CN109764823A - 用于混凝土面板堆石坝的变形监测系统及方法 - Google Patents
用于混凝土面板堆石坝的变形监测系统及方法 Download PDFInfo
- Publication number
- CN109764823A CN109764823A CN201910189325.1A CN201910189325A CN109764823A CN 109764823 A CN109764823 A CN 109764823A CN 201910189325 A CN201910189325 A CN 201910189325A CN 109764823 A CN109764823 A CN 109764823A
- Authority
- CN
- China
- Prior art keywords
- concrete
- pipeline
- walking
- padding layer
- concrete slab
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000012544 monitoring process Methods 0.000 title claims abstract description 34
- 238000000034 method Methods 0.000 title claims abstract description 15
- 238000012360 testing method Methods 0.000 claims description 5
- 238000012545 processing Methods 0.000 claims description 2
- 230000000694 effects Effects 0.000 abstract description 6
- 238000001514 detection method Methods 0.000 abstract description 3
- 239000000463 material Substances 0.000 description 7
- 238000004458 analytical method Methods 0.000 description 3
- 230000008901 benefit Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 3
- 230000000903 blocking effect Effects 0.000 description 2
- 238000004364 calculation method Methods 0.000 description 2
- 239000000835 fiber Substances 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 230000007704 transition Effects 0.000 description 2
- 238000004804 winding Methods 0.000 description 2
- 230000009471 action Effects 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 238000011144 upstream manufacturing Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Abstract
本发明涉及安全监测领域,公开了一种用于混凝土面板堆石坝的变形监测系统及方法,用以提升挠度的监测效果的准确性,以及实现对混凝土面板下的脱空变形检测。本发明包括处理器、检测仪、行走管道、混凝土面板以及垫料层,其中,所述混凝土面板设置在所述垫料层的上面;所述行走管道贴着所述混凝土面板,并沿着混凝土面板堆石坝的坡面自上而下安装于所述垫料层之中;变形监测时,所述检测仪用于沿着所述行走管道爬行,并将爬行轨迹信息发送给所述处理器;所述处理器用于对所述检测仪的爬行轨迹信息进行计算、分析,得出混凝土面板堆的绕度值、行走管道下的脱空值以及脱空部位。本发明适用于混凝土面板堆石坝的变形监测。
Description
技术领域
本发明涉及安全监测领域,特别涉及用于混凝土面板堆石坝的变形监测系统及方法。
背景技术
随着我国水电事业的迅速发展,各种水工建筑物的规模及其运行条件愈来愈复杂,高坝大库建筑物安全运行提出了更高的挑战,对水工建筑物安全性和稳定性的要求越来越高,要确保其安全稳定运行,因此,工程安全监测对水工建筑物的重要性不言而喻,尤其是在混凝土面板堆石坝中起防渗作用的混凝土面板,不仅需要可行的方案和高质量的施工技术确保其混凝土面板及其下基层坝料的变形协调,也需要监视其安全运行而可靠的监测手段,以便在运行时能够及时、准确、方便的测读监测数据,确保其工程建筑物(混凝土面板)的运行安全,因此,混凝土面板及其下基层坝料的变形监测就将成为关键。这就需要有能够及时、准确监测其变形的手段。
混凝土面板堆石坝的防渗系统为钢筋混凝土面板,钢筋混凝土面板位于堆石大坝的上游表面,其下依次为垫层料、过渡料、堆石体。这些结构在运行过程中,都会在水荷载和坝体自身沉降变形的作用下,久而久之,混凝土面板下的垫层料、过渡料、堆石体产生脱空变形空腔和引起发生的挠度变形,导致引起运行安全。
现在监测面板挠度变形及其位置还没有准确可靠的方法,仅是先将安装测斜仪的导管埋设于混凝土面板内,再将测斜仪沿一定间距(一般500~1000cm)安装固定于管中,利用测斜仪(包括固定式测斜仪和人工观测的活动式测斜仪)测得倾角,计算得出测斜仪本身长度50cm的变化值(实际是将其本身长度50cm延长扩大为面板两测点间的距离),最后通过假设不动点,叠加计算出各点相对假定不动点的变化值(绕度)。由于是相对假设不动点,也是将测斜仪本身长度50cm延长扩大为面板两测点间的距离,叠加计算得出的各点相对假定不动点的变化值(挠度),大致换算推套而得。这不但安装难度极大、效果差,浪费大量的人力和时间,还影响挠度的监测效果,其准确性和误差(精度)没法保证。
这种方法不管是自动化的固定式还是人工观测的活动测斜仪,安装、运行的难度极大。在过程中测斜仪都会因而其也极其容易卡堵或因电缆和道管损坏、堵塞而破坏,而其一旦破坏就难以修复而报废,终止或影响其监测及其效果。由于受各种因素的制约,相关监测技术规范亦未明确要求。
发明内容
本发明要解决的技术问题是:提供一种用于混凝土面板堆石坝的变形监测系统及方法,用以提升挠度的监测效果的准确性,以及实现对混凝土面板下的脱空变形检测。
为解决上述问题,本发明采用的技术方案是:用于混凝土面板堆石坝的变形监测系统,包括处理器、检测仪、行走管道、混凝土面板以及垫料层,所述混凝土面板设置在所述垫料层的上面;所述行走管道贴着所述混凝土面板,并沿着混凝土面板堆石坝的坡面自上而下安装于所述垫料层之中;
所述检测仪可以是光纤陀螺仪,变形监测时,所述检测仪用于沿着所述行走管道爬行,并将爬行轨迹发送给所述处理器;所述处理器用于对所述检测仪的爬行轨迹信息进行计算、分析,得出混凝土面板堆的绕度值、行走管道下的脱空值以及脱空部位。
进一步的,所述行走管道可通过卡环与所述混凝土面板紧贴设置。通过卡环使得行走管道紧贴混凝土面板,可使得行走管道与混凝土面板的形变保持一致,从而检测仪可获得更准确的行走轨迹。
用于混凝土面板堆石坝的变形监测方法,包括以下步骤:
A.设置混凝土面板堆石坝时,当设置完垫料层之后,在垫料层中开设凹槽,所述凹槽沿着混凝土面板堆石坝的坡面自上而下,用于容纳行走管道,并使得行走管道放入所述凹槽之后能够贴着垫料层上面的混凝土面板;
B.将行走管道放入步骤A设置好的凹槽中,并在垫料层上面设置混凝土面板;
C.牵引检测仪沿着行走管道爬行,并将检测仪的爬行轨迹信息发送给处理器;
D.通过处理器对检测仪的爬行轨迹信息进行计算、分析,从而得出混凝土面板堆的绕度值、行走管道下的脱空值以及脱空部位。
进一步的,步骤B将行走管道放入凹槽时,还在行走管道上设置了卡环;当垫料层上面设置混凝土面板之后,所述卡环用于使行走管道紧贴混凝土面板。通过卡环使得行走管道紧贴混凝土面板,可使得行走管道与混凝土面板的形变保持一致,从而检测仪可获得更准确的行走轨迹。
本发明与现有技术相比具有以下优点:
本发明仅需先将检测仪的行走管道紧贴着所述混凝土面板,并沿着混凝土面板堆石坝的坡面自上而下安装于所述垫料层之中,变形监测时,让监测仪沿行走管道顺坡牵引行走,这种方式不需复杂设备和技术,现场人员施工操作简单、方便,优势极大地节约了安装、观测的时间;计算变形量时,通过处理器对检测仪的爬行轨迹进行分析,就可以快速得出混凝土面板堆的绕度值、行走管道下的脱空值以及行走管道下的脱空部位,提高了监测的可靠性和准确性,具有重要的工程意义,为堆石坝的面板挠度及其下垫层料的脱空监测提供了非常好的应用实例,可以在类似工程全面推广。
此外,相比于将管道设置于混凝土面板之中的传统方式,本发明将行走管道设置在垫料层中,不会削弱混凝土面板的强度,在一定程度上也保障了混凝土面板堆石坝稳定性。
附图说明
图1为实施例的结构示意图。
图2为绕度分析图;
图3为脱空分析图。
图中编号:1是混凝土面板,2是行走管道,3是垫料层,4是卡环,L0是未变形时检测仪的正常行走爬行轨迹,L1是无脱空情况下检测仪的行走爬行轨迹,L2是有脱空情况下检测仪的行走爬行轨迹
具体实施方式
为了克服现有技术中存在的不足,本发明提供一种用于混凝土面板堆石坝的变形监测系统,包括处理器、检测仪、行走管道、混凝土面板以及垫料层,所述混凝土面板设置在所述垫料层的上面;所述行走管道贴着所述混凝土面板,并沿着混凝土面板堆石坝的坡面自上而下安装于所述垫料层之中;
所述检测仪可以是光纤陀螺仪,变形监测时,所述检测仪用于沿着所述行走管道爬行,并将爬行轨迹发送给所述处理器;所述处理器用于对所述检测仪的爬行轨迹信息进行计算、分析,得出混凝土面板堆的绕度值、行走管道下的脱空值以及脱空部位。
进一步的,所述行走管道可通过卡环与所述混凝土面板紧贴设置。通过卡环使得行走管道紧贴混凝土面板,可使得行走管道与混凝土面板的形变保持一致,从而检测仪可获得更准确的行走轨迹。
基于以上的系统,本发明还提供了一种用于混凝土面板堆石坝的变形监测方法,该方法包括以下步骤:
A.设置混凝土面板堆石坝时,当设置完垫料层之后,在垫料层中开设凹槽,所述凹槽沿着混凝土面板堆石坝的坡面自上而下,用于容纳行走管道,并使得行走管道放入所述凹槽之后能够贴着垫料层上面的混凝土面板。
B.将行走管道放入步骤A置好的凹槽中,并在垫料层上面设置混凝土面板。将行走管道放入凹槽时,还可以在行走管道上设置卡环;当垫料层上面设置混凝土面板之后,所述卡环用于使行走管道紧贴混凝土面板,通过卡环使得行走管道紧贴混凝土面板,可使得行走管道与混凝土面板的形变保持一致,从而检测仪可获得更准确的行走轨迹。
C.牵引检测仪沿着行走管道爬行,并将检测仪的爬行轨迹信息发送给处理器。
D.通过处理器对检测仪的爬行轨迹信息进行计算、分析,从而得出混凝土面板堆的绕度值、行走管道下的脱空值以及脱空部位。处理器进行轨迹分析时,可以先将所有时刻的轨迹进行曲线拟合,得到轨迹曲线,再根据所得曲线计算出混凝土面板堆的绕度值、行走管道下的脱空值以及脱空部位。
实施例
实施例提供一种用于混凝土面板堆石坝的变形监测系统,包括处理器、检测仪、行走管道2、混凝土面板1以及垫料层3,如图1所示,所述混凝土面板1设置在所述垫料层3的上面;所述行走管道2紧贴着所述混凝土面板1,并沿着混凝土面板堆石坝的坡面自上而下安装于所述垫料层3之中。本实施例中,所述行走管道2可通过卡环4与所述混凝土面板1紧贴设置,通过卡环4使得行走管道2紧贴混凝土面板1,可使得行走管道2与混凝土面板1的形变保持一致,从而检测仪可获得更准确的行走轨迹。
变形监测时,所述检测仪用于沿着所述行走管道2爬行,并将爬行轨迹发送给所述处理器;所述处理器用于对所述检测仪的爬行轨迹信息进行计算、分析,得出混凝土面板堆1的绕度值、行行走管道下的脱空部位以及脱空部位的脱空值。
实施例进行变形监测的工作原理如下:
设置混凝土面板堆石坝时,当设置完垫料层3之后,首先,在垫料层中开设凹槽,所述凹槽沿着混凝土面板堆石坝的坡面自上而下,用于容纳行走管道2,并使得行走管道2放入所述凹槽之后能够贴着垫料层3上面的混凝土面板1;
然后,将行走管道2放入设置好的凹槽中,并在垫料层3上面设置混凝土面板1;
之后,牵引检测仪沿着行走管道2爬行,并将检测仪的爬行轨迹信息发送给处理器;
最后,通过处理器对检测仪的爬行轨迹信息进行计算、分析,从而得出混凝土面板堆1的绕度值、行行走管道下的脱空部位以及脱空部位的脱空值。如果处理器上最终所呈现的轨迹图如图2所示,则表明混凝土面板堆发生了变形,处理器通过曲线L1即可计算并输出混凝土面板堆的绕度值;如果处理器上最终所呈现的轨迹图如图3所示,则表明混凝土面板堆发生了变形,同时,行走管道还发生了脱空现象,处理器将输出脱空值以及脱空的开始位置S1和结束位置S2。
Claims (4)
1.用于混凝土面板堆石坝的变形监测系统,包括处理器、检测仪、行走管道、混凝土面板以及垫料层,所述混凝土面板设置在所述垫料层的上面;其特征在于,所述行走管道贴着所述混凝土面板,并沿着混凝土面板堆石坝的坡面自上而下安装于所述垫料层之中;
变形监测时,所述检测仪用于沿着所述行走管道爬行,并将爬行轨迹发送给所述处理器;所述处理器用于对所述检测仪的爬行轨迹信息进行计算、分析,得出混凝土面板堆的绕度值、行走管道下的脱空值以及脱空部位。
2.如权利要求1所述的用于混凝土面板堆石坝的变形监测系统,其特征在于,所述行走管道通过卡环与所述混凝土面板紧贴设置。
3.用于混凝土面板堆石坝的变形监测方法,其特征在于,包括以下步骤:
A.设置混凝土面板堆石坝时,当设置完垫料层之后,在垫料层中开设凹槽,所述凹槽沿着混凝土面板堆石坝的坡面自上而下,用于容纳行走管道,并使得行走管道放入所述凹槽之后能够贴着垫料层上面的混凝土面板;
B.将行走管道放入步骤A设置好的凹槽中,并在垫料层上面设置混凝土面板;
C.牵引检测仪沿着行走管道爬行,并将检测仪的爬行轨迹信息发送给处理器;
D.通过处理器对检测仪的爬行轨迹信息进行计算、分析,从而得出混凝土面板堆的绕度值、行走管道下的脱空值以及脱空部位。
4.如权利要求3所述的用于混凝土面板堆石坝的变形监测方法,其特征在于,步骤B将行走管道放入凹槽时,还在行走管道上设置了卡环;当垫料层上面设置混凝土面板之后,所述卡环用于使行走管道紧贴混凝土面板。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910189325.1A CN109764823A (zh) | 2019-03-13 | 2019-03-13 | 用于混凝土面板堆石坝的变形监测系统及方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910189325.1A CN109764823A (zh) | 2019-03-13 | 2019-03-13 | 用于混凝土面板堆石坝的变形监测系统及方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109764823A true CN109764823A (zh) | 2019-05-17 |
Family
ID=66458980
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910189325.1A Pending CN109764823A (zh) | 2019-03-13 | 2019-03-13 | 用于混凝土面板堆石坝的变形监测系统及方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109764823A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110274570A (zh) * | 2019-07-30 | 2019-09-24 | 中国电建集团成都勘测设计研究院有限公司 | 用于堆石坝层间错动变形的监测系统 |
CN110274571A (zh) * | 2019-07-30 | 2019-09-24 | 中国电建集团成都勘测设计研究院有限公司 | 用于堆石坝防渗体心墙水平位移变形的监测系统 |
CN111947562A (zh) * | 2020-06-30 | 2020-11-17 | 深圳大学 | 一种堆石坝内、外变形一体化监测方法 |
Citations (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3804389A1 (de) * | 1988-02-12 | 1989-08-24 | Gewerk Eisenhuette Westfalia | Messeinrichtung, insbesondere fuer ueberlast-getriebe |
JP2000081316A (ja) * | 1998-09-07 | 2000-03-21 | Jiotetsuku:Kk | 変位測定装置およびダムのたわみ観測装置 |
CN1412521A (zh) * | 2002-12-03 | 2003-04-23 | 武汉理工大学 | 基于光纤陀螺技术检测水下工程结构形变的方法及装置 |
CN1558182A (zh) * | 2004-01-17 | 2004-12-29 | 湖北清江水布垭工程建设公司 | 坝体面板挠度或坝体内部水平及垂直变形的测量系统 |
CN1940473A (zh) * | 2004-01-17 | 2007-04-04 | 湖北清江水布垭工程建设公司 | 大坝面板挠度或坝体内部变形的监测管道 |
US20090184230A1 (en) * | 2008-01-22 | 2009-07-23 | Carney Jr Robert S | Concrete formwork system for forming cast in place horizontal slabs |
KR20090087600A (ko) * | 2008-02-13 | 2009-08-18 | 이규완 | 벤딩 센서 |
CN105133841A (zh) * | 2015-07-29 | 2015-12-09 | 五洋建设集团股份有限公司 | 空间曲面钢结构管桁架屋盖安装施工工法 |
CN105258670A (zh) * | 2015-11-06 | 2016-01-20 | 三峡大学 | 大坝内观沉降监测管 |
CN105910545A (zh) * | 2016-03-09 | 2016-08-31 | 四川大学 | 高土石坝变形监测的光纤传感技术与系统 |
CN106149641A (zh) * | 2016-08-25 | 2016-11-23 | 中国电建集团西北勘测设计研究院有限公司 | 一种使面板具备可维修性的面板堆石坝及方法 |
CN107131862A (zh) * | 2017-06-23 | 2017-09-05 | 中国电建集团贵阳勘测设计研究院有限公司 | 一种堆石坝面板变形监测装置及施工方法 |
US20180165896A1 (en) * | 2016-12-12 | 2018-06-14 | Hyundai Motor Company | Method of diagnosing oil leak of engine clutch in hybrid electric vehicle |
CN207537975U (zh) * | 2017-11-30 | 2018-06-26 | 中国电建集团成都勘测设计研究院有限公司 | 深厚覆盖层上面板堆石坝坝基防渗结构 |
CN207622708U (zh) * | 2017-12-21 | 2018-07-17 | 山西恒瑞金墒科技有限公司 | 一种水库大坝变形监测装置 |
CN109059845A (zh) * | 2018-06-29 | 2018-12-21 | 深圳大学 | 一种面板堆石坝内部形变监测方法及监测系统 |
CN109404012A (zh) * | 2018-11-21 | 2019-03-01 | 中国电建集团成都勘测设计研究院有限公司 | Ⅳ~ⅵ级围岩超挖隧道初期支护方法 |
-
2019
- 2019-03-13 CN CN201910189325.1A patent/CN109764823A/zh active Pending
Patent Citations (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3804389A1 (de) * | 1988-02-12 | 1989-08-24 | Gewerk Eisenhuette Westfalia | Messeinrichtung, insbesondere fuer ueberlast-getriebe |
JP2000081316A (ja) * | 1998-09-07 | 2000-03-21 | Jiotetsuku:Kk | 変位測定装置およびダムのたわみ観測装置 |
CN1412521A (zh) * | 2002-12-03 | 2003-04-23 | 武汉理工大学 | 基于光纤陀螺技术检测水下工程结构形变的方法及装置 |
CN1558182A (zh) * | 2004-01-17 | 2004-12-29 | 湖北清江水布垭工程建设公司 | 坝体面板挠度或坝体内部水平及垂直变形的测量系统 |
CN1940473A (zh) * | 2004-01-17 | 2007-04-04 | 湖北清江水布垭工程建设公司 | 大坝面板挠度或坝体内部变形的监测管道 |
US20090184230A1 (en) * | 2008-01-22 | 2009-07-23 | Carney Jr Robert S | Concrete formwork system for forming cast in place horizontal slabs |
KR20090087600A (ko) * | 2008-02-13 | 2009-08-18 | 이규완 | 벤딩 센서 |
CN105133841A (zh) * | 2015-07-29 | 2015-12-09 | 五洋建设集团股份有限公司 | 空间曲面钢结构管桁架屋盖安装施工工法 |
CN105258670A (zh) * | 2015-11-06 | 2016-01-20 | 三峡大学 | 大坝内观沉降监测管 |
CN105910545A (zh) * | 2016-03-09 | 2016-08-31 | 四川大学 | 高土石坝变形监测的光纤传感技术与系统 |
CN106149641A (zh) * | 2016-08-25 | 2016-11-23 | 中国电建集团西北勘测设计研究院有限公司 | 一种使面板具备可维修性的面板堆石坝及方法 |
US20180165896A1 (en) * | 2016-12-12 | 2018-06-14 | Hyundai Motor Company | Method of diagnosing oil leak of engine clutch in hybrid electric vehicle |
CN107131862A (zh) * | 2017-06-23 | 2017-09-05 | 中国电建集团贵阳勘测设计研究院有限公司 | 一种堆石坝面板变形监测装置及施工方法 |
CN207537975U (zh) * | 2017-11-30 | 2018-06-26 | 中国电建集团成都勘测设计研究院有限公司 | 深厚覆盖层上面板堆石坝坝基防渗结构 |
CN207622708U (zh) * | 2017-12-21 | 2018-07-17 | 山西恒瑞金墒科技有限公司 | 一种水库大坝变形监测装置 |
CN109059845A (zh) * | 2018-06-29 | 2018-12-21 | 深圳大学 | 一种面板堆石坝内部形变监测方法及监测系统 |
CN109404012A (zh) * | 2018-11-21 | 2019-03-01 | 中国电建集团成都勘测设计研究院有限公司 | Ⅳ~ⅵ级围岩超挖隧道初期支护方法 |
Non-Patent Citations (13)
Title |
---|
YOUNG-SHIN KANG等: "Ground test results of rotor governor and rate SAS for small tilt rotor UAV", 《2007 INTERNATIONAL CONFERENCE ON CONTROL, AUTOMATION AND SYSTEMS》 * |
刘夏平;唐述;杨作用;蔡卡宏;刘爱荣;: "脱空钢管混凝土短柱偏心受压破坏形态试验研究", 广州大学学报(自然科学版), no. 03 * |
刘畅;姬树军;彭薇薇;: "某水电站地下厂房压力钢管-外包混凝土脱空质量缺陷分析", 水电站设计, no. 03 * |
卞晓卫;蒋剑;余德平;李帅军;曹景阳;: "超长管路水管式沉降仪在阿尔塔什水利枢纽工程中的应用研究", 水利水电技术, no. 1 * |
叶勇;韩林海;陶忠;: "脱空对圆钢管混凝土受剪性能的影响分析", 工程力学, no. 1 * |
吴杰: "有机玻璃模型桥桥面形态与结构损伤关系研究", 《中国优秀硕士学位论文全文数据库 工程科技II辑》, pages 034 - 190 * |
张宏;凌建明;袁捷;钱劲松;: "基于板底脱空的水泥混凝土道面结构理论分析", 同济大学学报(自然科学版), no. 11 * |
张运达;王能峰;马金根;尹显科;: "瀑布沟水电站库首右岸拉裂变形体成因机制与稳定性分析", 中国地质灾害与防治学报, no. 04 * |
柳捷;: "脱空钢管混凝土拱桥极限承载力数值分析", 工程与建设, no. 02 * |
毛渐;王正中;刘铨鸿;: "堆石体分区和堆石料压缩模量对面板坝变形影响分析", 中国农村水利水电, no. 08 * |
蒋中明;李永澍;胡炜;王鹏;: "高面板堆石坝面板脱空效应", 长沙理工大学学报(自然科学版), no. 02 * |
郑仲寿, 李俊杰: "基于有限元仿真面板坝脱空分析", 东北水利水电, no. 08 * |
郭友军;丁海波;和少伟;刘金荣;王柱;: "混凝土面板堆石坝顶部面板脱空规律初探", 施工技术, no. 1 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110274570A (zh) * | 2019-07-30 | 2019-09-24 | 中国电建集团成都勘测设计研究院有限公司 | 用于堆石坝层间错动变形的监测系统 |
CN110274571A (zh) * | 2019-07-30 | 2019-09-24 | 中国电建集团成都勘测设计研究院有限公司 | 用于堆石坝防渗体心墙水平位移变形的监测系统 |
CN111947562A (zh) * | 2020-06-30 | 2020-11-17 | 深圳大学 | 一种堆石坝内、外变形一体化监测方法 |
CN111947562B (zh) * | 2020-06-30 | 2021-05-04 | 深圳大学 | 一种堆石坝内、外变形一体化监测方法 |
WO2022001104A1 (zh) * | 2020-06-30 | 2022-01-06 | 深圳大学 | 一种堆石坝内、外变形一体化监测方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11236612B2 (en) | Advanced monitoring device for whole-process deformation curve of surrounding rock of tunnel excavation and implementation method thereof | |
Mohamad et al. | Monitoring twin tunnel interaction using distributed optical fiber strain measurements | |
Wang et al. | Monitoring the behavior of segment joints in a shield tunnel using distributed fiber optic sensors | |
Sui et al. | Distributed fibre optic monitoring of damaged lining in double-arch tunnel and analysis of its deformation mode | |
CN109764823A (zh) | 用于混凝土面板堆石坝的变形监测系统及方法 | |
Zhu et al. | Performance monitoring of a curved shield tunnel during adjacent excavations using a fiber optic nervous sensing system | |
CN104180759B (zh) | 水库坝体沉陷与水平位移基准点检测装置及检测方法 | |
Zhang et al. | Deformation monitoring and performance analysis on the shield tunnel influenced by adjacent deep excavations | |
CN104061871B (zh) | 一种隧道非接触变形监测方法 | |
Li et al. | Experimental investigation on pipe-soil interaction due to ground subsidence via high-resolution fiber optic sensing | |
CN104748695A (zh) | 基于区段精细测量的大断面地下洞室早期变形监测方法 | |
Wang et al. | Fiber optic sensing and performance evaluation of a water conveyance tunnel with composite linings under super-high internal pressures | |
CN106021959A (zh) | 适用于深埋条件下仿矩形市政顶管隧道侧摩阻力计算方法 | |
Mohamad et al. | Distributed fibre optic inclinometer with cloud-based monitoring system | |
Dixon et al. | Landslide hazard evaluation by means of several monitoring techniques, including an acoustic emission sensor | |
Zhang et al. | Complex Deformation Monitoring of Shield Tunnel Segment Joints Using Distributed Fiber Optic Sensing Technology: Experimental Verification | |
CN1554924A (zh) | 一种地下洞室、隧道非接触式收敛监测的方法 | |
Liu et al. | Evaluation of effects of static pile driving on existing metro tunnel structure | |
Inaudi et al. | Geostructural monitoring with long-gage interferometric sensors | |
Franklin | The monitoring of structures in rock | |
Lunardi et al. | Tunnel monitoring system—a contribution for the preparation of guidelines | |
CN209432072U (zh) | 用于混凝土面板堆石坝的埋管结构以及变形监测系统 | |
Dewynter et al. | Brillouin optical fiber distributed sensor for settlement monitoring while tunneling the metro line 3 in Cairo, Egypt | |
Dong et al. | Monitoring and prediction of horizontal displacement of underground enclosure piles in subway foundation pits | |
Michelin et al. | Holistic approach for the construction monitoring of the Grand Paris Express metro network |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |