CN109902895A CN201711295073.8A CN201711295073A CN109902895A CN 109902895 A CN109902895 A CN 109902895A CN 201711295073 A CN201711295073 A CN 201711295073A CN 109902895 A CN109902895 A CN 109902895A
Authority
CN
China
Prior art keywords
production
time
specified
stage
test
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201711295073.8A
Other languages
Chinese (zh)
Inventor
朱伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Inventec Pudong Technology Corp
Inventec Corp
Original Assignee
Inventec Pudong Technology Corp
Inventec Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Inventec Pudong Technology Corp, Inventec Corp filed Critical Inventec Pudong Technology Corp
Priority to CN201711295073.8A priority Critical patent/CN109902895A/en
Publication of CN109902895A publication Critical patent/CN109902895A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

The present invention discloses a kind of test production scheduling system and method for production, it is product test production scheduling by specifying multiple production stages, and calculate the manufacturing time of each production stage, producing line and execution date and production time are executed to configure according to the manufacturing time of each production stage, the technical effect of test the production scheduling foundation and adjustment of the production that convenience is provided can be reached whereby.

Description

The test production scheduling system and method for production
Technical field
The present invention relates to a kind of production scheduling system and method, refer in particular to one kind and specify multiple production stages be product Test production scheduling and the manufacturing time for calculating each production stage, the manufacturing time according to each production stage configure Execute the test production scheduling system and method for producing line and the production of execution date and production time.
Background technique
The test manufacture stage before large-scale equipment production is necessary key link, determines the efficiency and cost of production.
Current test manufacture mode selects the raw materials for production of needs by the engineer for being proficient in processing procedure from a large amount of equipment, Process units determines production quantity and necessary production timing.Many production processes need according to a large amount of practical experience come Assessment.
In the actual production process, it goes back otherwise is completely cured according to the real process of production line and is adjusted, production each time Process requires to be recorded to improve production process.But since the uncertain factor of test production is various, it can to produce The production stage for needing to be adjusted in the process is various, be easy to cause the generation of production process adjustment mistake.
In summary, it is known that always exist test production scheduling for a long time in the prior art and be adjusted and be also easy to produce adjustment The problem of mistake, it is therefore necessary to improved technological means is proposed, to solve the problems, such as this.
Summary of the invention
There is a problem of that test production scheduling is adjusted in view of the prior art and be also easy to produce adjustment mistake, the present invention drapes over one's shoulders then Reveal a kind of test production scheduling system and method for production, in which:
The test production scheduling system of presently disclosed production, it includes: processor and storage device, place Managing device is for executing each instruction;Storage device is for storing multiple instruction, and instruction is loaded and executed by processor:
Specify multiple production stages for a test production scheduling, each production stage includes specified production producing line, specifies Process units, specified production material, specified procedure for producing, specified time date of manufacture and specified administrative staff;It calculates every The manufacturing time of one production stage;Manufacturing time configuration according to each production stage execute producing line and execution date with And the production time;And execution date according to each step and runing time calculating are put up a notice the time, and in execution date And administrative staff's device of notice to corresponding production stage is sent when the notice time.
The test production scheduling method of presently disclosed production, it includes the following steps:
Firstly, specifying multiple production stages is a test production scheduling, each production stage include specified production producing line, Specified process units, specified production material, specified procedure for producing, specified time date of manufacture and specified administrative staff;Then, Calculate the manufacturing time of each production stage;Then, producing line is executed according to the manufacturing time configuration of each production stage And execution date and production time;Finally, putting up a notice according to the execution date of each step and runing time calculating Time, and notice is sent to the administrative staff's device for corresponding to production stage in execution date and notice time.
Presently disclosed system and method is as above, and the difference between the prior art is by specifying multiple productions Step is product test production scheduling, and calculates the manufacturing time of each production stage, according to each production stage Manufacturing time configuration execute producing line and execution date and production time, then according to each step execution date and Runing time calculating is put up a notice the time, and the management of notice to corresponding production stage is sent in execution date and notice time Personnel's device.
By above-mentioned technological means, the test production scheduling that the present invention can reach the production of offer convenience is built The vertical technical effect with adjustment.
Detailed description of the invention
Fig. 1 is the system block diagram of the test production scheduling system of product of the present invention production.
Fig. 2 is the method flow diagram of the test production scheduling method of product of the present invention production.
Symbol description:
11 processors
12 storage devices
Specific embodiment
Carry out the embodiment that the present invention will be described in detail below in conjunction with schema and embodiment, how the present invention is applied whereby Technological means solves technical problem and reaches the realization process of technical effect to fully understand and implement.
It will illustrate the operation system and method for embodiment of the present invention with one embodiment below, and please also refer to figure Shown in 1 and Fig. 2, Fig. 1 is the system block diagram of the test production scheduling system of product of the present invention production;Fig. 2 is schematically shown as the present invention The method flow diagram of the test production scheduling method of production.
The test production scheduling system of presently disclosed production, it includes: processor 11 and storage device 12, processor 11 is for executing each instruction;Storage device 12 is for storing multiple instruction, and instruction is loaded and held by processor Row:
User can user interface provided by the test production scheduling system by production carry out product test production The foundation of scheduling, product test production scheduling include multiple production stages, each step includes specified production producing line, specifies Process units, specified production material, specified procedure for producing, specified time date of manufacture and specified administrative staff's (step 101) Deng herein by way of example only, application range of the invention not being limited to this.
Assuming that need 4 steps in one product A of production, in product test production scheduling i.e. respectively with four steps into The product test production scheduling of row product A is established, i.e. first step, which is specified, carries out the production, specified of product in A production producing line The production of product is carried out using A process units, specified the production of product carried out using A production material to D production material, specified makes Production, the date and time of appointed product production and the life of A administrative staff's management product of product are carried out with A procedure for producing It produces;Second step specifies and carries out the production of product in D production producing line, specified carry out the production of product using C process units, refers to Surely the production of product is carried out using B production material, E production material and F production material, specified produced using D procedure for producing Production, the date and time of appointed product production and the production of B administrative staff's management product of product, and so on, Ji Kejian The product test production scheduling of vertical product A does not limit to application range of the invention herein by way of example only with this.
After establishing test production scheduling, the manufacturing time (step 102) of each production stage is calculated, is calculated The manufacturing time of each production stage be time of the specified production material by specified process units manufacture multiplied by error time+ After 1 is maximized, multiplied by the Qty of the production stage, then divided by 3600, then divided by continuous manufacture quantity, along with what is missed the stop The summation of tune machine, the numerical value calculated are the manufacturing time of corresponding production stage, wherein corresponding to specified production material warp Spending time of specified process units manufacture multiplied by production stage/process units that error time+1 is maximized is bottleneck step Suddenly/bottleneck device.
Manufacturing time configuration according to each production stage executes producing line and specified execution date and specified production Time (step 103), specifically, it is assumed that when the specified execution date of production stage is " 2017/11/15 " and specified production Between be " when 10 ", the calculated manufacturing time of production stage institute is " 2 hours ", and test production scheduling system can inquire specified Execution date be " 2017/11/15 " and the specified production time be " when 10 " and specified execution date be " 2017/11/15 " with And the specified production time is that " when 10 " to " when 12 " can carry out the execution producing line of production stage, and execute production for what is be queried out The configuration of one of line progress production stage.
In addition to this, according to the manufacturing time configuration of each production stage execute producing line and specified execution date and After the specified production time can more add up the manufacturing time of each production stage, and according to specified execution date and specified life The production time finds out the manufacturing time after meeting aggregation to configure execution producing line.
Complete above-mentioned steps to establish product test production scheduling after, can according to each step execution date with And runing time calculating is put up a notice the time, that is, provides the purpose of prior notice, in execution date and notice time Administrative staff's device (step 104) of notice to corresponding production stage is sent, it is raw that administrative staff's device can carry out product test Produce the management that scheduling corresponds to production stage.
When product test production scheduling start execute when, any one production stage when the error occurs, generation error information And it is sent to administrative staff's device of corresponding production stage, it is wrong so as to alloing administrative staff to learn that production stage occurs in real time Accidentally, to carry out the exclusion of production stage mistake.
Further when product test production scheduling starts to execute, after the completion of any one production stage executes, generate At information and it is sent to administrative staff's device of corresponding production stage, administrative staff's device further receives administrative staff's input After confirmation message, confirmation message is sent to product test production scheduling system to complete production stage.
In summary, it is known that the difference between the present invention and the prior art is that by specifying multiple production stages be product Production scheduling is tested, and calculates the manufacturing time of each production stage, with the manufacturing time according to each production stage Configuration executes producing line and execution date and production time;Again according to the execution date of each step and runing time meter The notice time is calculated, and sends administrative staff's device of notice to corresponding production stage in execution date and notice time.
It can be adjusted by this technological means solving present in the prior art test production scheduling and be also easy to produce adjustment The problem of mistake, and then the test production scheduling for reaching the production for providing convenience establishes the technical effect with adjustment.
Although embodiment illustrated by the present invention is as above, only the content is not of the invention special directly to limit Sharp protection scope.Any those skilled in the art in the technical field of the invention are not departing from presently disclosed essence Under the premise of mind and range, a little change can be made in the formal and details of implementation.Scope of patent protection of the invention, Still it should be subject to the scope of the claims as defined in the appended claims.

Claims (10)

1. a kind of test production scheduling system of production, which is characterized in that it includes:
Processor, for executing each instruction;And
Storage device, for storing multiple instruction, described instruction is loaded and is executed by the processor:
Specifying multiple production stages is a test production scheduling, each production stage includes specified production producing line, specified production Device, specified production material, specified procedure for producing, specified time date of manufacture and specified administrative staff;
Calculate the manufacturing time of each production stage;
Manufacturing time configuration according to each production stage executes producing line and execution date and production time;And
It puts up a notice the time according to the execution date of each step and runing time calculating, and in execution date and described logical Administrative staff's device of notice to corresponding production stage is sent when knowing the time.
2. the test production scheduling system of production as described in claim 1, which is characterized in that calculate each production The manufacturing time of step is to be maximized multiplied by error time+1 time of the specified production material by specified process units manufacture Afterwards, multiplied by the Qty of the production stage, then divided by 3600, then divided by continuous manufacture quantity, along with that misses the stop adjusts the total of machine With the manufacturing time of the as corresponding production stage of the numerical value calculated, wherein corresponding to specified production material by specifying life The time of production device manufacturing is that bottleneck step/bottleneck fills multiplied by production stage/process units that error time+1 is maximized It sets.
3. the test production scheduling system of production as described in claim 1, which is characterized in that according to each production step Rapid manufacturing time configuration executes producing line and specified execution date and the specified production time also includes by each production step After rapid manufacturing time aggregation, and the manufacturing time after meeting aggregation is found out according to specified execution date and specified production time Producing line is executed with configuration.
4. the test production scheduling system of production as described in claim 1, which is characterized in that the product test production When scheduling starts to execute, when the error occurs, generation error information is simultaneously sent to corresponding production stage to any one production stage Administrative staff's device.
5. the test production scheduling system of production as described in claim 1, which is characterized in that the product test production When scheduling starts to execute, after the completion of any one production stage executes, generates and complete information and be sent to corresponding production stage Administrative staff's device after administrative staff's device further receives the confirmation message of administrative staff's input, sends confirmation message to production Product test production scheduling system to complete production stage.
6. a kind of test production scheduling method of production, which is characterized in that it includes:
Specifying multiple production stages is a test production scheduling, each production stage includes specified production producing line, specified production Device, specified production material, specified procedure for producing, specified time date of manufacture and specified administrative staff;
Calculate the manufacturing time of each production stage;
Manufacturing time configuration according to each production stage executes producing line and execution date and production time;And
It puts up a notice the time according to the execution date of each step and runing time calculating, and in execution date and described logical Administrative staff's device of notice to corresponding production stage is sent when knowing the time.
7. the test production scheduling method of production as claimed in claim 6, which is characterized in that calculate each production The manufacturing time of step is to be maximized multiplied by error time+1 time of the specified production material by specified process units manufacture Afterwards, multiplied by the Qty of the production stage, then divided by 3600, then divided by continuous manufacture quantity, along with that misses the stop adjusts the total of machine With the manufacturing time of the as corresponding production stage of the numerical value calculated, wherein corresponding to specified production material by specifying life The time of production device manufacturing is that bottleneck step/bottleneck fills multiplied by production stage/process units that error time+1 is maximized It sets.
8. the test production scheduling method of production as claimed in claim 6, which is characterized in that according to each production step Rapid manufacturing time configuration executes producing line and specified execution date and the specified production time also includes by each production step After rapid manufacturing time aggregation, and the manufacturing time after meeting aggregation is found out according to specified execution date and specified production time Producing line is executed with configuration.
9. the test production scheduling method of production as claimed in claim 6, which is characterized in that the product test production When scheduling starts to execute, when the error occurs, generation error information is simultaneously sent to corresponding production stage to any one production stage Administrative staff's device.
10. the test production scheduling method of production as claimed in claim 6, which is characterized in that the product test is raw When production scheduling starts to execute, after the completion of any one production stage executes, generates completion information and be simultaneously sent to corresponding production stage Administrative staff's device, administrative staff's device further receive administrative staff input confirmation message after, send confirmation message with Complete production stage.
CN201711295073.8A 2017-12-08 2017-12-08 The test production scheduling system and method for production Withdrawn CN109902895A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711295073.8A CN109902895A (en) 2017-12-08 2017-12-08 The test production scheduling system and method for production

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711295073.8A CN109902895A (en) 2017-12-08 2017-12-08 The test production scheduling system and method for production

Publications (1)

Publication Number Publication Date
CN109902895A true CN109902895A (en) 2019-06-18

Family

ID=66940490

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711295073.8A Withdrawn CN109902895A (en) 2017-12-08 2017-12-08 The test production scheduling system and method for production

Country Status (1)

Country Link
CN (1) CN109902895A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW200512623A (en) * 2002-03-26 2005-04-01 Nittodenko Corp Production scheduling management method and production scheduling management program
JP2010198339A (en) * 2009-02-25 2010-09-09 Nagaoka Univ Of Technology Schedule creation method, schedule creation device and computer program
TW201525628A (en) * 2013-11-27 2015-07-01 Celerint Llc System and method for semiconductor device handler throughput optimization
CN106529871A (en) * 2016-10-28 2017-03-22 上海福赛特机器人有限公司 Intelligent manufacturing method and system
CN106681291A (en) * 2017-01-09 2017-05-17 北京理工大学 Production scheduling method and system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW200512623A (en) * 2002-03-26 2005-04-01 Nittodenko Corp Production scheduling management method and production scheduling management program
JP2010198339A (en) * 2009-02-25 2010-09-09 Nagaoka Univ Of Technology Schedule creation method, schedule creation device and computer program
TW201525628A (en) * 2013-11-27 2015-07-01 Celerint Llc System and method for semiconductor device handler throughput optimization
CN106529871A (en) * 2016-10-28 2017-03-22 上海福赛特机器人有限公司 Intelligent manufacturing method and system
CN106681291A (en) * 2017-01-09 2017-05-17 北京理工大学 Production scheduling method and system

Similar Documents

Publication Publication Date Title
CN104536811B (en) Method for scheduling task based on HIVE tasks and device
CN104407576B (en) A kind of implementation method and control system of universal manufacturing unit
CN109412829A (en) A kind of prediction technique and equipment of resource distribution
WO2016090929A1 (en) Method, server and system for software system fault diagnosis
CN105069524B (en) Planned dispatching optimization method based on big data analysis
EP3451093B1 (en) Work assistance device, work assistance method, and work assistance program
CN103679388A (en) Production scheduling method and system
CN106528070A (en) Data table generation method and equipment
CN104809663A (en) Power professional technique service assurance surveillance system and method
CN104392311A (en) Intelligent production scheduling method based on state driving
CN115545664A (en) Automated project management system and method based on WBS
CN105956077B (en) Based on the matched digging flow system of semantic requirement
CN109902895A (en) The test production scheduling system and method for production
CN114399031A (en) Intelligent factory temperature and humidity control method based on federal learning
CN104077633A (en) Scheduling method based on bottleneck procedure
TW201428647A (en) System and method for controlling arrangement of production line
CN105549559A (en) Method used for acquiring continuous chemical industry production technology conformity based on team and group and apparatus thereof
CN101159605B (en) Flow control method capable of implementing state memory and recovery
CN109240757A (en) Configuration management system and method in a kind of big data component set
Baratov The issues of creating a formalized model of the technical documentation
CN105094069A (en) Process control method and system in manufacturing process of semiconductor device
CN107729046A (en) A kind of software version automation dissemination method and device
CN106909992B (en) Split charging production method and device of multi-variety small-batch mixed flow assembly line
US20140310682A1 (en) Device and method for generating application model based on layered structure
TW201918809A (en) Production schedule monitoring method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20190618