CN109898758A - Cement mortar pastes the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again - Google Patents

Cement mortar pastes the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again Download PDF

Info

Publication number
CN109898758A
CN109898758A CN201910254795.1A CN201910254795A CN109898758A CN 109898758 A CN109898758 A CN 109898758A CN 201910254795 A CN201910254795 A CN 201910254795A CN 109898758 A CN109898758 A CN 109898758A
Authority
CN
China
Prior art keywords
bac
cement mortar
waterproof roll
waterproof
coiled material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910254795.1A
Other languages
Chinese (zh)
Inventor
尚玉杰
孙玉明
赵恒�
王汉功
蒋蜜
段军舰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Haoyue Construction Engineering Co Ltd
Original Assignee
Shandong Haoyue Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Haoyue Construction Engineering Co Ltd filed Critical Shandong Haoyue Construction Engineering Co Ltd
Priority to CN201910254795.1A priority Critical patent/CN109898758A/en
Publication of CN109898758A publication Critical patent/CN109898758A/en
Pending legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of waterproof coiled material construction fields, paste the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again more particularly, to cement mortar.The cement mortar pastes the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again, its construction process are as follows: base treatment, cement mortar screeding layer is smeared, conserves, smears cement slurry adhesive layer, spread BCA waterproof roll, the isolation film for taking BAC waterproof roll shrimp surface off, dries in the air and puts 24 to 48 hours, to sealing joint, joint strengthening processing, inspection of quality.The beneficial effect is that: give full play to the high molecular polymer characteristic of BAC double-sided self-adhesive waterproof coiled materials, it can produce stronger bonding force, with high-intensitive, ductility is good, weatherability is strong and unique voluntarily filling, the lesser puncture of closely sealed base, crack equivalent damage, low engineering leakage problem can be effectively prevented from, and significant effect, there is extremely strong adaptivity.

Description

Cement mortar pastes the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again
Technical field
The present invention relates to waterproof coiled material construction fields, paste BAC waterproof roll elder generation screed-coat more particularly, to cement mortar The construction method of waterproof layer is done again.
Background technique
The utilization of the underground space be unable to do without the waterproof effect of hypogee, once there is leakage phenomenon, not only influences building The main reason for beauty drags down architecture quality, but will directly affect building function property amount, and common construction method causes leakage has, Waterproof layer weak spot is dealt with improperly, and waterproof material is damaged, construction joint caused by main structure leakiness, structural cracks, waterproof layer With main structure sky paving leakiness at " channeling water layer ", the main reason for being all the leakage for causing underground structure, to give people Routine work bring many inconvenience.
Summary of the invention
The purpose of the present invention is to provide cement mortar to paste the construction party that BAC waterproof roll elder generation screed-coat does waterproof layer again Method, the technical solution adopted by the present invention is that:
Cement mortar of the present invention pastes the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again, construction process are as follows: base Layer processing, smears cement mortar screeding layer, conserves, and smears cement slurry adhesive layer, spreads BCA waterproof roll, takes BAC waterproof roll shrimp table off The isolation film in face dries in the air and puts 24 to 48 hours, to sealing joint, joint strengthening processing, inspection of quality.
Further, the construction method particularly includes:
Base treatment: base is smooth, solid, Wu Mingshui, and base's bump is removed clean;
Smear cement mortar screeding layer: for cement mortar with a thickness of 10-20mm, paving should be noted compacting when smearing, and wooden float smoothes out, at inner corner trim Smear into the fillet that radius is 50mm;
Maintenance: maintenance can be stood when on people station to cement mortar final set, no soft sunken;
It smears cement slurry adhesive layer: cement slurry being smeared in the base being sufficiently humidified so as to, with a thickness of 3-5mm;
BCA waterproof roll is spread, the isolation film on BAC waterproof roll shrimp surface is taken off: taking the isolation of BAC mode coiled material lower surface off Coiled material is laid in cement mortar by film, is parallel docking between coiled material and adjacent web, abutment joint should spell sternly as far as possible, when adopting When with overlapping mode, lower layer coiled material upper surface overlapping part isolation film and upper layer coiled material lower surface isolation film are removed, then taken It connects closely knit;
Dry in the air and put 24 hours to 48 hours: drying in the air and put 24 hours to 48 hours, the specific time depending on environment temperature, under normal circumstances, Temperature is higher, and required time is shorter;
To sealing joint: sealing strip is sealed using additional self-adhesion, when to sealing joint, first by the surface on coiled material lapping position every It is removed from film, then pastes additional self-adhesion sealing strip, if overlapping part is contaminated, need to first cleaned out, when between upper and lower layer coiled material When using overlapping mode, it is not necessarily to self-adhesion sealing strip;
Closing in temporary sealing: BAC waterproof roll answers temporary sealing at coiled material closing in paving on wall, can with adhesive tape or Thickening cement slurry sealing, to prevent moisture at vertical strong receipts head too fast lost;
Joint strengthening processing: node carries out reinforcement processing after being in big roll material construction.
The invention has the advantages that: the high molecular polymer for having given full play to BAC double-sided self-adhesive waterproof coiled materials is special Property, can produce stronger bonding force, have that high-intensitive, ductility is good, weatherability is strong and unique voluntarily filling, closely sealed base compared with Small puncture, crack equivalent damage, can be effectively prevented from low engineering leakage problem, and significant effect, have extremely strong adaptive Property.
Specific embodiment
Cement mortar of the invention pastes the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again, construction stream Journey are as follows: base treatment smears cement mortar screeding layer, and cement slurry adhesive layer is smeared in maintenance, spreads BCA waterproof roll, takes BAC waterproof off The isolation film on coiled material shrimp surface, dries in the air and puts 24 to 48 hours, to sealing joint, joint strengthening processing, inspection of quality.
Further, the construction method particularly includes:
Base treatment: base is smooth, solid, Wu Mingshui, and base's bump is removed clean;
Smear cement mortar screeding layer: for cement mortar with a thickness of 10-20mm, paving should be noted compacting when smearing, and wooden float smoothes out, at inner corner trim Smear into the fillet that radius is 50mm;
Maintenance: maintenance can be stood when on people station to cement mortar final set, no soft sunken;
It smears cement slurry adhesive layer: cement slurry being smeared in the base being sufficiently humidified so as to, with a thickness of 3-5mm;
BCA waterproof roll is spread, the isolation film on BAC waterproof roll shrimp surface is taken off: taking the isolation of BAC mode coiled material lower surface off Coiled material is laid in cement mortar by film, is parallel docking between coiled material and adjacent web, abutment joint should spell sternly as far as possible, when adopting When with overlapping mode, lower layer coiled material upper surface overlapping part isolation film and upper layer coiled material lower surface isolation film are removed, then taken It connects closely knit;
Dry in the air and put 24 hours to 48 hours: drying in the air and put 24 hours to 48 hours, the specific time depending on environment temperature, under normal circumstances, Temperature is higher, and required time is shorter;
To sealing joint: sealing strip is sealed using additional self-adhesion, when to sealing joint, first by the surface on coiled material lapping position every It is removed from film, then pastes additional self-adhesion sealing strip, if overlapping part is contaminated, need to first cleaned out, when between upper and lower layer coiled material When using overlapping mode, it is not necessarily to self-adhesion sealing strip;
Closing in temporary sealing: BAC waterproof roll answers temporary sealing at coiled material closing in paving on wall, can with adhesive tape or Thickening cement slurry sealing, to prevent moisture at vertical strong receipts head too fast lost;
Joint strengthening processing: node carries out reinforcement processing after being in big roll material construction.
This construction method, which is primarily adapted for use in have done screed-coat or do not done levelling but Base Smoothness, meets screed-coat requirement The waterproofing works such as basement roof, side wall and roofing.
Its engineering method feature are as follows:
It is adaptable, deformation and the cracking of base can be well adapted for;
Whole cold bonding constructions, securely and reliably, free from environmental pollution, easy construction is clean;
To base's moisture content no requirement (NR), the construction period can be greatlyd save.
The present invention is not limited to the above-described embodiments, anyone should learn make under the inspiration of the present invention with the present invention With same or similar technical solution, fall within the scope of protection of the present invention.
Technology not described in detail in the present invention, shape, construction portion are well-known technique.

Claims (2)

1. cement mortar pastes the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again, construction process are as follows: at base Reason, smears cement mortar screeding layer, conserves, and smears cement slurry adhesive layer, spreads BCA waterproof roll, takes BAC waterproof roll shrimp surface off Isolation film dries in the air and puts 24 to 48 hours, to sealing joint, joint strengthening processing, inspection of quality.
2. cement mortar according to claim 1 pastes the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again, It is characterized in that: the construction method particularly includes:
Base treatment: base is smooth, solid, Wu Mingshui, and base's bump is removed clean;
Smear cement mortar screeding layer: for cement mortar with a thickness of 10-20mm, paving should be noted compacting when smearing, and wooden float smoothes out, at inner corner trim Smear into the fillet that radius is 50mm;
Maintenance: maintenance can be stood when on people station to cement mortar final set, no soft sunken;
It smears cement slurry adhesive layer: cement slurry being smeared in the base being sufficiently humidified so as to, with a thickness of 3-5mm;
BCA waterproof roll is spread, the isolation film on BAC waterproof roll shrimp surface is taken off: taking the isolation of BAC mode coiled material lower surface off Coiled material is laid in cement mortar by film, is parallel docking between coiled material and adjacent web, abutment joint should spell sternly as far as possible, when adopting When with overlapping mode, lower layer coiled material upper surface overlapping part isolation film and upper layer coiled material lower surface isolation film are removed, then taken It connects closely knit;
Dry in the air and put 24 hours to 48 hours: drying in the air and put 24 hours to 48 hours, the specific time depending on environment temperature, under normal circumstances, Temperature is higher, and required time is shorter;
To sealing joint: sealing strip is sealed using additional self-adhesion, when to sealing joint, first by the surface on coiled material lapping position every It is removed from film, then pastes additional self-adhesion sealing strip, if overlapping part is contaminated, need to first cleaned out, when between upper and lower layer coiled material When using overlapping mode, it is not necessarily to self-adhesion sealing strip;
Closing in temporary sealing: BAC waterproof roll answers temporary sealing at coiled material closing in paving on wall, can with adhesive tape or Thickening cement slurry sealing, to prevent moisture at vertical strong receipts head too fast lost;
Joint strengthening processing: node carries out reinforcement processing after being in big roll material construction.
CN201910254795.1A 2019-04-01 2019-04-01 Cement mortar pastes the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again Pending CN109898758A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910254795.1A CN109898758A (en) 2019-04-01 2019-04-01 Cement mortar pastes the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910254795.1A CN109898758A (en) 2019-04-01 2019-04-01 Cement mortar pastes the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again

Publications (1)

Publication Number Publication Date
CN109898758A true CN109898758A (en) 2019-06-18

Family

ID=66955254

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910254795.1A Pending CN109898758A (en) 2019-04-01 2019-04-01 Cement mortar pastes the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again

Country Status (1)

Country Link
CN (1) CN109898758A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111794391A (en) * 2020-07-05 2020-10-20 青岛新华友建工集团股份有限公司 Construction process for high-air-tightness deformation joint of passive house
CN114059771A (en) * 2021-12-03 2022-02-18 金雨伞防水材料有限公司 Construction process of reaction bonding type high-molecular wet-laid waterproof roll

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111794391A (en) * 2020-07-05 2020-10-20 青岛新华友建工集团股份有限公司 Construction process for high-air-tightness deformation joint of passive house
CN114059771A (en) * 2021-12-03 2022-02-18 金雨伞防水材料有限公司 Construction process of reaction bonding type high-molecular wet-laid waterproof roll
CN114059771B (en) * 2021-12-03 2023-02-17 金雨伞防水材料有限公司 Construction process of reaction bonding type high-molecular wet-laid waterproof roll

Similar Documents

Publication Publication Date Title
CN101994399B (en) Method for repairing leaked coiled-material water-proof roof
CN201588229U (en) Basement waterproof construction system
CN102797297A (en) Solar power generation composite waterproof self-adhesive coiled material and construction method thereof
CN205399843U (en) Roofing system structure
CN109898758A (en) Cement mortar pastes the construction method that BAC waterproof roll elder generation screed-coat does waterproof layer again
CN106988489A (en) A kind of implementation method of roofing system structure
CN201695411U (en) Waterproof system of bottom board and wall surface of basement
CN104762999A (en) Self-adhesion coiled material underground waterproof construction method
CN208618582U (en) A kind of lapped configuration of self-adhering-type polymer membranes
CN110469062A (en) A kind of construction method of building roofing waterproof layer
CN204343722U (en) swimming pool gutter
CN210263443U (en) Building waterproof structure
CN203742002U (en) Waterproof leak repairing structure with permeating and self-repairing functions
CN109898759A (en) Cement mortar pastes the construction method that BAC waterproof roll screed-coat and waterproof layer are constructed simultaneously
CN206667500U (en) A kind of toilet waterproofing structure
KR101028953B1 (en) Complex water proof treatment construction methode using surface treatment and water proof sheet and water proof structure and composite thereof
CN109537428A (en) A kind of beams of concrete face and its construction method with waterproof roll
CN104652715A (en) Method for preparing and constructing waterproof paint for steel structure roofs
CN208168180U (en) A kind of roof waterproof node apparatus
CN109898672A (en) A kind of construction method being mechanically fixed BAC waterproof roll
CN201695527U (en) Wet felting elastomer modified asphalt waterproof coiled material
CN211195191U (en) Stretch-proofing waterproofing membrane is used at corner
CN204266404U (en) A kind of outer-wall crack-resisting anti-leakage structure
CN207700485U (en) Steel structural roof
CN104343137B (en) Underground waterproof engineering construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190618