of the building, and then hoisted and disassembled uniformly. . If the internal space of the building is insufficient, the section steel needs to be cut off, which not only causes a lot of loss due to section dismantling, but also leads to a low reuse rate of section steel. After the cantilevered steel is disassembled, a large hole will be left on the external wall of the building. Even if the hole disappears through filling, due to the difference in time and properties between the filling material and the material around the hole, there will be a large seepage at the filling hole. leakage hazard. In addition, the cantilevered length of the existing cantilevered scaffolding is difficult to adjust. For this reason, the existing cantilevered scaffold construction structure needs to be improved.

发明内容Contents of the invention

为克服上述不足,本发明的目的是向本领域提供一种装配化型钢悬挑脚手架及其施工方法,使其解决现有悬挑脚手架拆装施工较为繁琐、不便,容易对建筑墙体或梁造成较大破损,修补后存在较大渗漏隐患,且悬挑脚手架悬挑长度不可调,型材重复利用率不高的技术问题。其目的是通过如下技术方案实现的。In order to overcome the above-mentioned deficiencies, the object of the present invention is to provide an assembled section steel cantilevered scaffold and its construction method to the field, so that it can solve the problem that the existing cantilevered scaffold is complicated and inconvenient to disassemble and construct, and it is easy to damage the building walls or beams. Large damage is caused, there is a large hidden danger of leakage after repair, and the cantilever length of the cantilevered scaffolding cannot be adjusted, and the technical problem of low reuse rate of profiles. Its purpose is achieved through the following technical solutions.

一种装配化型钢悬挑脚手架,该悬挑脚手架包括与建筑结构固定的悬挑型钢部分和拉杆组件,悬挑型钢部分包括用于支撑连接脚手架立杆的工字钢,工字钢上翼缘板设有与拉杆组件一端连接的吊耳板,拉杆组件另一端与建筑结构固定连接。其结构要点在于所述悬挑型钢部分还包括端板、槽钢调节梁,槽钢调节梁由两根平行的槽钢构成,且两根槽钢分别与所述工字钢的工字型两侧凹口呈滑动配合,槽钢调节梁的两根槽钢各一端均焊接固定于所述端板,端板与所述建筑结构之间通过对拉螺栓、螺母固定,槽钢调节梁的两根槽钢的上翼缘板、下翼缘板和腹板均设有沿槽钢调节梁长度方向均匀间隔分布的螺栓固定孔,所述工字钢的上翼缘板、下翼缘板、腹板设有相对槽钢调节梁滑动时与上述螺栓固定孔对位的螺栓孔,工字钢的上翼缘板、下翼缘板、腹板与槽钢调节梁的上翼缘板、下翼缘板、腹板之间通过螺栓、螺母固定。An assembled shaped steel cantilevered scaffold, the cantilevered scaffold includes a cantilevered steel part fixed to the building structure and a tie rod assembly, the cantilevered steel part includes an I-shaped steel for supporting and connecting the scaffold pole, and the upper flange of the I-shaped steel The plate is provided with a lug plate connected to one end of the pull rod assembly, and the other end of the pull rod assembly is fixedly connected to the building structure. The main point of its structure is that the cantilevered steel part also includes an end plate and a channel steel adjusting beam. The side notches are in a sliding fit, and each end of the two channel steels of the channel steel adjusting beam is welded and fixed to the end plate. The upper flange plate, the lower flange plate and the web plate of the root channel steel are all provided with bolt fixing holes evenly spaced along the length direction of the channel steel adjusting beam, and the upper flange plate, lower flange plate, The web is provided with bolt holes aligned with the bolt fixing holes when sliding relative to the channel steel adjusting beam, and the upper and lower flange plates of the I-beam and the upper and lower The flange plate and the web are fixed by bolts and nuts.

上述装配化型钢悬挑脚手架中,所述工字钢的上翼缘板沿长度方向设有两个吊耳板,两个吊耳板均通过拉杆组件与建筑结构连接,且各拉杆组件与建筑结构连接的锚固点相对于所述工字钢端板与建筑结构连接的锚固点不在同一竖向平面内。通过该结构,使工字钢支撑连接脚手架时,拉杆组件不会产生干涉。In the above assembled section steel cantilevered scaffolding, the upper flange plate of the I-beam is provided with two lug plates along the length direction, and the two lug plates are connected with the building structure through tie rod assemblies, and each tie rod assembly is connected with the building structure. The anchor point for structural connection is not in the same vertical plane as the anchor point for the connection between the I-beam end plate and the building structure. Through this structure, when the I-shaped steel support is connected to the scaffold, the tie rod assembly will not interfere.

上述装配化型钢悬挑脚手架中,所述拉杆组件包括附墙角度调节件、上拉杆、花篮螺栓和下拉杆,附墙角度调节件与建筑结构之间通过对拉螺栓、螺母固定连接,附墙角度调节件与上拉杆一端之间通过螺栓、螺母锁紧连接,上拉杆另一端与花篮螺栓一端螺纹连接,花篮螺栓另一端与下拉杆一端螺纹连接,下拉杆另一端与所述吊耳板之间通过螺栓、螺母锁紧连接。In the above-mentioned assembled steel cantilevered scaffolding, the tie rod assembly includes a wall-attached angle adjustment member, an upper pull rod, a basket bolt and a lower rod, and the wall-attached angle adjuster and the building structure are fixedly connected by pull bolts and nuts, and the attached wall The angle adjustment part is connected to one end of the upper tie rod through bolts and nuts, the other end of the upper tie rod is threaded to one end of the turnbuckle bolt, the other end of the turnbuckle bolt is threaded to one end of the lower rod, and the other end of the lower rod is connected to the lug plate. The connections are locked by bolts and nuts.

上述装配化型钢悬挑脚手架中,所述工字钢的上翼缘板沿长度方向设有用于定位支撑连接脚手架立杆的定位钢筋,且所述拉杆组件连接所述吊耳板时,拉杆组件与定位钢筋之间错位设置。In the above-mentioned assembled section steel cantilevered scaffold, the upper flange plate of the I-beam is provided along the length direction with a positioning steel bar for positioning, supporting and connecting the scaffold pole, and when the tie rod assembly is connected to the lug plate, the tie rod assembly Misalignment setting between positioning reinforcement.

该装配化型钢悬挑脚手架的施工方法为:首先将所述槽钢调节梁端部的端板与所述建筑结构之间通过对拉螺栓、螺母锁紧固定,并保持悬挑脚手架中的槽钢调节梁处于同一水平面内,然后将所述工字钢滑入槽钢调节梁内,并调节工字钢相对于槽钢调节梁的位置,调节完成后,将工字钢的上翼缘板、下翼缘板、腹板与槽钢调节梁的上翼缘板、下翼缘板、腹板之间通过螺栓、螺母锁紧固定,即完成工字钢与槽钢调节梁之间的固定;接下来,将拉杆组件一端与工字钢上的吊耳板通过螺栓、螺母锁紧连接,将拉杆组件另一端与建筑结构之间通过对拉螺栓、螺母锁紧固定,调整花篮螺栓,保持拉杆组件对工字钢的拉紧,即完成该悬挑型钢部分与建筑结构之间的连接;最后将脚手架立杆与工字钢连接定位,即完成该悬挑脚手架的安装施工。The construction method of the assembled section steel cantilevered scaffolding is as follows: first, the end plate at the end of the channel steel adjusting beam and the building structure are locked and fixed by pull bolts and nuts, and the groove in the cantilevered scaffolding is kept The steel adjusting beam is in the same horizontal plane, then slide the I-beam into the channel steel adjusting beam, and adjust the position of the I-beam relative to the channel steel adjusting beam. After the adjustment is completed, place the upper flange plate of the I-beam , the lower flange plate, web plate and the upper flange plate, lower flange plate, and web plate of the channel steel adjusting beam are locked and fixed by bolts and nuts, that is, the fixing between the I-beam and the channel steel adjusting beam is completed ; Next, connect one end of the tie rod assembly with the lug plate on the I-beam through bolts and nuts, lock and fix the other end of the tie rod assembly with the building structure through pull bolts and nuts, adjust the turnbuckle bolts, and keep The tensioning of the I-beam by the tie rod assembly is to complete the connection between the cantilevered steel part and the building structure; finally, the installation and construction of the cantilevered scaffold is completed by connecting and positioning the scaffold pole with the I-beam.

本发明通过对拉螺栓与建筑结构连接,对建筑结构破坏较小,容易修补,有效保证建筑外墙的抗渗漏性。同时,工字钢与槽钢调节梁设计为相对滑动,从而方便悬挑脚手架调节所需的悬挑长度,适用范围更广,且能够重复使用,减少型材浪费。其适合作为各类建筑的悬挑脚手架使用,或同类施工方法的改进。The invention is connected with the building structure through the pull bolts, which has less damage to the building structure, is easy to repair, and effectively ensures the leakage resistance of the building outer wall. At the same time, the I-beam and the channel steel adjusting beam are designed to slide relative to each other, so as to facilitate the adjustment of the required cantilever length of the cantilevered scaffolding, which has a wider application range and can be reused to reduce the waste of profiles. It is suitable for use as a cantilevered scaffold of various buildings, or as an improvement of similar construction methods.

附图说明Description of drawings

图1是本发明的立体结构示意图。Fig. 1 is a schematic diagram of the three-dimensional structure of the present invention.

图2是本发明的工字钢与槽钢调节梁配合的剖视结构示意图。Fig. 2 is a cross-sectional schematic diagram of the cooperation between the I-beam and the channel steel adjusting beam of the present invention.

图中序号及名称为:1、建筑结构,2、端板,3、槽钢调节梁,301、螺栓固定孔,4、工字钢,401、吊耳板,402、螺栓孔,403、定位钢筋,5、附墙角度调节件,6、上拉杆,7、花篮螺栓,8、下拉杆。The serial numbers and names in the figure are: 1. Building structure, 2. End plate, 3. Channel steel adjusting beam, 301. Bolt fixing hole, 4. I-beam, 401. Lug plate, 402. Bolt hole, 403. Positioning Steel bar, 5, angle adjustment piece attached to the wall, 6, upper pull rod, 7, turnbuckle bolt, 8, lower rod.

具体实施方式Detailed ways

现结合附图,对本发明作进一步描述。Now in conjunction with accompanying drawing, the present invention will be further described.

如图1、图2所示,该装配化型钢悬挑脚手架包括悬挑型钢部分和拉杆组件,悬挑型钢部分设有至少两组,各组悬挑型钢部分包括端板2、槽钢调节梁3和工字钢4,工字钢上翼缘板焊接设有与拉杆组件连接的吊耳板401和用于支撑连接脚手架的定位钢筋403,各工字钢上翼缘板均设有一对间隔分布的吊耳板和一对间隔分布的定位钢筋。槽钢调节梁由两根平行的槽钢构成,两根槽钢的槽口向外,且两根槽钢之间滑动设置上述工字钢,即两根槽钢分别与工字钢的工字型两侧凹口呈滑动配合,槽钢调节梁的两根槽钢各一端均焊接固定于端板,端板设有与建筑结构1连接的栓孔。槽钢调节梁的两根槽钢的上翼缘板、下翼缘板和腹板均设有沿槽钢调节梁长度方向均匀间隔分布的螺栓固定孔301,工字钢的上翼缘板、下翼缘板、腹板设有相对槽钢调节梁滑动时与上述螺栓固定孔对位的螺栓孔402,工字钢的上翼缘板、下翼缘板、腹板与槽钢调节梁的上翼缘板、下翼缘板、腹板之间通过螺栓、螺母、垫片锁紧固定。As shown in Figures 1 and 2, the assembled steel cantilevered scaffold includes cantilevered steel parts and tie rod assemblies. There are at least two groups of cantilevered steel parts, and each group of cantilevered steel parts includes end plates 2 and channel steel adjustment beams. 3 and I-beam 4, the upper flange plate of I-beam is welded with lug plate 401 connected with tie rod assembly and positioning steel bar 403 for supporting and connecting scaffolding, each I-beam upper flange plate is provided with a pair of spacers Distributed lug plates and a pair of spaced positioning reinforcement. The channel steel adjusting beam is composed of two parallel channel steels, the notches of the two channel steels are facing outwards, and the above-mentioned I-beams are slid between the two channel steels, that is, the two channel steels are respectively connected with the I-beams of the I-beams. The notches on both sides of the profile are in a sliding fit, and each end of the two channel steels of the channel steel adjusting beam is welded and fixed to the end plate, and the end plate is provided with a bolt hole connected to the building structure 1. The upper flange plate, the lower flange plate and the web plate of the two channel steels of the channel steel adjusting beam are all provided with bolt fixing holes 301 evenly spaced along the length direction of the channel steel adjusting beam, and the upper flange plate of the I-beam, The lower flange plate and the web are provided with bolt holes 402 aligned with the bolt fixing holes when sliding relative to the channel steel adjusting beam, and the upper flange plate, lower flange plate, web of the I-beam and the channel steel adjusting beam The upper flange plate, the lower flange plate, and the web are locked and fixed by bolts, nuts, and gaskets.

上述拉杆组件包括附墙角度调节件5、上拉杆6、花篮螺栓7和下拉杆8,各工字钢4对应两组拉杆组件,上拉杆一端和下拉杆一端均集成设有连接板,各拉杆组件中的附墙角度调节件与上拉杆一端的连接板之间通过螺栓、螺母锁紧固定,上拉杆另一端与花篮螺栓一端螺纹连接,花篮螺栓另一端与下拉杆一端螺纹连接,下拉杆另一端的连接板与工字钢上的吊耳板401通过螺栓、螺母锁紧固定。The above-mentioned tie rod assembly includes the wall-attached angle adjustment member 5, the upper tie rod 6, the turnbuckle bolt 7 and the lower rod 8. Each I-beam 4 corresponds to two sets of tie rod assemblies. One end of the upper tie rod and one end of the lower rod are integrated with a connecting plate, and each tie rod The wall-attached angle adjustment part in the assembly and the connecting plate at one end of the upper tie rod are locked and fixed by bolts and nuts, the other end of the upper tie rod is threaded with one end of the turnbuckle bolt, the other end of the turnbuckle bolt is threaded with one end of the lower rod, and the other end of the lower rod is threaded. The connecting plate at one end and the lug plate 401 on the I-beam are locked and fixed by bolts and nuts.

该装配化型钢悬挑脚手架与建筑结构1连接时,首先将槽钢调节梁3端部的端板2与建筑结构1之间通过对拉螺栓、螺母、垫片锁紧固定,确保各槽钢调节梁处于同一水平面内,然后将工字钢4滑入槽钢调节梁内,并调节工字钢相对于槽钢调节梁的位置,使工字钢达到所需的悬挑长度;调节完成后,将工字钢的上翼缘板、下翼缘板、腹板与槽钢调节梁的上翼缘板、下翼缘板、腹板之间通过螺栓、螺母、垫片锁紧固定,即完成工字钢与槽钢调节梁之间的固定。接下来,固定拉杆组件,将拉杆组件的下拉杆8与工字钢上的吊耳板401通过螺栓、螺母、垫片锁紧连接,将拉杆组件的附墙角度连接件5与建筑结构之间通过对拉螺栓、螺母、垫片锁紧固定,调整花篮螺栓,使上拉杆、下拉杆保持拉紧状态,即完成该悬挑型钢部分与建筑结构之间的连接;最后将脚手架立杆与工字钢上的定位钢筋403连接定位,即完成该悬挑脚手架的安装施工。When the assembled section steel cantilevered scaffold is connected to the building structure 1, firstly, the end plate 2 at the end of the channel steel adjusting beam 3 and the building structure 1 are locked and fixed by pulling bolts, nuts, and gaskets to ensure that each channel steel The adjusting beam is in the same horizontal plane, then slide the I-beam 4 into the channel steel adjusting beam, and adjust the position of the I-beam relative to the channel steel adjusting beam, so that the I-beam reaches the required cantilever length; after the adjustment is completed , the upper flange plate, lower flange plate, and web of the I-beam and the upper flange plate, lower flange plate, and web of the channel steel adjusting beam are locked and fixed by bolts, nuts, and gaskets, that is Complete the fixing between the I-beam and the channel steel adjusting beam. Next, the pull rod assembly is fixed, the pull rod 8 of the pull rod assembly is connected to the lug plate 401 on the I-beam through bolts, nuts, and gaskets, and the wall-attached angle connector 5 of the pull rod assembly is connected to the building structure. By locking and fixing the bolts, nuts and gaskets, adjusting the turnbuckle bolts, keeping the upper and lower rods in a tight state, the connection between the cantilevered steel part and the building structure is completed; finally, the scaffolding pole and the work The positioning reinforcing bar 403 on the cross-section steel is connected and positioned, and the installation and construction of the cantilevered scaffold is completed.

以上内容旨在说明本发明的技术手段,并非限制本发明的技术范围。本领域技术人员结合现有公知常识对本发明做显而易见的改进,亦落入本发明权利要求的保护范围之内。The above content is intended to illustrate the technical means of the present invention, but not to limit the technical scope of the present invention. Obvious improvements to the present invention made by those skilled in the art in combination with the existing common knowledge also fall within the protection scope of the claims of the present invention.

Claims (5)

1.一种装配化型钢悬挑脚手架,该悬挑脚手架包括与建筑结构(1)固定的悬挑型钢部分和拉杆组件,悬挑型钢部分包括用于支撑连接脚手架立杆的工字钢(4),工字钢上翼缘板设有与拉杆组件一端连接的吊耳板(401),拉杆组件另一端与建筑结构固定连接;其特征在于所述悬挑型钢部分还包括端板(2)、槽钢调节梁(3),槽钢调节梁由两根平行的槽钢构成,且两根槽钢分别与所述工字钢的工字型两侧凹口呈滑动配合,槽钢调节梁的两根槽钢各一端均焊接固定于所述端板,端板与所述建筑结构(1)之间通过对拉螺栓、螺母固定,槽钢调节梁的两根槽钢的上翼缘板、下翼缘板和腹板均设有沿槽钢调节梁长度方向均匀间隔分布的螺栓固定孔(301),所述工字钢的上翼缘板、下翼缘板、腹板设有相对槽钢调节梁滑动时与上述螺栓固定孔对位的螺栓孔(402),工字钢的上翼缘板、下翼缘板、腹板与槽钢调节梁的上翼缘板、下翼缘板、腹板之间通过螺栓、螺母固定。1. An assembled shaped steel cantilevered scaffold, the cantilevered scaffold includes a cantilevered steel part and a tie rod assembly fixed to the building structure (1), and the cantilevered steel part includes I-beams (4 ), the upper flange plate of the I-beam is provided with a lug plate (401) connected to one end of the tie rod assembly, and the other end of the tie rod assembly is fixedly connected to the building structure; it is characterized in that the cantilevered steel part also includes an end plate (2) . The channel steel adjusting beam (3). The channel steel adjusting beam is composed of two parallel channel steels, and the two channel steels are slidingly matched with the notches on both sides of the I-shaped steel of the I-shaped steel. The channel steel adjusting beam Each end of the two channel steels is welded and fixed to the end plate, and the end plate and the building structure (1) are fixed by pull bolts and nuts, and the upper flange plates of the two channel steels of the channel steel adjustment beam , the lower flange plate and the web are provided with bolt fixing holes (301) evenly spaced along the length direction of the channel steel adjusting beam, and the upper flange plate, the lower flange plate and the web of the I-beam are provided with relative The bolt holes (402) aligned with the above-mentioned bolt fixing holes when the channel steel adjusting beam slides, the upper flange plate, lower flange plate, web plate of the I-beam and the upper flange plate and lower flange of the channel steel adjusting beam The plates and webs are fixed by bolts and nuts. 2.根据权利要求1所述的装配化型钢悬挑脚手架,其特征在于所述工字钢(4)的上翼缘板沿长度方向设有两个吊耳板(401),两个吊耳板均通过拉杆组件与建筑结构(1)连接。2. The assembled section steel cantilevered scaffold according to claim 1, characterized in that the upper flange plate of the I-beam (4) is provided with two lug plates (401) along the length direction, and the two lugs The plates are all connected to the building structure (1) through tie rod assemblies. 3.根据权利要求1或2所述的装配化型钢悬挑脚手架,其特征在于所述拉杆组件包括附墙角度调节件(5)、上拉杆(6)、花篮螺栓(7)和下拉杆(8),附墙角度调节件与建筑结构(1)之间通过对拉螺栓、螺母固定连接,附墙角度调节件与上拉杆一端之间通过螺栓、螺母锁紧连接,上拉杆另一端与花篮螺栓一端螺纹连接,花篮螺栓另一端与下拉杆一端螺纹连接,下拉杆另一端与所述吊耳板(401)之间通过螺栓、螺母锁紧连接。3. The assembled section steel cantilevered scaffold according to claim 1 or 2, characterized in that the tie rod assembly includes a wall-attached angle adjustment piece (5), an upper tie rod (6), a turnbuckle bolt (7) and a lower rod ( 8), the wall-attached angle adjustment part and the building structure (1) are fixedly connected by pull bolts and nuts; One end of the bolt is threaded, the other end of the turnbuckle is threaded with one end of the lower rod, and the other end of the lower rod is connected with the lug plate (401) through bolts and nuts. 4.根据权利要求1所述的装配化型钢悬挑脚手架,其特征在所述工字钢(4)的上翼缘板沿长度方向设有用于定位支撑连接脚手架立杆的定位钢筋(403),且所述拉杆组件连接所述吊耳板时,拉杆组件与定位钢筋之间错位设置。4. The assembled section steel cantilevered scaffold according to claim 1, characterized in that the upper flange plate of the I-beam (4) is provided along the length direction with positioning steel bars (403) for positioning, supporting and connecting scaffold poles , and when the tie rod assembly is connected to the lug plate, the tie rod assembly and the positioning steel bar are misplaced. 5.一种如权利要求1所述的装配化型钢悬挑脚手架的施工方法,其特征在于首先将所述槽钢调节梁(3)端部的端板(2)与所述建筑结构(1)之间通过对拉螺栓、螺母锁紧固定,并保持悬挑脚手架中的槽钢调节梁处于同一水平面内,然后将所述工字钢(4)滑入槽钢调节梁内,并调节工字钢相对于槽钢调节梁的位置,调节完成后,将工字钢的上翼缘板、下翼缘板、腹板与槽钢调节梁的上翼缘板、下翼缘板、腹板之间通过螺栓、螺母锁紧固定,即完成工字钢与槽钢调节梁之间的固定;接下来,将拉杆组件一端与工字钢上的吊耳板(401)通过螺栓、螺母锁紧连接,将拉杆组件另一端与建筑结构之间通过对拉螺栓、螺母锁紧固定,调整花篮螺栓,使保持拉杆组件对工字钢的拉紧,即完成该悬挑型钢部分与建筑结构之间的连接;最后将脚手架立杆与工字钢连接定位,即完成该悬挑脚手架的安装施工。5. A construction method for assembled section steel cantilevered scaffolding as claimed in claim 1, characterized in that first, the end plate (2) at the end of the channel steel adjusting beam (3) is connected to the building structure (1 ) between the tension bolts and nuts, and keep the channel steel adjustment beam in the cantilevered scaffold in the same horizontal plane, then slide the I-beam (4) into the channel steel adjustment beam, and adjust the The position of the beam relative to the channel steel adjustment beam, after the adjustment is completed, the upper flange plate, lower flange plate, web plate of the I-beam and the upper flange plate, lower flange plate, web plate of the channel steel adjustment beam The bolts and nuts are used to lock and fix the I-beam and the channel steel adjusting beam; next, one end of the tie rod assembly and the lug plate (401) on the I-beam are locked by bolts and nuts Connection, the other end of the tie rod assembly and the building structure are locked and fixed by pulling bolts and nuts, and the turnbuckle bolts are adjusted to keep the tension of the tie rod assembly on the I-beam, that is, the connection between the cantilevered steel part and the building structure is completed. connection; finally, the scaffold pole is connected and positioned with the I-beam to complete the installation and construction of the cantilevered scaffold.
CN201810588066.5A 2018-06-08 2018-06-08 Assembling the shaped steel suspension scaffolding and its construction method Pending CN108590147A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810588066.5A CN108590147A (en) 2018-06-08 2018-06-08 Assembling the shaped steel suspension scaffolding and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810588066.5A CN108590147A (en) 2018-06-08 2018-06-08 Assembling the shaped steel suspension scaffolding and its construction method

Publications (1)

Publication Number Publication Date
CN108590147A true CN108590147A (en) 2018-09-28

Family

ID=63623434

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810588066.5A Pending CN108590147A (en) 2018-06-08 2018-06-08 Assembling the shaped steel suspension scaffolding and its construction method

Country Status (1)

Country Link
CN (1) CN108590147A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109457706A (en) * 2018-12-28 2019-03-12 北京城建北方集团有限公司 Foundation pit edge protection can be had enough to meet the need
CN110080528A (en) * 2019-04-30 2019-08-02 中国二十冶集团有限公司 The construction method of outer builder's jack I-steel
CN110656762A (en) * 2019-09-25 2020-01-07 宁波建工工程集团有限公司 Three-section type pull rod overhanging outer scaffold and construction method thereof
CN111270850A (en) * 2020-03-20 2020-06-12 中建三局集团有限公司 Novel fast-assembling exempts from to weld girder steel of encorbelmenting fixed device
CN111660022A (en) * 2019-03-06 2020-09-15 金川集团工程建设有限公司 Flatness control device and method for machining steel roof beam flange plate
CN114892981A (en) * 2022-05-29 2022-08-12 中国五冶集团有限公司 A method for setting double tie rods of super-long cantilever structural steel main beam
CN117266538A (en) * 2023-09-25 2023-12-22 上海市浦东新区建设(集团)有限公司 A kind of assembled cantilever component for external scaffolding construction

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2671574A1 (en) * 1991-01-10 1992-07-17 Vidal Fernand Suspended scaffolding cradle-iron (stirrup) and scaffolding module including the said cradle-iron
CN1258333A (en) * 1997-05-16 2000-06-28 约翰·克赖门特·普莱斯顿 Partially retractable building platform
CN201679098U (en) * 2010-05-14 2010-12-22 北京工业大学 Frame beam-column fire-resistant joints with catenary effect
CN202706508U (en) * 2012-06-25 2013-01-30 南通四建集团有限公司 Overhanging strength bearing steel beam construction member of scaffold
CN103470018A (en) * 2013-08-27 2013-12-25 天津二十冶建设有限公司 Detachable converter tooling platform
CN203856190U (en) * 2014-04-09 2014-10-01 中国建筑股份有限公司 Adjustable platform beam support device
CN203961238U (en) * 2014-07-22 2014-11-26 四川省第十五建筑有限公司 Bolt anchor slab adjustable tool formula builder's jack
CN204402020U (en) * 2014-12-31 2015-06-17 长沙远大住宅工业集团有限公司 A kind of extensible canopy of template platform
CN205777425U (en) * 2016-07-07 2016-12-07 中建三局集团有限公司 A kind of scalable hanging basket support means
CN208502206U (en) * 2018-06-08 2019-02-15 宁波建工工程集团有限公司 Assembling the shaped steel suspension scaffolding

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2671574A1 (en) * 1991-01-10 1992-07-17 Vidal Fernand Suspended scaffolding cradle-iron (stirrup) and scaffolding module including the said cradle-iron
CN1258333A (en) * 1997-05-16 2000-06-28 约翰·克赖门特·普莱斯顿 Partially retractable building platform
CN201679098U (en) * 2010-05-14 2010-12-22 北京工业大学 Frame beam-column fire-resistant joints with catenary effect
CN202706508U (en) * 2012-06-25 2013-01-30 南通四建集团有限公司 Overhanging strength bearing steel beam construction member of scaffold
CN103470018A (en) * 2013-08-27 2013-12-25 天津二十冶建设有限公司 Detachable converter tooling platform
CN203856190U (en) * 2014-04-09 2014-10-01 中国建筑股份有限公司 Adjustable platform beam support device
CN203961238U (en) * 2014-07-22 2014-11-26 四川省第十五建筑有限公司 Bolt anchor slab adjustable tool formula builder's jack
CN204402020U (en) * 2014-12-31 2015-06-17 长沙远大住宅工业集团有限公司 A kind of extensible canopy of template platform
CN205777425U (en) * 2016-07-07 2016-12-07 中建三局集团有限公司 A kind of scalable hanging basket support means
CN208502206U (en) * 2018-06-08 2019-02-15 宁波建工工程集团有限公司 Assembling the shaped steel suspension scaffolding

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109457706A (en) * 2018-12-28 2019-03-12 北京城建北方集团有限公司 Foundation pit edge protection can be had enough to meet the need
CN109457706B (en) * 2018-12-28 2024-04-02 北京城建北方集团有限公司 Can have enough to meet need foundation ditch face limit protection
CN111660022A (en) * 2019-03-06 2020-09-15 金川集团工程建设有限公司 Flatness control device and method for machining steel roof beam flange plate
CN110080528A (en) * 2019-04-30 2019-08-02 中国二十冶集团有限公司 The construction method of outer builder's jack I-steel
CN110656762A (en) * 2019-09-25 2020-01-07 宁波建工工程集团有限公司 Three-section type pull rod overhanging outer scaffold and construction method thereof
CN111270850A (en) * 2020-03-20 2020-06-12 中建三局集团有限公司 Novel fast-assembling exempts from to weld girder steel of encorbelmenting fixed device
CN114892981A (en) * 2022-05-29 2022-08-12 中国五冶集团有限公司 A method for setting double tie rods of super-long cantilever structural steel main beam
CN117266538A (en) * 2023-09-25 2023-12-22 上海市浦东新区建设(集团)有限公司 A kind of assembled cantilever component for external scaffolding construction

Similar Documents

Publication Publication Date Title
CN103291076B (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
CN103452311B (en) A kind of erection method of shaped steel suspended structural support frame
CN104261232B (en) Lifting device attached to special-shaped section and installation method thereof
CN111472530A (en) A flower basket tie rod I-beam cantilever bearing frame for construction engineering and its installation method
CN110306774B (en) Method and device for installing socket type cantilever scaffold
CN209780193U (en) Suspension type scaffold
AU2018282313A1 (en) Assembled building structure with combination of steel structure and concrete structure and construction method thereof
CN110725525A (en) A kind of supporting device of prefabricated cantilever scaffold and its construction method
CN211736298U (en) Double-rod diagonal cantilever scaffold
CN109869153A (en) The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method
CN111058555A (en) Windproof fireproof heat-preservation type quick-dismantling assembly building steel structure and splicing method thereof
CN207525755U (en) Composite pile anchor supporting device
CN219033285U (en) Reinforcing apparatus of buttress formula retaining wall buttress template
CN210976588U (en) Template reinforcing system for double shear walls at deformation joint
CN211572514U (en) Scalable regulation outer wall scaffold frame
CN109914780A (en) It is a kind of for building the inclined pull type suspension supporting I-steel supporting element of external scaffolding
CN204139369U (en) Assembling fire wall
CN218990875U (en) Assembled triangular truss cantilever support frame system
CN118958659A (en) A construction method for a post-casting belt top plate support-free formwork system
CN111424972A (en) Method and structure for reinforcing ultra-large type steel concrete beam side mold
CN115075530B (en) Cantilever structure and construction method thereof
CN106939697B (en) Combined template for constructing core barrel and construction method thereof
CN206554483U (en) A kind of full fabricated scaffold is encorbelmented component
CN108797365A (en) Formwork for bridge piers and its construction method
CN115897976A (en) An assembled triangular truss cantilevered support frame system and its installation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180928