CN109944626A - Tunnel phase change cold-storage cooling system - Google Patents

Tunnel phase change cold-storage cooling system Download PDF

Info

Publication number
CN109944626A
CN109944626A CN201910275251.3A CN201910275251A CN109944626A CN 109944626 A CN109944626 A CN 109944626A CN 201910275251 A CN201910275251 A CN 201910275251A CN 109944626 A CN109944626 A CN 109944626A
Authority
CN
China
Prior art keywords
tunnel
cold
storage
phase change
cooling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910275251.3A
Other languages
Chinese (zh)
Other versions
CN109944626B (en
Inventor
张国柱
王维
刘松玉
姜国栋
陈家威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southeast University
Original Assignee
Southeast University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southeast University filed Critical Southeast University
Priority to CN201910275251.3A priority Critical patent/CN109944626B/en
Publication of CN109944626A publication Critical patent/CN109944626A/en
Application granted granted Critical
Publication of CN109944626B publication Critical patent/CN109944626B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention provides a kind of tunnel phase change cold-storage cooling system, including cold-storage section and temperature descending section, cold-storage section be by tunnel ground temperature energy heat exchanger, water pump, distributive pipe, collector pipe and the indoor phase change cold-storage board group of cold-storage cave at closed cycle system;Phase change cold-storage plate first completes cold-storage in cold-storage chamber, the temperature descending section close to constructing tunnel face is transported along tunnel, temperature descending section includes cooling construction trolley, thermal insulation layer, removal shield door, outer circulation ventilation and interior circulating ventilation, and thermal insulation layer forms closing insulated space at tunnel excavation face rear with removal shield door;Temperature-reducing tablet and water pump, distributive pipe, collector pipe and phase change cold-storage plate in the construction trolley that cools down form closed circulation cooling system, combine cooling to closing insulated space with outer circulation ventilation and interior circulating ventilation.The present invention compares existing artificial ice making cooling method, has the significant progress such as construction is convenient, efficiency is high, renewable, operating cost is low.

Description

Tunnel phase change cold-storage cooling system
Technical field
The present invention relates to a kind of safe-guard systems of constructing tunnel, and in particular to a kind of cold for tunnel using phase-change material But the system to cool down.
Background technique
By taking the tunnel railway Sang Zhuling of Sichuan-Tibet as an example, tunnel overall length 16449m, maximum buried depth about 1347m are current China Railway tunnel build in the highest rock temperature tunnel that encounters, rock temperature reaches 81.9 DEG C in tunnel." railway tunnel construction specification " Temperature is not greater than 28 DEG C in TB10120-2002 regulation Tunnel, and tunnel highland warm calamity causes construction personnel's labour capacity to drop Low, mechanical equipment fault rate significantly increases, and seriously reduces construction efficiency;It is larger to construction personnel's health effect, altitude sickness morbidity Rate increases, and jeopardizes construction personnel's life security.The cooling of High-geotemperature constructing tunnel is mainly using reinforcement ventilation, heat-insulated, cold water (ice Block) cooling and mechanical refrigeration ventilation etc..+ spraying+reinforcement ventilated synthetic cooling skill that the tunnel Sang Zhuling is using cellular concrete+ice cube Art has dropped 10-20 DEG C in Tunnel at a temperature of environment, environment temperature controls within 45 DEG C, but still not up to as defined in specification Requirement within 28 DEG C.Analyze itself the reason is as follows that: (1) the blower cold consumption of Super Long Tunnel is big, and energy consumption is high, and operating cost It is high;(2) cool down 3-5 DEG C within the scope of 3m around ice cube, cool down inefficient;(3) gunite concrete for adding air entraining agent will be in hole Temperature reduces 2-3 DEG C, and heat insulation is limited.
Through retrieving, Chinese patent literature CN109209466A discloses a kind of shield tunnel construction cooling device and cooling side Method arranges refrigeration system and air cooling system in tunnel, and shield circulation is arranged outside tunnel;By refrigeration system It is connected with air cooling system, provides cold source for air cooling system;The natural wind that air cooling system and ground are sent into carries out Cold and hot exchange, cools down natural wind;Shield circulation is connected with refrigeration system, for carrying out to refrigeration system Radiating and cooling.
Tunnel is linear structure, passes through stratum and the geological structural belt of different buried depth, edpth of tunnel variation and geothermal anomaly Geological structural belt, which will lead in tunnel, has significant " the temperature difference ", how to be used for the antifreeze heating of tunnel in cold area, uses simultaneously Cooling down in High-geotemperature tunnel, raising efficiency+enhancing is heat-insulated+energy conservation and environmental protection, just become and solves the prominent of Super Long Tunnel highland warm calamity Cut.
Summary of the invention
Goal of the invention: in order to overcome the deficiencies in the prior art, the present invention will be low using tunnel ground temperature energy heat exchanger The country rock ground temperature of ground temperature section can be stored in phase change plate, substitute traditional artificial ice making, for empty in the hole of High-geotemperature section Gas cooling, reaches the purpose of cooling is high-efficient, environmentally protective and at low cost.
Technical solution: in order to solve the above technical problems, phase change cold-storage cooling system in tunnel provided by the invention, including cold-storage System and cooling system.
Wherein, cold accumulation system is by tunnel ground temperature energy heat exchanger, water pump, distributive pipe, collector pipe and the indoor phase of cold-storage cave Become the closed cycle system of hold-over plate composition;The phase change cold-storage plate first completes cold-storage in cold-storage chamber, transports along tunnel Cooling system is simultaneously attached thereto.
Cooling system close to constructing tunnel face arrange, including cooling construction trolley, thermal insulation layer, removal shield door, follow outside Ring ventilation, interior circulating ventilation and ambient intelligence monitoring system;Thermal insulation layer and removal shield door are at tunnel excavation face rear Form closing insulated space;Temperature-reducing tablet and water pump, distributive pipe, collector pipe and phase change cold-storage plate in the construction trolley that cools down are formed and are sealed Closed loop cooling system, using cooling construction trolley, outer circulation ventilation and interior circulating ventilation to closing insulated space joint cooling.
Specifically, the tunnel ground temperature energy heat exchanger includes several groups heat exchange pipe, and the heat exchange pipe is laid in Just between lining and splash guard, in hollow bolt and above tunnel inverted arch.
Specifically, the cooling construction trolley includes construction trolley, bracket, temperature-reducing tablet, distributive pipe and collector pipe.
Specifically, the ambient intelligence monitoring system is adopted by temperature sensor, air velocity transducer, humidity sensor, data Storage and analysis process system control the working condition of outer circulation ventilation and interior circulating ventilation according to construction environment monitoring data.
Present invention simultaneously provides the operational methods for using above system being the cooling of constructing tunnel face, comprising the following steps:
Step 1, before performing two linings, positions are laid with heat exchange in the tunnel surface Chu Chen, hollow bolt and above inverted arch etc. Heat exchange pipe is pierced by two lining concrete sidewalls via longitudinal drainage pipe lower section when pouring two lining concrete by pipeline;
Step 2, connect respectively with the inlet and outlet of heat exchange pipe by distributive pipe, collector pipe, and be located at cold-storage The water outlet of the indoor phase change cold-storage plate of cave, water inlet connection, are driven using water circulating pump, form closed circulation cold storage pipe Road;
Step 3, the first lining hole wall surface at tunnel construction tunnel face rear performs thermal insulation layer, and movement is installed in tunnel cross section Shield door constitutes closed construction space;
Step 4, phase change cold-storage plate is transported in closure construction space, by distributive pipe, collector pipe respectively and on cooling trolley Temperature-reducing tablet connection, driven using water circulating pump, form closed circulation temperature lowering pipeline;
Step 5, in closed construction space, lay in circulating fan, outer circulation blower air supply duct, temperature sensor, wet Spend sensor, air velocity transducer;
Step 6, the draft type and ventilation quantity of ambient intelligence monitoring system intelligent control blower are utilized.
In use, tunnel phase change cold-storage cooling system by tunnel ground temperature energy heat exchanger, phase change cold-storage plate, water pump, distributive pipe, Collector pipe, cold-storage chamber, cooling construction trolley, thermal insulation layer, removal shield door, outer circulation ventilation, interior circulating ventilation and environment Intelligent monitor system composition;Phase change cold-storage plate is formed by water pump, distributive pipe and collector pipe and tunnel ground temperature energy heat exchanger and is closed Circulation cold storage system, phase change cold-storage plate are placed in cold-storage chamber, after the completion of phase change cold-storage plate cold-storage, are transported in hole and are used for The cooling of area surface construction;Thermal insulation layer and removal shield door are formed at tunnel excavation face rear closes insulated space;Cooling Construction trolley forms closed circulation cooling system by water pump, distributive pipe and collector pipe and phase change cold-storage plate, is constructed using cooling Trolley, outer circulation ventilation and interior circulating ventilation are to closing insulated space joint cooling;
Inventive principle: between the first lining and splash guard of tunnel low land temperature section, the positions such as above in hollow bolt and tunnel inverted arch The heat exchange pipe for locating arrangement, with the heat exchange pipe in phase change cold-storage plate, connection forms closed circulation line, utilizes circulation Low temperature ground temperature in tunnel surrounding can be stored in phase change cold-storage plate by the heat transfer cycle medium in pipeline.Haulage vehicle is by phase transformation Hold-over plate is transported to High-geotemperature section in hole, connect by water pump, distributive pipe and collector pipe with the temperature lowering board in cooling construction trolley, Closed circulation line is formed, using the heat transfer cycle medium in circulation line to cooling Plate supplying cooling capacity, is realized to temperature lowering board The air cooling-down of surrounding.
The utility model has the advantages that reproducible ground temperature energy resource of the present invention using the low land warm area section in tunnel, to High-geotemperature section Hole in air cooling-down, replace traditional artificial ice making falling temperature technique, have the advantages that environmentally protective, operating cost is low etc., than pass Artificial 80% or more the ice making falling temperature technique energy conservation of system.And in heat-insulated enclosure space, pass through inside and outside circulating fan and cooling The temperature-reducing tablet of three-dimensional dispersed placement on trolley combines cooling, has many advantages, such as that good heat-insulation effect, cooling are high-efficient.Temperature-reducing tablet benefit It is fixed in construction trolley with bracket, forms integrated cooling device with construction trolley, by dividing, catchment pipeline and phase change cold-storage Plate connection has the advantages that easy to operate without loading, unloading temperature-reducing tablet repeatedly.
Except it is above-described present invention solves the technical problem that, constitute technical solution technical characteristic and by these technologies Outside advantage brought by the technical characteristic of scheme.To keep the object of the invention, technical scheme and beneficial effects clearer, below will In conjunction with the attached drawing in the embodiment of the present invention, to other for including in the other technologies problem of the invention that can solve, technical solution The advantages of technical characteristic and these technical characteristics are brought does apparent, complete description, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.The present invention being usually described and illustrated herein in the accompanying drawings is implemented The component of example can be arranged and be designed with a variety of different configurations.Therefore, below to the reality of the invention provided in the accompanying drawings The detailed description for applying example is not intended to limit the range of claimed invention, but is merely representative of selected implementation of the invention Example.Based on the embodiments of the present invention, obtained by those of ordinary skill in the art without making creative efforts Every other embodiment, shall fall within the protection scope of the present invention.
Detailed description of the invention
Fig. 1 is tunnel phase change cold-storage cooling working principle diagram;
Fig. 2 is heat-exchange tube arrangement cross-sectional view;
Fig. 3 is cold-storage chamber plan view;
Fig. 4 is cooling pipeline arrangement cross-sectional view;
In figure: 1 is just lining;2 be heat-exchange tube;3 be inverted arch;4 be two linings;5 be cold-storage chamber;6 be phase change cold-storage plate;7 be point Water pipe;8 be collector pipe;9 be thermal insulation layer;10 be removal shield door;11 be interior circulating fan;12 be outer circulation blower;13 are Cool down construction trolley;14 be bracket;15 be temperature-reducing tablet;16 be water pump;17 be face;18 be country rock;19 be transport vehicle.
Specific embodiment
Embodiment:
The tunnel cold accumulation cooling-down system of the present embodiment is as shown in Figure 1, phase change cold-storage plate 6 passes through circulating pump, distributive pipe 7 and collector pipe 8 form closed circulation cold accumulation system with tunnel ground temperature energy heat exchanger (being mainly made of heat-exchange tube 2), and the cold accumulation system is by cooling capacity It is transmitted to the phase change cold-storage plate 6 for being packed into closed cold-storage chamber 5, the phase change cold-storage plate 6 for completing cold-storage is transported to by transport vehicle 19 Cool down in hole for area surface construction;It is specifically rectangular after tunnel excavation face with thermal insulation layer 9 and removal shield door 10 At closing insulated space;Temperature-reducing tablet 15 is arranged in the construction trolley 13 that cools down, temperature-reducing tablet 15 is by water pump 16 and circulation line and phase Become hold-over plate 6 and forms closed circulation cooling system, it is right using cooling construction trolley 13, outer circulation ventilation 12 and interior circulating ventilation 11 Close insulated space joint cooling.
As shown in Fig. 2, tunnel ground temperature energy heat exchanger includes multiple groups heat-exchange tube 2, heat-exchange tube can be laid in just lining and prevent Between water plate, in hollow bolt and above tunnel inverted arch etc. at positions, each group heat-exchange tube 2 is connected through distributive pipe 7 and collector pipe 8 Into cold-storage chamber 5 as shown in Figure 3, cooling capacity is transmitted in phase change cold-storage plate 6 using circulation line.
As shown in figure 4, cooling pipe routing be mounted on cooling construction trolley 13 bracket 14 on temperature-reducing tablet 15, distributive pipe 7, The circulation line that collector pipe 8, water pump 15 and the phase change cold-storage plate 6 shipped are connected to form utilizes the cooling capacity of exchange phase change cold-storage plate 6 For construction space cooling.
Ambient intelligence monitoring system is by temperature sensor, air velocity transducer, humidity sensor, data collector and analysis Reason system composition controls the working condition of outer circulation ventilation and interior circulating ventilation according to construction environment monitoring data.
In use, implementation process is as follows:
(1) before performing two linings, positions are laid with heat-exchange tube in the tunnel surface Chu Chen, hollow bolt and above inverted arch etc. Heat exchange pipe is pierced by two lining concrete sidewalls via longitudinal drainage pipe lower section when pouring two lining concrete by road;
(2) connect respectively with the inlet and outlet of heat exchange pipe by distributive pipe, collector pipe, and with positioned at cold-storage chamber The water outlet of interior phase change cold-storage plate, water inlet connection, are driven using water circulating pump, form closed circulation cold storage pipeline;
(3) the first lining hole wall surface at tunnel construction tunnel face rear performs thermal insulation layer, and mobile screen is installed in tunnel cross section Door is covered, closed construction space is constituted;
(4) phase change cold-storage plate is transported in closure construction space, by distributive pipe, collector pipe respectively with cooling trolley on drop Warm piece connection, is driven using water circulating pump, forms closed circulation temperature lowering pipeline;
(5) in closed construction space, interior circulating fan, outer circulation blower air supply duct, temperature sensor, humidity is laid and is passed Sensor, air velocity transducer;
(6) draft type and ventilation quantity of ambient intelligence monitoring system intelligent control blower are utilized.
In the description of the present invention, it is also necessary to which explanation is unless specifically defined or limited otherwise, term " setting ", " installation ", " connected ", " connection " shall be understood in a broad sense, for example, it may be fixedly connected, may be a detachable connection or one Connect to body;It can be mechanical connection, be also possible to be electrically connected;It can be directly connected, it can also be indirect by intermediary It is connected, can be the connection inside two elements.For the ordinary skill in the art, on being understood with concrete condition State the concrete meaning of term in the present invention.
It should also be noted that similar label and letter indicate similar terms in following attached drawing, therefore, once a certain Xiang Yi It is defined in a attached drawing, does not then need that it is further defined and explained in subsequent attached drawing.
In the description of the present invention, it should be noted that term " center ", "upper", "lower", "left", "right", "vertical", The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, or be somebody's turn to do Invention product using when the orientation or positional relationship usually put, be merely for convenience of description of the present invention and simplification of the description, without It is that the device of indication or suggestion meaning or element must have a particular orientation, be constructed and operated in a specific orientation, therefore not It can be interpreted as limitation of the present invention.
The present invention provides a kind of completely new thinking and method for constructing tunnel cooling, implements the side of the technical solution There are many method and approach, and the above is only the preferred embodiments provided in an illustrative manner.Those skilled in the art can be not inclined Many changes are expected in the case where from the present invention, are changed and are substituted.It should be appreciated that can be used during practicing the present invention To the various alternative solutions of embodiments of the invention described herein.Appended claims are intended to limit the scope of the invention, And therefore cover the method and structure in the range of these claims and its equivalent item.Each composition being not known in the present embodiment The available prior art in part is realized.

Claims (5)

1. a kind of tunnel phase change cold-storage cooling system, including cold-storage section and temperature descending section, it is characterised in that:
The cold-storage section is by tunnel ground temperature energy heat exchanger, water pump, distributive pipe, collector pipe and the indoor phase change cold-storage plate of cold-storage cave The closed cycle system of composition;The phase change cold-storage plate first completes cold-storage in cold-storage chamber, transports temperature descending section simultaneously along tunnel It is attached thereto;
The temperature descending section is arranged close to constructing tunnel face, including cooling construction trolley, thermal insulation layer, removal shield door, outer circulation Ventilation, interior circulating ventilation and ambient intelligence monitoring system;Thermal insulation layer is rectangular after tunnel excavation face with removal shield door At closing insulated space;Temperature-reducing tablet and water pump, distributive pipe, collector pipe and phase change cold-storage plate in the construction trolley that cools down are formed and are closed Circulation temperature lowering system, using cooling construction trolley, outer circulation ventilation and interior circulating ventilation to closing insulated space joint cooling.
2. phase change cold-storage cooling system in tunnel according to claim 1, it is characterised in that: the tunnel ground temperature energy heat exchanger Including several groups heat exchange pipe, the heat exchange pipe, which is laid in, just to be served as a contrast between splash guard, faces upward in hollow bolt with tunnel Arch top.
3. phase change cold-storage cooling system in tunnel according to claim 2, it is characterised in that: the cooling construction trolley includes Bracket, temperature-reducing tablet, distributive pipe and collector pipe.
4. phase change cold-storage cooling system in tunnel according to claim 3, it is characterised in that: the ambient intelligence monitoring system By temperature sensor, air velocity transducer, humidity sensor, data collector and analysis process system, monitored according to construction environment Data, the working condition of control outer circulation ventilation and interior circulating ventilation.
5. it is the operational method of constructing tunnel face cooling using tunnel phase change cold-storage cooling system described in claim 1, it is special Sign be the following steps are included:
Step 1, before performing two linings, positions are laid with heat exchange in the tunnel surface Chu Chen, hollow bolt and above inverted arch etc. Heat exchange pipe is pierced by two lining concrete sidewalls via longitudinal drainage pipe lower section when pouring two lining concrete by pipeline;
Step 2, connect respectively with the inlet and outlet of heat exchange pipe by distributive pipe, collector pipe, and be located at cold-storage The water outlet of the indoor phase change cold-storage plate of cave, water inlet connection, are driven using water circulating pump, form closed circulation cold storage pipe Road;
Step 3, the first lining hole wall surface at tunnel construction tunnel face rear performs thermal insulation layer, and movement is installed in tunnel cross section Shield door constitutes closed construction space;
Step 4, phase change cold-storage plate is transported in closure construction space, by distributive pipe, collector pipe respectively and on cooling trolley Temperature-reducing tablet connection, driven using water circulating pump, form closed circulation temperature lowering pipeline;
Step 5, in closed construction space, lay in circulating fan, outer circulation blower air supply duct, temperature sensor, wet Spend sensor, air velocity transducer;
Step 6, the draft type and ventilation quantity of ambient intelligence monitoring system intelligent control blower are utilized.
CN201910275251.3A 2019-04-08 2019-04-08 Tunnel phase change cold accumulation cooling system Active CN109944626B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910275251.3A CN109944626B (en) 2019-04-08 2019-04-08 Tunnel phase change cold accumulation cooling system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910275251.3A CN109944626B (en) 2019-04-08 2019-04-08 Tunnel phase change cold accumulation cooling system

Publications (2)

Publication Number Publication Date
CN109944626A true CN109944626A (en) 2019-06-28
CN109944626B CN109944626B (en) 2020-12-29

Family

ID=67013867

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910275251.3A Active CN109944626B (en) 2019-04-08 2019-04-08 Tunnel phase change cold accumulation cooling system

Country Status (1)

Country Link
CN (1) CN109944626B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110905581A (en) * 2019-12-13 2020-03-24 湖南工程学院 Movable type excavation roadway cooling equipment
CN113431634A (en) * 2021-08-03 2021-09-24 中铁高新工业股份有限公司 Special thermal-insulated platform truck of underground space construction

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2615552Y (en) * 2003-03-17 2004-05-12 牛铁智 Geothermal utilizating air conditioner
WO2005088076A1 (en) * 2004-03-04 2005-09-22 Graham Paul Bloom An airconditioning system
US20120006503A1 (en) * 2010-07-06 2012-01-12 Chung-Hsin Electric And Machinery Manufacturing Corp. Ventilation system for tunnel engineering
CN103900178A (en) * 2014-03-24 2014-07-02 深圳达实智能股份有限公司 Ground source heat pump energy storage central air-conditioning system
CN104697263A (en) * 2015-03-10 2015-06-10 王琰 Self-prefreezing liquid nitrogen tunnel quick freezer
CN104901412A (en) * 2015-07-03 2015-09-09 成都博世德能源科技股份有限公司 Combined energy supply system based on natural gas distributive energy and ground source heat pump
CN105371340A (en) * 2015-12-17 2016-03-02 哈尔滨五建工程有限责任公司 Small solar ground-source heat pump system for villas in severe cold area and running method
CN106089264A (en) * 2016-06-12 2016-11-09 东南大学 Tunnel based on phase-changing and temperature-regulating concrete anti-freezing and heat-insulating structure and construction method
CN106595103A (en) * 2016-12-16 2017-04-26 绍兴文理学院 Construction method of energy tunnel layer burned geothermal heat exchange system
CN206522888U (en) * 2017-02-22 2017-09-26 广东澳亿美节能科技有限公司 The hot and cold air-conditioning system of quaternary integrated combined-type

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2615552Y (en) * 2003-03-17 2004-05-12 牛铁智 Geothermal utilizating air conditioner
WO2005088076A1 (en) * 2004-03-04 2005-09-22 Graham Paul Bloom An airconditioning system
US20120006503A1 (en) * 2010-07-06 2012-01-12 Chung-Hsin Electric And Machinery Manufacturing Corp. Ventilation system for tunnel engineering
CN103900178A (en) * 2014-03-24 2014-07-02 深圳达实智能股份有限公司 Ground source heat pump energy storage central air-conditioning system
CN104697263A (en) * 2015-03-10 2015-06-10 王琰 Self-prefreezing liquid nitrogen tunnel quick freezer
CN104901412A (en) * 2015-07-03 2015-09-09 成都博世德能源科技股份有限公司 Combined energy supply system based on natural gas distributive energy and ground source heat pump
CN105371340A (en) * 2015-12-17 2016-03-02 哈尔滨五建工程有限责任公司 Small solar ground-source heat pump system for villas in severe cold area and running method
CN106089264A (en) * 2016-06-12 2016-11-09 东南大学 Tunnel based on phase-changing and temperature-regulating concrete anti-freezing and heat-insulating structure and construction method
CN106595103A (en) * 2016-12-16 2017-04-26 绍兴文理学院 Construction method of energy tunnel layer burned geothermal heat exchange system
CN206522888U (en) * 2017-02-22 2017-09-26 广东澳亿美节能科技有限公司 The hot and cold air-conditioning system of quaternary integrated combined-type

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王昆等: "《基于相变材料的深井热害防治措施》", 《河南理工大学学报(自然科学版》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110905581A (en) * 2019-12-13 2020-03-24 湖南工程学院 Movable type excavation roadway cooling equipment
CN110905581B (en) * 2019-12-13 2021-06-15 湖南工程学院 Movable type excavation roadway cooling equipment
CN113431634A (en) * 2021-08-03 2021-09-24 中铁高新工业股份有限公司 Special thermal-insulated platform truck of underground space construction
CN113431634B (en) * 2021-08-03 2022-07-01 中铁高新工业股份有限公司 Special thermal-insulated platform truck of underground space construction

Also Published As

Publication number Publication date
CN109944626B (en) 2020-12-29

Similar Documents

Publication Publication Date Title
CN102099577B (en) Thermal energy system and operation method thereof
CN109519640B (en) Ventilation shaft attemperator and heat preserving method
CN106813333B (en) Double pipe laying air through tunnels couple air-conditioning system with phase-changing energy-storing
CN106593511B (en) A kind of thermal post_buckling roadway support cooling system and method
CN109944626A (en) Tunnel phase change cold-storage cooling system
CN107724377A (en) For preventing and treating the compression-type refrigerating system of Permafrost Degeneration
CN110118666B (en) Experimental method of environment-friendly cold region tunnel freezing injury simulation indoor experimental system
CN106150539A (en) A kind of high temperature getting working face liquid CO2freezing by change of state heat sink and method
CN110067588A (en) Tunnel quenching system based on phase change cold-storage
CN205975239U (en) Automatic is wall ventilation pipe passed through in control by temperature change compound road bed of piece metalling
CN205154229U (en) Attached water film board heat exchanger heat sink of high temperature mine tunnel wall
CN202547190U (en) Buried pipe system of ground source heat pump
CN103410549A (en) System and method by means of power plant waste heat for conducting aeration cooling on mine
CN110080817A (en) Tunnel ventilation cooling system based on phase change cold-storage
CN202899172U (en) Propylene glycol heating system of refrigeration storage floor
CN207277314U (en) A kind of ground heating type soil body crust freezing prevention and control device
CN104018871A (en) Coal mine high-temperature tunneling roadway sectional cooling device and method
CN105843291B (en) A kind of one-storey house silo heat dissipation temperature control system based on hot pipe technique
CN204830262U (en) Be used for interior capillary wall heat exchanger of subway tunnel
CN206532160U (en) A kind of one-storey house silo radiating temperature control system based on hot pipe technique
CN202194678U (en) System for cooling mine by utilizing constant-temperature water bearing stratum
CN107313796A (en) A kind of coal mine heat evil prevention and controls
CN212154833U (en) Tunnel face rapid cooling device
CN208996765U (en) A kind of mine shaft defroster
CN206581334U (en) It is a kind of based on solar powered intelligent air water drawing device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant