CN109884463A - A kind of detection of buried cable and standardized management method - Google Patents

A kind of detection of buried cable and standardized management method Download PDF

Info

Publication number
CN109884463A
CN109884463A CN201811648811.7A CN201811648811A CN109884463A CN 109884463 A CN109884463 A CN 109884463A CN 201811648811 A CN201811648811 A CN 201811648811A CN 109884463 A CN109884463 A CN 109884463A
Authority
CN
China
Prior art keywords
cable
data
detection
standardized management
management
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811648811.7A
Other languages
Chinese (zh)
Inventor
徐亮
楼伟杰
程辉阳
张丹阳
颜韬韬
叶加炜
毛水强
姜奕
董勇腾
陈天来
李志坚
陈炜
王晓
严民
刘婧芸
张锦亮
严志明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JINHUA TRANSMISSION ENGINEERING Co Ltd
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
JINHUA TRANSMISSION ENGINEERING Co Ltd
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JINHUA TRANSMISSION ENGINEERING Co Ltd, Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical JINHUA TRANSMISSION ENGINEERING Co Ltd
Priority to CN201811648811.7A priority Critical patent/CN109884463A/en
Publication of CN109884463A publication Critical patent/CN109884463A/en
Pending legal-status Critical Current

Links

Landscapes

  • Locating Faults (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The invention discloses a kind of buried cable detection and standardized management method, including the following steps: step 1: cable on-site data gathering;Step 2: field data transmission;Step 3: field data cloud platform storage;Step 4: field data standardized management;Step 5: troubleshooting.Beneficial effects of the present invention: the blank that platform has filled up power cable data cloud platform is managed by building cable field data;Using wireless PDA terminal, power cable information is called in scene typing in real time, realizes resource-sharing;Information-based guarantee is provided for the intelligent operation and maintenance of power distribution network.

Description

A kind of detection of buried cable and standardized management method
Technical field
The invention belongs to Force system fault detection and administrative skill field, in particular to a kind of buried cable detection and mark Standardization management method.
Background technique
With the development of society, the expansion in city, mentioning for environmental requirement is done, and the quantity of power cable is continuously increased;Cable Management work it is increasingly heavier;Five Hua Zuomen of cable management system at present, level is uneven, and maximum problem is to be necessarily mounted at platform In formula PC machine, on-site data gathering is extremely difficult, and information input is usually manual entry;Workload is very big, and error rate is very It is high.
Summary of the invention
Mesh of the invention solves the problems, such as that the on-site data gathering of power cable is difficult, Information Administration Mode is backward, proposes A kind of buried cable detection and standardized management method, can be with collection in worksite data, and data are called at scene, by big data cloud Platform applies to the storage and transmission of field data, keeps the management work of power cable lighter, is more convenient, more in real time.
To realize the above-mentioned technical purpose, a kind of technical solution provided by the invention is, a kind of buried cable detection and mark Standardization management method, which is characterized in that including the following steps:
Step 1: cable on-site data gathering;
Step 2: field data transmission;
Step 3: field data cloud platform storage;
Step 4: field data standardized management;
Step 5: troubleshooting.
Preferably, in the step 1, cable field data, the cable field data are acquired by cable detector Include: track detection and fault detection.
Preferably, track detection includes the track data, tag data, disk remainder of real-time detection power cable According to, depth of burying data, covering data.
Preferably, a kind of buried cable detection according to claim 2 and standardized management method, feature exist In: the fault detection include quickly the detecting of power cable fault, accurately identify, safety is stabbed.
Preferably, in the step 2, data transmission, the PAD are realized in PAD terminal and cable detector communication connection Data Integration packing is issued field data cloud platform storage by the electronic tag of terminal recognition on-site cable.
Preferably, in the step 3, data cloud platform is connect with the PAD terminal called realizes data transmission.
Preferably, it in the step 4, is measured by the on-site cable of computer data management cell call cloud platform storage Data packet carries out the standardized management of cable field data.
Preferably, the field data standardized management include icon standard management, information standardization management with And way to manage standardized management.
Preferably, the icon standard management includes following icon: power cable, transition joint, fault point, terminal Head, channel management, tunnel, direct-burried, land mark, underground marker;The information standardization management includes following information: electricity The specifications and models of power cable, laying scene, failure modes, nature of trouble, test report;The way to manage standardized management Including following way to manage: power cable construction management, detection management, trial, reporting standards.
Beneficial effects of the present invention: 1, it by build cable field data manages platform filled up power cable data cloud flat The blank of platform;2, using wireless PDA terminal, scene typing in real time calls power cable information, realizes resource-sharing;3, for The intelligent operation and maintenance of power grid provide information-based ensure.
Detailed description of the invention
Fig. 1 is the flow chart of a kind of buried cable detection of the present invention and standardized management method.
Specific embodiment
It is right with reference to the accompanying drawings and examples for the purpose of the present invention, technical solution and advantage is more clearly understood The present invention is described in further detail, it should be appreciated that the specific embodiments described herein are only one kind of the invention Most preferred embodiment, only to explain the present invention, and the scope of protection of the present invention is not limited, and those of ordinary skill in the art are not having Every other embodiment obtained under the premise of creative work is made, shall fall within the protection scope of the present invention.
Embodiment: as shown in Figure 1, a kind of buried cable detection and standardized management method, which is characterized in that including with Under several steps:
Step 1, cable on-site data gathering;
Step 2, field data transmission;
Step 3, field data cloud platform storage;
Step 4, field data standardized management;
Step 5: troubleshooting.
Preferably, in the step 1, cable field data, the cable field data are acquired by cable detector Include: track detection and fault detection.In the present embodiment, the track of cable may be implemented by cable failure detection instrument device Detection and fault detection, and the data that real-time storage detects.
Preferably, track detection includes the track data, tag data, disk remainder of real-time detection power cable According to, depth of burying data, covering data.In the present embodiment, track detection includes the track data of cable, the street between multistage cable Head data, disk remainder evidence, the coverage data of the depth data of cable burial and cable.
Preferably, a kind of buried cable detection according to claim 2 and standardized management method, feature exist In: the fault detection include quickly the detecting of power cable fault, accurately identify, safety is stabbed.In the present embodiment, therefore Barrier detection includes that detection and malfunction elimination, the fault distinguishing of fault point and positioning, cable are carried out to the routine data of cable Safety stab.
Preferably, in the step 2, data transmission, the PAD are realized in PAD terminal and cable detector communication connection Data Integration packing is issued field data cloud platform storage by the electronic tag of terminal recognition on-site cable.In the present embodiment, Surface mark board well lid is opened in construction site, and PAD terminal scans the electronic tag under well lid, matches the position letter of current cable Breath, then by PAD terminal and cable fault measuring instrument communication connection, on-site test personnel are measured with cable fault measuring instrument Cable field data is transported to PAD terminal, and cable position information and cable field data are packaged by PAD, are sent to cloud, realizes End data is shared.
Preferably, in the step 3, data cloud platform is connect with the PAD terminal called realizes data transmission.
Preferably, it in the step 4, is measured by the on-site cable of computer data management cell call cloud platform storage Data packet carries out the standardized management of cable field data.In the present embodiment, computer terminal transfers cloud platform and obtains my data, uses The information management platform of self-service research and development, decompresses data packet, and data are recorded in the display pattern of setting by certain format.
Preferably, the field data standardized management include icon standard management, information standardization management with And way to manage standardized management.In the present embodiment, the design of field data data management platform follows three kinds of design logics: point It Wei not icon standard management, information standardization management and way to manage standardized management.
Preferably, the icon standard management includes following icon: power cable, transition joint, fault point, terminal Head, channel management, tunnel, direct-burried, land mark, underground marker;The information standardization management includes following information: electricity The specifications and models of power cable, laying scene, failure modes, nature of trouble, test report;The way to manage standardized management Including following way to manage;Power cable construction management, detection management, trial, reporting standards.It, will in the present embodiment Collected data are successively referred in the different display modules of management platform, and information management platform can be sentenced according to field data The type and treatment measures of disconnected cable fault, while Trouble Report is generated, it sounds an alarm and timely maintenance personal is notified to go to Fault point processing, improves the efficiency of breakdown maintenance;Fault prediction model can be used simultaneously, judge the fault point easily broken down And fault type, accomplish to take precautions against, reduces maintenance cost.
The specific embodiment of the above be a kind of detection of buried cable of the present invention and standardized management method compared with Good embodiment, limits specific implementation range of the invention not with this, and the scope of the present invention includes being not limited to this specifically in fact Mode is applied, equivalence changes made by all shape, structures according to the present invention are within the scope of the invention.

Claims (9)

1. a kind of buried cable detection and standardized management method, which is characterized in that including the following steps:
Step 1, cable on-site data gathering;
Step 2, field data transmission;
Step 3, field data cloud platform storage;
Step 4, field data standardized management;
Step 5: troubleshooting.
2. a kind of buried cable detection according to claim 1 and standardized management method, it is characterised in that: the step In rapid 1, cable field data is acquired by cable detector, the cable field data includes: track detection and event Barrier detection.
3. a kind of buried cable detection according to claim 2 and standardized management method, it is characterised in that: described Track detection includes the track data, tag data, disk remainder evidence, depth of burying data, covering of real-time detection power cable Data.
4. a kind of buried cable detection according to claim 2 and standardized management method, it is characterised in that: described Fault detection includes quickly detecting, accurately identify, stabbing safely for power cable fault.
5. a kind of buried cable detection according to claim 1 and standardized management method, it is characterised in that: the step In rapid 2, data transmission, the electronics of the PAD terminal recognition on-site cable are realized in PAD terminal and cable detector communication connection Data Integration packing is issued field data cloud platform storage by label.
6. a kind of buried cable detection according to claim 1 and standardized management method, it is characterised in that: the step In rapid 3, data cloud platform is connect with the PAD terminal called realizes data transmission.
7. a kind of buried cable detection according to claim 1 and standardized management method, it is characterised in that: the step In rapid 4, by the on-site cable measurement data packet of computer data management cell call cloud platform storage, cable scene number is carried out According to standardized management.
8. a kind of buried cable detection according to claim 1 or claim 7 and standardized management method, it is characterised in that: institute The field data standardized management stated includes icon standard management, information standardization management and way to manage standardization pipe Reason.
9. a kind of buried cable detection according to claim 8 and standardized management method, it is characterised in that: described Icon standard management includes following icon: power cable, transition joint, fault point, terminals, channel management, tunnel, straight It buries, land mark, underground marker;The information standardization management includes following information: the specifications and models of power cable are applied If scene, failure modes, nature of trouble, test report;The way to manage standardized management includes following way to manage: Power cable construction management, detection management, trial, reporting standards.
CN201811648811.7A 2018-12-30 2018-12-30 A kind of detection of buried cable and standardized management method Pending CN109884463A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811648811.7A CN109884463A (en) 2018-12-30 2018-12-30 A kind of detection of buried cable and standardized management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811648811.7A CN109884463A (en) 2018-12-30 2018-12-30 A kind of detection of buried cable and standardized management method

Publications (1)

Publication Number Publication Date
CN109884463A true CN109884463A (en) 2019-06-14

Family

ID=66925421

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811648811.7A Pending CN109884463A (en) 2018-12-30 2018-12-30 A kind of detection of buried cable and standardized management method

Country Status (1)

Country Link
CN (1) CN109884463A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111579898A (en) * 2020-04-22 2020-08-25 广东电网有限责任公司 Regional resource sharing method and system based on cloud platform

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101930470A (en) * 2010-09-07 2010-12-29 上海盈隽实业有限公司 Urban power network geographic information system and urban pipeline geographic information system
CN104283309A (en) * 2014-05-23 2015-01-14 国家电网公司 Online monitoring technical system for 110-kV high-voltage cable
CN104853090A (en) * 2015-04-21 2015-08-19 浙江图维电力科技有限公司 On-site data collection method for power cable survey
CN106557892A (en) * 2016-12-08 2017-04-05 天津市矩辉数据科技有限公司 City Buried Pipeline GIS-Geographic Information System
CN107340440A (en) * 2017-05-22 2017-11-10 合肥瑞达软件科技有限公司 The system for searching cable trace online using cloud computing
CN108470386A (en) * 2018-04-16 2018-08-31 国网上海市电力公司 A kind of cable run intelligent inspection system based on GPS and cloud platform
CN108564752A (en) * 2018-06-15 2018-09-21 四川艾贝斯科技发展有限公司 Cable anti-theft system based on NB-IoT and its alarm method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101930470A (en) * 2010-09-07 2010-12-29 上海盈隽实业有限公司 Urban power network geographic information system and urban pipeline geographic information system
CN104283309A (en) * 2014-05-23 2015-01-14 国家电网公司 Online monitoring technical system for 110-kV high-voltage cable
CN104853090A (en) * 2015-04-21 2015-08-19 浙江图维电力科技有限公司 On-site data collection method for power cable survey
CN106557892A (en) * 2016-12-08 2017-04-05 天津市矩辉数据科技有限公司 City Buried Pipeline GIS-Geographic Information System
CN107340440A (en) * 2017-05-22 2017-11-10 合肥瑞达软件科技有限公司 The system for searching cable trace online using cloud computing
CN108470386A (en) * 2018-04-16 2018-08-31 国网上海市电力公司 A kind of cable run intelligent inspection system based on GPS and cloud platform
CN108564752A (en) * 2018-06-15 2018-09-21 四川艾贝斯科技发展有限公司 Cable anti-theft system based on NB-IoT and its alarm method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111579898A (en) * 2020-04-22 2020-08-25 广东电网有限责任公司 Regional resource sharing method and system based on cloud platform

Similar Documents

Publication Publication Date Title
CN104880986A (en) System and method for comprehensive pipe gallery management based on BIM
CN109919451B (en) Digital power grid system and method based on real power grid topology analysis and safety knowledge base
CN103414251A (en) Substation network communication simulation system based on IEC 61850
CN106841908A (en) The visual presentation method of the distribution network failure positioning based on power grid GIS
CN107290623A (en) A kind of transmission line malfunction reason recognition methods based on Auto-matching
CN102435868A (en) Power quality monitoring system
CN104266681A (en) Electric cable well state safety monitoring system based on Internet of Things and GIS
CN204465143U (en) Distribution line detects and management system
CN109712262A (en) Line data-logging method based on technology of Internet of things
US20200153503A1 (en) Modular Systems and Methods for Monitoring and Distributing Power
CN105655920A (en) Multifunctional air-ground dual-purpose electric unmanned aerial vehicle
CN103412213A (en) Crosslinked polyethylene high-voltage cable on-line monitoring and early warning system
CN106026388A (en) Substation fault information automatic publishing and processing system
CN109884463A (en) A kind of detection of buried cable and standardized management method
CN201142127Y (en) Landslide monitoring apparatus
CN204376958U (en) Based on Big Dipper location and the railway Landslide Forecast System of Minimal routing jumping figure agreement
CN203535128U (en) Crosslinked polyethylene high-voltage cable on-line monitoring and early warning system
CN114065955A (en) Power cable visual monitoring maintenance management system based on GIS
CN113240240A (en) Offshore oilfield group power system reliability assessment system and method thereof
CN204330009U (en) Based on the cable shaft status safety monitoring system of Internet of Things and GIS
CN205638554U (en) Colliery floods alarm system based on image and hydrologic data monitoring
CN204613941U (en) The data acquisition system (DAS) of pipeline facility
CN204374737U (en) A kind of water supply well management control system
CN106888128A (en) A kind of transformer station's Intranet monitoring system and its monitoring method
CN105373888A (en) Transmission line physical information fusion multi-layer management and control method and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190614