CN109784574A - The prediction technique and device of equipment state, storage medium, electronic device - Google Patents

The prediction technique and device of equipment state, storage medium, electronic device Download PDF

Info

Publication number
CN109784574A
CN109784574A CN201910069090.2A CN201910069090A CN109784574A CN 109784574 A CN109784574 A CN 109784574A CN 201910069090 A CN201910069090 A CN 201910069090A CN 109784574 A CN109784574 A CN 109784574A
Authority
CN
China
Prior art keywords
model
prediction
target device
history
physical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910069090.2A
Other languages
Chinese (zh)
Inventor
张燧
黄建军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinao Shuneng Technology Co Ltd
Original Assignee
Xinao Shuneng Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinao Shuneng Technology Co Ltd filed Critical Xinao Shuneng Technology Co Ltd
Priority to CN201910069090.2A priority Critical patent/CN109784574A/en
Publication of CN109784574A publication Critical patent/CN109784574A/en
Pending legal-status Critical Current

Links

Abstract

The present invention provides a kind of prediction technique of equipment state and device, storage medium, electronic devices, wherein this method comprises: acquisition target device history running parameter during the sampling period and history environment parameter;Physical prediction model is established using the history running parameter, and establishes to return using the history environment parameter and establishes model;The state value of the target device is predicted according to the physical prediction model and the regressive prediction model, wherein the state value is used to characterize the probability that the target device breaks down.Through the invention, it solves in the prior art using the technical problem of the failure rate inaccuracy of single model prediction equipment.

Description

The prediction technique and device of equipment state, storage medium, electronic device
Technical field
The present invention relates to energy technology field, prediction techniques and device in particular to a kind of equipment state, storage Medium, electronic device.
Background technique
In the prior art, predictive maintenance (Predictive Maintenance, abbreviation PdM) is that " industry 4.0 " proposes One of key innovations.Based on continuous measurement and analysis, predictive maintenance can predict such as machine parts residue use Organs' index such as service life.Crucial operational parameter data with aid decision, can judge the operating status of machine, optimize the dimension of machine Shield opportunity.
In integrated energy system, since there are a large amount of equipment, and there is the relationship of coupling in equipment each other, any A part goes wrong, and can all whole system be caused to go wrong.And when equipment goes wrong, then go to place under repair, and often Industrial production can be delayed.So the predictive maintenance of equipment is just particularly important.
In traditional predictive maintenance, for equipment modeling, if only fitting dynamic using inputoutput data Curve, and it is inaccurate for obtaining prediction result because model is during foundation, it is main it is emphasised that the data collected it Between relationship, do not reflect the physical characteristic of equipment.And modeled only for the physical characteristic of equipment, in different areas, In season, under the influence of the factors such as facility switching strategy, obtained prediction result is also inaccuracy, can ignore the true work of equipment Make state, while the model in physical modeling needs a large amount of expertise.In the prior art simultaneously using single prediction mode It is unable to the fault condition that Accurate Prediction goes out equipment.
For the above-mentioned problems in the prior art, at present it is not yet found that the solution of effect.
Summary of the invention
The embodiment of the invention provides a kind of prediction technique of equipment state and device, storage medium, electronic devices.
According to one embodiment of present invention, a kind of prediction technique of equipment state is provided, comprising:
Acquire target device history running parameter during the sampling period and history environment parameter;
Physical prediction model is established using the history running parameter, and is established and is returned using the history environment parameter Establish model;
The state value of the target device is predicted according to the physical prediction model and the regressive prediction model, wherein The state value is used to characterize the probability that the target device breaks down.
Optionally, the state value of the target device is predicted according to the physical prediction model and the regressive prediction model Include:
Obtain current operating parameters and current environment parameter of the target device in predetermined period;
The current operating parameters are inputted into the physical prediction model and obtain the first prediction result, by the current environment Parameter inputs the regressive prediction model and obtains the second prediction result;
First prediction result and second prediction result are input to default forecasting effective measure model, obtained described State value of the target device in described predetermined period.
Optionally, establishing physical prediction model using the history running parameter includes:
Determine the fault point of the target device;
For each fault point select an original physical model, wherein the original physical model include it is following it One: pipe crack equation, equation of heat transfer, ACOUSTIC WAVE EQUATION, air force equation;
Using the history running parameter training original physical model, the physical prediction model is obtained.
Optionally, establishing regressive prediction model using the history environment parameter includes:
The history environment parameter is analyzed, the recurrence characteristic of the target device is obtained;
Select corresponding with the recurrence characteristic original regression model, wherein the original regression model include it is following it One: integrating rolling average autoregression Arima model, seasonalARIMA model;
Using original regression model described in the history environment parameter training, the regressive prediction model is obtained.
Optionally, acquisition target device history running parameter during the sampling period and history environment parameter include:
The input data of target device during the sampling period, output data, and operation number are acquired in first database According to, and the environment temperature of target device during the sampling period, ambient humidity, light intensity are acquired in the second database.
Optionally, in the state for predicting the target device according to the physical prediction model and the regressive prediction model After value, the method also includes:
When the state value that prediction obtains is greater than threshold value, generates and be used to indicate the early warning that the target device needs to safeguard Information.
According to another embodiment of the invention, a kind of prediction meanss of equipment state are provided, comprising:
Acquisition module, for acquiring target device history running parameter during the sampling period and history environment parameter;
Module is established, for establishing physical prediction model, and the use history ring using the history running parameter Border parameter, which is established to return, establishes model;
Prediction module, for predicting the target device according to the physical prediction model and the regressive prediction model State value, wherein the state value is used to characterize the probability that the target device breaks down.
Optionally, the prediction module includes:
Acquiring unit, for obtaining current operating parameters and current environment ginseng of the target device in predetermined period Number;
Processing unit obtains the first prediction result for the current operating parameters to be inputted the physical prediction model, The current environment parameter is inputted into the regressive prediction model and obtains the second prediction result;
Predicting unit, for first prediction result and second prediction result to be input to default forecasting effective measure Model obtains state value of the target device in described predetermined period.
Optionally, the module of establishing includes:
Determination unit, for determining the fault point of the target device;
First selecting unit, for selecting an original physical model for each fault point, wherein the original object Managing model includes following one: pipe crack equation, equation of heat transfer, ACOUSTIC WAVE EQUATION, air force equation;
First training unit, for obtaining the object using the history running parameter training original physical model Manage prediction model.
Optionally, the module of establishing includes:
Analytical unit obtains the recurrence characteristic of the target device for analyzing the history environment parameter;
Second selecting unit, for selecting original regression model corresponding with the recurrence characteristic, wherein described original time Returning model includes following one: integrating rolling average autoregression Arima model, seasonalARIMA model;
Second training unit, for obtaining described return using original regression model described in the history environment parameter training Return prediction model.
Optionally, the acquisition module includes:
Acquisition unit exports number for acquiring the input data of target device during the sampling period in first database According to and operation data, and target device environment temperature during the sampling period, environmental wet are acquired in the second database Degree, light intensity.
Optionally, described device further include: generation module is used in the prediction module according to the physical prediction model After the state value for predicting the target device with the regressive prediction model, it is greater than threshold value in the state value that prediction obtains When, it generates and is used to indicate the warning information that the target device needs to safeguard.
According to still another embodiment of the invention, a kind of storage medium is additionally provided, meter is stored in the storage medium Calculation machine program, wherein the computer program is arranged to execute the step in any of the above-described embodiment of the method when operation.
According to still another embodiment of the invention, a kind of electronic device, including memory and processor are additionally provided, it is described Computer program is stored in memory, the processor is arranged to run the computer program to execute any of the above-described Step in embodiment of the method.
Through the invention, acquisition target device history running parameter during the sampling period and history environment parameter, and make Physical prediction model is established with the history running parameter, and establishes to return using the history environment parameter and establishes model, The state value that the target device is finally predicted according to the physical prediction model and the regressive prediction model is more by acquiring The device parameter of a dimension, and establish physics and return two kinds of models, forecast analysis, solution are carried out to the probability of malfunction of target device It has determined in the prior art using the technical problem of the failure rate inaccuracy of single model prediction equipment.
Detailed description of the invention
The drawings described herein are used to provide a further understanding of the present invention, constitutes part of this application, this hair Bright illustrative embodiments and their description are used to explain the present invention, and are not constituted improper limitations of the present invention.In the accompanying drawings:
Fig. 1 is a kind of hardware block diagram of the prediction terminal of equipment state of the embodiment of the present invention;
Fig. 2 is the flow chart of the prediction technique of equipment state according to an embodiment of the present invention;
Fig. 3 is the flow diagram that the embodiment of the present invention predicts the state of equipment;
Fig. 4 is the structural block diagram of the prediction meanss of equipment state according to an embodiment of the present invention.
Specific embodiment
In order to enable those skilled in the art to better understand the solution of the present invention, below in conjunction in the embodiment of the present invention Attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is only The embodiment of a part of the invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill people The model that the present invention protects all should belong in member's every other embodiment obtained without making creative work It encloses.
It should be noted that description and claims of this specification and term " first " in above-mentioned attached drawing, " Two " etc. be to be used to distinguish similar objects, without being used to describe a particular order or precedence order.It should be understood that using in this way Data be interchangeable under appropriate circumstances, so as to the embodiment of the present invention described herein can in addition to illustrating herein or Sequence other than those of description is implemented.In addition, term " includes " and " having " and their any deformation, it is intended that cover Cover it is non-exclusive include, for example, the process, method, system, product or equipment for containing a series of steps or units are not necessarily limited to Step or unit those of is clearly listed, but may include be not clearly listed or for these process, methods, product Or other step or units that equipment is intrinsic.
Embodiment 1
Embodiment of the method provided by the embodiment of the present application one can in server, the network terminal, terminal or It is executed in similar arithmetic unit.For running on the server, Fig. 1 is a kind of the pre- of equipment state of the embodiment of the present invention Survey the hardware block diagram of terminal.As shown in Figure 1, server 10 may include at one or more (only showing one in Fig. 1) It manages device 102 (processing unit that processor 102 can include but is not limited to Micro-processor MCV or programmable logic device FPGA etc.) Memory 104 for storing data, optionally, above-mentioned server can also include the transmission device for communication function 106 and input-output equipment 108.It will appreciated by the skilled person that structure shown in FIG. 1 is only to illustrate, simultaneously The structure of above-mentioned server is not caused to limit.For example, server 10 may also include than shown in Fig. 1 more or less groups Part, or with the configuration different from shown in Fig. 1.
Memory 104 can be used for storing computer program, for example, the software program and module of application software, such as this hair The corresponding computer program of the prediction technique of equipment state in bright embodiment, processor 102 are stored in memory by operation Computer program in 104 realizes above-mentioned method thereby executing various function application and data processing.Memory 104 May include high speed random access memory, may also include nonvolatile memory, as one or more magnetic storage device, flash memory, Or other non-volatile solid state memories.In some instances, memory 104 can further comprise relative to processor 102 Remotely located memory, these remote memories can pass through network connection to server 10.The example of above-mentioned network includes But be not limited to internet, intranet, local area network, mobile radio communication and combinations thereof.
Transmitting device 106 is used to that data to be received or sent via a network.Above-mentioned network specific example may include The wireless network that the communication providers of server 10 provide.In an example, transmitting device 106 includes a network adapter (Network Interface Controller, referred to as NIC), can be connected by base station with other network equipments so as to It is communicated with internet.In an example, transmitting device 106 can be radio frequency (Radio Frequency, referred to as RF) Module is used to wirelessly be communicated with internet.
A kind of prediction technique of equipment state is provided in the present embodiment, and Fig. 2 is equipment according to an embodiment of the present invention The flow chart of the prediction technique of state, as shown in Fig. 2, the process includes the following steps:
Step S202, acquisition target device history running parameter during the sampling period and history environment parameter;
Step S204 is established physical prediction model using the history running parameter, and is joined using the history environment Number, which is established to return, establishes model;
Step S206 predicts the state of the target device according to the physical prediction model and the regressive prediction model Value, wherein the state value is used to characterize the probability that the target device breaks down.It, can also be into other than failure rate The fault messages such as one-step prediction time of failure.
Through the above steps, joined by acquisition target device history running parameter during the sampling period and history environment Number, and physical prediction model is established using the history running parameter, and establish to return using the history environment parameter and build Formwork erection type finally predicts the state value of the target device according to the physical prediction model and the regressive prediction model, leads to The device parameter for acquiring multiple dimensions is crossed, and establishes physics and returns two kinds of models, the probability of malfunction of target device is carried out pre- Analysis is surveyed, is solved in the prior art using the technical problem of the failure rate inaccuracy of single model prediction equipment.
Optionally, the executing subject of above-mentioned steps can be plant maintenance platform, and server, terminal etc. specifically can be Processor, algoritic module etc., but not limited to this.
The application scenarios of the present embodiment can be applied and be detected etc. in scenes in the node O&M of energy network, equipment fault, Target device can be gas internal-combustion engine, waste heat boiler, steam boiler, bromine cooling machine, photovoltaic apparatus, earth source heat pump, wind energy plant, Energy storage device etc..
In an embodiment of the present embodiment, predicted according to the physical prediction model and the regressive prediction model The state value of the target device includes:
S11 obtains current operating parameters and current environment parameter of the target device in predetermined period;Prediction week Phase can be above-mentioned using the period, be also possible to other times section, current operating parameters and current environment parameter can represent mesh Operating condition in the marking device proximal segment time;
The current operating parameters are inputted the physical prediction model and obtain the first prediction result by S12, will be described current Environmental parameter inputs the regressive prediction model and obtains the second prediction result;
First prediction result and second prediction result are input to default forecasting effective measure model, obtained by S13 State value of the target device in described predetermined period.
Specifically, the default forecasting effective measure model of the present embodiment can be a Weighted Average Algorithm either physical Equal algorithm.
Optionally, the event that physical prediction model comprises determining that the target device is established using the history running parameter Barrier point;An original physical model is selected for each fault point, wherein the original physical model includes following one: Pipe crack equation, equation of heat transfer, ACOUSTIC WAVE EQUATION, air force equation;Use the history running parameter training original Beginning physical model obtains the physical prediction model.
Optionally, establishing regressive prediction model using the history environment parameter includes: the analysis history environment parameter, Obtain the recurrence characteristic of the target device;Select original regression model corresponding with the recurrence characteristic, wherein described original Regression model includes following one: integrating rolling average autoregression (Autoregressive Integrated Moving Average model, Arima) model, seasonalARIMA model;Using original time described in the history environment parameter training Return model, obtains the regressive prediction model.
Optionally, acquisition target device history running parameter during the sampling period and history environment parameter include: the The input data of target device during the sampling period, output data and operation data are acquired in one database, and second The environment temperature of target device during the sampling period, ambient humidity, light intensity are acquired in database.
In an embodiment of the present embodiment, pre- according to the physical prediction model and the regressive prediction model It surveys after the state value of the target device, further includes: when the state value that prediction obtains is greater than threshold value, generation is used to indicate The target device needs the warning information safeguarded.Further, the difference of threshold value can also be higher than according to predicted value, is generated Different grades of warning information, for example, being higher than, threshold value is more, and warning level is higher, and the probability that target device breaks down is got over Height, equipment is more dangerous, needs emergency service.
The complete scheme of the present embodiment is illustrated below, Fig. 3 is that the embodiment of the present invention carries out in advance the state of equipment The flow diagram of survey, comprising:
S31. a period is selected, from scada (data acquisition and supervisor control) and weather environment database Data are obtained, the input of equipment is obtained in scada, is exported, operation data, collects environment temperature, humidity, light in weather data library The data such as strong.Photovoltaic, the presence of the equipment such as underground heat, needs to obtain environmental data.
S32. the point for being likely to occur failure to equipment is classified, and is selected suitable physical model and is established the differential equation. The device data being collected into is tested simultaneously, sees whether data have the properties such as periodical, the suitable recurrence mould of reselection Type.
S33. by the data of the environmental data and equipment collected, the relevant parameter of model is solved in physical model, Obtain complete physical model.So establishing two kinds of models, and applied forecasting availability model reasonably divides two kinds of results Analysis, so as to obtain more accurately prediction result.
S34. go out the dynamical equation of equipment by Regression Model Simulator.
S35. the equation calculation prediction result obtained by step S33 and step S34.
S36. by prediction result input prediction availability model, final result is obtained.As result display apparatus needs to tie up Shield, then safeguarded.
For the equipment after maintenance, above-mentioned 1-6 step, more new physics and regression model are repeated at once, and update.For not The equipment of maintenance, with the increase of operation hours, the physical model and regression model of corresponding equipment can all become, and be The accuracy for guaranteeing predictive maintenance result, needs to repeat at periodic or other desired above-mentioned steps, new predictive maintenance result is calculated.
In the present embodiment, the dynamic model of equipment constructs the differential equation of equipment fault, passes through from the principle of physics Evolution equation predicts the severity of failure.Pass through the input of collecting device, output, operation data and facility environment data (such as photovoltaic apparatus needs temperature, humidity, the data such as sunshine), can determine the parameter of the differential equation, and then can pass through prediction Failure changes the fault time to determine equipment.The device systems complicated for one, it is assumed that dynamic model meets certain relationship, Then by the data that observe output and input estimate the parameter of model allow we assume that model be similar to Real dynamic model.In the technical program, carried out for same equipment, while using failure predication of two kinds of models to equipment Modeling, one is physical model (the building failure differential equation), the dynamic of two fittings obtained for the input and output by data Model.Two kinds of modelings bring two kinds of prediction results, in this two kinds of results, using forecasting effective measure model, finally obtain equipment The prediction result of failure.
It should be noted that for the various method embodiments described above, for simple description, therefore, it is stated as a series of Combination of actions, but those skilled in the art should understand that, the present invention is not limited by the sequence of acts described because According to the present invention, some steps may be performed in other sequences or simultaneously.Secondly, those skilled in the art should also know It knows, the embodiments described in the specification are all preferred embodiments, and related actions and modules is not necessarily of the invention It is necessary.
Through the above description of the embodiments, those skilled in the art can be understood that according to above-mentioned implementation The method of example can be realized by means of software and necessary general hardware platform, naturally it is also possible to by hardware, but it is very much In the case of the former be more preferably embodiment.Based on this understanding, technical solution of the present invention is substantially in other words to existing The part that technology contributes can be embodied in the form of software products, which is stored in a storage In medium (such as ROM/RAM, magnetic disk, CD), including some instructions are used so that a terminal device (can be mobile phone, calculate Machine, server or network equipment etc.) method that executes each embodiment of the present invention.
Embodiment 2
A kind of load prediction device neural network based is additionally provided in the present embodiment, and the device is for realizing above-mentioned Embodiment and preferred embodiment, the descriptions that have already been made will not be repeated.As used below, term " module " can be real The combination of the software and/or hardware of existing predetermined function.Although device described in following embodiment is preferably realized with software, But the realization of the combination of hardware or software and hardware is also that may and be contemplated.
Fig. 4 is the structural block diagram of the prediction meanss of equipment state according to an embodiment of the present invention, as shown in figure 4, the device Include: acquisition module 40, establish module 42, prediction module 44, wherein
Acquisition module 40, for acquiring target device history running parameter during the sampling period and history environment parameter;
Module 42 is established, for establishing physical prediction model, and the use history using the history running parameter Environmental parameter, which is established to return, establishes model;
Prediction module 44, for predicting the target device according to the physical prediction model and the regressive prediction model State value, wherein the state value is used to characterize the probability that the target device breaks down.
Optionally, the prediction module includes: acquiring unit, for obtaining the target device working as in predetermined period Preceding running parameter and current environment parameter;Processing unit, for the current operating parameters to be inputted the physical prediction model The first prediction result is obtained, the current environment parameter is inputted into the regressive prediction model and obtains the second prediction result;Prediction Unit obtains institute for first prediction result and second prediction result to be input to default forecasting effective measure model State state value of the target device in described predetermined period.
Optionally, the module of establishing comprises determining that unit, for determining the fault point of the target device;First choosing Unit is selected, for selecting an original physical model for each fault point, wherein the original physical model includes following One of: pipe crack equation, equation of heat transfer, ACOUSTIC WAVE EQUATION, air force equation;First training unit, for described in use The history running parameter training original physical model, obtains the physical prediction model.
Optionally, the module of establishing includes: analytical unit, for analyzing the history environment parameter, obtains the mesh The recurrence characteristic of marking device;Second selecting unit, for selecting original regression model corresponding with the recurrence characteristic, wherein The original regression model includes following one: integrating rolling average autoregression Arima model, seasonalARIMA model;The Two training units, for obtaining the regressive prediction model using original regression model described in the history environment parameter training.
Optionally, the acquisition module includes: acquisition unit, is being sampled for acquiring target device in first database Input data in period, output data and operation data, and target device is acquired in sampling week in the second database Environment temperature in phase, ambient humidity, light intensity.
Optionally, described device further include: generation module is used in the prediction module according to the physical prediction model After the state value for predicting the target device with the regressive prediction model, it is greater than threshold value in the state value that prediction obtains When, it generates and is used to indicate the warning information that the target device needs to safeguard.
It should be noted that above-mentioned modules can be realized by software or hardware, for the latter, Ke Yitong Following manner realization is crossed, but not limited to this: above-mentioned module is respectively positioned in same processor;Alternatively, above-mentioned modules are with any Combined form is located in different processors.
Embodiment 3
The embodiments of the present invention also provide a kind of storage medium, computer program is stored in the storage medium, wherein The computer program is arranged to execute the step in any of the above-described embodiment of the method when operation.
Optionally, in the present embodiment, above-mentioned storage medium can be set to store by executing based on following steps Calculation machine program:
S1, acquisition target device history running parameter during the sampling period and history environment parameter;
S2 is established physical prediction model using the history running parameter, and is established using the history environment parameter Model is established in recurrence;
S3 predicts the state value of the target device according to the physical prediction model and the regressive prediction model, In, the state value is used to characterize the probability that the target device breaks down.
Optionally, in the present embodiment, above-mentioned storage medium can include but is not limited to: USB flash disk, read-only memory (Read- Only Memory, referred to as ROM), it is random access memory (Random Access Memory, referred to as RAM), mobile hard The various media that can store computer program such as disk, magnetic or disk.
The embodiments of the present invention also provide a kind of electronic device, including memory and processor, stored in the memory There is computer program, which is arranged to run computer program to execute the step in any of the above-described embodiment of the method Suddenly.
Optionally, above-mentioned electronic device can also include transmission device and input-output equipment, wherein the transmission device It is connected with above-mentioned processor, which connects with above-mentioned processor.
Optionally, in the present embodiment, above-mentioned processor can be set to execute following steps by computer program:
S1, acquisition target device history running parameter during the sampling period and history environment parameter;
S2 is established physical prediction model using the history running parameter, and is established using the history environment parameter Model is established in recurrence;
S3 predicts the state value of the target device according to the physical prediction model and the regressive prediction model, In, the state value is used to characterize the probability that the target device breaks down.
Optionally, the specific example in the present embodiment can be with reference to described in above-described embodiment and optional embodiment Example, details are not described herein for the present embodiment.
Obviously, those skilled in the art should be understood that each module of the above invention or each step can be with general Computing device realize that they can be concentrated on a single computing device, or be distributed in multiple computing devices and formed Network on, optionally, they can be realized with the program code that computing device can perform, it is thus possible to which they are stored It is performed by computing device in the storage device, and in some cases, it can be to be different from shown in sequence execution herein Out or description the step of, perhaps they are fabricated to each integrated circuit modules or by them multiple modules or Step is fabricated to single integrated circuit module to realize.In this way, the present invention is not limited to any specific hardware and softwares to combine.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.It is all within principle of the invention, it is made it is any modification, etc. With replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of prediction technique of equipment state characterized by comprising
Acquire target device history running parameter during the sampling period and history environment parameter;
Physical prediction model is established using the history running parameter, and establishes to return using the history environment parameter and establish Model;
The state value of the target device is predicted according to the physical prediction model and the regressive prediction model, wherein described State value is used to characterize the probability that the target device breaks down.
2. the method according to claim 1, wherein according to the physical prediction model and the regression forecasting mould Type predicts that the state value of the target device includes:
Obtain current operating parameters and current environment parameter of the target device in predetermined period;
The current operating parameters are inputted into the physical prediction model and obtain the first prediction result, by the current environment parameter It inputs the regressive prediction model and obtains the second prediction result;
First prediction result and second prediction result are input to default forecasting effective measure model, obtain the target State value of the equipment in described predetermined period.
3. the method according to claim 1, wherein establishing physical prediction model using the history running parameter Include:
Determine the fault point of the target device;
An original physical model is selected for each fault point, wherein the original physical model includes following one: pipe Road crack equation, equation of heat transfer, ACOUSTIC WAVE EQUATION, air force equation;
Using the history running parameter training original physical model, the physical prediction model is obtained.
4. the method according to claim 1, wherein establishing regressive prediction model using the history environment parameter Include:
The history environment parameter is analyzed, the recurrence characteristic of the target device is obtained;
Select original regression model corresponding with the recurrence characteristic, wherein the original regression model includes following one: whole Close rolling average autoregression Arima model, seasonalARIMA model;
Using original regression model described in the history environment parameter training, the regressive prediction model is obtained.
5. the ginseng the method according to claim 1, wherein the history of acquisition target device during the sampling period works It is several to include: with history environment parameter
The input data of target device during the sampling period, output data and operation data are acquired in first database, with And the environment temperature of target device during the sampling period, ambient humidity, light intensity are acquired in the second database.
6. the method according to claim 1, wherein according to the physical prediction model and the regression forecasting After the state value of target device described in model prediction, the method also includes:
When the state value that prediction obtains is greater than threshold value, generates and be used to indicate the early warning letter that the target device needs to safeguard Breath.
7. a kind of prediction meanss of equipment state characterized by comprising
Acquisition module, for acquiring target device history running parameter during the sampling period and history environment parameter;
Module is established, for establishing physical prediction model using the history running parameter, and is joined using the history environment Number, which is established to return, establishes model;
Prediction module, for predicting the state of the target device according to the physical prediction model and the regressive prediction model Value, wherein the state value is used to characterize the probability that the target device breaks down.
8. device according to claim 7, which is characterized in that the prediction module includes:
Acquiring unit, for obtaining current operating parameters and current environment parameter of the target device in predetermined period;
Processing unit obtains the first prediction result for the current operating parameters to be inputted the physical prediction model, by institute It states the current environment parameter input regressive prediction model and obtains the second prediction result;
Predicting unit, for first prediction result and second prediction result to be input to default forecasting effective measure mould Type obtains state value of the target device in described predetermined period.
9. a kind of storage medium, which is characterized in that be stored with computer program in the storage medium, wherein the computer Program is arranged to execute method described in any one of claim 1 to 6 when operation.
10. a kind of electronic device, including memory and processor, which is characterized in that be stored with computer journey in the memory Sequence, the processor are arranged to run the computer program to execute side described in any one of claim 1 to 6 Method.
CN201910069090.2A 2019-01-24 2019-01-24 The prediction technique and device of equipment state, storage medium, electronic device Pending CN109784574A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910069090.2A CN109784574A (en) 2019-01-24 2019-01-24 The prediction technique and device of equipment state, storage medium, electronic device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910069090.2A CN109784574A (en) 2019-01-24 2019-01-24 The prediction technique and device of equipment state, storage medium, electronic device

Publications (1)

Publication Number Publication Date
CN109784574A true CN109784574A (en) 2019-05-21

Family

ID=66501312

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910069090.2A Pending CN109784574A (en) 2019-01-24 2019-01-24 The prediction technique and device of equipment state, storage medium, electronic device

Country Status (1)

Country Link
CN (1) CN109784574A (en)

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110388773A (en) * 2019-07-15 2019-10-29 重庆美的通用制冷设备有限公司 Fault detection method, system and the water cooler of water cooler
CN110517731A (en) * 2019-10-23 2019-11-29 上海思路迪医学检验所有限公司 Genetic test quality monitoring data processing method and system
CN110672332A (en) * 2019-09-10 2020-01-10 上海电力大学 Gas turbine fault early warning system based on SARIMA model
CN110705729A (en) * 2019-10-14 2020-01-17 中国铁道科学研究院集团有限公司通信信号研究所 Fault detection method and device for track power supply system, server and storage medium
CN110851342A (en) * 2019-11-08 2020-02-28 中国工商银行股份有限公司 Fault prediction method, device, computing equipment and computer readable storage medium
CN111178378A (en) * 2019-11-07 2020-05-19 腾讯科技(深圳)有限公司 Equipment fault prediction method and device, electronic equipment and storage medium
CN111368890A (en) * 2020-02-26 2020-07-03 珠海格力电器股份有限公司 Fault detection method and device and information physical fusion system
CN111626498A (en) * 2020-05-25 2020-09-04 成都中电熊猫显示科技有限公司 Equipment operation state prediction method, device, equipment and storage medium
CN111750925A (en) * 2019-12-24 2020-10-09 广州极飞科技有限公司 Equipment aging prediction system, method and device
CN112101662A (en) * 2020-09-16 2020-12-18 珠海格力电器股份有限公司 Equipment health condition and life cycle detection method, storage medium and electronic equipment
CN112578725A (en) * 2020-12-16 2021-03-30 中国水产科学研究院南海水产研究所 Fishery water aquaculture facility safety early warning system and method based on Internet of things
CN112667710A (en) * 2020-12-24 2021-04-16 深圳市英威腾电气股份有限公司 Inverter overheating early warning method and device, computer equipment and storage medium
CN112733454A (en) * 2021-01-13 2021-04-30 新智数字科技有限公司 Equipment predictive maintenance method and device based on joint learning
CN113051700A (en) * 2019-12-27 2021-06-29 北京国双科技有限公司 Equipment reliability monitoring method and device
CN113505533A (en) * 2021-07-06 2021-10-15 新智数字科技有限公司 Equipment health state prediction method and device
CN113574482A (en) * 2019-08-30 2021-10-29 Oppo广东移动通信有限公司 Rule checking method and device and computer equipment
CN113849987A (en) * 2021-11-03 2021-12-28 中国民用航空飞行学院 Performance test method and device of piston engine, electronic equipment and medium
CN113917911A (en) * 2021-11-05 2022-01-11 重庆赛迪奇智人工智能科技有限公司 Electronic tag fault detection method and device
CN115310240A (en) * 2022-10-11 2022-11-08 烟台杰瑞石油装备技术有限公司 Oil-gas fracturing pump equipment service life prediction method and device and nonvolatile storage medium
CN116204387A (en) * 2023-04-26 2023-06-02 之江实验室 Chip current prediction method and device, medium and electronic equipment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8151146B2 (en) * 2008-06-11 2012-04-03 At&T Intellectual Property I, L.P. Tool for predicting fault-prone software files
CN102968670A (en) * 2012-10-23 2013-03-13 北京京东世纪贸易有限公司 Method and device for predicting data
CN106600064A (en) * 2016-12-16 2017-04-26 东软集团股份有限公司 Data prediction method and device
CN106611244A (en) * 2016-12-06 2017-05-03 国电南瑞科技股份有限公司 Multi-dimensional comprehensive assessment method for state of power distribution automation secondary device
CN106934728A (en) * 2017-05-09 2017-07-07 四川金信石信息技术有限公司 A kind of power grid security risk management and control intelligent evaluation method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8151146B2 (en) * 2008-06-11 2012-04-03 At&T Intellectual Property I, L.P. Tool for predicting fault-prone software files
CN102968670A (en) * 2012-10-23 2013-03-13 北京京东世纪贸易有限公司 Method and device for predicting data
CN106611244A (en) * 2016-12-06 2017-05-03 国电南瑞科技股份有限公司 Multi-dimensional comprehensive assessment method for state of power distribution automation secondary device
CN106600064A (en) * 2016-12-16 2017-04-26 东软集团股份有限公司 Data prediction method and device
CN106934728A (en) * 2017-05-09 2017-07-07 四川金信石信息技术有限公司 A kind of power grid security risk management and control intelligent evaluation method

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021008176A1 (en) * 2019-07-15 2021-01-21 重庆美的通用制冷设备有限公司 Fault detection method and system for water chilling unit, and water chilling unit
CN110388773A (en) * 2019-07-15 2019-10-29 重庆美的通用制冷设备有限公司 Fault detection method, system and the water cooler of water cooler
CN113574482A (en) * 2019-08-30 2021-10-29 Oppo广东移动通信有限公司 Rule checking method and device and computer equipment
CN113574482B (en) * 2019-08-30 2023-12-08 Oppo广东移动通信有限公司 Rule checking method and device and computer equipment
CN110672332A (en) * 2019-09-10 2020-01-10 上海电力大学 Gas turbine fault early warning system based on SARIMA model
CN110705729A (en) * 2019-10-14 2020-01-17 中国铁道科学研究院集团有限公司通信信号研究所 Fault detection method and device for track power supply system, server and storage medium
CN110517731A (en) * 2019-10-23 2019-11-29 上海思路迪医学检验所有限公司 Genetic test quality monitoring data processing method and system
CN111178378B (en) * 2019-11-07 2023-05-16 腾讯科技(深圳)有限公司 Equipment fault prediction method and device, electronic equipment and storage medium
CN111178378A (en) * 2019-11-07 2020-05-19 腾讯科技(深圳)有限公司 Equipment fault prediction method and device, electronic equipment and storage medium
CN110851342A (en) * 2019-11-08 2020-02-28 中国工商银行股份有限公司 Fault prediction method, device, computing equipment and computer readable storage medium
CN111750925A (en) * 2019-12-24 2020-10-09 广州极飞科技有限公司 Equipment aging prediction system, method and device
CN113051700B (en) * 2019-12-27 2023-12-29 北京国双科技有限公司 Equipment reliability monitoring method and device
CN113051700A (en) * 2019-12-27 2021-06-29 北京国双科技有限公司 Equipment reliability monitoring method and device
CN111368890A (en) * 2020-02-26 2020-07-03 珠海格力电器股份有限公司 Fault detection method and device and information physical fusion system
CN111626498A (en) * 2020-05-25 2020-09-04 成都中电熊猫显示科技有限公司 Equipment operation state prediction method, device, equipment and storage medium
CN111626498B (en) * 2020-05-25 2023-10-24 成都京东方显示科技有限公司 Equipment running state prediction method, device, equipment and storage medium
CN112101662A (en) * 2020-09-16 2020-12-18 珠海格力电器股份有限公司 Equipment health condition and life cycle detection method, storage medium and electronic equipment
CN112578725A (en) * 2020-12-16 2021-03-30 中国水产科学研究院南海水产研究所 Fishery water aquaculture facility safety early warning system and method based on Internet of things
CN112667710A (en) * 2020-12-24 2021-04-16 深圳市英威腾电气股份有限公司 Inverter overheating early warning method and device, computer equipment and storage medium
CN112733454A (en) * 2021-01-13 2021-04-30 新智数字科技有限公司 Equipment predictive maintenance method and device based on joint learning
CN113505533A (en) * 2021-07-06 2021-10-15 新智数字科技有限公司 Equipment health state prediction method and device
CN113849987A (en) * 2021-11-03 2021-12-28 中国民用航空飞行学院 Performance test method and device of piston engine, electronic equipment and medium
CN113917911A (en) * 2021-11-05 2022-01-11 重庆赛迪奇智人工智能科技有限公司 Electronic tag fault detection method and device
CN115310240A (en) * 2022-10-11 2022-11-08 烟台杰瑞石油装备技术有限公司 Oil-gas fracturing pump equipment service life prediction method and device and nonvolatile storage medium
CN116204387A (en) * 2023-04-26 2023-06-02 之江实验室 Chip current prediction method and device, medium and electronic equipment

Similar Documents

Publication Publication Date Title
CN109784574A (en) The prediction technique and device of equipment state, storage medium, electronic device
CN108375715B (en) Power distribution network line fault risk day prediction method and system
CN115578015B (en) Sewage treatment whole process supervision method, system and storage medium based on Internet of things
El Jazzar et al. Digital twin in construction: An empirical analysis
Gallagher et al. Development and application of a machine learning supported methodology for measurement and verification (M&V) 2.0
KR20210041724A (en) Apparatus and method for predicting failure of electric car charger
CN109492790A (en) Wind turbines health control method based on neural network and data mining
Sučić et al. The concept of an integrated performance monitoring system for promotion of energy awareness in buildings
CN116822115A (en) Environment management method and system for intelligent park based on digital twin technology
CN115865992A (en) Wisdom water conservancy on-line monitoring system
Kim et al. A POMDP framework for integrated scheduling of infrastructure maintenance and inspection
CN109784575A (en) The prediction technique and device of equipment state, storage medium, electronic device
Christodoulou et al. Wireless sensor networks for water loss detection
CN116756909A (en) Early warning diagnosis system of thermal power plant based on data model and mechanism model
Dong Mine gas emission prediction based on Gaussian process model
CN117390944A (en) Substation operation condition simulation system
JPH11175503A (en) Time-sequential data predicting device
Majumder et al. Real-time monitoring of power production in modular hydropower plant: most significant parameter approach
CN103337000B (en) A kind of safe monitoring and pre-alarming method of oil-gas gathering and transportation system
Reuland et al. Monitoring-Driven Post-earthquake Building Damage Tagging
Balin et al. An evaluation approach for eliminating the failure effect in gas turbine using fuzzy multiple criteria
Hajali-Mohamad et al. Optimal estimating the project completion time and diagnosing the fault in the project
CN116757303A (en) Sedimentation prediction method, system and equipment
Karna et al. Temperature Prediction using Regression Model
Atef et al. Understanding the effect of interdependency and vulnerability on the performance of civil infrastructure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190521