CN109853856A - 一种剪力墙钢筋间距控制施工工艺 - Google Patents

一种剪力墙钢筋间距控制施工工艺 Download PDF

Info

Publication number
CN109853856A
CN109853856A CN201811614251.3A CN201811614251A CN109853856A CN 109853856 A CN109853856 A CN 109853856A CN 201811614251 A CN201811614251 A CN 201811614251A CN 109853856 A CN109853856 A CN 109853856A
Authority
CN
China
Prior art keywords
spacing
steel bar
reinforcing steel
shear force
construction technology
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811614251.3A
Other languages
English (en)
Inventor
刘国栋
赵兵
李青松
张凤伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN XINYU BUILDING ENGINEERING Co Ltd
Original Assignee
TIANJIN XINYU BUILDING ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN XINYU BUILDING ENGINEERING Co Ltd filed Critical TIANJIN XINYU BUILDING ENGINEERING Co Ltd
Priority to CN201811614251.3A priority Critical patent/CN109853856A/zh
Publication of CN109853856A publication Critical patent/CN109853856A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

本发明提供了一种剪力墙钢筋间距控制施工工艺,剪力墙竖向钢筋间距采用定型卡具进行控制,剪力墙横向钢筋间距采用梯子筋进行控制。应用本发明的技术方案,能够有效的提高剪力墙钢筋间距的绑扎质量合格率,有效保证墙筋安装质量。

Description

一种剪力墙钢筋间距控制施工工艺
技术领域
本发明属于建筑钢筋定位技术领域,具体而言,涉及一种剪力墙钢筋间距控制施工工艺。
背景技术
钢筋偏位现象是建筑领域中的质量通病,对建筑物外观及混凝土结构有一定的影响,特别对于住宅楼,若出现钢筋偏位质量问题,有效截面变小,承载力降低,进而会对建筑物结构稳定性存在影响,是业主们关注的重点质量问题。
目前实施过程中采用的是竖向梯子筋和横向梯子筋来控制间距,但是主体施工过程中剪力墙钢筋间距的绑扎质量合格率较低,因此提出了本发明的施工工艺。
发明内容
本发明的主要目的在于提供一种剪力墙钢筋间距控制施工工艺,旨在提高剪力墙钢筋间距的绑扎质量合格率。
为了实现上述的目的,本发明提供了一种剪力墙钢筋间距控制施工工艺,剪力墙竖向钢筋间距采用定型卡具进行控制,剪力墙横向钢筋间距采用梯子筋进行控制。
更进一步的,所述竖向钢筋长度超过1m加设定型卡具。
更进一步的,所述竖向钢筋设置定型卡具沿墙均匀设置2道,且墙高超过3m的按照1m间距均匀设置,内墙两面设置,外墙只设置在墙内侧。
更进一步的,所述定型卡具设置后采用绑丝或者墙筋绑扎固定。
更进一步的,所述定型卡具材质采用Φb5冷拔丝。
更进一步的,所述横向钢筋长度在1m内的加设1道梯子筋,1-2.5m内加设2道梯子筋,2.5m以上或者2.5m以上的其余部分按照1m间距1道加设。
更进一步的,所述横向钢筋设置梯子筋距离暗柱边500mm设置第1道梯子筋,其余按照1m间距1道加设。
更进一步的,所述梯子筋主筋即为剪力墙主筋,与下层所甩剪力墙主筋绑扎搭接牢固。
应用本发明的技术方案,能够有效的提高剪力墙钢筋间距的绑扎质量合格率,有效保证墙筋安装质量。
附图说明
构成本申请的一部分的说明书附图用来提供对本发明的进一步理解,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。在附图中:
图1示意性示出了本发明实施过程的平面图;
图2示意性示出了本发明实施过程的立面图;
图3示意性示出了本发明实施过程的剖面图;
其中,上述附图包括以下附图标记:
1为定型卡具,2为梯子筋,3为暗柱。
具体实施方式
需要说明的是,在不冲突的情况下,本申请中的实施例及实施例中的特征可以相互组合。下面将参考附图并结合实施例来详细说明本发明。
应该指出,以下详细说明都是示例性的,旨在对本申请提供进一步的说明。除非另有指明,本文使用的所有技术和科学术语具有与本申请所属技术领域的普通技术人员通常理解的相同含义。
需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本申请的示例性实施方式。如在这里所使用的,除非上下文另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合。
需要说明的是,本申请的说明书和权利要求书及上述附图中的术语“第一”、“第二”等是用于区别类似的对象,而不必用于描述特定的顺序或先后次序。应该理解这样使用的数据在适当情况下可以互换,以便这里描述的本申请的实施方式例如能够以除了在这里图示或描述的那些以外的顺序实施。
此外,属于“包括”和“具有”以及他们的任何变形,意图在于覆盖不排他的包含,例如,包含了一系列步骤或单元的过程、方法、系统、产品、或设备不必限于清楚地列出的那些步骤或单元,而是可包括没有清楚地列出的或对于这些过程、方法、产品或设备固有的其它步骤或单元。
为了便于描述,在这里可以使用空间相对术语,如“在……之上”、“在……上方”、“在……上表面”、“上面的”等,用来描述如在图中所示的一个器件或特征与其他器件或特征的空间位置关系。应当理解的是,空间相对术语旨在包含除了器件在图中所描述的方位之外的在使用或操作中的不同方位。
例如,如果附图中的器件被倒置,则描述为“在其他器件或构造的上方”或“在其他器件或构造之上”的器件之后将被定位为“在其他器件或构造下方”或“在其他器件或构造之下”。因而,示例性术语“在……上方”可以包括“在……上方”和“在……下方”两种方位。该器件也可以其他不同定位旋转90度或处于其他方位,并且对这里所使用的空间相对描述作出相应解释。
参见图1至图3所示,本发明提供了一种剪力墙钢筋间距控制施工工艺,剪力墙竖向钢筋间距采用定型卡具1进行控制,剪力墙横向钢筋间距采用梯子筋2进行控制。
更进一步的,所述竖向钢筋长度超过1m加设定型卡具1。所述竖向钢筋设置定型卡具1沿墙均匀设置2道,且墙高超过3m的按照1m间距均匀设置,内墙两面设置,外墙只设置在墙内侧。所述定型卡具1设置后采用绑丝或者墙筋绑扎固定。
优选的,所述定型卡具1材质采用Φb5冷拔丝。
更进一步的,所述横向钢筋长度在1m内的加设1道梯子筋2,1-2.5m内加设2道梯子筋2,2.5m以上或者2.5m以上的其余部分按照1m间距1道加设。所述横向钢筋设置梯子筋2距离暗柱3边500mm设置第1道梯子筋2,其余按照1m间距1道加设。所述梯子筋2主筋即为剪力墙主筋,与下层所甩剪力墙主筋绑扎搭接牢。
以上所述仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。

Claims (8)

1.一种剪力墙钢筋间距控制施工工艺,其特征在于:剪力墙竖向钢筋间距采用定型卡具进行控制,剪力墙横向钢筋间距采用梯子筋进行控制。
2.如权利要求1所述的一种剪力墙钢筋间距控制施工工艺,其特征在于:所述竖向钢筋长度超过1m加设定型卡具。
3.如权利要求2所述的一种剪力墙钢筋间距控制施工工艺,其特征在于:所述竖向钢筋设置定型卡具沿墙均匀设置2道,且墙高超过3m的按照1m间距均匀设置,内墙两面设置,外墙只设置在墙内侧。
4.如权利要求3所述的一种剪力墙钢筋间距控制施工工艺,其特征在于:所述定型卡具设置后采用绑丝或者墙筋绑扎固定。
5.如权利要求1-4任一条所述的一种剪力墙钢筋间距控制施工工艺,其特征在于:所述定型卡具材质采用Φb5冷拔丝。
6.如权利要求1所述的一种剪力墙钢筋间距控制施工工艺,其特征在于:所述横向钢筋长度在1m内的加设1道梯子筋,1-2.5m内加设2道梯子筋,2.5m以上或者2.5m以上的其余部分按照1m间距1道加设。
7.如权利要求5所述的一种剪力墙钢筋间距控制施工工艺,其特征在于:所述横向钢筋设置梯子筋距离暗柱边500mm设置第1道梯子筋,其余按照1m间距1道加设。
8.如权利要求6所述的一种剪力墙钢筋间距控制施工工艺,其特征在于:所述梯子筋主筋即为剪力墙主筋,与下层所甩剪力墙主筋绑扎搭接牢固。
CN201811614251.3A 2018-12-27 2018-12-27 一种剪力墙钢筋间距控制施工工艺 Pending CN109853856A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811614251.3A CN109853856A (zh) 2018-12-27 2018-12-27 一种剪力墙钢筋间距控制施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811614251.3A CN109853856A (zh) 2018-12-27 2018-12-27 一种剪力墙钢筋间距控制施工工艺

Publications (1)

Publication Number Publication Date
CN109853856A true CN109853856A (zh) 2019-06-07

Family

ID=66892738

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811614251.3A Pending CN109853856A (zh) 2018-12-27 2018-12-27 一种剪力墙钢筋间距控制施工工艺

Country Status (1)

Country Link
CN (1) CN109853856A (zh)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020016464A (ko) * 2000-08-25 2002-03-04 신현준 외부마감 일체형 스틸스터드 벽체 조립시스템
CN1844605A (zh) * 2006-03-07 2006-10-11 朱秦江 复合保温隔热混凝土建筑钢筋精确定位系统及其施工方法
CN1936228A (zh) * 2006-03-07 2007-03-28 朱秦江 混凝土建筑钢筋精确定位系统及其施工方法
CN104088402A (zh) * 2014-07-21 2014-10-08 李红波 一种防止施工中竖向钢筋变形的结构及方法
CN105155853A (zh) * 2015-08-20 2015-12-16 中铁建大桥工程局集团第五工程有限公司 一种高层住宅楼钢筋混凝定位施工工艺
CN206873768U (zh) * 2017-06-22 2018-01-12 江苏宇辉住宅工业有限公司 竖向钢筋定位结构

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020016464A (ko) * 2000-08-25 2002-03-04 신현준 외부마감 일체형 스틸스터드 벽체 조립시스템
CN1844605A (zh) * 2006-03-07 2006-10-11 朱秦江 复合保温隔热混凝土建筑钢筋精确定位系统及其施工方法
CN1936228A (zh) * 2006-03-07 2007-03-28 朱秦江 混凝土建筑钢筋精确定位系统及其施工方法
CN104088402A (zh) * 2014-07-21 2014-10-08 李红波 一种防止施工中竖向钢筋变形的结构及方法
CN105155853A (zh) * 2015-08-20 2015-12-16 中铁建大桥工程局集团第五工程有限公司 一种高层住宅楼钢筋混凝定位施工工艺
CN206873768U (zh) * 2017-06-22 2018-01-12 江苏宇辉住宅工业有限公司 竖向钢筋定位结构

Similar Documents

Publication Publication Date Title
CN102713106B (zh) 用于加强和轻量化地板和屋顶框架的方法和装置
EP0119165A2 (de) Kragplattenanschlusselement
CN101958519B (zh) 一种双回路双分裂输电线路直线塔带电异地升高改造方法
CN109853856A (zh) 一种剪力墙钢筋间距控制施工工艺
CN105133854B (zh) 一种竖向构件的置换卸载结构及施工方法
US3102611A (en) Cellular floor construction
EP3437168A1 (de) Verfahren zur erweiterung der elektrischen übertragungskapazität eines freileitungsmastsystems
EP3040496A1 (en) Structure reinforcement system and method
CN102116058B (zh) 一种剪力墙结构叠合外墙l型连接节点
JP7222807B2 (ja) バスダクトの布設方法およびバスダクト構造体の構成方法
US3300912A (en) Hanger means for sheet metal sectional roofing and flooring
KR20190098599A (ko) 유공보용 강성보강 장치
US3197926A (en) Hanger means for sheet metal sectional roofing and flooring
CN210152311U (zh) 一种简易施工作业层电梯井道口临时防护装置
KR101186825B1 (ko) 철근콘크리트 유공보 보강장치
CN208088620U (zh) 一种混凝土楼板
CN113802754B (zh) 一种金属板吊顶及其施工方法
CN105152034B (zh) 用于斜屋顶幕墙的索道吊装系统
JP2020084562A (ja) 張弦梁構造体
CN213087215U (zh) 屋面钢梁混凝土柱排架装置
CN211369017U (zh) 索桁架大跨度通廊结构
CN107989201A (zh) 成品桥架预埋件
Kussman et al. Design example for beams with web openings
CN109695316A (zh) 定型化水泥砂浆垫块及控制现浇楼板厚度的施工工艺
Nizamani et al. Reinforced Concrete Buildings with Plane Frame, Shear Wall with and without Openings

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190607