CN203535128U - Crosslinked polyethylene high-voltage cable on-line monitoring and early warning system - Google Patents

Crosslinked polyethylene high-voltage cable on-line monitoring and early warning system Download PDF

Info

Publication number
CN203535128U
CN203535128U CN201320447289.2U CN201320447289U CN203535128U CN 203535128 U CN203535128 U CN 203535128U CN 201320447289 U CN201320447289 U CN 201320447289U CN 203535128 U CN203535128 U CN 203535128U
Authority
CN
China
Prior art keywords
data
early warning
tension cable
crosslinked polyethylene
warning system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320447289.2U
Other languages
Chinese (zh)
Inventor
曾宪乐
王珂
兰翀
代顺坤
陈弋
黄山蓬
张丹
孔德武
丁鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Welldone Electric Equipment Co ltd
Nanning Power Supply Bureau of Guangxi Power Grid Co Ltd
Original Assignee
Shanghai Welldone Electric Equipment Co ltd
Nanning Power Supply Bureau of Guangxi Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Welldone Electric Equipment Co ltd, Nanning Power Supply Bureau of Guangxi Power Grid Co Ltd filed Critical Shanghai Welldone Electric Equipment Co ltd
Priority to CN201320447289.2U priority Critical patent/CN203535128U/en
Application granted granted Critical
Publication of CN203535128U publication Critical patent/CN203535128U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a crosslinked polyethylene high-voltage cable on-line monitoring and early warning system, which is mainly composed of an on-site data collection device, a data transmission network and a monitoring center. Various state data of a sensor sampling high-voltage cable and the environment where the sensor sampling high-voltage cable is located are collected by the on-site data collection device through measurement sensors of all function modules, and then reported to an intelligent data management platform of the monitoring center through the data transmission network. The crosslinked polyethylene high-voltage cable on-line monitoring and early warning system is comprehensive in function, compact in structure, stable, reliable and convenient to install and maintain, and is capable of achieving comprehensive, real-time and automatic monitoring and early warning. When the crosslinked polyethylene high-voltage cable on-line monitoring and early warning system is applied, high-voltage cable operation maintainers can well know the state of the cable and the state of the environment where the cable operates at any time and find defects in time. Therefore, the occurrence of power accidents is avoided.

Description

Crosslinked polyethylene high-tension cable on-line monitoring early warning system
Technical field
The utility model belongs to high-tension cable monitoring technical field, relates in particular to a kind of crosslinked polyethylene high-tension cable on-line monitoring early warning system.
Background technology
The ac high-voltage long-distance transmission line of 110kV and above grade adopts long apart from overhead transmission line conventionally, when entering urban area, overhead transmission line generally can access corresponding transformer station by the crosslinked polyethylene high-tension cable (hereinafter to be referred as " high-tension cable ") that is laid in underground, then by power equipments such as transformers, convert different electric pressures to, give various electricity consumptions region transmission of electricity in urban district.If there is suddenly power failure in transmission line of electricity, can cause city large-area power-cuts, when serious, will cause whole city to have a power failure, bring immeasurable economic loss.In order to guarantee transmission line of electricity safety, stable operation, need to carry out Real-Time Monitoring to overhead transmission line and the high-tension cable that is laid in underground state, and early warning in time before fault occurs, avoid occurring the electric power accident of power failure suddenly.
Now more to the monitoring means of overhead transmission line, and technology comparative maturity.But different from overhead transmission line, high-tension cable is laid in underground, there are the multiple system of layings such as tunnel, direct-burried, cable duct, running environment is complicated, and monitoring means is less, and this has brought very large difficulty to daily operation maintenance.At present the detection method of the underground high-tension cable that is laid in and means are divided into tradition and modernization two classes, specific as follows:
1, traditional detection method and means
(1) regular or irregular manual patrol, to find the abnormal and hidden danger of high-tension cable and affiliated facility thereof and process in time.
(2) regularly hv cable termination, the first-class critical cables annex of indirect are carried out to artificial infrared thermal imaging test.
(3) regular manual measurement high-tension cable metal sheath electric current.
(4) every year important Voltage Cable Lines Construction is carried out to preventive trial one time, main project comprises that testing insulation resistance of main, insulating sheath resistance and major insulation does AC voltage withstand test.
In real work, because Voltage Cable Lines Construction is more and more, all strictly by rules, carry out artificial daily operation maintenance and service work is difficult to realize.High-voltage cable joint or terminal or in special electric power work well, otherwise on high-tension cable shaft tower, the state parameters such as the metal sheath electric current of these cables of manual measurement or surface temperature need to spend a large amount of human and material resources, financial resources; Simultaneously owing to being regularly detection or making an inspection tour, conventionally cannot know the real-time running state of high-tension cable in section the interval time of patrolling and examining for twice, so that before high-tension cable fault occurs, operation maintenance personnel cannot obtain necessary early warning information in time, have caused some unnecessary economic losses.
2, modern monitoring method and means
Be mainly the various on-Line Monitor Device of utilizing modern power electronics technology, computer technology and mechanics of communication design to produce, host computer Real-time Collection also shows various Monitoring Data, realizes the object of high-tension cable state on_line monitoring.For example, yet this type of on-line equipment that different manufacturers is produced only has a kind of function conventionally, can only measure a state parameter of high-tension cable:
(1) high-tension cable metal sheath electric current on-Line Monitor Device, by being arranged on the survey sensor on high-voltage cable middle joint or terminals metal sheath, the electric current of Real-Time Monitoring high-tension cable metal sheath.
(2) distributed fiber temperature measuring device, utilize optical fiber measurement high-tension cable surface temperature, by the Special temperature measurement optical fiber on the high-tension cable surface that is laid in, the surface temperature of Real-Time Monitoring high-tension cable, optical fiber need to paste high-tension cable surface and lay, and from top, is applied to terminal.
(3) distributed partial-discharge measuring device, by being arranged on measurement of partial discharge sensor and the harvester on high-voltage cable middle joint or terminals, measure in real time the shelf depreciation situation of the significant points such as high-voltage cable joint, grasp the insulation situation of high-tension cable.
Because high-tension cable on-Line Monitor Device there is no unified standard criterion at aspects such as profile specification, data acquisition modes, so different vendor can and produce relevant apparatus according to the feature design of own product, research and development, cause these to install at the scene mounting means, networking, the aspect such as integrated has different requirements.The sensor that device is joined that even some function is identical all has larger difference at aspects such as profile, mounting meanss, there is no versatility, so that the on-the-spot confusion of installing, difficult in maintenance; In addition, the on-Line Monitor Device of the types of functionality that different vendor produces is conventionally different at aspects such as profile, size, performances, they to be integrated, all be arranged in the limited space of high-voltage cable joint well, the comprehensive monitoring that realizes high-tension cable state is very loaded down with trivial details, and system performance also can be unstable.
Utility model content
The technical problems to be solved in the utility model is to provide a kind of complete function, compact conformation, reliable and stable crosslinked polyethylene high-tension cable on-line monitoring early warning system.
For solving the problems of the technologies described above, the utility model is by the following technical solutions: crosslinked polyethylene high-tension cable on-line monitoring early warning system, mainly on-site data gathering device, three parts of data transmission network and Surveillance center, consist of, on-site data gathering device connects Surveillance center by data transmission network; On-site data gathering device comprises communication module, main control module and six functional modules, six functional modules are respectively high-tension cable metal sheath function of current module, surface temperature functional module, transient short-circuit fault current functional module, vibration information functional module, partial discharge quantity functional module, environmental functional module, and each functional module contains corresponding monitoring modular and survey sensor; Communication module connects main control module, and main control module connects respectively six functional modules.
On-site data gathering device, by the survey sensor sampling high-tension cable of each each functional module and the various status datas of environment of living in thereof, then reports the intelligent data management platform of Surveillance center by data transmission network.
Surveillance center comprises intelligent data management platform and communication apparatus, and intelligent data management platform comprises Database Systems, data management system and data distribution system.
Surveillance center possesses the alarm mode that GSM SMS notification, screen display interface prompting and Email are reported to the police; The collection of intelligent data management platform, analysis, processing and permanent storage Condition Monitoring Data, show all status datas in real time on Bing Surveillance center screen, various data sheet functions are provided simultaneously; Database Systems are used for depositing the Condition Monitoring Data of various interim or permanent storage; Data management system, based on design of database system, is used for collecting the various Condition Monitoring Datas that on-site data gathering device reports, and to these data analysis, processing, statistics and storage, the information such as sorts of systems user is managed simultaneously; Data distribution system, also based on database design, adopts the mode of website to issue various high-voltage cable state monitoring data.
Data transmission network is wireless network or cable network.
Wireless network is GPRS or 3G network, and cable network is industrial bus or Ethernet.
Monitoring modular comprises that the anti-electromagnetic interference (EMI) connecting is successively inhaled wave circuit I, anti-electromagnetic interference (EMI) is inhaled wave circuit II, anti-electromagnetic interference (EMI) suction wave circuit III, signal processing circuit, A/D change-over circuit and technical grade embedded scm.
The problem existing for current crosslinked polyethylene high-tension cable monitoring technology, inventor has designed a kind of crosslinked polyethylene high-tension cable on-line monitoring early warning system, mainly by on-site data gathering device, 3 parts of data transmission network and Surveillance center, formed, on-site data gathering device, by the survey sensor sampling high-tension cable of each each functional module and the various status datas of environment of living in thereof, then reports the intelligent data management platform of Surveillance center by data transmission network.The utlity model has following outstanding advantages:
Complete function, to high-tension cable and the state that lays environment thereof realized comprehensively, in real time, automatic monitoring and early warning, in real time, the information such as Monitoring High Voltage Cable metal sheath electric current, surface temperature, transient short-circuit fault current, vibration information, partial discharge quantity and ambient condition continuously.
Wherein, on-site data gathering device adopts modular design, compact conformation, and it integrates multiple tradition and modernization monitoring method and means, has realized integrated data acquisition object, simultaneously conveniently installs and safeguards; According to function, the various survey sensor profile of mounting means Uniting specification, avoid field wiring chaotic.
In addition, the utility model has increased the multiple early warning means such as the short notice of GSM, daemon software prompting, Email warning on the basis of existing on-line monitoring technique, realized the object of high-tension cable state comprehensive on-line monitoring, early warning, be convenient to the state that high-tension cable operation maintenance personnel grasp cable and running environment thereof at any time, find in time defect, avoid occurring electric power accident.
Accompanying drawing explanation
Fig. 1 is the structural representation of the utility model crosslinked polyethylene high-tension cable on-line monitoring early warning system.
Fig. 2 is the structural representation of on-site data gathering device in the utility model on-line monitoring early warning system.
Fig. 3 is the structural representation of the functional module of on-site data gathering device in the utility model on-line monitoring early warning system.
In figure: 1 on-site data gathering device, 2 data transmission networks, 3 Surveillance center, 4 communication modules, 5 main control modules, 6 functional modules, 7 high-tension cable metal sheath function of current modules, 8 surface temperature functional modules, 9 transient short-circuit fault current functional modules, 10 vibration information functional modules, 11 partial discharge quantity functional modules, 12 environmental functional modules, 13 survey sensors, 14 monitoring modulars, 15 anti-electromagnetic interference (EMI) are inhaled wave circuit I, 16 anti-electromagnetic interference (EMI) are inhaled wave circuit II, 17 anti-electromagnetic interference (EMI) are inhaled wave circuit III, 18 signal processing circuits, 19A/D change-over circuit, 20 technical grade embedded scms, 21 client computers, 22 intelligent data management platforms, 23 communication apparatus.
Embodiment
As shown in Figures 1 to 3, the utility model crosslinked polyethylene high-tension cable on-line monitoring early warning system, adopt distributed frame, mainly on-site data gathering device 1,3 three parts of data transmission network 2 and Surveillance center, consist of, on-site data gathering device connects Surveillance center by data transmission network.Different according to the length of Monitoring High Voltage Cable, conventionally need to use 1 cover or overlap field data harvester more.On-site data gathering device adopts modular design, comprise communication module 4, main control module 5 and six functional modules 6, communication module connects main control module, main control module connects respectively six functional modules (high-tension cable metal sheath function of current module 7, surface temperature functional module 8, transient short-circuit fault current functional module 9, vibration information functional module 10, partial discharge quantity functional module 11, environmental functional module 12), each module all adopts the design of technical grade embedded scm, except communication module and main control module, separate during other operations of module for status monitoring, be independent of each other, if there is a module to break down, can not cause device machine failure, greatly improved the stability of system, reliability.Each functional module contains corresponding monitoring modular 14 and survey sensor 13, and monitoring modular comprises that the anti-electromagnetic interference (EMI) connecting is successively inhaled wave circuit I15, anti-electromagnetic interference (EMI) is inhaled wave circuit II16, anti-electromagnetic interference (EMI) suction wave circuit III17, signal processing circuit 18, A/D change-over circuit 19 and technical grade embedded scm 20.Data transmission network is GPRS or 3G wireless network, also can be the various industrial bus that form of communication cable or optical cable, Ethernet etc., several data transmission network mode has increased dirigibility and the diversity of on-site data gathering device networking, has greatly improved the application of system under various complicated.Surveillance center comprises intelligent data management platform 22 and supporting communication apparatus 23, system is equipped with different communication apparatus (as wireless telecommunications system or wire communication equipment) according to the type of data transmission network, be used for receiving the Condition Monitoring Data that on-site data gathering device reports, be transferred to that intelligent data management platform is analyzed, processed, statistics and permanent storage; Intelligent data management platform comprises Database Systems (professional database), data management system and data distribution system.
High-tension cable surrounding enviroment are conventionally comparatively severe, there is very strong electromagnetic interference (EMI), there was dampness in the air, environment temperature is sometimes up to 50 degree left and right, work that can be reliable and stable under rugged surroundings in order to ensure system data harvester, various function module circuit plates electronic devices and components used in on-site data gathering device, integrated circuit is all selected by industrial rank, satisfied temperature scope is in the environment for use of-25 degree~85 degree, and in the input of signal and power supply, on output interface, adopt at least 3 grades of anti-electromagnetic interference (EMI) to inhale wave circuit, each function module circuit plate is used and has insulation simultaneously, moistureproof, anticreep, shockproof, dustproof, anticorrosion, anti-aging, the coating of resistance to corona applies, guaranteed that device is strong in electromagnetic interference (EMI), high temperature, stable operation in the rugged surroundings of high humidity.
On-site data gathering device, by the survey sensor sampling high-tension cable of each each functional module and the various status datas of environment of living in thereof, then reports the intelligent data management platform of Surveillance center by data transmission network.Surveillance center possesses the alarm mode that GSM SMS notification, screen display interface prompting and Email are reported to the police, and gets final product timely and effective notice high-tension cable operation maintenance personnel when there is early warning information; The collection of intelligent data management platform, analysis, processing and permanent storage Condition Monitoring Data, show all status datas in real time on Bing Surveillance center screen, various data sheet functions are provided simultaneously; Database Systems are used for depositing the Condition Monitoring Data of various interim or permanent storage; Data management system, based on design of database system, is used for collecting the various Condition Monitoring Datas that on-site data gathering device reports, and to these data analysis, processing, statistics and storage, the information such as sorts of systems user is managed simultaneously; Data distribution system, also based on database design, adopts the mode of website to issue various high-voltage cable state monitoring data, and other client computers 21 of LAN (Local Area Network) inside are used the WEB browsers such as IE to check these data.
The utility model on-line monitoring early warning system data transmission procedure: first each measurement function module of on-site data gathering device is by gathering high-tension cable with the corresponding survey sensor of self function and laying the status data of environment, and these status datas are aggregated into main control module carry out data packings and process, and convert the data layout of standard to, be transferred to communication module; Then these data report the intelligent data management platform of Surveillance center by data transmission network, Platform Server is processed, analyzes, is added up data, and data permanent storage in Database Systems, finally various status datas are distributed to the client computer of LAN (Local Area Network) inside with the form of website, for high-tension cable operation maintenance personnel inquiry.
For avoiding high-tension cable to lay the functional module permanent damage that strong electromagnetic in environment causes data collector, in functional module, designed the multistage suction wave circuit of anti-electromagnetic interference (EMI), be that the status data signal that survey sensor obtains is inhaled wave circuit III and is transferred to signal processing circuit through anti-electromagnetic interference (EMI) suction wave circuit I, anti-electromagnetic interference (EMI) suction wave circuit II, anti-electromagnetic interference (EMI), the technical grade embedded scm that is finally transferred to corresponding module by A/D change-over circuit is done further processing.

Claims (7)

1. a crosslinked polyethylene high-tension cable on-line monitoring early warning system, is characterized in that being comprised of on-site data gathering device, three parts of data transmission network and Surveillance center, and on-site data gathering device connects Surveillance center by data transmission network; Described on-site data gathering device comprises communication module, main control module and six functional modules, six functional modules are respectively high-tension cable metal sheath function of current module, surface temperature functional module, transient short-circuit fault current functional module, vibration information functional module, partial discharge quantity functional module, environmental functional module, and each functional module contains corresponding monitoring modular and survey sensor; Communication module connects main control module, and main control module connects respectively six functional modules.
2. crosslinked polyethylene high-tension cable on-line monitoring early warning system according to claim 1, it is characterized in that: described on-site data gathering device, by the survey sensor sampling high-tension cable of each each functional module and the various status datas of environment of living in thereof, then reports the intelligent data management platform of Surveillance center by data transmission network.
3. crosslinked polyethylene high-tension cable on-line monitoring early warning system according to claim 1, it is characterized in that: described Surveillance center comprises intelligent data management platform and communication apparatus, intelligent data management platform comprises Database Systems, data management system and data distribution system.
4. crosslinked polyethylene high-tension cable on-line monitoring early warning system according to claim 3, is characterized in that: described Surveillance center possesses the alarm mode that GSM SMS notification, screen display interface prompting and Email are reported to the police; The collection of described intelligent data management platform, analysis, processing and permanent storage Condition Monitoring Data, show all status datas in real time on Bing Surveillance center screen, various data sheet functions are provided simultaneously; Described Database Systems are used for depositing the Condition Monitoring Data of various interim or permanent storage; Data management system, based on design of database system, is used for collecting the various Condition Monitoring Datas that on-site data gathering device reports, and to these data analysis, processing, statistics and storage, the information such as sorts of systems user is managed simultaneously; Data distribution system, also based on database design, adopts the mode of website to issue various high-voltage cable state monitoring data.
5. crosslinked polyethylene high-tension cable on-line monitoring early warning system according to claim 1, is characterized in that: described data transmission network is wireless network or cable network.
6. crosslinked polyethylene high-tension cable on-line monitoring early warning system according to claim 5, is characterized in that: described wireless network is GPRS or 3G network, and described cable network is industrial bus or Ethernet.
7. crosslinked polyethylene high-tension cable on-line monitoring early warning system according to claim 1, is characterized in that: described monitoring modular comprises that the anti-electromagnetic interference (EMI) connecting is successively inhaled wave circuit I, anti-electromagnetic interference (EMI) is inhaled wave circuit II, anti-electromagnetic interference (EMI) suction wave circuit III, signal processing circuit, A/D change-over circuit and technical grade embedded scm.
CN201320447289.2U 2013-07-25 2013-07-25 Crosslinked polyethylene high-voltage cable on-line monitoring and early warning system Expired - Fee Related CN203535128U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320447289.2U CN203535128U (en) 2013-07-25 2013-07-25 Crosslinked polyethylene high-voltage cable on-line monitoring and early warning system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320447289.2U CN203535128U (en) 2013-07-25 2013-07-25 Crosslinked polyethylene high-voltage cable on-line monitoring and early warning system

Publications (1)

Publication Number Publication Date
CN203535128U true CN203535128U (en) 2014-04-09

Family

ID=50421322

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320447289.2U Expired - Fee Related CN203535128U (en) 2013-07-25 2013-07-25 Crosslinked polyethylene high-voltage cable on-line monitoring and early warning system

Country Status (1)

Country Link
CN (1) CN203535128U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104991149A (en) * 2015-08-06 2015-10-21 陕西古源电力科技有限公司 Single core power cable online state monitoring device and method
CN105182102A (en) * 2015-07-16 2015-12-23 江西华强金源电气有限公司 Small hydropower internet access wire outlet end monitoring device
CN105203866A (en) * 2015-07-17 2015-12-30 长沙理工大学 Novel online fault diagnosis method for high-voltage XLPE cable
CN106771722A (en) * 2016-11-30 2017-05-31 国网福建省电力有限公司 Feeder line fault on-line monitoring system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105182102A (en) * 2015-07-16 2015-12-23 江西华强金源电气有限公司 Small hydropower internet access wire outlet end monitoring device
CN105203866A (en) * 2015-07-17 2015-12-30 长沙理工大学 Novel online fault diagnosis method for high-voltage XLPE cable
CN104991149A (en) * 2015-08-06 2015-10-21 陕西古源电力科技有限公司 Single core power cable online state monitoring device and method
CN106771722A (en) * 2016-11-30 2017-05-31 国网福建省电力有限公司 Feeder line fault on-line monitoring system

Similar Documents

Publication Publication Date Title
CN103412213A (en) Crosslinked polyethylene high-voltage cable on-line monitoring and early warning system
CN104092310B (en) A kind of intelligent power distribution monitoring and energy management system backstage
CN209282929U (en) A kind of electric power box intelligent monitoring protection management system
CN102435871A (en) On-line monitoring system for data collection of electric arresters based on GPS (Global Positioning System) synchronization
CN212208349U (en) Online risk assessment device of distribution transformer based on multisource information
CN211296946U (en) Railway electric power comprehensive operation and maintenance management system
CN203535128U (en) Crosslinked polyethylene high-voltage cable on-line monitoring and early warning system
CN102636710A (en) Online monitoring system of high-voltage equipment
CN103730894B (en) EMS image checking mehtod and device
CN105334811A (en) Wireless tower monitoring method of power lines based on ZigBee network
Yan et al. Application status and development trends for intelligent perception of distribution network
CN104377821A (en) Power transformation equipment online monitoring system
CN103389437A (en) Device and method for monitoring shielding current of secondary control cable of transformer substation in real time
CN112684292A (en) Wind power plant current collection line monitoring system, method and device
CN104377823A (en) On-line monitoring system for power transmission equipment
CN202533529U (en) High-voltage equipment on-line monitoring system
CN102707195A (en) Oscilloscope fault analysis platform and establishment method thereof
CN205506953U (en) Electric energy quality detection device based on radio communication
CN104898580A (en) Wireless oil pumping unit controller with three-phase electric acquisition
CN106026383A (en) Intelligent transformer station equipment state multi-system cooperative diagnosis method based on information fusion
CN107328438A (en) A kind of power transformer runs comprehensive monitor system
CN105445633A (en) High-voltage cable protective layer loop current multi-state monitoring device
CN203164360U (en) Transformer device insulation online monitoring system
CN105098993A (en) Network message analysis and fault recording system of intelligent substation
CN103344549B (en) Electronic equipment extent of corrosion remote monitoring method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140409

Termination date: 20140725

EXPY Termination of patent right or utility model