CN109944270A - A kind of photo-thermal power station tower foundation foundation bolt fast-positioning device - Google Patents

A kind of photo-thermal power station tower foundation foundation bolt fast-positioning device Download PDF

Info

Publication number
CN109944270A
CN109944270A CN201910269869.9A CN201910269869A CN109944270A CN 109944270 A CN109944270 A CN 109944270A CN 201910269869 A CN201910269869 A CN 201910269869A CN 109944270 A CN109944270 A CN 109944270A
Authority
CN
China
Prior art keywords
foundation
foundation bolt
bolt
photo
thermal power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910269869.9A
Other languages
Chinese (zh)
Other versions
CN109944270B (en
Inventor
刘晶晶
王伟
张聪
刘红超
郭军
韩雨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Hebei Jiankan Group Co.,Ltd.
Original Assignee
Hebei Construction Prospecting Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Construction Prospecting Research Institute Co Ltd filed Critical Hebei Construction Prospecting Research Institute Co Ltd
Priority to CN201910269869.9A priority Critical patent/CN109944270B/en
Publication of CN109944270A publication Critical patent/CN109944270A/en
Application granted granted Critical
Publication of CN109944270B publication Critical patent/CN109944270B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a kind of photo-thermal power station tower foundation foundation bolt fast-positioning devices, including cushion cap punching block, cabinet, foundation bolt positioning framework, longitudinal screw mandrel, take-up housing, nut seat, laterally adjust bolt, the fixing steel plate equipped with multiple foundation bolts and transparent material scutum;Fixing steel plate is installed respectively on the left and right ends portion of foundation bolt positioning framework, transparent material scutum there are two pieces and is respectively erected in above fixing steel plate.The characteristics of present invention is used cooperatively with total station, has structure simple, convenient and quick construction, is accurately positioned foundation bolt quickly.

Description

A kind of photo-thermal power station tower foundation foundation bolt fast-positioning device
Technical field
The present invention relates to construction and installation technical field, especially a kind of photo-thermal power station tower foundation foundation bolt is quickly positioned Device.
Background technique
The principle of photo-thermal power generation is using thousands of face mirror reflections, convergence sunlight to absorption tower, by solar energy It is converted into thermal energy, is done work by thermal energy and generates steam drive steam turbine power generation.Therefore, the installation accuracy of reflective mirror directly determines too Positive energy absorptivity, and reflective mirror installation accuracy is dependent firstly on the pre-buried precision of basic foundation bolt.In the prior art, lower margin spiral shell The work progress of bolt has as following drawbacks;It on the one hand, often can be due to the deviation of bolt relative position each in foundation bolt group Or integral position offset, cause the equipment on top or structure installation to encounter difficulties, installation progress is made not to be able to satisfy construction needs;Separately On the one hand, the accurate installation of foundation bolt group is complicated, and operation difficulty is big, and expends duration, and construction needs to be used for multiple times high-precision It spends total station and carries out position checking.The problems such as low, complicated for operation, time-consuming for above-mentioned installation accuracy, develop novel lower margin Bolt fast-positioning device has important Engineering Guidance meaning.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of photo-thermal power station tower foundation foundation bolts quickly to position dress It sets, is used cooperatively with total station, have structure simple, convenient and quick construction, the characteristics of being accurately positioned foundation bolt quickly.
In order to solve the above technical problems, the technical scheme adopted by the invention is that: a kind of photo-thermal power station tower foundation lower margin Bolt fast-positioning device, including cushion cap punching block, cabinet, foundation bolt positioning framework, longitudinal screw mandrel, take-up housing, nut seat, cross To adjustment bolt, the fixing steel plate equipped with multiple foundation bolts and transparent material scutum;The top of the cushion cap steel mould box body is flat Face, the foundation bolt positioning framework are located in cushion cap steel mould box body, and the longitudinal screw mandrel has two, and to both pass through foundation bolt fixed Position frame is simultaneously erected on two top surfaces up and down of cushion cap steel mould box body, and the take-up housing has two pairs and is separately mounted to pile cap steel On two top surfaces up and down of moulding box body, the both ends of longitudinal screw mandrel are each passed through the through-hole of take-up housing, set on the outside of take-up housing There is longitudinally adjusted nut compatible with longitudinal screw mandrel;The nut seat has a pair of left and right for being connected to cushion cap steel mould box body On two top surfaces, the bolt that laterally adjusts has two and is connect respectively by screw thread with nut seat, laterally adjusts the spiral shell of bolt Line end head is contacted with the left and right ends of foundation bolt positioning framework;Divide on the left and right ends portion of foundation bolt positioning framework Not An Zhuan fixing steel plate, the transparent material scutum has two pieces and is respectively erected in above fixing steel plate.
A kind of above-mentioned photo-thermal power station tower foundation foundation bolt fast-positioning device, the lower part of the take-up housing are equipped with recessed The top surface of slot, the groove and cushion cap steel mould box body is slidably matched.
A kind of above-mentioned photo-thermal power station tower foundation foundation bolt fast-positioning device, further includes longitudinal fine-tuning nut, institute Longitudinal fine-tuning nut is stated to be located at the two sides up and down of fixing steel plate and connect by screw thread with longitudinal screw mandrel.
A kind of above-mentioned photo-thermal power station tower foundation foundation bolt fast-positioning device, the transparent material scutum pass through bracket It is erected above fixing steel plate.
A kind of above-mentioned photo-thermal power station tower foundation foundation bolt fast-positioning device, the transparent material scutum are glass Plate.
A kind of above-mentioned photo-thermal power station tower foundation foundation bolt fast-positioning device, the transparent material scutum are plastics Plate.
A kind of photo-thermal power station tower foundation foundation bolt fast-positioning device provided by the invention, be provided with cushion cap punching block, Cabinet, longitudinal screw mandrel, take-up housing, nut seat, laterally adjusts bolt, equipped with multiple foundation bolts at foundation bolt positioning framework Fixing steel plate and transparent material scutum;The top of cushion cap steel mould box body is plane, and foundation bolt positioning framework is located at cushion cap steel mould box In vivo, longitudinal screw mandrel has two to both pass through foundation bolt positioning framework and is erected at two top surfaces up and down of cushion cap steel mould box body On, take-up housing has two pairs and is separately mounted on two top surfaces up and down of cushion cap steel mould box body, the both ends difference of longitudinal screw mandrel Across the through-hole of take-up housing, longitudinally adjusted nut compatible with longitudinal screw mandrel is equipped in the outside of take-up housing;Nut seat has one There are two and respectively by screw thread and spiral shell to bolt on the top surface of left and right two for being connected to cushion cap steel mould box body, is laterally adjusted Base connection, the end of thread head for laterally adjusting bolt is contacted with the left and right ends of foundation bolt positioning framework;In foundation bolt Fixing steel plate is installed respectively, transparent material scutum there are two pieces and is respectively erected in fixing steel plate above the left and right ends portion of positioning framework Top.
This technical solution sets up transparent material scutum as see-throughization measuring above fixing steel plate and marks platform, records The foundation bolt that total station is measured is properly positioned information, is compared by the physical location with foundation bolt, rapidly and accurately over the ground Foot bolt makes position correction.See-throughization measuring label platform can effectively, chronically record the accurate location of bolt, accomplish The accurate positioning of bolt group can also accomplish the implementing monitoring of position and adjustment in time in work progress, accomplish that foundation bolt is fast It is prompt, conveniently, be accurately positioned.The method have the benefit that: structure is simple, and it is convenient to construct, and foundation bolt positioning accuracy is high, It monitors bolt location in real time, reduces bolt and position measuring workload, reduce construction manpower, reduce measuring instrument input cost.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the invention.
Fig. 2 is the bottom view of Fig. 1.
Fig. 3 is the left view of Fig. 2.
Each part numbers in figure are as follows: cushion cap steel mould box body 1, bracket 3, transparent material scutum 4, laterally adjusts spiral shell at fixing steel plate 2 Bolt 5, nut seat 6, foundation bolt positioning framework 7, take-up housing 8, longitudinal screw mandrel 9, longitudinally adjusted nut 10, longitudinal fine-tuning nut 11, cabinet column 12.
4 foundation bolt labels in Fig. 1 on the fixing steel plate 2 of left side are divided into 7-1,7-2,7-3,7-4;Right positioner steel 4 foundation bolt labels on plate 2 are divided into 7-5,7-6,7-7,7-8.
Specific embodiment
The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
See Fig. 1,2,3, details are as follows by the present invention: firstly, making fixing steel plate 2 and lower margin according to foundation bolt distribution form Bolt positioning framework 7 accurately processes the loading hole of four foundation bolts by jig boring machine on fixing steel plate 2, by four In the hole that foundation bolt is mounted on fixing steel plate 2 and fasten accurate positionin, packaged there are four the positioning steel of foundation bolt by two Plate 2 is fixed on the both ends of foundation bolt positioning framework 7, and is tentatively determined using bolt 5 and longitudinally adjusted nut 10 is laterally adjusted Position fixing steel plate 2.Next, using high precision total station on fixed transparent material scutum 4 in measuring foundation bolt group Bolt accurate location in two diagonal directions, such as: it can be with the bolt 7-1 and right positioner on fixing steel plate 2 on the left of measuring The diagonal line between bolt 7-7 on steel plate 2, and marked on transparent material scutum 4, according to mark position, utilize transverse direction Adjustment bolt 5 and the quick accurate adjustment bolt position of longitudinally adjusted nut 10, it is ensured that bolt group position meets design requirement.? In subsequent concreting, the work progress such as vibrate, the complete of bolt location can be accomplished according to label real-time monitoring bolt location Process monitoring can be quickly adjusted according to label in time if any exception.

Claims (6)

1. a kind of photo-thermal power station tower foundation foundation bolt fast-positioning device, it is characterised in that: including cushion cap steel mould box body (1), foundation bolt positioning framework (7), longitudinal screw mandrel (9), take-up housing (8), nut seat (6), laterally adjust bolt (5), be equipped with The fixing steel plate (2) and transparent material scutum (4) of multiple foundation bolts;
The top of the cushion cap steel mould box body (1) is plane, and the foundation bolt positioning framework (7) is located at cushion cap steel mould box body (1) in, the longitudinal screw mandrel (9) has two to both pass through foundation bolt positioning framework (7) and is erected at cushion cap steel mould box body (1) On upper and lower two top surfaces, the take-up housing (8) has two pairs and is separately mounted to two top surfaces up and down of cushion cap steel mould box body (1) On, the both ends of longitudinal screw mandrel (9) are each passed through the through-hole of take-up housing (8), are equipped with and longitudinal screw mandrel in the outside of take-up housing (8) (9) compatible longitudinally adjusted nut (10);The left side that the nut seat (6) has a pair to be connected to cushion cap steel mould box body (1) On right two top surfaces, the bolt (5) that laterally adjusts has two and is connect respectively by screw thread with nut seat (6), laterally adjusts The end of thread head of bolt (5) is contacted with the left and right ends of foundation bolt positioning framework (7);In foundation bolt positioning framework (7) Left and right ends portion above install respectively fixing steel plate (2), the transparent material scutum (4) has two pieces and is respectively erected in positioning steel Above plate (2).
2. a kind of photo-thermal power station tower foundation foundation bolt fast-positioning device according to claim 1, it is characterised in that: The lower part of the take-up housing (8) is equipped with groove, and the top surface of the groove and cushion cap steel mould box body (1) is slidably matched.
3. a kind of photo-thermal power station tower foundation foundation bolt fast-positioning device according to claim 2, feature exist In: it further include longitudinal fine-tuning nut (11), the longitudinal direction fine-tuning nut (11) is located at the two sides up and down of fixing steel plate (2) and leads to Screw thread is crossed to connect with longitudinal screw mandrel (9).
4. a kind of photo-thermal power station tower foundation foundation bolt fast-positioning device according to claim 3, it is characterised in that: The transparent material scutum (4) is erected above fixing steel plate (2) by bracket (3).
5. a kind of photo-thermal power station tower foundation foundation bolt fast-positioning device according to claim 4, it is characterised in that: The transparent material scutum (4) is glass plate.
6. a kind of photo-thermal power station tower foundation foundation bolt fast-positioning device according to claim 4, it is characterised in that: The transparent material scutum (4) is plastic plate.
CN201910269869.9A 2019-04-04 2019-04-04 Quick positioner of light and heat power station pylon basis rag bolt Active CN109944270B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910269869.9A CN109944270B (en) 2019-04-04 2019-04-04 Quick positioner of light and heat power station pylon basis rag bolt

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910269869.9A CN109944270B (en) 2019-04-04 2019-04-04 Quick positioner of light and heat power station pylon basis rag bolt

Publications (2)

Publication Number Publication Date
CN109944270A true CN109944270A (en) 2019-06-28
CN109944270B CN109944270B (en) 2021-03-12

Family

ID=67012564

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910269869.9A Active CN109944270B (en) 2019-04-04 2019-04-04 Quick positioner of light and heat power station pylon basis rag bolt

Country Status (1)

Country Link
CN (1) CN109944270B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07317082A (en) * 1994-05-23 1995-12-05 Matsushita Electric Works Ltd Anchor frame
CN103215968A (en) * 2013-03-14 2013-07-24 江苏扬州建工建设集团有限公司 Embedded construction method of circular large-cross-section track-type equipment anchor bolt
CN203247603U (en) * 2013-05-29 2013-10-23 中国建筑第二工程局有限公司 High-position foundation bolt positioning device
CN204059395U (en) * 2014-07-14 2014-12-31 中国建筑第八工程局有限公司 The pre-buried location structure of stone bolt
CN208009467U (en) * 2018-03-23 2018-10-26 中建海峡建设发展有限公司 A kind of foundation bolt installation control device
CN208293601U (en) * 2018-04-05 2018-12-28 中匠华湄模板制造有限公司 A kind of dedicated foundation bolt positioning and fixing device of construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07317082A (en) * 1994-05-23 1995-12-05 Matsushita Electric Works Ltd Anchor frame
CN103215968A (en) * 2013-03-14 2013-07-24 江苏扬州建工建设集团有限公司 Embedded construction method of circular large-cross-section track-type equipment anchor bolt
CN203247603U (en) * 2013-05-29 2013-10-23 中国建筑第二工程局有限公司 High-position foundation bolt positioning device
CN204059395U (en) * 2014-07-14 2014-12-31 中国建筑第八工程局有限公司 The pre-buried location structure of stone bolt
CN208009467U (en) * 2018-03-23 2018-10-26 中建海峡建设发展有限公司 A kind of foundation bolt installation control device
CN208293601U (en) * 2018-04-05 2018-12-28 中匠华湄模板制造有限公司 A kind of dedicated foundation bolt positioning and fixing device of construction

Also Published As

Publication number Publication date
CN109944270B (en) 2021-03-12

Similar Documents

Publication Publication Date Title
ES2386288T3 (en) Machining device, in particular sawing device for cutting boards
CN106370142A (en) Wide range displacement sensor calibrating device and calibrating method
PT637482E (en) PROCEDURE FOR POSITIONING A SUPPORT FOR RAW FISH IN A PROCESSING MACHINE AS WELL AS THEIR SUPPORT FOR RAW FISH
CN105880699B (en) A kind of keyway in-process measurement method of rotor support power generator
CN102306207A (en) Method for assembling and positioning vertical column array type fuselage wall panel and device thereof
CN110525606B (en) Digital positioning auxiliary tool for slipway hull and use method thereof
CN201940832U (en) Fixture for clamping wind power generator set base
CN109944270A (en) A kind of photo-thermal power station tower foundation foundation bolt fast-positioning device
CN105772815B (en) The method of 90 degree of V-grooves of Spiral distribution on the big profile shaft of general NC Boring machine processing
CN105346082A (en) Movement device of 3D printer
CN103696410A (en) Efficient installation method for nut columns of gear and rack climbing-type vertical ship lift and auxiliary device
CN102896283B (en) Sector-shaped section overhauling arc butting device of H-type blank continuous casting machine
CN116837726A (en) Accurate installation method of main girder cable guide pipe of cable-stayed bridge
CN102500941A (en) Welding positioning process for mounting columns of conductor rails of megawatt wind driven generators
CN215045941U (en) Conveying equipment for section steel production
CN109405721A (en) A kind of aligning tool and the method using tool correction dividing head
CN214686494U (en) Simple universal marking and ranging device
CN211294636U (en) Wind vane adjusting device of wind turbine
CN103776354A (en) Concentric detector
CN115355227A (en) Sectional type wind power blade splicing tool and splicing method
CN209181710U (en) A kind of aligning tool
CN208542585U (en) A kind of cast member size detection machine
CN108106580B (en) Blade profile measuring and clamping device
CN107175357B (en) A kind of rib PRECISION HOLE manufacture auxiliary mould
CN106052658A (en) Photothermal power generation heat collector tower positioning and measuring device and power positioning method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 050000 No. 555 Huai'an West Road, Luquan District, Shijiazhuang City, Hebei Province

Patentee after: China Hebei Jiankan Group Co.,Ltd.

Address before: 050031 No. 58 Southern China Avenue, Shijiazhuang, Hebei

Patentee before: HEBEI CONSTRUCTION AND INVESTIGATION RESEARCH INSTITUTE Co.,Ltd.

CP03 Change of name, title or address