CN109778595A - A kind of shear hinge for floating plate - Google Patents

A kind of shear hinge for floating plate Download PDF

Info

Publication number
CN109778595A
CN109778595A CN201711122982.1A CN201711122982A CN109778595A CN 109778595 A CN109778595 A CN 109778595A CN 201711122982 A CN201711122982 A CN 201711122982A CN 109778595 A CN109778595 A CN 109778595A
Authority
CN
China
Prior art keywords
floating plate
shear hinge
shearing resistance
construction
resistance unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711122982.1A
Other languages
Chinese (zh)
Other versions
CN109778595B (en
Inventor
任奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING JIUZHOUYIGUI SHOCK AND VIBRATION ISOLATION Co Ltd
Original Assignee
BEIJING JIUZHOUYIGUI SHOCK AND VIBRATION ISOLATION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING JIUZHOUYIGUI SHOCK AND VIBRATION ISOLATION Co Ltd filed Critical BEIJING JIUZHOUYIGUI SHOCK AND VIBRATION ISOLATION Co Ltd
Priority to CN201711122982.1A priority Critical patent/CN109778595B/en
Publication of CN109778595A publication Critical patent/CN109778595A/en
Application granted granted Critical
Publication of CN109778595B publication Critical patent/CN109778595B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The present invention relates to rail traffic vibration isolation technique fields, disclose a kind of shear hinge for floating plate, it includes the shearing resistance unit connecting with the first floating plate and the position-limiting unit being embedded in the second floating plate, the shearing resistance unit is using closure or non-closed annular steel construction, the position-limiting unit uses the tubular construction matched with the shearing resistance unit, so that the annular steel construction is plugged in the tubular construction, concreting mouth is additionally provided on the annular steel construction between first floating plate and second floating plate.There is better shear behavior and anti-bending strength compared to traditional shear hinge provided by the present invention for the shear hinge of floating plate, and reduce forces acted on rail and plate end fastener stress, so as to avoid using encryption vibration isolator the problem of increasing plate end rigidity, to greatly reduce cost.

Description

A kind of shear hinge for floating plate
Technical field
The present invention relates to rail traffic vibration isolation technique field more particularly to a kind of shear hinges for floating plate.
Background technique
In urban track traffic, in order to which the vibration interference surrounding enviroment generated when subway train operation are effectively reduced, often The purpose of vibration and noise reducing is realized using steel spring floating slab road bed vibrating isolation system.Since floating plate is elastic support structure, steel Rail deflection is much larger than common railway roadbed, is especially located at two floating plate junctions, and there are the plate stitch of 30mm, and rail is in most herein Unfavorable stress, plate end support stiffness is low, needs to coordinate the deformation between two floating plates of front and back with shear hinge.However it is traditional Shear hinge be solid bar (as shown in Figure 1), in the middle part of the floating plate or float on floating plate surface, bar sectional area is small, need It is arranged 4 groups, but still cannot resist torque and shearing well.In actual use, at plate stitch rail still have stress compared with Greatly, larger situation is deformed, plate end fastener is also subjected to very big stress, is easily damaged, and influences its service life.Floating plate plate end In order to improve rail and fastener stress condition, need to increase plate end rigidity, thus increasing using the method for densifying plate end vibration isolator Manufacturing cost is added.
Summary of the invention
(1) technical problems to be solved
The object of the present invention is to provide a kind of shear hinges for floating plate, it is intended at least the solution prior art or related skill One of technical problem present in art.
(2) technical solution
In order to solve the above-mentioned technical problems, the present invention provides a kind of shear hinges for floating plate comprising with first The shearing resistance unit of floating plate connection and the position-limiting unit being embedded in the second floating plate, the shearing resistance unit use closure or non- The annular steel construction of closure, the position-limiting unit uses the tubular construction matched with the shearing resistance unit, so that the ring Shape steel construction is plugged in the tubular construction, the ring steel between first floating plate and second floating plate Concreting mouth is additionally provided in structure.
It wherein, further include being connect with the first longitudinal direction reinforced steel bar ring of the annular steel structure connection and with the tubular construction Second longitudinal direction reinforced steel bar ring, the longitudinal reinforcement of first floating plate are plugged in the first longitudinal direction reinforced steel bar ring, and described second is floating The longitudinal reinforcement for setting plate is plugged in the second longitudinal direction reinforced steel bar ring.
Wherein, the annular steel construction is U-shaped.
Wherein, the bottom of the annular steel construction of the U-shaped is additionally provided with stiffening plate, and the stiffening plate is located at the bottom Center, and it is parallel with the side wall of the U-shaped steel.
Wherein, the annular steel construction is annular.
Wherein, the first longitudinal direction reinforced steel bar ring and the second longitudinal direction reinforced steel bar ring are elongated hole, first floating plate At least two longitudinal reinforcements be plugged in the same first longitudinal direction reinforced steel bar ring, at least two of second floating plate are vertical It is plugged in the same second longitudinal direction reinforced steel bar ring to reinforcing bar.
Wherein, the quantity of the described first vertical muscle fixed ring is multiple, and multiple first vertical muscle fixed rings are along the shearing resistance The length direction of unit is spaced apart;The quantity of the second vertical muscle fixed ring is multiple, multiple second vertical muscle fixed rings Length direction along the position-limiting unit is spaced apart.
Wherein, the one end of the tubular construction far from the shearing resistance unit is closed, in the inside of the tubular construction One end far from the shearing resistance unit is provided with elastic packed layer.
Wherein, gas vent is additionally provided on the barrel of the tubular construction.
Wherein, lubricant layer is coated on the inner wall of the position-limiting unit.
(3) beneficial effect
Shear hinge provided by the present invention for floating plate includes the shearing resistance unit connecting with the first floating plate and pre-buried Position-limiting unit in the second floating plate, for the shearing resistance unit using closure or non-closed annular steel construction, the limit is single Member is using the tubular construction matched with the shearing resistance unit, so that the annular steel construction is plugged on the tubular construction It is interior, concreting is additionally provided on the annular steel construction between first floating plate and second floating plate Mouthful, by concreting mouth to the inside casting concrete of annular steel construction, combined using concrete and annular steel construction Steel pipe girder construction is formed, so that its sectional area is much larger than traditional shear hinge, to substantially increase shear resistance, and is had Good anti-bending strength.Further, since shear hinge is set to immediately below rail, thus reduce forces acted on rail and plate end fastener by Power, so as to avoid using encryption vibration isolator the problem of increasing plate end rigidity, to greatly reduce cost, and extend rail And the service life of fastener.The fatigue life of shear hinge itself also greatly enhances.
Detailed description of the invention
Fig. 1 is the structural schematic diagram according to a kind of shear hinge for floating plate of the prior art;
Fig. 2 is a kind of structural schematic diagram of a preferred embodiment of the shear hinge for floating plate according to the present invention;
Fig. 3 is one of Fig. 2 for the shearing resistance unit of the shear hinge of floating plate and the structural schematic diagram of the first floating plate;
Fig. 4 is one of Fig. 2 for the position-limiting unit of the shear hinge of floating plate and the structural schematic diagram of the second floating plate;
Fig. 5 is the cross-sectional view of a preferred embodiment of the shearing resistance unit in Fig. 3;
Fig. 6 is the cross-sectional view of a preferred embodiment of the position-limiting unit in Fig. 4;
Fig. 7 is the cross-sectional view of another preferred embodiment of shearing resistance unit;
Fig. 8 is the cross-sectional view of another preferred embodiment of shearing resistance unit;
Fig. 9 is the cross-sectional view of another preferred embodiment of position-limiting unit.
In figure, 1: the first floating plate;2: the second floating plates;3: shear hinge;31: shearing resistance unit;32: position-limiting unit;33: the One vertical muscle fixed ring;34: the second vertical muscle fixed rings;35: concreting mouth;36: stiffening plate;4: longitudinal reinforcement;5: elasticity is filled out Fill layer;6: gas vent;7: concrete.
Specific embodiment
With reference to the accompanying drawings and examples, specific embodiments of the present invention will be described in further detail.Following instance For illustrating the present invention, but it is not intended to limit the scope of the invention.
Fig. 2 to Fig. 6 shows an a kind of preferred embodiments of shear hinge 3 for floating plate according to the present invention.Such as Shown in figure, which includes the shearing resistance unit 31 connecting with the first floating plate 1 and the limit that is embedded in the second floating plate 2 Bit location 32, shearing resistance unit 31 use cross section for U-shaped steel construction.The use of position-limiting unit 32 is matched with shearing resistance unit 31 Tubular construction, so that shearing resistance unit 31 can be plugged in tubular construction.
In use, the shearing resistance unit 31 connecting with the first floating plate 1 is plugged on the limit list in the second floating plate 2 In member 32, wherein there are the plate stitch of about 30mm between the first floating plate 1 and the second floating plate 2, be located at the by shearing resistance unit 31 The opening of the U-shaped steel structure of part between one floating plate 1 and the second floating plate 2 pours coagulation to the inside of U-shaped steel structure Soil 7, the advantage combined using concrete seven and U-shaped steel structure form square steel tube girder construction.Due to the U-shaped steel of shearing resistance unit 31 Structure is combined with concrete seven, so that its sectional area is much larger than traditional shear hinge 3, thus substantially increases shear resistance, The shear resistance of single shear hinge 3 provided by the present invention is greater than 4 groups of traditional shear hinges 3, therefore each plate stitch only needs setting 2 Group shear hinge 3 can meet shearing resistance demand.And the U-shaped steel structure of the shear hinge 3 is combined with concrete seven, so that cross section is used Property square it is larger, thus have good anti-bending strength.Further, since shear hinge 3 is set to immediately below rail, thus reduce rail Stress and plate end fastener stress, so as to avoid using encryption vibration isolator the problem of increasing plate end rigidity, to greatly reduce into This.
It is preferred that the shear hinge 3 further includes the first vertical muscle fixed ring 33 connecting with shearing resistance unit 31, wherein the first floating plate 1 Longitudinal reinforcement 4 be plugged in the first vertical muscle fixed ring 33, in order to which shearing resistance unit 31 is fixed on floating plate longitudinal reinforcement 4 On, step of ligation is eliminated, and greatly enhance with the concrete binding force of the first floating plate 1.Similarly, the preferred shear hinge 3 It further include the second vertical muscle fixed ring 34 being connect with position-limiting unit 32, the longitudinal reinforcement 4 of the second floating plate 2 is plugged on the second vertical muscle In fixed ring 34, in order to which position-limiting unit 32 to be fixed on floating plate longitudinal reinforcement 4, step of ligation is eliminated, and with second The concrete binding force of floating plate 2 greatly enhances.It, can be when pouring the first floating plate 1 and the second floating plate 2 when manufacture, it will The longitudinal reinforcement 4 of first floating plate 1 is plugged in the first vertical muscle fixed ring 33, and the longitudinal reinforcement 4 of the second floating plate 2 is plugged on In second vertical muscle fixed ring 34, when pouring the first floating plate 1 and the second floating plate 2 while the coagulation in U-shaped steel structure is poured Soil 7, so that the first floating plate 1 and the second floating plate 2 are combined closely with shear hinge 3, are formed an entirety, are further increased Shear resistance.
It should be noted that, although the cross section of the shearing resistance unit 31 shown in this embodiment is U-shaped, however, it is necessary to Illustrate, in some other embodiment of the invention, the cross section of the shearing resistance unit 31 may be other closures or The non-closed annular steel construction of person.Herein, closure or non-closed annular steel construction include annulus, vesica piscis, rectangle Ring, hexagonal rings etc., and annulus (as shown in figure 8, position-limiting unit engaged therewith 32 is as shown in Figure 9), vesica piscis, rectangle What ring, hexagonal rings etc. can be closure is also possible to non-closed (having opening), when annular steel construction is closure, Part of the shearing resistance unit 31 between the first floating plate 1 and the second floating plate 2 is provided with concreting mouth 35, will pass through The concreting mouth 35 is to ring steel inside configuration casting concrete 7.When annular steel construction is non-closure, then by ring The opening of shape steel construction is used as concreting mouth 35, to be poured by the concreting mouth 35 to ring steel inside configuration Concrete seven.
Further, when the cross section of annular steel construction is U-shaped, preferably the centre in the bottom of annular steel construction is set It is equipped with the stiffening plate 36 (as shown in Figure 7) being parallel to each other with the side wall of U-shaped structure, to further increase the anti-of the shear hinge 3 It cuts and anti-bending strength.And steel reinforcement cage preferably is additionally provided in the inside of annular steel construction.
In addition, the first vertical muscle fixed ring 33 and the second vertical muscle fixed ring 34 are elongated hole, at least the two of the first floating plate 1 Root longitudinal reinforcement 4 is plugged in the same first vertical muscle fixed ring 33, at least two 4 grafting of longitudinal reinforcement of the second floating plate 2 In the same second vertical muscle fixed ring 34.Shear hinge 3 provided by the present invention is by setting the first vertical muscle fixed ring 33 to Elongated hole, so that at least two longitudinal reinforcements 4 of the first floating plate 1 are plugged in the same first vertical muscle fixed ring 33, from And make vertical there are still being able to be plugged on same first when error when the spacing between the longitudinal reinforcement 4 on the first floating plate 1 In muscle fixed ring 33, and improve work efficiency.Similarly, elongated hole is set by the second vertical muscle fixed ring 34, so that the At least two longitudinal reinforcements 4 of two floating plates 2 are plugged in the same second vertical muscle fixed ring 34, so that it is floating to work as second The spacing between longitudinal reinforcement 4 on plate 2 is mentioned there are still being able to be plugged in the same second vertical muscle fixed ring 34 when error High working efficiency.
In this embodiment, the quantity of the first vertical muscle fixed ring 33 is two, and two the first vertical muscle fixed rings 33 are along shearing resistance The length direction of unit 31 is spaced apart, and is fixed so that the longitudinal reinforcement 4 of the first floating plate 1 sequentially passes through two the first vertical muscle Ring 33, to improve the connection reliability of the first floating plate 1 and shearing resistance unit 31.It should be noted that, although in the embodiment In show two the first vertical muscle fixed rings 33, however it will be understood by those of skill in the art that it is of the invention it is other once In embodiment, the quantity of the first vertical muscle fixed ring 33 is also possible to two or more, such as three, and four etc., the first floating plate 1 Longitudinal reinforcement 4 sequentially passes through the multiple first vertical muscle fixed rings 33.
Similarly, in this embodiment, the quantity of the second vertical muscle fixed ring 34 is two, two the second vertical muscle fixed rings 34 Length direction along position-limiting unit 32 is spaced apart, and is indulged so that the longitudinal reinforcement 4 of the second floating plate 2 sequentially passes through two second Muscle fixed ring 34, to improve the connection reliability of the second floating plate 2 and position-limiting unit 32.It should be noted that, although at this Show two the second vertical muscle fixed rings 34 in embodiment, however it will be understood by those of skill in the art that in of the invention its It is once in embodiment, and the quantity of the second vertical muscle fixed ring 34 is also possible to two or more, such as three, and four etc., second is floating The longitudinal reinforcement 4 for setting plate 2 sequentially passes through the multiple second vertical muscle fixed rings 34.
In addition, can also be arranged on shearing resistance unit 31 multiple along shearing resistance list in some other embodiment of the invention First vertical muscle fixed ring 33 of the width direction arrangement of member 31, and more longitudinal reinforcements 4 of the first floating plate 1 are corresponded and are inserted It connects in the first vertical muscle fixed ring 33 that one or a column arrange along its length.It similarly, can also be on position-limiting unit 32 The second vertical muscle fixed ring 34 that multiple width directions along position-limiting unit 32 arrange, and more longitudinal directions of the second floating plate 2 are set Reinforcing bar 4, which corresponds, to be plugged in one or the second vertical muscle fixed ring 34 that arranges along its length of column.
Further, the one end of tubular construction far from shearing resistance unit 31 is closed, and separate in the inside of tubular construction One end of shearing resistance unit 31 is provided with elastic packed layer 5, which can be used the high molecular materials systems such as rubber polyurethane At so that it, so as to provide extendable room, will not influence floating plate and deformed and stretched due to caused by temperature with elasticity Contracting.
Further, gas vent 6 is additionally provided on the barrel of tubular construction, for coagulation in floating plate and shear hinge 3 For being vented, draining when soil 7 pours, 32 cohesion collection gas of position-limiting unit is prevented, concrete seven is influenced and pours, guarantee that concrete seven pours It builds closely knit, prevents from forming cavity.
In addition, being coated with lubricant layer on the inner wall of position-limiting unit 32, for concrete seven to be isolated, concrete seven and limit are prevented The inner wall adhesion of bit location 32, guarantee shearing resistance unit 31 can the longitudinal sliding motion in position-limiting unit 32, to will not influence floating Plate is deformed and is stretched due to caused by temperature.
Further, when shear hinge 3 after the installation is completed, since shearing resistance unit 31 is in the first floating plate 1 and the second floating plate 2 Between plate stitch at be exposed in air, therefore preferably in shearing resistance unit 31 between the first floating plate 1 and the second floating plate 2 Part outside apply anti-corrosion material (such as hot galvanizing etc.) and prolonged its service life with preventing shearing resistance unit 31 from getting rusty.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of shear hinge for floating plate, which is characterized in that including the shearing resistance unit that is connect with the first floating plate and pre- The position-limiting unit being embedded in the second floating plate, the shearing resistance unit is using closure or non-closed annular steel construction, the limit Unit uses the tubular construction matched with the shearing resistance unit, so that the annular steel construction is plugged on the tubular construction It is interior, concreting is additionally provided on the annular steel construction between first floating plate and second floating plate Mouthful.
2. shear hinge as described in claim 1, which is characterized in that further include the first longitudinal direction with the annular steel structure connection Reinforced steel bar ring and the second longitudinal direction reinforced steel bar ring connecting with the tubular construction, the longitudinal reinforcement of first floating plate are plugged on described In first longitudinal direction reinforced steel bar ring, the longitudinal reinforcement of second floating plate is plugged in the second longitudinal direction reinforced steel bar ring.
3. shear hinge as claimed in claim 2, which is characterized in that the annular steel construction is U-shaped.
4. shear hinge as claimed in claim 3, which is characterized in that the bottom of the annular steel construction of the U-shaped, which is additionally provided with, to be added Strong plate, the stiffening plate are located at the center of the bottom, and parallel with the side wall of the U-shaped steel.
5. shear hinge as claimed in claim 2, which is characterized in that the annular steel construction is annular.
6. shear hinge as claimed in claim 2, which is characterized in that the first longitudinal direction reinforced steel bar ring and the second longitudinal direction reinforcing bar Ring is elongated hole, and at least two longitudinal reinforcements of first floating plate are plugged on the same first longitudinal direction reinforced steel bar ring Interior, at least two longitudinal reinforcements of second floating plate are plugged in the same second longitudinal direction reinforced steel bar ring.
7. shear hinge as claimed in claim 6, which is characterized in that the quantity of the first vertical muscle fixed ring be it is multiple, it is multiple The first vertical muscle fixed ring is spaced apart along the length direction of the shearing resistance unit;The quantity of the second vertical muscle fixed ring is Multiple, multiple second vertical muscle fixed rings are spaced apart along the length direction of the position-limiting unit.
8. such as shear hinge of any of claims 1-7, which is characterized in that the tubular construction is far from the shearing resistance list Member one end be it is closed, one end of the shearing resistance unit is provided with elastic packed layer in the inside of the tubular construction.
9. such as shear hinge of any of claims 1-7, which is characterized in that also set up on the barrel of the tubular construction There is gas vent.
10. such as shear hinge of any of claims 1-7, which is characterized in that coated on the inner wall of the position-limiting unit There is lubricant layer.
CN201711122982.1A 2017-11-14 2017-11-14 Shear hinge for floating slab Active CN109778595B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711122982.1A CN109778595B (en) 2017-11-14 2017-11-14 Shear hinge for floating slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711122982.1A CN109778595B (en) 2017-11-14 2017-11-14 Shear hinge for floating slab

Publications (2)

Publication Number Publication Date
CN109778595A true CN109778595A (en) 2019-05-21
CN109778595B CN109778595B (en) 2023-12-15

Family

ID=66493486

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711122982.1A Active CN109778595B (en) 2017-11-14 2017-11-14 Shear hinge for floating slab

Country Status (1)

Country Link
CN (1) CN109778595B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110670425A (en) * 2019-09-25 2020-01-10 北京九州一轨隔振技术有限公司 Plate end connecting device and rail structure
CN112012379A (en) * 2020-08-14 2020-12-01 厦门特房建设工程集团有限公司 Aluminum pipe connecting structure, special-shaped aluminum pipe curtain wall and construction method of special-shaped aluminum pipe curtain wall

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202117182U (en) * 2011-06-07 2012-01-18 隔而固(青岛)振动控制有限公司 Sheering hinge and application thereof
KR101225661B1 (en) * 2011-12-02 2013-01-25 한국건설기술연구원 Concrete shear key strengthened with steel cover plate and tension member and the construction method therewith
CN103089273A (en) * 2013-01-14 2013-05-08 西南交通大学 Construction method of longitudinal opening long-span large-volume concrete tunnel lining structure
CN103243618A (en) * 2013-03-29 2013-08-14 隔而固(青岛)振动控制有限公司 Easy-maintenance central shear hinge and application thereof
KR20150128465A (en) * 2014-05-09 2015-11-18 화성궤도 주식회사 Roadbed concrete or asphalt concrete block construction on the railway track roadbed for the device and installation structure and the installation using the same installation method roadbed
CN105484109A (en) * 2015-11-21 2016-04-13 隔而固(青岛)振动控制有限公司 Easy-to-assemble floating track bed precast slab and application thereof
CN106592342A (en) * 2015-11-21 2017-04-26 隔而固(青岛)振动控制有限公司 Durable floating track bed slab and floating track bed
CN207878189U (en) * 2017-11-14 2018-09-18 北京九州一轨隔振技术有限公司 A kind of shear hinge for floating plate

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202117182U (en) * 2011-06-07 2012-01-18 隔而固(青岛)振动控制有限公司 Sheering hinge and application thereof
KR101225661B1 (en) * 2011-12-02 2013-01-25 한국건설기술연구원 Concrete shear key strengthened with steel cover plate and tension member and the construction method therewith
CN103089273A (en) * 2013-01-14 2013-05-08 西南交通大学 Construction method of longitudinal opening long-span large-volume concrete tunnel lining structure
CN103243618A (en) * 2013-03-29 2013-08-14 隔而固(青岛)振动控制有限公司 Easy-maintenance central shear hinge and application thereof
KR20150128465A (en) * 2014-05-09 2015-11-18 화성궤도 주식회사 Roadbed concrete or asphalt concrete block construction on the railway track roadbed for the device and installation structure and the installation using the same installation method roadbed
CN105484109A (en) * 2015-11-21 2016-04-13 隔而固(青岛)振动控制有限公司 Easy-to-assemble floating track bed precast slab and application thereof
CN106592342A (en) * 2015-11-21 2017-04-26 隔而固(青岛)振动控制有限公司 Durable floating track bed slab and floating track bed
CN207878189U (en) * 2017-11-14 2018-09-18 北京九州一轨隔振技术有限公司 A kind of shear hinge for floating plate

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张伟等: "《建筑施工技术》", 上海:同济大学出版社, pages: 375 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110670425A (en) * 2019-09-25 2020-01-10 北京九州一轨隔振技术有限公司 Plate end connecting device and rail structure
CN112012379A (en) * 2020-08-14 2020-12-01 厦门特房建设工程集团有限公司 Aluminum pipe connecting structure, special-shaped aluminum pipe curtain wall and construction method of special-shaped aluminum pipe curtain wall
CN112012379B (en) * 2020-08-14 2022-05-03 厦门特房建设工程集团有限公司 Aluminum pipe connecting structure, special-shaped aluminum pipe curtain wall and construction method of special-shaped aluminum pipe curtain wall

Also Published As

Publication number Publication date
CN109778595B (en) 2023-12-15

Similar Documents

Publication Publication Date Title
CN104612050B (en) A kind of simply supported beam continuous new construction of bridge bridge floor and constructional method
KR101022853B1 (en) Composite girder for constructing bridge
CN204551241U (en) A kind of crack resistance type seamless bridge bridge abutment structure with X muscle
CN101949135B (en) Transverse anchorage system outside hollow slab bridge body and construction process thereof
CN102852244B (en) Detachable self-resetting type energy-dissipation coupling beam
KR101823492B1 (en) Steel plate girder through bridge and the construction method thereof
KR101816142B1 (en) Girder-plate type bridge using arch-shape composite girder and construction method thereof
CN207878189U (en) A kind of shear hinge for floating plate
KR101768903B1 (en) Drain pipe connect device for bridge
CN109778595A (en) A kind of shear hinge for floating plate
CN111455735A (en) Track unit for bridge and track structure
CN104631436A (en) Method for improving integral type bridge abutment sustaining pile stress performance by H-shaped concrete pile
CN209779363U (en) split type vacuum pipeline structure and magnetic suspension high-speed train using same
CN103195260B (en) A kind ofly ensure the ruggedized construction that New And Old Concrete Structures is jointly stressed and construction method thereof
CN201010998Y (en) Steel tube concrete beam pole connecting node structure
KR100646208B1 (en) Steel Plate Girder Structure for Reduction of Noise and Vibration
CN103911948B (en) Be applied to horizontal purlin formula steel work and the construction method thereof of wide concrete rib plate-girder
JP6543652B2 (en) Precast floor system and bridge structure
KR101831770B1 (en) Pile union type steel compose rigid-frame bridge
KR102174574B1 (en) Concrete steel box girder with arch web double plate and its construction method
CN111455819B (en) Support between pre-compaction steel pipe concrete rib
CN204919326U (en) Adopt ultra high performance concrete's simply supported girder bridge bridge floor to construct in succession
CN208415089U (en) A kind of fashioned iron-cell compartment bridge expanssion joint
CN109457866B (en) Anti-sliding partially-wrapped composite beam and prefabricating method thereof
CN209818077U (en) Prefabricated section coupling assembling and have its inverted arch structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 102402 No.32 Guangmao Road, Doudian Town, Fangshan District, Beijing

Applicant after: Beijing Jiuzhou first rail Environmental Technology Co.,Ltd.

Address before: 100070 6068, 6th floor, block a, office park, No.11 Xinghuo Road, Science City, Fengtai District, Beijing

Applicant before: BEIJING JIUZHOUYIGUI SHOCK AND VIBRATION ISOLATION Co.,Ltd.

CB02 Change of applicant information
GR01 Patent grant