CN109803139A CN201910117361.7A CN201910117361A CN109803139A CN 109803139 A CN109803139 A CN 109803139A CN 201910117361 A CN201910117361 A CN 201910117361A CN 109803139 A CN109803139 A CN 109803139A
Authority
CN
China
Prior art keywords
power cycle
test
dut
ping
xpon
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910117361.7A
Other languages
Chinese (zh)
Other versions
CN109803139B (en
Inventor
朱永
白云波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Tianyi Comheart Telecom Co Ltd
Original Assignee
Sichuan Tianyi Comheart Telecom Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Tianyi Comheart Telecom Co Ltd filed Critical Sichuan Tianyi Comheart Telecom Co Ltd
Publication of CN109803139A publication Critical patent/CN109803139A/en
Application granted granted Critical
Publication of CN109803139B publication Critical patent/CN109803139B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a kind of xPON terminals and set-top box Power Cycle test macro and test method, it includes test PC, single-chip microcontroller and automatic switch plate;The test PC is built-in with primary control program, is built-in with SCM program in the single-chip microcontroller;The SCM program realizes that control relay carries out the on-off of AC or DC, and then treats test equipment DUT and carry out switching the problem that scents a hidden danger;The primary control program tested in PC carries out multiple control to the automatic switch plate by communication serial port, realize that control automatic switch plate carries out switching on and shutting down, in addition LAN mouth and WLAN mouthfuls of progress ping packets and statistics and record to the DUT of connection, and control operation are connected to the serial ports of equipment DUT to be tested to record the starting information of DUT.It is tested the present invention has the advantages that controlling two kinds of power on/off modes by SCM program and primary control program and treating test equipment DUT, there is the feature high-efficient, test is accurate and testing cost is low compared to manual testing.

Description

XPON terminal and set-top box Power Cycle test macro and test method
Technical field
The present invention relates to a kind of test macro and test method more particularly to xPON terminals and set-top box Power Cycle Test macro and test method.
Background technique
Power Cycle test is the starting validity of common consumer electronics product and the means of testing of stability. It is tested repeatedly during power on/off continuous to product for the starting initialization procedure for being easiest to break down, to It was found that the design hidden danger unstable because of system caused by the reasons such as electrifying timing sequence is inaccurate, malreduction.
Traditional power cycle test is tested using manually switching on and shutting down, time-consuming and laborious, is tested low with efficiency of research and development Under.Or tested using automatic switching tool and cannot monitor or record test process, effective number can not be provided to research and development According to progress case study.
Summary of the invention
The purpose of the present invention is to overcome the shortcomings of the existing technology, provides xPON terminal and set-top box Power Cycle Test macro and test method solve deficiency existing for existing test method.
The purpose of the present invention is achieved through the following technical solutions: xPON terminal and set-top box Power Cycle test system System, it includes test PC, single-chip microcontroller and automatic switch plate;The test PC is built-in with primary control program, in the single-chip microcontroller It is built-in with SCM program;The SCM program realizes that control relay carries out the on-off of AC or DC, and then to be measured Examination equipment DUT carries out switching the problem that scents a hidden danger;The primary control program in PC is tested by communication serial port to the automatic switch Plate carries out multiple control, realizes that control automatic switch plate carries out switching on and shutting down, LAN mouth and WLAN mouthfuls of progress to the DUT of connection Ping packet is simultaneously counted and is recorded, and in addition control operation is connected to the serial ports of equipment DUT to be tested to record the starting letter of DUT Breath.
In the single-chip microcontroller on-off mode of program setting include the n times set time switching on and shutting down and m random time Switching on and shutting down.
XPON terminal and set-top box Power Cycle test method, the method the following steps are included:
S1, input t0_ limit and t0_end;
S2, first time Power Cycle loop test is completed;
S3, second of Power Cycle loop test is completed;
S4, process data and ping packet loss are counted, test terminates.
The step S2 completes first time Power Cycle loop test, and specific step is as follows:
S21, DUT are powered on 1 second, power-off time t1, DUT powers on 20 seconds beginning ping;
S22, judge t0Whether _ end is zero;
S23, record starting time t0, 1000 byte packet of ping 10, and record packet receiving number;
S24, DUT are powered off 1 second, and judge whether first time Power Cycle loop test is completed.
The step S3 completes second of Power Cycle loop test, and specific step is as follows:
S31, DUT power on t3Second, it powers off 1 second, DUT powers on 20 seconds beginning ping;
S32, judge t0Whether _ end is zero;
S33, record starting time t0, 1000 byte packet of ping 10, and record packet receiving number;
S34, DUT are powered off 1 second, and judge whether second of Power Cycle loop test is completed.
The step S22 judges t0Whether _ end is zero and the step S32 judges t0_ end whether be in zero if t0_ end is zero and judges whether ping connects, if t0_ end, which is not zero, judges t0Whether ping connects before _ end.
Whether the step S24 judges first time Power Cycle loop test in completing if first time Power The completion of Cycle loop test then starts second of Power Cycle loop test, if first time Power Cycle circulation is surveyed Examination is without completing then return step S21;During the step S34 judges whether second of Power Cycle loop test is completed If second of Power Cycle loop test is completed, step S4 is carried out;If second of Power Cycle loop test It does not complete, then return step S31.
Described judges whether ping connects, and record starting time t is carried out if connecting0, 1000 byte packet 10 of ping It is a, and record packet receiving number;Continue to judge if being not switched on;Described zero judges t0Whether ping connects before _ end, if It connects, then carries out record starting time t0, 1000 byte packet of ping 10, and packet receiving number is recorded, if be not switched on, remember It records a NG not pass through, and DUT is powered off 1 second.
The present invention controls two kinds of power on/off modes by SCM program and primary control program and treats test equipment DUT progress Test has the feature high-efficient, test is accurate and testing cost is low compared to manual testing.
Detailed description of the invention
Fig. 1 is the block diagram of present system;
Fig. 2 is the flow chart of the method for the present invention.
Specific embodiment
The present invention will be further described with reference to the accompanying drawing, but protection scope of the present invention is not limited to following institute It states.
As shown in Figure 1, xPON terminal and set-top box Power Cycle test macro, it include test PC, single-chip microcontroller and from Dynamic switchboard;The test PC is built-in with primary control program, is built-in with SCM program in the single-chip microcontroller;The monolithic Machine program realizes that control relay carries out the on-off of AC or DC, and then treats test equipment DUT and carry out switching to scent a hidden danger asking Topic point;The primary control program tested in PC carries out multiple control to the automatic switch plate by communication serial port, realizes that control is automatic Switchboard carries out switching on and shutting down, and the LAN mouth and WLAN mouthfuls of progress ping packets to the DUT of connection are simultaneously counted and recorded, and control In addition operation is connected to the serial ports of equipment DUT to be tested to record the starting information of DUT.
Preferably, communication serial port includes RS232 and RS485 etc. serial ports.
In the single-chip microcontroller on-off mode of program setting include the n times set time switching on and shutting down and m random time Switching on and shutting down.
As shown in Fig. 2, xPON terminal and set-top box Power Cycle test method, the method the following steps are included:
S1, input t0_ limit and t0_end;
S2, first time Power Cycle loop test is completed;
S3, second of Power Cycle loop test is completed;
S4, process data and ping packet loss are counted, test terminates.
The step S2 completes first time Power Cycle loop test, and specific step is as follows:
S21, DUT are powered on 1 second, power-off time t1, DUT powers on 20 seconds beginning ping;
S22, judge t0Whether _ end is zero;
S23, record starting time t0, 1000 byte packet of ping 10, and record packet receiving number;
S24, DUT are powered off 1 second, and judge whether first time Power Cycle loop test is completed.
The step S3 completes second of Power Cycle loop test, and specific step is as follows:
S31, DUT power on t3Second, it powers off 1 second, DUT powers on 20 seconds beginning ping;
S32, judge t0Whether _ end is zero;
S33, record starting time t0, 1000 byte packet of ping 10, and record packet receiving number;
S34, DUT are powered off 1 second, and judge whether second of Power Cycle loop test is completed.
The step S22 judges t0Whether _ end is zero and the step S32 judges t0_ end whether be in zero if t0_ end is zero and judges whether ping connects, if t0_ end, which is not zero, judges t0Whether ping connects before _ end.
Whether the step S24 judges first time Power Cycle loop test in completing if first time Power The completion of Cycle loop test then starts second of Power Cycle loop test, if first time Power Cycle circulation is surveyed Examination is without completing then return step S21;During the step S34 judges whether second of Power Cycle loop test is completed If second of Power Cycle loop test is completed, step S4 is carried out;If second of Power Cycle loop test It does not complete, then return step S31.
Described judges whether ping connects, and record starting time t is carried out if connecting0, 1000 byte packet 10 of ping It is a, and record packet receiving number;Continue to judge if being not switched on;Described zero judges t0Whether ping connects before _ end, if It connects, then carries out record starting time t0, 1000 byte packet of ping 10, and packet receiving number is recorded, if be not switched on, remember It records a NG not pass through, and DUT is powered off 1 second.
The above is only a preferred embodiment of the present invention, it should be understood that the present invention is not limited to described herein Form should not be regarded as an exclusion of other examples, and can be used for other combinations, modifications, and environments, and can be at this In the text contemplated scope, modifications can be made through the above teachings or related fields of technology or knowledge.And those skilled in the art institute into Capable modifications and changes do not depart from the spirit and scope of the present invention, then all should be in the protection scope of appended claims of the present invention It is interior.

Claims (8)

1.xPON terminal and set-top box Power Cycle test macro, it is characterised in that: it include test PC, single-chip microcontroller and from Dynamic switchboard;The test PC is built-in with primary control program, is built-in with SCM program in the single-chip microcontroller;The monolithic Machine program realizes that control relay carries out the on-off of AC or DC, and then treats test equipment DUT and carry out switching to scent a hidden danger asking Topic point;The primary control program tested in PC carries out multiple control to the automatic switch plate by communication serial port, realizes that control is automatic Switchboard carries out switching on and shutting down, and the LAN mouth and WLAN mouthfuls of progress ping packets to the DUT of connection are simultaneously counted and recorded, and control In addition operation is connected to the serial ports of equipment DUT to be tested to record the starting information of DUT.
2. xPON terminal according to claim 1 and set-top box Power Cycle test macro, it is characterised in that: described Single-chip microcontroller in the on-off mode of program setting include the switching on and shutting down of n times set time and the switching on and shutting down of m random time.
3.xPON terminal and set-top box Power Cycle test method, it is characterised in that: the method the following steps are included:
S1, input t0_ limit and t0_end;
S2, first time Power Cycle loop test is completed;
S3, second of Power Cycle loop test is completed;
S4, process data and ping packet loss are counted, test terminates.
4. xPON terminal according to claim 3 and set-top box Power Cycle test method, it is characterised in that: described Step S2 complete first time Power Cycle loop test specific step is as follows:
S21, DUT are powered on 1 second, power-off time t1, DUT powers on 20 seconds beginning ping;
S22, judge t0Whether _ end is zero;
S23, record starting time t0, 1000 byte packet of ping 10, and record packet receiving number;
S24, DUT are powered off 1 second, and judge whether first time Power Cycle loop test is completed.
5. xPON terminal according to claim 4 and set-top box Power Cycle test method, it is characterised in that: described Step S3 complete second of Power Cycle loop test specific step is as follows:
S31, DUT power on t3Second, it powers off 1 second, DUT powers on 20 seconds beginning ping;
S32, judge t0Whether _ end is zero;
S33, record starting time t0, 1000 byte packet of ping 10, and record packet receiving number;
S34, DUT are powered off 1 second, and judge whether second of Power Cycle loop test is completed.
6. xPON terminal according to claim 5 and set-top box Power Cycle, it is characterised in that: the step S22 Judge t0Whether _ end is zero and the step S32 judges t0Whether _ end is in zero if t0_ end is zero and judges that ping is No connection, if t0_ end, which is not zero, judges t0Whether ping connects before _ end.
7. xPON terminal according to claim 5 and set-top box Power Cycle test method, it is characterised in that: described Step S24 judge first time Power Cycle loop test in whether completing if first time Power Cycle loop test Completion then starts second of Power Cycle loop test, returns if if first time Power, Cycle loop test is not completed Return step S21;Whether the step S34 judges second of Power Cycle loop test in completing if second of Power Cycle loop test is completed, then carries out step S4;If second of Power Cycle loop test is not completed, step is returned Rapid S31.
8. xPON terminal according to claim 6 and set-top box Power Cycle test method, it is characterised in that: described Judge whether ping connects, if connect if carry out record starting time t0, 1000 byte packet of ping 10, and record receipts Packet number;Continue to judge if being not switched on;Described zero judges t0Whether ping connects before _ end, if it is switched on, then carrying out Record starting time t0, 1000 byte packet of ping 10, and packet receiving number is recorded, if be not switched on, NG of record is not logical It crosses, and DUT is powered off 1 second.
CN201910117361.7A 2019-01-07 2019-02-15 xPON terminal and set top box Power Cycle test system and test method Active CN109803139B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201910013403 2019-01-07
CN2019100134032 2019-01-07

Publications (2)

Publication Number Publication Date
CN109803139A true CN109803139A (en) 2019-05-24
CN109803139B CN109803139B (en) 2022-03-11

Family

ID=66561051

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910117361.7A Active CN109803139B (en) 2019-01-07 2019-02-15 xPON terminal and set top box Power Cycle test system and test method

Country Status (1)

Country Link
CN (1) CN109803139B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111314175A (en) * 2020-02-14 2020-06-19 西安广和通无线通信有限公司 Communication device performance testing device, system and method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1877350A (en) * 2006-04-26 2006-12-13 深圳创维-Rgb电子有限公司 Testing method and device for abnormal power-on and power-off of electronic product
CN102255774A (en) * 2011-06-28 2011-11-23 迈普通信技术股份有限公司 Test system and test method for switch-on and switch-off of communication device as well as fault location method
CN102540105A (en) * 2011-12-31 2012-07-04 曙光信息产业股份有限公司 Method for testing AC and DC on/off machines
CN104901848A (en) * 2015-06-02 2015-09-09 上海斐讯数据通信技术有限公司 Automated testing system and method for startup and shutdown of router
CN106569925A (en) * 2016-11-15 2017-04-19 惠州大亚湾华北工控实业有限公司 On/off stability test module and on/off stability test method
CN107765119A (en) * 2017-09-30 2018-03-06 四川九州电子科技股份有限公司 A kind of automatic detection machine starts abnormal method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1877350A (en) * 2006-04-26 2006-12-13 深圳创维-Rgb电子有限公司 Testing method and device for abnormal power-on and power-off of electronic product
CN102255774A (en) * 2011-06-28 2011-11-23 迈普通信技术股份有限公司 Test system and test method for switch-on and switch-off of communication device as well as fault location method
CN102540105A (en) * 2011-12-31 2012-07-04 曙光信息产业股份有限公司 Method for testing AC and DC on/off machines
CN104901848A (en) * 2015-06-02 2015-09-09 上海斐讯数据通信技术有限公司 Automated testing system and method for startup and shutdown of router
CN106569925A (en) * 2016-11-15 2017-04-19 惠州大亚湾华北工控实业有限公司 On/off stability test module and on/off stability test method
CN107765119A (en) * 2017-09-30 2018-03-06 四川九州电子科技股份有限公司 A kind of automatic detection machine starts abnormal method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111314175A (en) * 2020-02-14 2020-06-19 西安广和通无线通信有限公司 Communication device performance testing device, system and method

Also Published As

Publication number Publication date
CN109803139B (en) 2022-03-11

Similar Documents

Publication Publication Date Title
CN102255774A (en) Test system and test method for switch-on and switch-off of communication device as well as fault location method
CN107561378B (en) A kind of direct-current traction power supply protective device test macro
CN102347786A (en) Power line narrowband carrier field test device applied to low voltage centralized meter reading system
CN109324251B (en) Converter module test system
CN109803139A (en) XPON terminal and set-top box Power Cycle test macro and test method
CN203396869U (en) Integrated test equipment
CN108845251A (en) The GIS combination electric appliance comprehensive tester and test method of double-station disconnecting link
CN109858300A (en) A kind of automation barcode scanning production detection system and its production detection method
CN109302331A (en) A kind of system and method for automatic test storage network switch
CN207396592U (en) A kind of current tester
CN103592527B (en) Test system
CN207588113U (en) Network interface plug-in and pull-off device and network interface insert-pull detection system
CN203607926U (en) Intelligent monitoring system of air conditioners of transformer substation
CN208873282U (en) Blue tooth voice automatic testing equipment
CN207096620U (en) liquid crystal display performance test system
CN102830303A (en) Ethernet power supply testing equipment
CN211457130U (en) Power line carrier communication module production test system
CN204855728U (en) Ageing and test state device of fast switch over semiconductor device
CN101173969A (en) System, device and method for implementing complete automatic test of MP3 player
CN101382569A (en) Circuit breaking test device
CN107765119A (en) A kind of automatic detection machine starts abnormal method
CN208445537U (en) For controlling the switching device of power supply power supply
CN206096427U (en) Detection apparatus for be used for intelligent ammeter output interface signals
CN101408453A (en) Method for testing wireless gas meter function
CN206725719U (en) PLC plate analog detection tools

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant