CN109861385A - Secondary device soft pressing plate anti-misoperation locking design method - Google Patents

Secondary device soft pressing plate anti-misoperation locking design method Download PDF

Info

Publication number
CN109861385A
CN109861385A CN201811490363.2A CN201811490363A CN109861385A CN 109861385 A CN109861385 A CN 109861385A CN 201811490363 A CN201811490363 A CN 201811490363A CN 109861385 A CN109861385 A CN 109861385A
Authority
CN
China
Prior art keywords
pressing plate
secondary device
soft pressing
device soft
error
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811490363.2A
Other languages
Chinese (zh)
Inventor
徐贵清
郑开玮
陈勇
孙云东
李国源
陈晓旭
刘书玉
南亚楠
孙建刚
张耀心
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201811490363.2A priority Critical patent/CN109861385A/en
Publication of CN109861385A publication Critical patent/CN109861385A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/16Electric power substations

Abstract

The invention discloses a kind of secondary device soft pressing plate anti-misoperation locking design methods comprising following steps: 1) implementing to improve to anti-error management software on original interface basis, secondary device soft pressing plate virtual knob is added in primary equipment interval;2) primary equipment grid switching operation logical order is combined, establishment includes the anti-error logical formula of secondary device soft pressing plate;3) the anti-error program of secondary device soft pressing plate is write according to above-mentioned logical formula;4) simulation grid switching operation is carried out in substation field, debugs anti-misoperation locking program;5) online monitoring system and the communication connection of microcomputer anti-error management software are debugged, it is ensured that anti-error management software and monitoring background data transfer real-time.Due to joined the anti mis-closedown function of secondary device soft pressing plate, in operation, each step has to pass through unlock verification to operation operator, even if the secondary device soft pressing plate for moving back other intervals can not be thrown by going to the wrong way interval, and then avoids misoperation fault.

Description

Secondary device soft pressing plate anti-misoperation locking design method
Technical field
The present invention relates to intelligent field of power transformation, especially a kind of secondary device soft pressing plate anti-misoperation locking design method.
Background technique
110 kilovolts are put into operation in family, station, fort in 2015, are put into operation so far, two classes of the power transformation O&M warps by multiple grid switching operation It goes through, finds the station secondary device soft pressing plate anti-misoperation locking existing defects, anti-error management software only includes primary equipment, secondary device Soft pressing plate is not incorporated into anti-misoperation locking, and when remote operation is implemented at online monitoring system interface, secondary device soft pressing plate lacks anti- Accidentally verify.When running operator's operation secondary device soft pressing plate, once interval is gone to the wrong way, miscarrying/accidentally move back other interval secondaries Equipment soft pressing plate will lead to relevant device and be failure to actuate or malfunction, causes misoperation fault.
Summary of the invention
A kind of can be avoided is provided and is occurred because of maloperation it is an object of the invention to solve above-mentioned technical problem The secondary device soft pressing plate anti-misoperation locking design method of leapfrog accident.
In order to solve the above-mentioned technical problem, the present invention adopts the following technical scheme:
A kind of secondary device soft pressing plate anti-misoperation locking design method, includes the following steps:
1) anti-error management software is implemented to improve on original interface basis, secondary device is added in primary equipment interval Soft pressing plate virtual knob;
2) it consults substation field and runs dedicated regulation, in conjunction with primary equipment grid switching operation logical order, establishment includes two The anti-error logical formula of secondary device soft pressing plate;
3) the anti-error program of secondary device soft pressing plate is write according to above-mentioned logical formula;
4) simulation grid switching operation is carried out in substation field, debugs anti-misoperation locking program;
5) online monitoring system and the communication connection of microcomputer anti-error management software are debugged, it is ensured that after anti-error management software and monitoring Number of units is according to transmission real-time.
The beneficial effects of the present invention are: the completion of this work, realizes in the secondary soft pressing plate five-defence block function in family, station, fort Can, system can 2441 bus connection switch of normal occlusion in the case of formerly exiting secondary soft pressing plate.The case where not exiting secondary soft pressing plate Under, the failure of 2441 bus connection switches is closed in five anti-alarms.Due to joined the anti mis-closedown function of secondary device soft pressing plate, operation operation In operation, each step has to pass through unlock verification to personnel, moves back the secondary of other intervals even if going to the wrong way interval and can not throw Equipment soft pressing plate, and then avoid misoperation fault.
Detailed description of the invention
Fig. 1 is schematic diagram before secondary device soft pressing plate anti-misoperation locking installs additional;
Fig. 2 is schematic diagram after secondary device soft pressing plate anti-misoperation locking installs additional.
Specific embodiment
The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments:
Referring to Fig. 1 and Fig. 2, secondary device soft pressing plate anti-misoperation locking design method of the invention, includes the following steps:
1. implementing to improve to anti-error management software on original interface basis, it is soft that secondary device is added in primary equipment interval Pressing plate virtual knob.
2. consulting substation field runs dedicated regulation, in conjunction with primary equipment grid switching operation logical order, establishment includes two The anti-error logical formula of secondary device soft pressing plate.
2012 Switching Conditions: 2012 trolleies push-in are pulled open, 2011 switches disconnect, and 2441 switches close, 2441 trolleies push-in, 2022 switches close, 2022 trolleies push-in, and 2441 segmentation prepared auto restart soft pressing plates exit, and 2012,2021 outlet soft pressing plates exit; 2012 trolleies push-in, 2011 switches disconnect, and 2441 switches close, and 2441 trolleies push-in, 2021 switches close, and 2021 trolleies push away Enter, 2441 segmentation prepared auto restart soft pressing plates exit, and 2012,2021 outlet soft pressing plates exit.
3. the anti-error program of secondary device soft pressing plate is write according to above-mentioned logical formula, by taking 2441 bus connection switches as an example, half When the interruption maintenance of face, it only 2441 prepared auto restart pressing plates, 2441 from throw jump 2012 pressing plates and 2021 pressing plates and exit in the case where, It could operate.
Y2441-1H:{ } | 1 | 2441=00!
Y2441-1L:{ } | 1 | 2441=00+2441=01 (2012=00+2021=00)!
Y2441-2H:{}|1|!
Y2441-2L:{}|1|!
Y2441-3H:{ } | 1 | 2441=00!
Y2441-3L:{ } | 1 | 2441=00+2441=01 (2012=00+2021=00)!
Y2441-4H:{ } | 1 | 2441=00!
Y2441-4L:{ } | 1 | 2441=00+2441=01 (2012=00+2021=00)!
4. group member carries out simulation grid switching operation in substation field for the validity of proving program, we continue By taking 2441 bus connection switches as an example, at the end of demifacet interruption maintenance, correct operating process is first to exit 2441 bus connection switches, then 2441 related secondary soft pressing plates are thrown again.In the case where 2441 bus connection switches do not disconnect, it is related secondary soft that we directly throw 2441 Secondary soft pressing plate failure is thrown in pressing plate, at this time five anti-alarm.
5. debugging online monitoring system and the communication connection of microcomputer anti-error management software, it is ensured that after anti-error management software and monitoring Number of units is according to transmission real-time.
Primary equipment anti-misoperation locking principle is used for reference, the logical formula of secondary device soft pressing plate is worked out, in original anti-error pipe It manages on basis of software, the anti mis-closedown function of secondary device soft pressing plate is added, avoids the leapfrog accident occurred because of maloperation.
In conclusion the contents of the present invention are not limited in the above embodiments, those skilled in the art can be It is proposed other embodiments within technological guidance's thought of the invention, but these embodiments be included in the scope of the present invention it It is interior.

Claims (1)

1. a kind of secondary device soft pressing plate anti-misoperation locking design method, which comprises the steps of:
1) anti-error management software is implemented to improve on original interface basis, the soft pressure of secondary device is added in primary equipment interval Plate virtual knob;
2) it consults substation field and runs dedicated regulation, in conjunction with primary equipment grid switching operation logical order, establishment is set comprising secondary The anti-error logical formula of standby soft pressing plate;
3) the anti-error program of secondary device soft pressing plate is write according to above-mentioned logical formula;
4) simulation grid switching operation is carried out in substation field, debugs anti-misoperation locking program;
5) online monitoring system and the communication connection of microcomputer anti-error management software are debugged, it is ensured that number of units after anti-error management software and monitoring According to transmission real-time.
CN201811490363.2A 2018-12-06 2018-12-06 Secondary device soft pressing plate anti-misoperation locking design method Pending CN109861385A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811490363.2A CN109861385A (en) 2018-12-06 2018-12-06 Secondary device soft pressing plate anti-misoperation locking design method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811490363.2A CN109861385A (en) 2018-12-06 2018-12-06 Secondary device soft pressing plate anti-misoperation locking design method

Publications (1)

Publication Number Publication Date
CN109861385A true CN109861385A (en) 2019-06-07

Family

ID=66890721

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811490363.2A Pending CN109861385A (en) 2018-12-06 2018-12-06 Secondary device soft pressing plate anti-misoperation locking design method

Country Status (1)

Country Link
CN (1) CN109861385A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10649581B1 (en) 2011-08-05 2020-05-12 P4tents1, LLC Devices, methods, and graphical user interfaces for manipulating user interface objects with visual and/or haptic feedback
CN114826965A (en) * 2022-04-14 2022-07-29 国电南瑞科技股份有限公司 Monitoring system reconstruction and extension do not disturb method based on plant station side panoramic data

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107546854A (en) * 2017-09-12 2018-01-05 国家电网公司 Transformer station's pressing plate method for preventing misoperation and device
CN107591892A (en) * 2017-08-07 2018-01-16 许继集团有限公司 A kind of intelligent substation O&M method and system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107591892A (en) * 2017-08-07 2018-01-16 许继集团有限公司 A kind of intelligent substation O&M method and system
CN107546854A (en) * 2017-09-12 2018-01-05 国家电网公司 Transformer station's pressing plate method for preventing misoperation and device

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
卜强生: "智能变电站继电保护软压板防误操作策略及实现", 《电力自动化设备》 *
铁道部劳动和卫生司编: "《高速铁路变配电设备检修岗位》", 31 October 2012, 中国铁道出版社 *
陈勇等: "基于分段开关保护误动的事故分析及对策", 《电子技术与软件工程》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10649581B1 (en) 2011-08-05 2020-05-12 P4tents1, LLC Devices, methods, and graphical user interfaces for manipulating user interface objects with visual and/or haptic feedback
US10649580B1 (en) 2011-08-05 2020-05-12 P4tents1, LLC Devices, methods, and graphical use interfaces for manipulating user interface objects with visual and/or haptic feedback
US10656759B1 (en) 2011-08-05 2020-05-19 P4tents1, LLC Devices, methods, and graphical user interfaces for manipulating user interface objects with visual and/or haptic feedback
US10671213B1 (en) 2011-08-05 2020-06-02 P4tents1, LLC Devices, methods, and graphical user interfaces for manipulating user interface objects with visual and/or haptic feedback
US10788931B1 (en) 2011-08-05 2020-09-29 P4tents1, LLC Devices, methods, and graphical user interfaces for manipulating user interface objects with visual and/or haptic feedback
US10996787B1 (en) 2011-08-05 2021-05-04 P4tents1, LLC Gesture-equipped touch screen system, method, and computer program product
US11061503B1 (en) 2011-08-05 2021-07-13 P4tents1, LLC Devices, methods, and graphical user interfaces for manipulating user interface objects with visual and/or haptic feedback
US11740727B1 (en) 2011-08-05 2023-08-29 P4Tents1 Llc Devices, methods, and graphical user interfaces for manipulating user interface objects with visual and/or haptic feedback
CN114826965A (en) * 2022-04-14 2022-07-29 国电南瑞科技股份有限公司 Monitoring system reconstruction and extension do not disturb method based on plant station side panoramic data
CN114826965B (en) * 2022-04-14 2023-08-29 国电南瑞科技股份有限公司 Monitoring system reconstruction and expansion non-disturbance method based on panoramic data of plant station end

Similar Documents

Publication Publication Date Title
CN109617241B (en) Intelligent sequential control system and method based on panoramic data in transformer substation
CN101917056B (en) 220kV bus switch spare automatic switching method of 550kV station
CN103679350A (en) Power grid switching operation ticket automatic generating system and method
CN103022994B (en) Method for achieving fault isolation and recovery of power distribution network with permeability distribution type power supply
CN109861385A (en) Secondary device soft pressing plate anti-misoperation locking design method
CN109802355B (en) Method and device for preventing misoperation of relay protection soft pressing plate
CN105406603A (en) Power grid adjustment and control end anti-misoperation locking method
CN102447305A (en) Topological anti-misoperation system for power grid
CN101661283B (en) System for completing sequential control by intelligent one-key operation
CN108448718B (en) One-key sequential control method and system for intelligent substation protection device
CN108879663B (en) One-key sequence control method and system for electric power system with exception handling
WO2014059721A1 (en) Transition method for monitoring system modification process during intelligent modification of conventional substation
CN208596200U (en) A kind of novel power distribution network fault diagnostic device based on DSP and FPGA
CN205178647U (en) Relay protection of transformer substation intelligence clamp plate system
CN102868218A (en) Transition method for improving monitoring system in intelligent improvement of ordinary transformer substation
CN103475104A (en) Unlocking screen for misoperation-preventive locking system of integrated automation substation
CN106655508A (en) New remote checking method for transformer substation monitoring system improvement
CN105656202A (en) Measurement and control five-prevention operation device for reducing unlocking frequency of five-prevention system of substation
CN107944570B (en) Automatic processing method and device for intelligent substation sequential control atypical state
CN108471164B (en) Intelligent detection and alarm method and device for pressing plate of transformer protection device
CN114977486A (en) Anti-misoperation system and method for remote control soft pressing plate of combined intelligent substation
CN103105843B (en) A kind of anti-error check module for supervisory system
CN211428996U (en) Information, networking and intelligent power control system
CN113410907A (en) IES700 system-based intelligent linkage anti-misoperation locking method for monitoring remote control operation
CN209358241U (en) A kind of internal bridge stub protection adaptively throws the control circuit moved back

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190607