CN109830897A - Assemblied distribution - Google Patents

Assemblied distribution Download PDF

Info

Publication number
CN109830897A
CN109830897A CN201910212075.9A CN201910212075A CN109830897A CN 109830897 A CN109830897 A CN 109830897A CN 201910212075 A CN201910212075 A CN 201910212075A CN 109830897 A CN109830897 A CN 109830897A
Authority
CN
China
Prior art keywords
power distribution
distribution cabinet
fire hydrant
fixed
copper sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910212075.9A
Other languages
Chinese (zh)
Other versions
CN109830897B (en
Inventor
奚正华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG GUANGRUI ELECTRIC POWER TECHNOLOGY Co.,Ltd.
Original Assignee
奚正华
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 奚正华 filed Critical 奚正华
Priority to CN201910212075.9A priority Critical patent/CN109830897B/en
Publication of CN109830897A publication Critical patent/CN109830897A/en
Application granted granted Critical
Publication of CN109830897B publication Critical patent/CN109830897B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a kind of assemblied distributions, including the power distribution cabinet for pouring the fire hydrant being fixed on ground He being set to fire hydrant upper end, the fire hydrant is equipped with a fixture, fixture includes the first arc panel and the second arc panel, one piece of installation by adhering or more of the first copper sheet on the inner wall of second arc panel, the outside wall surface of second arc panel, which is right against at the first copper sheet, is equipped with a through-hole, one metal tube of installation is welded and fixed outside through-hole, one or more copper wire is equipped in metal tube, copper wire one end is respectively mounted one second copper sheet, the copper wire other end is both secured on the first copper sheet, a pipeline is cased with outside power distribution cabinet.The configuration of the present invention is simple, it can be directly fixed on fire hydrant, without prior joints cement, increase installation effectiveness and speed, and the heat inside power distribution cabinet can be transmitted on fire hydrant, and be taken away by the water inside fire hydrant, and radiating rate is considerably increased, effectively fire hydrant can be covered simultaneously, avoid getting rusty for fire hydrant.

Description

Assemblied distribution
Technical field
The present invention relates to a kind of assemblied distributions.
Background technique
Power distribution cabinet (case) sub-power power distribution cabinet (case) and light distribution cabinet (case), metering cabinet (case), are the ends of distribution system Grade equipment.Power distribution cabinet is the general designation of motor control center.Power distribution cabinet is used in the occasion that load is more dispersed, circuit is less; The occasion that motor control center concentrates for load, circuit is more.Their electric energy a certain circuit of upper level controller switching equipment Distribute to nearest load.This grade of equipment reply load provides protection, monitoring and control.
Currently, being installed on extraneous power distribution cabinet during installation, the casting concrete pedestal on bottom surface in advance is needed, in coagulation After native pedestal is cooling, then by bolt power distribution cabinet is fixed on pedestal, this just needs to consume a large amount of time, causes assembly effect The reduction of rate, and power distribution cabinet can generate a large amount of heat at work, once heat is excessive, it will cause internal electron parts Quick aging influences service life.
Summary of the invention
It is easy to use technical problem to be solved by the invention is to provide a kind of structure is simple, fire-fighting can be directly fixed on On bolt, it is not necessarily to prior joints cement, increases installation effectiveness and speed, and the heat inside power distribution cabinet can be transmitted to fire hydrant On, and taken away by the water inside fire hydrant, radiating rate is considerably increased, while can effectively cover fire hydrant, avoided Fire hydrant gets rusty, and facilitates opening fire hydrant, for the assemblied distribution for winning speed of putting out a fire.
The present invention is achieved through the following technical solutions: a kind of assemblied distribution, including pours and be fixed on ground On fire hydrant and be set to the power distribution cabinet of fire hydrant upper end, the fire hydrant is equipped with a fixture, and fixture includes the first arc Plate and the second arc panel, one piece of installation by adhering or more of the first copper sheet on the inner wall of the second arc panel, the first copper sheet The outside wall surface of inner wall and fire hydrant offsets, and the outside wall surface of the second arc panel, which is right against at the first copper sheet, is equipped with a through-hole, leads to One metal tube of installation is welded and fixed outside hole, the bottom surface that metal tube upper end both passes through power distribution cabinet extends to inside power distribution cabinet, gold Belong to and being welded and fixed between pipe and power distribution cabinet, one or more copper wire is equipped in metal tube, copper wire one end both passes through metal tube It extending to inside power distribution cabinet, and one second copper sheet of installation is welded and fixed, the second copper sheet is both secured on the inner wall of power distribution cabinet, The copper wire other end both passes through metal tube and through-hole, and is fixedly welded on the first copper sheet, and a pipeline, pipeline are cased with outside power distribution cabinet Cross section it is identical as the cross section of power distribution cabinet, lower end of duct is sheathed on outside fire hydrant, and installation is welded and fixed in power distribution cabinet upper end One framework, the two sides of framework are vertically equipped with a screw hole, and the top surface of pipeline is right against at screw hole embedded be welded and fixed One bearing is installed, a screw rod is threadedly coupled in screw hole, screw rod lower end is inserted into the inner ring of bearing, and is welded with inner ring Fixed, one handle of installation is welded and fixed in upper end.
The length of copper wire is different as a preferred technical solution, and more than one fixation is equipped on the second copper sheet Hole is equipped with a fixing bolt in fixation hole, and fixing bolt is both secured on the inner wall of power distribution cabinet.
As a preferred technical solution, on the inner wall of pipeline by seccotine be fixedly mounted one first rubber layer, first The inner wall of rubber layer and the outside wall surface of power distribution cabinet offset.
One second rubber layer is fixedly mounted by seccotine on the end face of lower end of duct as a preferred technical solution, the The bottom surface of two rubber layers offsets with ground.
A fixed part, the first, second arc are equipped on the both ends of the first, second arc panel as a preferred technical solution, It offsets between fixed part between shape plate, and is cooperated by screw bolt and nut and fixed.
A telescopic is cased on screw rod as a preferred technical solution, flexible set upper side is fixed on by seccotine On the bottom surface of framework, lower end passes through seccotine and is fixed on the top surface of pipeline.
The sealing bottom surface setting of power distribution cabinet as a preferred technical solution, has between power distribution cabinet and fire hydrant for tool By distance.
The beneficial effects of the present invention are: the configuration of the present invention is simple, easy to use, it can be directly fixed on fire hydrant, be not necessarily to Prior joints cement increases installation effectiveness and speed, and the heat inside power distribution cabinet can be transmitted on fire hydrant, and by fire-fighting Water inside bolt is taken away, and considerably increases radiating rate, while can effectively cover fire hydrant, avoids the life of fire hydrant Rust, facilitates opening fire hydrant, wins speed for fire fighting.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with It obtains other drawings based on these drawings.
Fig. 1 is overall structure diagram of the invention;
Fig. 2 is the structural schematic diagram of the second arc panel in the present invention;
Fig. 3 is the structural schematic diagram of the second copper sheet in the present invention.
Specific embodiment
As shown in Figure 1, Figure 2 and Figure 3, this assemblied distribution, including pouring the fire hydrant 17 being fixed on ground and setting It is placed in the power distribution cabinet 1 of 17 upper end of fire hydrant, the fire hydrant 17 is equipped with a fixture, and fixture includes the first arc panel 12 and second Arc panel 11, one piece of installation by adhering or more of the first copper sheet 14 on the inner wall of the second arc panel 11, the first copper sheet 14 The outside wall surface of inner wall and fire hydrant 17 offsets, and the outside wall surface of the second arc panel 11 is right against at the first copper sheet 14 that be equipped with one logical One metal tube 8 of installation is welded and fixed outside through-hole 15 for hole 15, and the bottom surface that 8 upper end of metal tube both passes through power distribution cabinet 1, which extends to, matches It inside electric cabinet 1, is welded and fixed between metal tube 8 and power distribution cabinet 1, one or more copper wire 6, copper wire 6 is equipped in metal tube 8 One end both passes through metal tube 8 and extends to inside power distribution cabinet 1, and one second copper sheet 10 of installation is welded and fixed, and the second copper sheet 10 is It is fixed on the inner wall of power distribution cabinet 1,6 other end of copper wire both passes through metal tube 8 and through-hole 15, and is fixedly welded on the first copper sheet On 14, a pipeline 7 is cased with outside power distribution cabinet 1, the cross section of pipeline 7 is identical as the cross section of power distribution cabinet 1, and 7 lower end of pipeline is arranged Outside fire hydrant 17, one framework 3 of installation is welded and fixed in 1 upper end of power distribution cabinet, and the two sides of framework 3 are vertically equipped with a screw hole, The top surface of pipeline 7 is right against at screw hole embedded be welded and fixed and installs a bearing 5, is threadedly coupled a screw rod in screw hole 4,4 lower end of screw rod is inserted into the inner ring of bearing 5, and is welded and fixed with inner ring, and one handle 2 of installation is welded and fixed in upper end.
In the present embodiment, the length of copper wire 6 is different, and more than one fixation hole 13 is equipped on the second copper sheet 10, A fixing bolt is equipped in fixation hole 13, fixing bolt is both secured on the inner wall of power distribution cabinet 1, effectively by the second copper sheet It is fixed on the inner wall of power distribution cabinet, makes on the inner wall of the second copper sheet and power distribution cabinet offseting always.
In the present embodiment, one first rubber layer 18, the first rubber layer are fixedly mounted by seccotine on the inner wall of pipeline 7 The outside wall surface of 18 inner wall and power distribution cabinet 1 offsets, and increases leakproofness by the first rubber layer.
In the present embodiment, one second rubber layer 9, the second rubber are fixedly mounted by seccotine on the end face of 7 lower end of pipeline The bottom surface of layer 9 offsets with ground, moves down in pipeline, can increase by the second rubber layer of lower end of duct close by screw rod Feng Xing.
In the present embodiment, a fixed part, the first, second arc panel are equipped on the both ends of the first, second arc panel 12,11 12, it offsets between the fixed part between 11, and passes through screw bolt and nut cooperation and fix.
In the present embodiment, a telescopic is cased on screw rod 4, flexible set upper side passes through seccotine and is fixed on framework 3 On bottom surface, lower end passes through seccotine and is fixed on the top surface of pipeline 7, and telescopic is made of rubber material, passes through telescopic energy Effectively screw rod is covered, increases the service life of screw rod.
In the present embodiment, the sealing bottom surface of power distribution cabinet 1 is arranged, and has between power distribution cabinet 1 and fire hydrant 17 and passes through for tool Distance, enable workpiece to extend to the top of fire hydrant, and rotate the switch on fire hydrant.
Wherein, the bottom surface of pipeline is equipped with an arc port passed through for installation pipe, the bottom opening of arc port, power distribution cabinet Bottom surface on the installation pipe of installation one or more is welded and fixed, the L-shaped structure setting of installation pipe, installation pipe one end passes through arc Mouth extends to the external world, so that the movement of pipeline will not influence installation pipe.
Working principle: since fire hydrant is made of metal material, so that heat-conducting effect is preferable, so that the heat in power distribution cabinet It can be transmitted to along copper wire on the first copper sheet, the heat on the first copper sheet can be then transmitted in the outside wall surface of fire hydrant, fire hydrant Heat in outside wall surface can then be taken away by the water inside fire hydrant, to greatly increase the heat-transfer rate of power distribution cabinet.
During installation, the first, second arc panel is clipped on fire hydrant, and passes through screw bolt and nut for the first, second arc Shape board clamping can effectively be fixed power distribution cabinet by fixture, and power distribution cabinet is made to be located at fire hydrant upper end, and metallic rod therein is branch Support member effectively withstands power distribution cabinet, facilitates installation and removal.
Effectively fire hydrant can be covered by pipeline, extraneous rainwater is avoided and contacted with fire hydrant, avoid fire-fighting Bolt gets rusty, and facilitates fire hydrant subsequent use, when using fire hydrant, rotates handle, the rotation of handle has driven spiral shell Bar rises screw rod along screw hole, and the movement of screw rod has driven pipeline, can be effectively by distribution by the pipeline moved up Thermovent on cabinet is blocked, and also fire hydrant is enable to be exposed at the external world, to not influence the use of fire hydrant.
The beneficial effects of the present invention are: the configuration of the present invention is simple, easy to use, it can be directly fixed on fire hydrant, be not necessarily to Prior joints cement increases installation effectiveness and speed, and the heat inside power distribution cabinet can be transmitted on fire hydrant, and by fire-fighting Water inside bolt is taken away, and considerably increases radiating rate, while can effectively cover fire hydrant, avoids the life of fire hydrant Rust, facilitates opening fire hydrant, wins speed for fire fighting.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any The change or replacement expected without creative work, should be covered by the protection scope of the present invention.Therefore, of the invention Protection scope should be determined by the scope of protection defined in the claims.

Claims (7)

1. a kind of assemblied distribution, it is characterised in that: including pouring the fire hydrant being fixed on ground and being set to fire hydrant The power distribution cabinet of upper end, the fire hydrant are equipped with a fixture, and fixture includes the first arc panel and the second arc panel, the second arc panel Inner wall on one piece of installation by adhering or more of the first copper sheet, the outside wall surface phase of the inner wall and fire hydrant of the first copper sheet It supports, the outside wall surface of the second arc panel, which is right against at the first copper sheet, is equipped with a through-hole, and one gold medal of installation is welded and fixed outside through-hole Belong to pipe, the bottom surface that metal tube upper end both passes through power distribution cabinet extends to inside power distribution cabinet, and welding is solid between metal tube and power distribution cabinet It is fixed, one or more copper wire is equipped in metal tube, copper wire one end both passes through metal tube and extends to inside power distribution cabinet, and welds One second copper sheet is fixedly mounted, the second copper sheet is both secured on the inner wall of power distribution cabinet, the copper wire other end both pass through metal tube and Through-hole, and be fixedly welded on the first copper sheet, a pipeline, the cross section of pipeline and the cross section of power distribution cabinet are cased with outside power distribution cabinet Identical, lower end of duct is sheathed on outside fire hydrant, and one framework of installation is welded and fixed in power distribution cabinet upper end, and the two sides of framework are vertically set There is a screw hole, the top surface of pipeline is right against at screw hole embedded be welded and fixed and installs a bearing, equal screw thread in screw hole A screw rod is connected, screw rod lower end is inserted into the inner ring of bearing, and is welded and fixed with inner ring, and installation one is welded and fixed in upper end Handle.
2. assemblied distribution according to claim 1, it is characterised in that: the length of copper wire is different, the second copper sheet On be equipped with more than one fixation hole, a fixing bolt is equipped in fixation hole, fixing bolt is both secured to the interior of power distribution cabinet On wall surface.
3. assemblied distribution according to claim 1, it is characterised in that: fixed on the inner wall of pipeline by seccotine One first rubber layer is installed, the inner wall of the first rubber layer and the outside wall surface of power distribution cabinet offset.
4. assemblied distribution according to claim 1, it is characterised in that: solid by seccotine on the end face of lower end of duct Dingan County fills one second rubber layer, and bottom surface and the ground of the second rubber layer offset.
5. assemblied distribution according to claim 1, it is characterised in that: be all provided on the both ends of the first, second arc panel There is a fixed part, offset between the fixed part between the first, second arc panel, and is cooperated by screw bolt and nut and fixed.
6. assemblied distribution according to claim 1, it is characterised in that: be cased with a telescopic, telescopic on screw rod Upper end passes through seccotine and is fixed on the bottom surface of framework, and lower end passes through seccotine and is fixed on the top surface of pipeline.
7. assemblied distribution according to claim 1, it is characterised in that: the sealing bottom surface of power distribution cabinet is arranged, power distribution cabinet Have at a distance from passing through for tool between fire hydrant.
CN201910212075.9A 2019-03-20 2019-03-20 Combined power distribution cabinet Active CN109830897B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910212075.9A CN109830897B (en) 2019-03-20 2019-03-20 Combined power distribution cabinet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910212075.9A CN109830897B (en) 2019-03-20 2019-03-20 Combined power distribution cabinet

Publications (2)

Publication Number Publication Date
CN109830897A true CN109830897A (en) 2019-05-31
CN109830897B CN109830897B (en) 2021-02-05

Family

ID=66870522

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910212075.9A Active CN109830897B (en) 2019-03-20 2019-03-20 Combined power distribution cabinet

Country Status (1)

Country Link
CN (1) CN109830897B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205883836U (en) * 2016-08-06 2017-01-11 广州锡杨电子有限公司 Industrial computer fan -less housing
CN206072972U (en) * 2016-09-26 2017-04-05 杭州富阳佳畅机械有限公司 A kind of safe LED street lamp
CN107318246A (en) * 2017-07-05 2017-11-03 滁州市立坤电器设备有限公司 A kind of Electric Appliance Cabinet of good cooling effect
CN207279482U (en) * 2017-08-25 2018-04-27 郑州大学 A kind of municipal administration multifunction energy-saving street lamp
CN108665915A (en) * 2018-05-03 2018-10-16 杨煜海 A kind of video disc player good with protection effect
CN208462223U (en) * 2018-08-07 2019-02-01 梅州科捷电路有限公司 A kind of water proof type single-layer printed circuit plate

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205883836U (en) * 2016-08-06 2017-01-11 广州锡杨电子有限公司 Industrial computer fan -less housing
CN206072972U (en) * 2016-09-26 2017-04-05 杭州富阳佳畅机械有限公司 A kind of safe LED street lamp
CN107318246A (en) * 2017-07-05 2017-11-03 滁州市立坤电器设备有限公司 A kind of Electric Appliance Cabinet of good cooling effect
CN207279482U (en) * 2017-08-25 2018-04-27 郑州大学 A kind of municipal administration multifunction energy-saving street lamp
CN108665915A (en) * 2018-05-03 2018-10-16 杨煜海 A kind of video disc player good with protection effect
CN208462223U (en) * 2018-08-07 2019-02-01 梅州科捷电路有限公司 A kind of water proof type single-layer printed circuit plate

Also Published As

Publication number Publication date
CN109830897B (en) 2021-02-05

Similar Documents

Publication Publication Date Title
CN109830897A (en) Assemblied distribution
CN212419997U (en) Novel welding wire molten pool stirring device
CN110880688B (en) Energy-saving outdoor distribution box based on electrical equipment
CN209419022U (en) A kind of outdoor water-proof control cabinet for power distribution
CN102646876A (en) Connecting structure of concrete electric pole and grounding wire
CN206195208U (en) Distribution box
CN211084505U (en) Prebaked anode carbon bowl water absorption device
CN204934591U (en) A kind of heatable jug used for heating up water and molten metal draw equipment
CN104191231B (en) Table top type micro-satellite quick general assembly operating board
CN208723476U (en) Flase floor threads protection pipe sub-assembly
CN104456765A (en) Air conditioner outdoor unit
CN209801754U (en) Air conditioner convenient to installation
CN210669381U (en) Large-span wire collecting bridge
CN206135252U (en) Distribution box
CN202601851U (en) Connecting structure between a concrete pole and a ground wire
CN205037572U (en) Magnesium stick mounting structure of water heater
CN209960895U (en) Elbow drying device
CN209958094U (en) Electric heating pipe reversely mounted on pulsator washing machine
CN213509646U (en) Multi-degree-of-freedom rotating device for concrete pouring gate
CN209133276U (en) A kind of support insulator drainage wire-connecting device
CN215541939U (en) Portable high-efficient electric room electric cleaning gun
CN211728516U (en) Novel water jet equipment of digit control machine tool processing usefulness
CN214528178U (en) Wall-mounted household water purifier fixing mechanism
CN212917611U (en) Slagging-off device for steelmaking
CN218169008U (en) Gantry type numerical control flame cutting machine with circulating cooling structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20210120

Address after: 5b, 5 / F, Lotte Gemini, no.6, Lotte Century City, Weihai Economic and Technological Development Zone, Shandong Province, 264200

Applicant after: SHANDONG GUANGRUI ELECTRIC POWER TECHNOLOGY Co.,Ltd.

Address before: 322112 No.23, Qianping, Shijing village, zuocan Town, Dongyang City, Jinhua City, Zhejiang Province

Applicant before: Xi Zhenghua

GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Combined power distribution cabinet

Effective date of registration: 20210618

Granted publication date: 20210205

Pledgee: Weihai Branch of China Merchants Bank Co.,Ltd.

Pledgor: SHANDONG GUANGRUI ELECTRIC POWER TECHNOLOGY Co.,Ltd.

Registration number: Y2021990000532

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20230811

Granted publication date: 20210205

Pledgee: Weihai Branch of China Merchants Bank Co.,Ltd.

Pledgor: SHANDONG GUANGRUI ELECTRIC POWER TECHNOLOGY Co.,Ltd.

Registration number: Y2021990000532