CN109826157A - A kind of cut-pff wall convenient for construction - Google Patents

A kind of cut-pff wall convenient for construction Download PDF

Info

Publication number
CN109826157A
CN109826157A CN201910140655.1A CN201910140655A CN109826157A CN 109826157 A CN109826157 A CN 109826157A CN 201910140655 A CN201910140655 A CN 201910140655A CN 109826157 A CN109826157 A CN 109826157A
Authority
CN
China
Prior art keywords
hydro
expansive rubber
rubber
expansive
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910140655.1A
Other languages
Chinese (zh)
Other versions
CN109826157B (en
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Yihui Construction Co., Ltd
Original Assignee
李敬文
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 李敬文 filed Critical 李敬文
Priority to CN201910140655.1A priority Critical patent/CN109826157B/en
Publication of CN109826157A publication Critical patent/CN109826157A/en
Application granted granted Critical
Publication of CN109826157B publication Critical patent/CN109826157B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same

Abstract

The present invention relates to a kind of cut-pff walls convenient for construction.Its technical solution is: including concrete wall, hydro-expansive rubber plate, top protection rubber sleeve, the concrete wall be externally provided with multiple hydro-expansive rubber board groups at water barrier, and concrete wall top be equipped with top protection rubber sleeve, the section of the concrete wall is that lower part uses trapezium structure, top uses rectangular parallelepiped structure, the hydro-expansive rubber plate gradually thinning structure from lower to upper.Beneficial effect is: based on the present invention utilizes armored concrete, carrying out antiseepage, damp proof using hydro-expansive rubber plate, the top protection of concrete wall is done using top protection rubber sleeve, achieve the purpose that protect armored concrete;The present invention frame structure can be tied by the reinforcing bar of armored concrete and hydro-expansive rubber plate built-in connection carries out gun iron link, is connected as one its protection with basis, and construction simplifies, and extends the service life of concrete dykes and dams significantly.

Description

A kind of cut-pff wall convenient for construction
Technical field
The present invention relates to a kind of cut-pff wall and method convenient for construction, in particular to a kind of concrete cuts.
Background technique
Cut-pff wall is that one kind is built in the ground diaphragm wall for playing antiseepage in loose pervious bed or earth and rockfill dam (weir), is answered extensively For dykes and dams, building aspect, bottom is embedded in certain depth in basement rock or opposite impervious stratum, can be truncated or reduce ground In infiltration water flow, to guarantee ground seepage stability and gate dam safety.Antiseepage wall technology is because its structure is reliable, anti-seepage effect Well, the advantages that all kinds of formation conditions, easy construction is adapted to, " stream soil ", " piping " are isotonic especially behind processing leakage of dam foundation, dam It works well on deformation potential problem, is at home and abroad widely used thoroughly.China's water conservancy and hydropower coating and native stone enclose There is a generally preferred cut-pff wall of the Anti-seeping technology of anti-consolidation pressure on weir etc., present cut-pff wall generally comprise normal concrete cut-pff wall, Armored concrete cut-pff wall, Clay-concrete cut-pff wall, plastic concrete cut-off wall and mortar cut-pff wall.Its there are the problem of It is: high stress problem of the concrete cut because of wall caused by high elastic modulus, plastic concrete cut-off wall intensity and impermeability It is lower, and durability is poor;Wall is generally partially thick, improves cost;Scene laying in construction site is excessive, the construction period is inclined It is long, larger to the disturbance of former dam body etc.;In addition, belonging to inorganic mineral material by the concrete of cement setting, the stability of itself is very It is good.But concrete/reinforced concrete structure of practical engineering application be in the natural environment, will necessarily meet with many destructions because Element, such as winter can endure cold, and coastal cut-pff wall can (chlorine, which can penetrate into concrete, in seawater causes reinforcing bar to become rusty by sea water intrusion Erosion), in some Soils In The Regions containing sulfate or have acid rain can corrosion concrete, the service life of concrete can also be greatly reduced.
Moreover, concrete structure it is naturally occurring have many subtle capillary channels, subtle crack (being invisible to the naked eye) and Hole.Along with work progress is manual operation, there can be non-uniform situation of vibrating, will lead to honeycomb and hole formation.This The channel that a little hidden danger have just given water to enter concrete structure, water slowly leak via these capillary channels, crack, hole. It destroys reinforcing bar, destroy concrete.Water is most fearful to the corrosion of armored concrete.It is seeped by capillary channel, crack, hole Enter in concrete structure, the reinforcing bar in concrete structure is corroded, causes steel bar corrosion to expand and then destroy concrete knot Structure, and then generate bigger crack.Crack increases, and water increases, and corrodes peace that is also just more severe, and then destroying cut-pff wall entirety Quan Xing causes cut-pff wall to scrap or occur serious safety accident.
Chinese patent literature Publication No. 105951857B, patent name are the " composite anti-penetrating for water conservancy project coffering Wall and its construction method ", it is fast which provides a kind of speed of application, good seepage-proof property, construction cost it is relatively low be used for water The compound impervious wall of work coffering.Compound impervious wall includes concrete cut ontology, soft organic barrier film and antiseepage Connection structure, the concrete cut ontology in cubic metre of earth and stone basis with it is described soft in the body of landfill cofferdam weir The connection that organic barrier film passes through the anti-seepage linkage antiseepage is an entirety.The construction method first pours coagulation Native guide groove, concrete cut pour, soft organic antiseepage transition film, the arrangement for determining support frame and rear pouring concrete Cover pouring of emitting.Itself the problem is that: since water directly contacts cut-pff wall, although design have soft organic antiseepage thin Film, but still effect is less desirable, causes the reduced service life of cut-pff wall.
Chinese patent literature Publication No. 104746633A, patent name are " a kind of waterproof, seepage control metope ", comprising: first Brick wall body and the second brick wall body, first brick wall body are arranged in parallel in the side of the second brick wall body, and described first It is provided with gap between brick wall body and the second brick wall body, is filled with concrete structure, the concrete knot in the gap A waterproof layer is provided in structure, the waterproof layer is made of water-proof concrete and non-woven fabric net, and the non-woven fabric net dipping is solid Change among water-proof concrete, the non-woven fabric net is parallel with the first brick wall body.By the above-mentioned means, of the present invention Waterproof, seepage control metope, water-proof concrete are arranged in centre, strengthen the connection between the first brick wall body and the second brick wall body, Structure is stronger, and double-faced waterproofing, relative inexpensiveness, but its waterproof effect and not satisfactory.
Chinese patent literature Publication No. 103088786B, patent name are " cut-pff wall and its construction method ", the present invention It is flexibly connected by more piece barrier sheet, the barrier sheet is anti-rot plastic plate, and barrier sheet is by mainboard and set on mainboard two sides Connection flanging and connection folding ear are provided with a machine template in mainboard bottom and mount slot, and the barrier sheet flexible connection refers to adjacent Two section barrier sheets are wedging connections, i.e. the connection flanging of later section barrier sheet is plugged in the connection folding ear of previous section barrier sheet. Antiseepage wall construction of the present invention is simple, easy for construction, cheap, using the poles such as polyethylene or polypropylene anticorrosive material, service life It is extremely long and strong due to using being flexibly connected, adapting to resistance to shear of soil deformability between each section barrier sheet, it will not cracked thing Therefore cost performance is very high.It is suitble to the sub-bottom changes of rivers,lakes and seas reservoir, is also suitble to the Anti-seeping technology of soil property building.Existing for it Problem is: still there may be the hidden danger of leak for anti-rot plastic plate, moreover, the interface of multiple anti-rot plastic plates is inevitably The case where leaking, time have grown the lost of life for still resulting in concrete wall.
Summary of the invention
The purpose of the present invention is to drawbacks described above of the existing technology, provide a kind of cut-pff wall convenient for construction, It is combined together using hydro-expansive rubber plate with concrete, and hydro-expansive rubber plate is made according to the needs of cut-pff wall and is convenient for The structure of connection forms waterproof layer, and use special preparation side so that the external and internal wall of cut-pff wall be protected Method, manufactured hydro-expansive rubber plate is convenient for construction, and waterproof effect is good.
A kind of cut-pff wall convenient for construction that the present invention mentions, technical solution is: including concrete wall (1), meeting water Expanded rubber plate (2), top protection rubber sleeve (3) are externally provided with multiple hydro-expansive rubber plates in the concrete wall (1) (2) form water barrier, and concrete wall (1) top be equipped with top protection rubber sleeve (3), the concrete walls The section of body (1) is that lower part uses trapezium structure, and top uses rectangular parallelepiped structure, and the hydro-expansive rubber plate (2) is under Up gradually thinning structure.
Preferably, hydro-expansive rubber plate (2) are equipped on the outside of the trapezium structure of the lower part of concrete wall (1), upper Top protection rubber sleeve (3) are cased with outside the rectangular parallelepiped structure in portion.
Preferably, the downside of above-mentioned proof rubber set (3) is pyramidal structure, inner wall and hydro-expansive rubber plate (2) Top contact, outside is covered on the outer wall of hydro-expansive rubber plate (2).
Preferably, above-mentioned hydro-expansive rubber plate (2) includes mainboard (2.1), built-in connection (2.2), upper notch (2.3), connecting hole (2.4), lower notch (2.5), lower sieve tray (2.6), sieve line (2.7), upper sieve tray (2.8) are preset, in master The top side of plate (2.1) is equipped with upper notch (2.3), and the lower part other side is equipped with lower notch (2.5), at upper notch (2.3) Built-in connection (2.2) are equipped in mainboard, and the inner end protrusion of built-in connection (2.2), and are connect admittedly with upper sieve tray (2.8) Fixed, outer end reaches outside mainboard;It is equipped in mainboard at the lower notch (2.5) default connecting hole (2.4), passes through lower sieve tray (2.6);It is connect between the lower sieve tray (2.6) and upper sieve tray (2.8) by more sieve lines (2.7).
Preferably, above-mentioned lower sieve tray (2.6) and upper sieve tray (2.8) are rectangular shaped, and multiple through having above Sieve pore and macropore.
Preferably, set on the upside of the mainboard (2.1) of each group of hydro-expansive rubber plate (2) there are three or three or more pre-buried Connector (2.2), set on the downside of the mainboard (2.1) there are three or three or more default connecting holes (2.4), two groups of water-swellable rubbers When offset plate (2) is connected, the built-in connection (2.2) of one group of hydro-expansive rubber plate (2) and another group of default connecting hole (2.4) it connects.
Preferably, above-mentioned hydro-expansive rubber plate (2) is by the way that hydro-expansive rubber sulphur is added in hydro-expansive rubber piece Change mold, then vulcanizes on vulcanizer and be made, the hydro-expansive rubber sulfurizing mould includes positioning pin (a1), cope plate (a2), lower template (a3), open die bush item (a4), lower rubber compensation item (a5), compensation axis (a6), connecting pin (a9), upper rubber mend Repay item (a10), by lower rubber compensation item (a5) and compensation axis (a6) pass through connecting pin (a9) be fixed together, and with open die bush item (a4) it is installed along with the side of lower template (a3), and inserts bottom hydro-expansive rubber piece, then in the another of lower template (a3) Built-in connection (2.2) and upper sieve tray (2.8) are installed in side, continue to insert middle layer hydro-expansive rubber piece, then by upper rubber Compensation item (a10) covers on the upside of built-in connection (2.2), is further continued for filling middle layer hydro-expansive rubber piece, and in lower template (a3) lower sieve tray (2.6) are installed in downside, and more sieves are equipped between lower sieve tray (2.6) and upper sieve tray (2.8) Line (2.7);Set on the lower sieve tray (2.6) there are three or three or more macropores, install compensation axis respectively at macropore (a6), filling outer layer hydro-expansive rubber piece is then proceeded to, then cope plate (a2) is mounted on lower template (a3), stationary positioned It sells (a1).
Preferably, the top of above-mentioned lower template (a3), which is equipped with, runs glue groove (a12), run glue groove (a12) and bolster it Between gap, open the gap area between die bush item (a4) and cope plate.
Preferably, above-mentioned cope plate (a2) opens mould screw hole (a7) equipped with multiple, and opens mould screw hole (a7) and run glue groove (a12) corresponding.
Preferably, the bottom of above-mentioned lower template (a3) is equipped with multiple open and serves as a contrast a screw hole (a11), and opens lining screw hole (a11) with lower template (a3) in install open die bush item (a4) it is corresponding, and install open lining bolts.
The beneficial effects of the present invention are: the present invention is using based on armored concrete, using hydro-expansive rubber plate into It is row antiseepage, damp proof, the top protection of concrete wall is done using top protection rubber sleeve, to protect hydro-expansive rubber plate, is made Hydro-expansive rubber is unlikely to expand and influence the purpose of its anti-seepage and anti-wet by top, to reach guarantor in rainy days Protect the purpose of armored concrete;The present invention can tie frame structure by the reinforcing bar of armored concrete and hydro-expansive rubber plate is pre-buried Connector carries out gun iron link, is connected as one its protection with basis, and the whole lower part that presents is trapezium structure, and top is Rectangular parallelepiped structure, in this way the temperature change requirement to adapt to dykes and dams;
In addition, the hydro-expansive rubber plate that the present invention uses be also especially made of, pass through dedicated hydro-expansive rubber plate sulphur Change mold and dedicated hydro-expansive rubber plate is made, and in the production process, is gradually to add from inside to outside to make water absorbing force Strong special hydro-expansive rubber needs to select different water absorbing forces in the cavity between bolster when vulcanizing production Hydro-expansive rubber, specifically bottom hydro-expansive rubber piece, middle layer hydro-expansive rubber piece and outer layer hydro-expansive rubber piece, Layering forms together with built-in connection and sieve line and upper and lower sieve tray, and is sulfided into the special hydro-expansive rubber of monoblock type Plate, the connection between the hydro-expansive rubber plate are the mechanical forces by built-in connection and default connecting hole, make to match upper and lower Notch is combined closely, therefore there is no leakage problems between special hydro-expansive rubber plate;
In addition, the present invention is equipped in the concrete wall and closes to solve the problems, such as that the concrete of the dam construction expands with heat and contract with cold The swollen eye of heat that removing the work is set, and in the swollen intraocular placement rubber bar of heat, utilize the elasticity of rubber, so that it may very good solution concrete wall Anti-seepage and anti-wet and temperature change contradiction, easy construction of the present invention, and good water-proof effect in a word, make cut-pff wall use the longevity Life greatly improves.
Detailed description of the invention
Attached drawing 1 is side view of the invention;
Attached drawing 2 is positive structure schematic of the invention;
Attached drawing 3 is the sectional view of hydro-expansive rubber plate;
Attached drawing 4 is the outline drawing of hydro-expansive rubber plate;
Attached drawing 5 is the top view of hydro-expansive rubber sulfurizing mould;
Attached drawing 6 is the Section A-A figure of hydro-expansive rubber sulfurizing mould;
Attached drawing 7 is the section B-B figure of hydro-expansive rubber sulfurizing mould;
Attached drawing 8 is the side cross-sectional, view of multiple hydro-expansive rubber plates;
Attached drawing 9 is construction schematic diagram when hydro-expansive rubber plate is connect with reinforcing bar;
In upper figure: concrete wall 1, hydro-expansive rubber plate 2, top protection rubber sleeve 3, connector 4, lightning rod 5, reinforcing bar 6, Mainboard (2.1), built-in connection (2.2), upper notch (2.3), default connecting hole (2.4), lower notch (2.5), lower sieve tray (2.6), line (2.7), upper sieve tray (2.8) are sieved;Positioning pin a1, cope plate a2, lower template a3, die bush a4, lower rubber benefit are opened Repay an a5, compensation axis a6, open mould screw hole a7, die sinking hole a8, connecting pin a9, upper rubber compensation a10, open lining screw hole (a11), It runs glue groove (a12).
Specific embodiment
Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings, it should be understood that preferred reality described herein Apply example only for the purpose of illustrating and explaining the present invention and is not intended to limit the present invention.
Referring to attached Fig. 1 and 2, a kind of cut-pff wall (concrete cut) convenient for construction that the present invention mentions, technical side Case is: including concrete wall (1), hydro-expansive rubber plate (2), top protection rubber sleeve (3), in the concrete wall (1) be externally provided with the water barrier of multiple hydro-expansive rubber plates (2) composition, and the top of concrete wall (1) be equipped with top Proof rubber set (3), the section of the concrete wall (1) are that lower part uses trapezium structure, and top uses rectangular parallelepiped structure, The hydro-expansive rubber plate (2) gradually thinning structure from lower to upper.
Hydro-expansive rubber plate (2) are equipped on the outside of the trapezium structure of the lower part of concrete wall (1), in the rectangular of top Top protection rubber sleeve (3) are cased with outside body structure;The downside of proof rubber set (3) is pyramidal structure, inner wall and water-swellable rubber The top of offset plate (2) contacts, and outside is covered on the outer wall of hydro-expansive rubber plate (2).
Referring to attached drawing 3 and 4, the hydro-expansive rubber plate (2) that the present invention mentions includes mainboard (2.1), built-in connection (2.2), upper notch (2.3), default connecting hole (2.4), lower notch (2.5), lower sieve tray (2.6), sieve line (2.7), upper sieve pore Plate (2.8) is equipped with upper notch (2.3) in the top side of mainboard (2.1), and the lower part other side is equipped with lower notch (2.5), lacks upper Be equipped with built-in connection (2.2) in mainboard at mouthful (2.3), and the inner end protrusion of built-in connection (2.2), and with upper sieve tray (2.8) it is connected and fixed, outer end reaches outside mainboard;It is equipped in mainboard at the lower notch (2.5) default connecting hole (2.4), Across lower sieve tray (2.6);It is connect between the lower sieve tray (2.6) and upper sieve tray (2.8) by more sieve lines (2.7).
Wherein, lower sieve tray (2.6) and upper sieve tray (2.8) are rectangular shaped, and above through there is multiple sieve pores and big Hole, multiple sieve pores can make the more preferable of sieve tray and concrete coagulation, and macropore is then for manufacturing default connecting hole (2.4) 's.
In addition, set on the upside of the mainboard (2.1) of each group of hydro-expansive rubber plate (2) there are three or three or more pre-buried companies Fitting (2.2), set on the downside of the mainboard (2.1) there are three or three or more default connecting holes (2.4), two groups of hydro-expansive rubbers When plate (2) is connected, the built-in connection (2.2) of one group of hydro-expansive rubber plate (2) and another group of default connecting hole (2.4) Connection.
Referring to attached drawing 5-7, the hydro-expansive rubber plate (2) that the present invention mentions is met by the way that hydro-expansive rubber piece to be added Then water-expansible rubber sulfurizing mould vulcanizes on vulcanizer and is made, the hydro-expansive rubber sulfurizing mould includes positioning pin (a1), cope plate (a2), lower template (a3), open die bush item (a4), lower rubber compensation item (a5), compensation axis (a6), connecting pin (a9), lower rubber compensation item (a5) and compensation axis (a6) are fixed on one by connecting pin (a9) by upper rubber compensation item (a10) It rises, and is installed along with the side of lower template (a3) with die bush item (a4) is opened, and insert bottom hydro-expansive rubber piece, then under Other side installation built-in connection (2.2) of template (a3) and upper sieve tray (2.8) continue to insert middle layer hydro-expansive rubber Then piece covers upper rubber compensation item (a10) on the upside of built-in connection (2.2), be further continued for filling middle layer hydro-expansive rubber Piece, and install lower sieve tray (2.6) in the downside of lower template (a3), and lower sieve tray (2.6) and upper sieve tray (2.8) it Between be equipped with more sieve lines (2.7);Set on the lower sieve tray (2.6) there are three or three or more macropores, distinguish at macropore Compensation axis (a6) is installed, then proceedes to filling outer layer hydro-expansive rubber piece, then cope plate (a2) is mounted on lower template (a3) On, fixed locating stud (a1).
Wherein, the top of lower template (a3), which is equipped with, runs glue groove (a12), runs the gap between glue groove (a12) and bolster, The gap area between die bush item (a4) and cope plate is opened, in this way, in vulcanization, when glue groove is run in discovery rubber spilling, into Row heat preservation, pressure maintaining when the time reaches 45 minutes or more, just complete the vulcanization process of rubber.
In addition, above-mentioned cope plate (a2) opens mould screw hole (a7) equipped with multiple, and opens mould screw hole (a7) and run glue groove (a12) It is corresponding, it opens mould screw hole and bolt cooperates, can play and cope plate and lower template are forced into the effect separated, this is mainly four When the die sinking hole in week cannot separate bolster, bolster separation is realized with this method.
Die sinking hole (a8) is equipped at outer ledge between the lower template (a3) and cope plate (a2).
In addition, the bottom of lower template (a3) of the invention, which is equipped with multiple open, serves as a contrast a screw hole (a11), and open lining screw hole (a11) with lower template (a3) in install open die bush item (a4) it is corresponding, and install open lining bolts, this be also vulcanization complete After when needing to dismantle, rectangular configuration is opened into die bush item (a4) from lower template after opening cope plate, then by opening lining bolts Ejection, consequently facilitating easier dismantle the hydro-expansive rubber plate vulcanizated.It should be understood that opening die bush item (a4) is square Shape structure, and the section on top is the structure of right-angled trapezium, outside is inclined-plane, its effect is to be installed to lower template in cope plate When, guiding role is played, cope plate is more easily installed in lower template.
In addition, the production method for the hydro-expansive rubber plate that the present invention mentions, comprising the following steps:
1), according to the needs of the coefficient of expansion, rubber is kneaded respectively, bottom hydro-expansive rubber piece is made, water is met in middle layer Expanded rubber piece and outer layer hydro-expansive rubber piece;
2), by lower rubber compensation item (a5) and compensation axis (a6) pass through connecting pin (a9) be fixed together, and with open die bush item (a4) it is formed together an entirety A;
3) whole A, is mounted on the side in lower template (a3),;
4), by bottom hydro-expansive rubber piece, the coefficient of expansion is five times after water suction, by the bottom shape of lower template (a3), is used Wallpaper knife is cut into corresponding shape, and puts it into lower template (a3).
5) it, is further filled with middle layer hydro-expansive rubber piece, the coefficient of expansion is twice after water suction, needs to be cut into fragment, then Upper rubber compensation item (a10) is covered on the upside of the built-in connection (2.2), is further continued for filling middle layer hydro-expansive rubber piece, and Lower sieve tray (2.6) are installed in the downside of lower template (a3), and are equipped between lower sieve tray (2.6) and upper sieve tray (2.8) More sieve lines (2.7);Set on the lower sieve tray (2.6) there are three or three or more macropores, install benefit respectively at macropore Repay axis (a6);
6) outer layer hydro-expansive rubber piece, then, is inserted, the coefficient of expansion is one times after water suction, according to mold shape, is cut into Corresponding shape filling, after the height of outer layer hydro-expansive rubber piece, which is higher by, opens die bush item (a4) 5 ~ 6mm, then by cope plate (a2) it is mounted on lower template (a3), and positioning pin (a1) is installed, form hydro-expansive rubber sulfurizing mould;
7) heating mechanism for, opening vulcanizer, preheats the sheet rubber of each layer in hydro-expansive rubber sulfurizing mould, when When temperature reaches 120 DEG C ~ 150 DEG C, start to pressurize, sees run in glue groove (a12) whether have rubber spilling, when discovery has rubber It when spilling, is kept the temperature, pressure maintaining, when the time reaching 45 minutes or more, just completes the vulcanization process of rubber.
8) after the vulcanization process for, completing rubber, entire hydro-expansive rubber sulfurizing mould is hung out and is cooled down, temperature is worked as When spending suitable, it can be opened;
9), when opening mold, firstly, positioning pin (a1) is opened, then by the die sinking hole (a8) on cope plate (a2), by cope plate (a2) it is come out from lower template (a3), if cope plate cannot be acted open by being opened hole (a8), opens mould spiral shell in cope plate (a2) Bolt is installed at hole (a7), cope plate (a2) and lower template (a3) are separated by force, and cope plate (a2) is hung away;
Second step is exactly integrally to invert lower template (a3), is rotated using lining bolts are opened along lining screw hole (a11) is opened, thus Die bush item (a4) taking-up will be opened, then, overturns lower template (a3), takes compensation axis (a6) and upper rubber compensation item (a10) away;
Third step, then lower template (a3) is overturn, it takes out connecting pin (a9), then can take out hydro-expansive rubber plate (2), then Lower rubber compensation item (a5) is taken out, the production of one group of hydro-expansive rubber plate (2) is completed.
Since the downside of concrete wall (1) is trapezium structure, it can be kept full according to replacement cope plate and lower template is required The inclined requirement of foot, is finally made the multiple groups hydro-expansive rubber plate (2) for meeting concrete wall (1) requirement.
Referring to attached drawing 8 and 9, the construction method for the cut-pff wall convenient for construction that the present invention mentions, comprising the following steps:
It 1, is needs according to engineering first, the hydro-expansive rubber plate (2) that production matches with concrete wall (1), and by Under up, the wall thickness of hydro-expansive rubber plate is more and more thinner, and the water-swellable of the produced in lengths respective numbers according to dam body Rubber slab (2);
2, second, first reinforcing bar 6 is tied up on the basis of former dam body, then, hydro-expansive rubber plate (2) is sequentially connected, It is connected and fixed by the built-in connection of one group of hydro-expansive rubber plate (2) and another group of default connecting hole (2.4), is successively arranged Column fix, and outermost end again with reinforcing bar bundle frame structure be connected and fixed or directly by connector 4 and the chance water of the other side it is swollen The built-in connection of swollen rubber slab is fixedly connected, and after making its later period casting concrete, can be connected as one with concrete wall, And entirety is set to be rendered as the concrete exterior sheathing of trapezium structure, and the swollen pipe of a lot of heat is installed;Then, wooden outer in top installation Template forms the cavity of rectangular shape;
3, third, after reaching dam designs requirement, to the exterior sheathing luminal perfusion coagulation of hydro-expansive rubber plate (2) composition Soil, since inside is equipped with multiple swollen pipes of heat, and the swollen pipe close of heat has corrosion-resistant ageing-resistant rubber bar, can form multiple install The swollen eye of heat of rubber bar, moreover, because built-in connection is equipped in hydro-expansive rubber plate (2), it can be by hydro-expansive rubber Plate (2) is closely linked with concrete wall, and this construction does not need the exterior sheathing for dismantling lower part again yet, only disassembly top Rectangular shape on the outside of wooden exterior sheathing, reduce working procedure;
4, finally, rectangular parallelepiped structure outer wall at the top of the concrete wall solidified, puts on the top of Ageing-resistant corrosion-resistant Proof rubber set 3, protects the upper position of the hydro-expansive rubber plate (2) of lower part, avoids rainy or natural ring To the destruction of hydro-expansive rubber plate (2) under border, the service life of entire dykes and dams is extended, to complete entire concrete anti-seepage The production of wall.
Furthermore it is possible to lightning rod 5 is installed in dykes and dams as needed, in addition, needing in prolonged use to dike Dam is conserved, such as replacement top protection rubber sleeve 3, can extend the service life of hydro-expansive rubber plate;It is also in need What is illustrated is bottom hydro-expansive rubber piece, middle layer hydro-expansive rubber piece and outer layer hydro-expansive rubber piece using existing The hydro-expansive rubber of technology, water-swellable coefficient is different, can meet the requirements, and corrosion-resistant ageing-resistant;Its basic principle It is when cut-pff wall encounters water, hydro-expansive rubber plate can obstruct erosion of the water to concrete, to extend concrete wall Service life.
In addition, the formula for the hydro-expansive rubber that the present invention uses is existing conventional techniques.It is of course also possible to use following Formula is made: the formula of bottom hydro-expansive rubber is using as follows: nitrile rubber 13kg, water-absorbing resin 10kg, stearic acid SA 0.13kg, di-iron trioxide 0.26kg, anti-aging agent RD (2,2,4- trimethyl -1,2- dihyaroquinoline condensate) 0.26kg, rush Into agent CZ(chemical name N- cyclohexyl -2-[4-morpholinodithio sulfenamide) 0.16kg, rubber accelerator DM (chemical name: 2, 2'- dithio-bis-benzothiazole) 0.26kg, activating agent zinc oxide 0.65kg, desiccant calcium oxide 0.65kg, reinforcing agent titanium dioxide Silicon 2.6kg, plasticizer DOP (dioctyl phthalate) 1.95k, pre-dispersed medicine glue S-80 0.04kg of sulphur, vulcanization crosslinking agent DCP 0.26kg, peg4000 1.3kg, methyl diphenylene diisocyanate MDI 0.08kg, silica 1kg.Wherein, water suction tree Rouge can be using the commercial product BS-3 Hydroxylated acrylic resin of Nanjing match regular senior middle school's molecular material Co., Ltd, and peg4000 is ring Oxidative ethane condensation product, the product produced such as Jiangsu Hai'an petrochemical plant.The expansion multiple of the hydro-expansive rubber is 5 times.
The formula of middle layer hydro-expansive rubber is using as follows: nitrile rubber 13kg, water-absorbing resin 6kg, stearic acid SA 0.12kg, di-iron trioxide 0.21kg, anti-aging agent RD (2,2,4- trimethyl -1,2- dihyaroquinoline condensate) 0.22kg, rush Into agent CZ(chemical name N- cyclohexyl -2-[4-morpholinodithio sulfenamide) 0.15kg, rubber accelerator DM (chemical name: 2, 2'- dithio-bis-benzothiazole) 0.26kg, activating agent zinc oxide 0.6kg, desiccant calcium oxide 0.6kg, reinforcing agent silica 2.2kg, plasticizer DOP (dioctyl phthalate) 1.9k, pre-dispersed medicine glue S-80 0.04kg of sulphur, vulcanization crosslinking agent DCP 0.26kg, peg4000 1.2kg, methyl diphenylene diisocyanate MDI 0.08kg, silica 0.9kg.Wherein, water-absorbing resin Can be using the commercial product BS-3 Hydroxylated acrylic resin of Nanjing match regular senior middle school's molecular material Co., Ltd, peg4000 is epoxy Oxide condensate, the product produced such as Jiangsu Hai'an petrochemical plant.The expansion multiple of the hydro-expansive rubber is 2 times.
The formula of outer layer hydro-expansive rubber is using as follows: nitrile rubber 13kg, water-absorbing resin 3kg, stearic acid SA 0.13kg, di-iron trioxide 0.24kg, anti-aging agent RD (2,2,4- trimethyl -1,2- dihyaroquinoline condensate) 0.25kg, rush Into agent CZ(chemical name N- cyclohexyl -2-[4-morpholinodithio sulfenamide) 0.13kg, rubber accelerator DM (chemical name: 2, 2'- dithio-bis-benzothiazole) 0.23kg, activating agent zinc oxide 0.6kg, desiccant calcium oxide 0.6kg, reinforcing agent silica 2.1kg, plasticizer DOP (dioctyl phthalate) 1.9k, pre-dispersed medicine glue S-80 0.04kg of sulphur, vulcanization crosslinking agent DCP 0.26kg, peg4000 1.3kg, methyl diphenylene diisocyanate MDI 0.08kg, silica 0.8kg.Wherein, water-absorbing resin Can be using the commercial product BS-3 Hydroxylated acrylic resin of Nanjing match regular senior middle school's molecular material Co., Ltd, peg4000 is epoxy Oxide condensate, the product produced such as Jiangsu Hai'an petrochemical plant.The expansion multiple of the hydro-expansive rubber is 1 times.
The above, is only part preferred embodiment of the invention, and anyone skilled in the art may benefit Equivalent technical solution is modified or is revised as with the technical solution of above-mentioned elaboration.Therefore, technology according to the present invention Any simple modification or substitute equivalents that scheme is carried out, belong to the greatest extent the scope of protection of present invention.

Claims (7)

1. a kind of cut-pff wall convenient for construction, it is characterized in that: including concrete wall (1), hydro-expansive rubber plate (2), top Proof rubber set (3) is externally provided with the water barrier of multiple hydro-expansive rubber plate (2) compositions in the concrete wall (1), and The top of concrete wall (1) be equipped with top protection rubber sleeve (3), the section of the concrete wall (1) is lower part Using trapezium structure, top uses rectangular parallelepiped structure, the hydro-expansive rubber plate (2) gradually thinning knot from lower to upper Structure;
The hydro-expansive rubber plate (2) includes mainboard (2.1), built-in connection (2.2), upper notch (2.3), default connection Hole (2.4), lower notch (2.5), lower sieve tray (2.6), sieve line (2.7), upper sieve tray (2.8), on the top one of mainboard (2.1) Side is equipped with upper notch (2.3), and the lower part other side is equipped with lower notch (2.5), and pre-buried company is equipped in the mainboard at upper notch (2.3) Fitting (2.2), and the inner end protrusion of built-in connection (2.2), and be connected and fixed with upper sieve tray (2.8), outer end reaches master Outside plate;It is equipped with default connecting hole (2.4), passes through lower sieve tray (2.6) in mainboard at the lower notch (2.5);The lower sieve It is connect between orifice plate (2.6) and upper sieve tray (2.8) by more sieve lines (2.7);
The lower sieve tray (2.6) and upper sieve tray (2.8) are rectangular shaped, and above through having multiple sieve pores and macropore;
Set on the upside of the mainboard (2.1) of each group of hydro-expansive rubber plate (2) there are three or three or more built-in connections (2.2), set on the downside of the mainboard (2.1) there are three or three or more default connecting holes (2.4), two groups of hydro-expansive rubber plates (2) when being connected, the built-in connection (2.2) of one group of hydro-expansive rubber plate (2) and another group of default connecting hole (2.4) are even It connects.
2. the cut-pff wall according to claim 1 convenient for construction, it is characterized in that: the ladder in the lower part of concrete wall (1) Hydro-expansive rubber plate (2) are equipped on the outside of shape structure, top protection rubber sleeve (3) are cased with outside the rectangular parallelepiped structure on top.
3. the cut-pff wall according to claim 1 convenient for construction, it is characterized in that: the downside of the proof rubber set (3) For pyramidal structure, inner wall is contacted with the top of hydro-expansive rubber plate (2), and outside is covered on the outer of hydro-expansive rubber plate (2) Wall.
4. the cut-pff wall according to claim 1 convenient for construction, it is characterized in that: the hydro-expansive rubber plate (2) is logical It crosses and hydro-expansive rubber sulfurizing mould is added in hydro-expansive rubber piece, then vulcanize on vulcanizer and be made, the chance water is swollen Swollen vulcanization of rubber mold includes positioning pin (a1), cope plate (a2), lower template (a3), opens die bush item (a4), lower rubber compensation item (a5), axis (a6), connecting pin (a9), upper rubber compensation item (a10) are compensated, lower rubber compensation item (a5) and compensation axis (a6) is logical It crosses connecting pin (a9) to be fixed together, and be installed along with the side of lower template (a3) with die bush item (a4) is opened, and inserts bottom Hydro-expansive rubber piece, then built-in connection (2.2) and upper sieve tray (2.8) are installed in the other side of lower template (a3), continue Middle layer hydro-expansive rubber piece is inserted, then upper rubber compensation item (a10) is covered on the upside of built-in connection (2.2), is further continued for Middle layer hydro-expansive rubber piece, and the sieve tray (2.6) under the installation of the downside of lower template (a3) are inserted, and in lower sieve tray (2.6) more sieve lines (2.7) are equipped between upper sieve tray (2.8);Set on the lower sieve tray (2.6) there are three or three with On macropore, install compensation axis (a6) respectively at macropore, then proceed to filling outer layer hydro-expansive rubber piece, then by cope plate (a2) it is mounted on lower template (a3), fixed locating stud (a1).
5. the cut-pff wall according to claim 4 convenient for construction, it is characterized in that: the top of the lower template (a3) is equipped with It runs glue groove (a12), runs the gap between glue groove (a12) and bolster, the gap opened between die bush item (a4) and cope plate connects It is logical.
6. the cut-pff wall according to claim 5 convenient for construction, it is characterized in that: the cope plate (a2) is equipped with multiple open Mould screw hole (a7), and it is corresponding with glue groove (a12) is run to open mould screw hole (a7).
7. the cut-pff wall according to claim 5 convenient for construction, it is characterized in that: the bottom of the lower template (a3) is equipped with It is multiple to open lining screw hole (a11), and it is corresponding to open the opening of installation in lining screw hole (a11) and lower template (a3) die bush item (a4), And it installs and opens lining bolts.
CN201910140655.1A 2018-09-28 2018-09-28 Cut-off wall convenient to construction Active CN109826157B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910140655.1A CN109826157B (en) 2018-09-28 2018-09-28 Cut-off wall convenient to construction

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201811140749.0A CN109113024B (en) 2018-09-28 2018-09-28 A kind of concrete cut
CN201910140655.1A CN109826157B (en) 2018-09-28 2018-09-28 Cut-off wall convenient to construction

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201811140749.0A Division CN109113024B (en) 2018-09-28 2018-09-28 A kind of concrete cut

Publications (2)

Publication Number Publication Date
CN109826157A true CN109826157A (en) 2019-05-31
CN109826157B CN109826157B (en) 2020-09-08

Family

ID=64857106

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201811140749.0A Active CN109113024B (en) 2018-09-28 2018-09-28 A kind of concrete cut
CN201910140655.1A Active CN109826157B (en) 2018-09-28 2018-09-28 Cut-off wall convenient to construction

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201811140749.0A Active CN109113024B (en) 2018-09-28 2018-09-28 A kind of concrete cut

Country Status (1)

Country Link
CN (2) CN109113024B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110965521A (en) * 2019-07-22 2020-04-07 张谦 Membrane structure protective wall for dam erosion protection and application method thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110044339B (en) * 2019-04-09 2020-10-20 李敬文 Device and method for comprehensively monitoring and utilizing barrier-free river channel

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2712998Y (en) * 2004-06-10 2005-07-27 衡水丰泽工程橡胶科技开发有限公司 Slowly water-swellable rubber waterstop strip
CN102011412A (en) * 2010-12-31 2011-04-13 中国水电顾问集团中南勘测设计研究院 Concrete anti-seepage wall joint
CN102041800A (en) * 2010-12-08 2011-05-04 四川路航建设工程有限责任公司 Method for constructing PVC (polyvinyl chloride) composite geomembrane watertight core of earth-rockfill dam
US9034454B1 (en) * 2011-09-30 2015-05-19 Southern Rubber Company, Inc. Composite joint filler seal material for joints in precast concrete structures

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA1145131A (en) * 1980-04-05 1983-04-26 Hajime Yamaji Aqueously-swelling water stopper and a process of stopping water thereby
CN101451360A (en) * 2007-11-30 2009-06-10 上海久隆电力(集团)有限公司 Antiseep installation technique of cable working well
CN204645097U (en) * 2015-05-11 2015-09-16 青岛一建集团有限公司 A kind of hydro-expansive rubber repairs deformation joint structure
CN206956669U (en) * 2017-03-31 2018-02-02 中国电建集团华东勘测设计研究院有限公司 A kind of attachment structure of cut-pff wall and concrete cover
CN207484405U (en) * 2017-04-26 2018-06-12 中国电建集团西北勘测设计研究院有限公司 A kind of concrete cut
CN207159937U (en) * 2017-06-26 2018-03-30 党文文 A kind of concrete watertight wall joint
CN207553031U (en) * 2017-09-08 2018-06-29 马乐军 A kind of impervious water conservancy structure of flood bank
CN107740380A (en) * 2017-09-18 2018-02-27 杭州国电大坝安全工程有限公司 Concrete deformation seam resistant abrasion leakage preventing structure and its construction method
CN207376572U (en) * 2017-10-30 2018-05-18 武汉江韵勘测工程集团有限公司 A kind of underwater bridge matrix of antiseep

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2712998Y (en) * 2004-06-10 2005-07-27 衡水丰泽工程橡胶科技开发有限公司 Slowly water-swellable rubber waterstop strip
CN102041800A (en) * 2010-12-08 2011-05-04 四川路航建设工程有限责任公司 Method for constructing PVC (polyvinyl chloride) composite geomembrane watertight core of earth-rockfill dam
CN102011412A (en) * 2010-12-31 2011-04-13 中国水电顾问集团中南勘测设计研究院 Concrete anti-seepage wall joint
US9034454B1 (en) * 2011-09-30 2015-05-19 Southern Rubber Company, Inc. Composite joint filler seal material for joints in precast concrete structures

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110965521A (en) * 2019-07-22 2020-04-07 张谦 Membrane structure protective wall for dam erosion protection and application method thereof

Also Published As

Publication number Publication date
CN109113024A (en) 2019-01-01
CN109826157B (en) 2020-09-08
CN109113024B (en) 2019-04-19

Similar Documents

Publication Publication Date Title
CN109113024B (en) A kind of concrete cut
CN106149764A (en) A kind of precast assembly pipe gallery bell and spigot waterproof construction
CN109356162A (en) A kind of OPT interlocking pile slip casting around pile water-stopping method and slip casting pipe device
US20130309013A1 (en) Reinforcement system for increased lateral stability of flood wall
CN105926617A (en) Structure capable of proving protection for anti-floating anchor rod and construction method thereof
CN109338995A (en) A kind of cut-pff wall hydro-expansive rubber plate
CN109291473A (en) A kind of cut-pff wall hydro-expansive rubber plate and production method
JP4535902B2 (en) Seismic joint for concrete structure and its construction method
CN201826306U (en) Bladder-type anticorrosive device with pile shoe and anticorrosive pile using same
KR100676416B1 (en) Method and structure for bridge pier mould construction using concrete water barrier
CN215562332U (en) Hydraulic engineering dykes and dams prevention of seepage ecological protection structure
CN115573302A (en) Anti-seepage and anti-impact flood bank for hydraulic engineering and anti-seepage method thereof
CN105464226B (en) The flexible waterstop of integrated component formula and its application in building deformation joint waterproof
CN115045342A (en) Water-swelling plugging ring for pile-first packer and using method thereof
CN110397088B (en) Advanced water-stop post-pouring strip structure of river beach working condition basement and construction method
CN210768806U (en) Can carry out prefabricated tunnel lining structure that accurate was corrected to deformation section line type
CN209891239U (en) Piston type foundation support structure
CN210597321U (en) From waterproof fender pile and from waterproof supporting system
CN209243728U (en) A kind of OPT interlocking pile slip casting around pile pipe device
CN208563267U (en) A kind of earth and rockfill dam pressure slope body discharge structure
CN105089060A (en) Foundation pit support system using atmospheric pressure as support force
CN106382123B (en) A kind of macromolecule tunnel waterproofing layer and its construction technology
CN204644979U (en) Reinforced earth arch dam discharge structure system
CN220248101U (en) Novel tunnel impervious structure
JP2019157619A (en) Composite segment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20200814

Address after: Room 1109-1120, No.9 Haibo Xingdu, No.1 Guanghui street, high tech Zone, Hengyang City, Hunan Province

Applicant after: Hunan Yihui Construction Co., Ltd

Address before: 257000 Shandong city of Dongying province Lijin County Jin Road No. 638 two

Applicant before: Li Jingwen

GR01 Patent grant
GR01 Patent grant