CN109881868A - A kind of construction painting bracket - Google Patents

A kind of construction painting bracket Download PDF

Info

Publication number
CN109881868A
CN109881868A CN201910076992.9A CN201910076992A CN109881868A CN 109881868 A CN109881868 A CN 109881868A CN 201910076992 A CN201910076992 A CN 201910076992A CN 109881868 A CN109881868 A CN 109881868A
Authority
CN
China
Prior art keywords
operation platform
support frame
welded
construction
bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910076992.9A
Other languages
Chinese (zh)
Inventor
马作京
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Dai Bai Rick Building Engineering Co Ltd
Original Assignee
Tianjin Dai Bai Rick Building Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Dai Bai Rick Building Engineering Co Ltd filed Critical Tianjin Dai Bai Rick Building Engineering Co Ltd
Priority to CN201910076992.9A priority Critical patent/CN109881868A/en
Publication of CN109881868A publication Critical patent/CN109881868A/en
Pending legal-status Critical Current

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The invention discloses a kind of construction painting brackets, including operation platform, secondary support frame device, clamping screw and crank hand, the left and right sides of the operation platform is hinged with main backstop, and horizontal pedal is welded at the position between main backstop, the middle position of the operation platform bottom is welded with welding block, one end of the pair support frame device and welding block are articulated and connected, the other end of the pair support frame device is articulated and connected with wherein one group horizontal pedal, and operation platform top outer surface opens up sliding slot at a side position at back.The present invention passes through the intermeshing of gear and belt, cooperate staggered fixing clamp up and down, reduce the stubborn situation of the artificial hand of construction material, while mitigating trouble to construction personnel, also certain holding power is provided to whole device, so that bearing plate is integrated with whole device, overall construction design is beautiful, designs advantages of simple in structure.

Description

A kind of construction painting bracket
Technical field
The present invention relates to architectural engineering auxiliary tool technology field, specially a kind of construction painting bracket.
Background technique
Currently, need to carry out the painting of building surface layer after good for building construction with the continuous development of building trade, When being painted, when needing construction material, it usually needs manually carried up with hand, so that construction personnel also soak through by usual sweat stream Back, causes the working efficiency of construction personnel to reduce, and needs a hand-held construction material, another in operation platform construction personnel Hand painting, it is time-consuming and laborious to cause plastering wall in this way, therefore, proposes a kind of construction painting in view of the above problems and props up Frame.
Summary of the invention
The purpose of the present invention is to provide a kind of construction painting brackets, to solve constructor in above-mentioned background technique The working efficiency of member reduces, the time-consuming and laborious problem of plastering wall.
To achieve the above object, the invention provides the following technical scheme: a kind of construction painting bracket, including construction Platform, secondary support frame device, clamping screw and crank hand, the left and right sides of the operation platform are hinged with main backstop, and Horizontal pedal is welded at position between main backstop, the middle position of the operation platform bottom is welded with welding block, One end of the pair support frame device and welding block are articulated and connected, and the other end of the pair support frame device horizontal is stepped on wherein one group Plate articulated connection, operation platform top outer surface open up sliding slot at a side position at back, and in the inside of sliding slot Embedded with sliding block, fixed link is welded at the top of the sliding block, and the inside of fixed link is inserted with built-in rod, the clamping screw Fixed rod outer surface is run through in one end, is fixedly connected between the built-in rod and fixed link by clamping screw, the operation platform Top is equipped with bearing plate close to positive side, and the upper and lower ends of bearing plate pass through bearing and are arranged gear, the gear Outer surface be enclosed with belt, one end of the crank hand is fixedly connected through bearing plate with bearing.
Preferably, the secondary support frame device includes the first expansion bracket, adjusting set and the second expansion bracket, the adjusting set One end be arranged with the first expansion bracket, the other end of the adjusting set is arranged with adjusting set, first expansion bracket, second flexible It is fixedly connected between frame and adjusting set by adjusting screw.
Preferably, the contact surface junction of the sliding slot and sliding block pressing has friction pad, and the thickness of friction pad is set as 5mm, the outer surface of cupular part of the operation platform are provided with herringbone convex block.
Preferably, it is provided with preformed hole at the front position of the bearing plate and operation platform, the bearing plate and applies It is fixedly connected between work platform by fixed screw.
Preferably, fixing clamp is welded on the built-in rod and belt, and fixing clamp is provided with three groups, on the belt Fixing clamp in being staggered up and down.
Preferably, the outer surface of the gear is welded with double wedge, and the belt inner wall is provided with concave tooth and double wedge phase Mutually engagement.
Compared with prior art, the beneficial effects of the present invention are: construction painting bracket, passes through gear and belt Intermeshing, cooperate staggered fixing clamp up and down, reduce the stubborn situation of the artificial hand of construction material, construction personnel is given to mitigate While trouble, certain holding power is also provided to whole device, so that bearing plate is integrated with whole device, overall structure It is designed beautifully, advantages of simple is designed in structure, use easy to operate, and fixed link is slided in sliding slot by sliding block Be used cooperatively so that construction personnel when painting can one it is hand steered, the operation of another hand strengthens peace when construction personnel's work Quan Xing, and practicability is very high, low manufacture cost, is suitable for large-scale productionization and uses.
Detailed description of the invention
Fig. 1 is that structure of the invention faces diagrammatic cross-section;
Fig. 2 is structure side view diagrammatic cross-section of the invention;
Fig. 3 is operation platform schematic top plan view of the invention;
Fig. 4 is the partial enlargement diagram in Fig. 1 at A;
Fig. 5 is secondary support frame device structure schematic elevation view of the invention.
In figure: 1, operation platform;2, main backstop;3, welding block;4, secondary support frame device;41, the first expansion bracket;42, Adjusting set;43, the second expansion bracket;5, sliding slot;6, sliding block;7, fixed link;8, built-in rod;9, clamping screw;10, bearing plate;11, Belt;12, gear;13, crank hand;14, fixing clamp;15, horizontal pedal.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Please refer to Fig. 1-5, a kind of embodiment provided by the invention: a kind of construction is flat with painting bracket, including construction Platform 1, secondary support frame device 4, clamping screw 9 and crank hand 13, the left and right sides of operation platform 1 are hinged with main backstop 2, and Horizontal pedal 15 is welded at position between main backstop 2, the middle position of 1 bottom of operation platform is welded with welding block 3, One end of secondary support frame device 4 and welding block 3 are articulated and connected, the other end of secondary support frame device 4 and wherein one group of horizontal pedal 15 Articulated connection is adjusted preferably, secondary support frame device 4 includes the first expansion bracket 41, adjusting set 42 and the second expansion bracket 43 One end of set 42 is arranged with the first expansion bracket 41, and the other end of adjusting set 42 is arranged with adjusting set 42, the first expansion bracket 41, second It is fixedly connected between expansion bracket 43 and adjusting set 42 by adjusting screw, the first expansion bracket 41 and the second expansion bracket 43 from adjusting The suitable length of extraction in set 42, and adjusting screw is tightened, the first expansion bracket 41, the second expansion bracket 43 and adjusting set 42 is fixed It is locked, 2 angle of main backstop is adjusted by adjusting secondary 4 length of support frame device, consequently facilitating adjusting the height of whole device.
1 top outer surface of operation platform opens up sliding slot 5 at a side position at back, and the inside of sliding slot 5 is embedded with Sliding block 6, the top of sliding block 6 is welded with fixed link 7, and the inside of fixed link 7 is inserted with built-in rod 8, and sliding slot 5 connects with sliding block 6 The pressing of contacting surface junction has friction pad, and the thickness of friction pad is set as 5mm, and the outer surface of cupular part of operation platform 1 is provided with Herringbone convex block, since pressing has friction pad between sliding block 6 and sliding slot 5, so that there is certain rub between sliding block 6 and sliding slot 5 Power is wiped, construction personnel needs artificial external force to push built-in rod 8, so that sliding block 6 is slided along sliding slot 5, so that sliding block 6 exists Sliding is more stable in sliding slot 5, meanwhile, the herringbone convex block of 1 outer surface of coordinative construction platform strengthens the safety of whole device Property.
7 outer surface of fixed link is run through in one end of clamping screw 9, solid by clamping screw 9 between built-in rod 8 and fixed link 7 Fixed connection, 1 top of operation platform is equipped with bearing plate 10 close to positive side, and the upper and lower ends of bearing plate 10 pass through axis Bearing sleeve sets gear 12, is fixedly connected between bearing plate 10 and operation platform 1 by fixed screw, so that bearing plate 10 and construction are flat The assembling easy to disassemble of platform 1, the outer surface of gear 12 are enclosed with belt 11, and one end of crank hand 13 is solid through bearing plate 10 and bearing Fixed connection, the outer surface of gear 12 are welded with double wedge, and 11 inner wall of belt is provided with concave tooth and double wedge is intermeshed, bearing plate 10 and operation platform 1 front position at be provided with preformed hole, fixing clamp 14 is welded in built-in rod 8 and belt 11, and Fixing clamp 14 is provided with three groups, and the fixing clamp 14 on belt 11 in being staggered up and down, and construction personnel by shaking crank manually Hand 13, crank hand 13 are rotated by bearing band moving gear 12, and the intermeshing of gear 12 and belt 11, cooperation is staggered up and down Fixing clamp 14, reduce the stubborn situation of the artificial hand of construction material, construction personnel given to mitigate trouble.
Working principle: before work, whole device is lain in ground by construction personnel, and the first expansion bracket 41 and second are stretched Frame 43 extracts suitable length out out of adjusting set 42, and tightens adjusting screw, by the first expansion bracket 41, the second expansion bracket 43 and adjusts Section set 42 is fixed locked, and while adjusting, the first expansion bracket 41 drives 1 two sides main backstop 2 of operation platform, passes through articulated shaft It is opened to two sides, adjusts 2 angle of main backstop by adjusting secondary 4 length of support frame device, after waiting adjustment proper angle, construction Bearing plate 10 is fixed at the front position of operation platform 1 by personnel by fixed screw, and last construction personnel is whole by what is done well A device erects, and rides at the wall locations for preparing painting.
When preparation, construction personnel will be arranged construction material in fixing clamp 14, when construction personnel rides on horizontal pedal 15 Onto operation platform 1, construction personnel is hand-held built-in rod 8 is retracted to suitable height out of fixed link 7 after, tighten clamping screw 9, after fixed link 7 and built-in rod 8 are fixed, construction personnel shakes crank hand 13 clockwise manually, and crank hand 13 passes through bearing band Moving gear 12 rotates clockwise, so that the belt 11 engaged with gear 12 rotates clockwise, so that 11 bottom of belt is consolidated Clamp 14 drives construction material vertically upward, waits when rising to construction personnel's hand and can take, stops shaking, construction personnel will build Material takes out out of fixing clamp 14, and in the fixing clamp 14 being placed in built-in rod 8, and and then, construction personnel one hand steered Built-in rod 8, another hand hold painting and carry out painting work to metope, when construction personnel is mobile, due to sliding block 6 and sliding slot 5 Between pressing have friction pad so that there are certain frictional force between sliding block 6 and sliding slot 5, construction personnel needs artificial outer pushes Dynamic built-in rod 8, so that sliding block 6 is slided along sliding slot 5, after waiting construction materials brush complete, the construction material that construction personnel will brush, In the fixing clamp 14 for taking out, and being placed on belt 11 out of fixing clamp 14 in built-in rod 8, crank is shaken counterclockwise with defensive position 11 bottom of belt is got out new construction material vertical ascent by hand 13, after doing well such as aforesaid operations, continues the powder of construction personnel Dataller makees, and practicability is very high, and low manufacture cost, is suitable for large-scale productionization and uses.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case where without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.

Claims (6)

1. a kind of construction painting bracket, including operation platform (1), secondary support frame device (4), clamping screw (9) and shake Handle (13), it is characterised in that: the left and right sides of the operation platform (1) is hinged with main backstop (2), and main backstop (2) it is welded at the position between horizontal pedal (15), the middle position of operation platform (1) bottom is welded with welding block (3), one end and welding block (3) of the secondary support frame device (4) are articulated and connected, the other end of the pair support frame device (4) It is articulated and connected with wherein one group horizontal pedal (15), operation platform (1) the top outer surface is opened at a side position at back If sliding slot (5), and the inside of sliding slot (5) is embedded with sliding block (6), is welded with fixed link (7) at the top of the sliding block (6), and solid The inside of fixed pole (7) is inserted with built-in rod (8), and fixed link (7) outer surface is run through in one end of the clamping screw (9), described interior It sets and is fixedly connected between bar (8) and fixed link (7) by clamping screw (9), close to positive one at the top of the operation platform (1) Side is equipped with bearing plate (10), and the upper and lower ends of bearing plate (10) pass through bearing and are arranged gear (12), the gear (12) Outer surface be enclosed with belt (11), one end of the crank hand (13) is fixedly connected through bearing plate (10) with bearing.
2. a kind of construction according to claim 1 painting bracket, it is characterised in that: the pair support frame device It (4) include the first expansion bracket (41), adjusting set (42) and the second expansion bracket (43), one end of the adjusting set (42) is arranged with The other end of first expansion bracket (41), the adjusting set (42) is arranged with adjusting set (42), first expansion bracket (41), second It is fixedly connected between expansion bracket (43) and adjusting set (42) by adjusting screw.
3. a kind of construction according to claim 1 painting bracket, it is characterised in that: the sliding slot (5) and sliding block (6) contact surface junction pressing has a friction pad, and the thickness of friction pad is set as 5mm, outside the top of the operation platform (1) Surface is provided with herringbone convex block.
4. a kind of construction according to claim 1 painting bracket, it is characterised in that: the bearing plate (10) and apply It is provided with preformed hole at the front position of work platform (1), passes through fixed spiral shell between the bearing plate (10) and operation platform (1) Silk is fixedly connected.
5. a kind of construction according to claim 1 painting bracket, it is characterised in that: the built-in rod (8) and skin It is welded with fixing clamp (14) on band (11), and fixing clamp (14) is provided with three groups, the fixing clamp (14) on the belt (11) In being staggered up and down.
6. a kind of construction according to claim 1 painting bracket, it is characterised in that: the appearance of the gear (12) Face is welded with double wedge, and belt (11) inner wall is provided with concave tooth and double wedge is intermeshed.
CN201910076992.9A 2019-01-27 2019-01-27 A kind of construction painting bracket Pending CN109881868A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910076992.9A CN109881868A (en) 2019-01-27 2019-01-27 A kind of construction painting bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910076992.9A CN109881868A (en) 2019-01-27 2019-01-27 A kind of construction painting bracket

Publications (1)

Publication Number Publication Date
CN109881868A true CN109881868A (en) 2019-06-14

Family

ID=66927096

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910076992.9A Pending CN109881868A (en) 2019-01-27 2019-01-27 A kind of construction painting bracket

Country Status (1)

Country Link
CN (1) CN109881868A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112112410A (en) * 2020-09-10 2020-12-22 浙江可久建筑工程有限公司 Liftable building construction platform

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112112410A (en) * 2020-09-10 2020-12-22 浙江可久建筑工程有限公司 Liftable building construction platform

Similar Documents

Publication Publication Date Title
CN206632817U (en) A kind of metal pipe material sanding apparatus
CN109881868A (en) A kind of construction painting bracket
CN106122196A (en) The fixing device that a kind of serviceability is strong
CN207288445U (en) A kind of decorative panel for building double-side efficient apparatus for shaping
CN109296917A (en) A kind of mobile phone self-shooting bar
CN210961887U (en) Special oral cavity inspection device's of department of stomatology telescopic bracket
CN207033324U (en) A kind of step ladder for house ornamentation
CN108789314A (en) A kind of intermetallic composite coating internal stress adjusting platform fixed equipment
CN104482375A (en) Fixing device for adjusting AP installing angle
CN106246094A (en) A kind of novel mounting attachment and using method thereof
CN203945870U (en) A kind of Portable movable foldable formula blackboard
CN216527782U (en) Safety warning sign is used in multi-use architecture construction
CN207063275U (en) A kind of attachment structure of frame top plate and stile
CN209924394U (en) Painting frame for constructional engineering
CN205584071U (en) Quick assembly disassembly solar cell panel fixed knot constructs
CN208681539U (en) A kind of intermetallic composite coating internal stress adjusting platform fixed equipment
CN112520629A (en) Building frame integrating weight lifting function
CN209573950U (en) Multifunctional foldable computer chair frame assembly, multifunctional foldable computer chair
CN207314780U (en) A kind of extension type construction platform
CN207812975U (en) A kind of Novel herringbone ladder
CN104847063A (en) Electric folding attic staircase
CN210254931U (en) Pipeline welding pipeline positioning device
CN206017344U (en) A kind of strong fixing device of performance
CN208363577U (en) A kind of climbing frame bottom slide rail type facilitates the walkway board of connection
CN210918475U (en) Telescopic aluminum alloy rail guard is used in bridge construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190614