CN109763606A - A kind of construction method of reinforced concrete combination batter post - Google Patents
A kind of construction method of reinforced concrete combination batter post Download PDFInfo
- Publication number
- CN109763606A CN109763606A CN201910066583.0A CN201910066583A CN109763606A CN 109763606 A CN109763606 A CN 109763606A CN 201910066583 A CN201910066583 A CN 201910066583A CN 109763606 A CN109763606 A CN 109763606A
- Authority
- CN
- China
- Prior art keywords
- batter post
- concrete
- construction
- template
- lower section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The present invention discloses a kind of construction method of reinforced concrete combination batter post, includes the following steps: (1) preparation of construction;(2) batter post positioning and joint bar;(3) batter post bottom steel pipe support is set up and lower section taper pile shuttering is laid with;(4) reinforcement installation;(5) PVC chute is arranged;(6) lower section taper pile shuttering is reinforced;(7) concrete optimum;(8) lower section batter post concreting;(9) lower section batter post side form is removed;(10) upper section construction of inclined column: upper section construction of inclined column process repeats step (2) to (9) with lower section construction of inclined column process.Batter post concrete of the present invention is not easy the case where vibrating, optimised coagulation soil match ratio, adjusts concrete slump, and when concrete vibrating is vibrated using chute assistance, and the molding of batter post reinforced concrete structure is good.
Description
Technical field
The invention belongs to reinforced concrete construction technical fields, and in particular to a kind of construction of reinforced concrete combination batter post
Method.
Background technique
" nationwide fitness programs " have become the indispensable a part of our people's daily life at present, and what is come into being is a large amount of
The construction of gymnasium building, under the premise of meeting building function and requiring, more and more handsome in appearance, sport for being in various forms
Class building occurs as emerging rapidly in large numbersBamboo shoots after a spring rain.In the main structure construction stage of stadiums, armored concrete batter post is often had
Formwork reinforcement is insecure, piece is unsatisfactory for requirement, concrete vibrating is not in place, causes bloated concrete, spillage, honeycomb, pitted skin
Phenomena such as.If the cast-in-place structural size that will cause armored concrete batter post that takes appropriate measures not in time and bearing capacity are discontented with
Sufficient code requirement ultimately causes economic loss, quality accident, safety accident.
Summary of the invention
Goal of the invention: present invention aims in view of the deficiencies of the prior art, provide a kind of reinforced concrete combination batter post
Construction method, the present invention be suitable for armored concrete batter post, especially in public building main structure construction, and to coagulation
The engineering that native presentation quality has higher requirements.
Technical solution: a kind of construction method of reinforced concrete combination batter post of the present invention includes the following steps:
(1) preparation of construction: 1) technique preparation: design drawing is familiar with before construction, detailed reinforced concrete combination batter post is worked out and applies
Work method is specified outside quantity, cross-sectional sizes, vertical section sequence of construction and the concrete formation of reinforced concrete combination batter post
Appearance quality requirement;2) people, machine, material prepare: with an appropriate number of construction according to the size of project amount and the factor of operating environment
Operating personnel is simultaneously equipped with corresponding administrative staff, prepares the resources such as the material needed in construction and Work tool;According to live practical
Situation is equipped with corresponding rapidoprint and installation tool:
(2) batter post positioning and joint bar: according to structure, architectural discipline design drawing, using Tekla software modeling, determine that batter post exists
The accurate positionin of plane;The construction of batter post joint bar is carried out after entry level column reinforcement installation, joint bar is certain by in-depth drawing bending
Angle carries out joint bar auxiliary positioning using mold;
(3) batter post bottom steel pipe support is set up and lower section taper pile shuttering is laid with: batter post being considered as Vierendeel girder, using building safety of siping tea
Software for calculation is checked, and requires progress batter post steel pipe support to set up according to high-supported formwork according to calculated result, supporting erection finishes
Afterwards, the laying of batter post end template is carried out;
(4) reinforcement installation: after batter post end template is laid, batter post reinforcement installation is carried out, PVC is placed in time in installation process and slips
Slot vibrates to concrete with ancillary vibration stick;
(5) PVC chute is arranged: in batter post reinforcing bar process of binding, reserving 2 single u-shaped PVC chutes in batter post and facilitates concrete vibrating
The insertion of stick extracts PVC chute with vibrating spear during concrete vibrating;
(6) lower section taper pile shuttering is reinforced: after reinforcement installation, carrying out the reinforcing of lower section taper pile shuttering, lower section batter post column bottom absolute altitude
4.700m, the high 8.700m of batter post top mark, the bed die of batter post support to beam bottom, and the backform and side form of batter post carry out segmentation support;Institute
The top-side for stating template is provided with venthole, and the length direction on the outer surface of the template along template is provided with several wood
The outer surface of a tree, used in making timber for boats, the bottom of the template is reinforced using double steel pipe around surrounding, and middle and upper part is reinforced using tie,
The bed die side of the batter post is evenly arranged with several column bottoms cross bar, and column bottom cross bar is close to the bottom of double steel pipe and tie,
Diagonal brace is provided on the cross bar of the column bottom, the other end of the diagonal brace is fixed in base by being set to the timber wedge of base, under
After the completion of section taper pile shuttering is reinforced, then carry out pouring for concrete;
(7) concrete optimum: adjustment concrete coarse-fine aggregate gradation determines concrete mix, the slump before concreting;
(8) lower section batter post concreting: after the completion of formwork reinforcement, carrying out watering to template and moisten, carry out concreting,
In concreting process, is vibrated by the chute in setting template with vibrating spear, make coagulation rammed earth, finally by chute
It is extracted with vibrating spear;
1) batter post maximum segment pours height no more than 2m, pours layered segmentation, check at any time the stability of shuttering supporting, especially
It pays attention to the deformation of formwork reinforcement system herein;
2) it is carried out before batter post concreting in strict accordance with scheme, in the environment of hot weather, template watering is carried out, to protect
The water retention property of Surface Quality of Concrete and concrete is demonstrate,proved;
3) after the completion of concreting, temporarily should not demoulding, guarantee that concrete obtains sufficient moisture-keeping maintaining;
(9) lower section batter post side form is removed: lower section batter post concreting completion reaches demoulding condition, carries out column top, side mould
Plate Demolition Construction, to observe the construction molding situation of concrete;Batter post after demoulding is carried out uniformly using curing compound
Sprinkling wraps up plastic film on its surface, to reach concrete wet curing function and effect;Batter post bed die waits for reaching with feeding intensity of test block
It can be removed to 100% side;
(10) upper section construction of inclined column: upper section construction of inclined column process is identical as lower section construction of inclined column process, repeats step (2) to (9).
Preferably, in the step (10), before the reinforcing of upper section taper pile shuttering, it is additionally provided with facing convenient for constructing operation
When ladder, the temporary ladder in being provided with operating platform on the same plane of completed batter post, the temporary ladder with it is upper
It is also equipped with operating platform in plane between at the top of section taper pile shuttering, the operating platform completely spreads template, the ground of the template
Face is evenly arranged with several brace a tree, used in making timber for boats;The two sides of the temporary ladder are respectively arranged with ladder handrail, and the ladder handrail is
In order to guarantee the safety of construction personnel;The bottom end of the temporary ladder is provided with cushion block.
Preferably, in the step (10), before the reinforcing of upper section taper pile shuttering, the backform and side form of upper section batter post are supported
To beam bottom.
Preferably, the template uses mirror surface formwork, and the size of the mirror surface formwork is 1830mm × 915mm × 15mm.
Preferably, the tie uses finished product reinforcing member.
The utility model has the advantages that it is fixed simulate to batter post using Tekla and related software in (1) construction method of the present invention
Position is determined that batter post projects accurate location in horizontal plane, and is accurately positioned using batter post mold;Batter post mold is regarded as when checking
Three-D space structure is converted two-dimension plane structure by Vierendeel girder, the present invention, is convenient for site operation, guarantees the accurate positioning of batter post
With it is easy for construction;
(2) for tie using sizing reinforcing member, template uses mirror surface formwork, and can be used in turn in the present invention, and material is effectively reduced
The proportion of goods damageds of material meet the requirement of green construction;The use of sizing reinforcing member makes template without screw rod eye, and hole is not present, mixed
Solidifying soil pour after the completion of without partial cells pitted skin caused by spillage, without cutting off the Screw arbor with nut at both-ends deformed in column, easy demoulding can be with
The mould bases for improving batter post is used in turn rate;
(3) chute is provided in the template in the present invention in advance, the design of chute can assist vibrating spear to carry out vibrated concrete,
Coagulation rammed earth is set to ensure that the molding of batter post structure is good, concrete shifts to an earlier date trial, and optimised coagulation soil match ratio adjusts coagulation
The native slump, after batter post demoulding has been effectively ensured, the presentation quality of concrete improves an acceptable quality level of main structure.
Detailed description of the invention
Fig. 1 is the construction process figure of reinforced concrete combination batter post of the present invention;
Fig. 2 is the structural schematic diagram that lower section batter post of the present invention is reinforced;
Fig. 3 is the structural schematic diagram that upper section batter post of the present invention is reinforced;
Fig. 4 is the structural plan figure in gymnasium described in embodiment;
Fig. 5 is the sectional view in nationwide fitness programs shop described in embodiment.
In figure, 1- chute;2- venthole;3- ladder handrail;4- wood a tree, used in making timber for boats;5- template;6- temporary ladder;7- cushion block;8- wood
Wedge;9- diagonal brace;10- column bottom cross bar;11- beam;12- tie;13- double steel pipe.
Specific embodiment
Technical solution of the present invention is described in detail below by attached drawing, but protection scope of the present invention is not limited to
The embodiment.
Embodiment: a kind of construction method of reinforced concrete combination batter post includes the following steps:
(1) preparation of construction: 1) technique preparation: design drawing is familiar with before construction, detailed reinforced concrete combination batter post is worked out and applies
Work method is specified outside quantity, cross-sectional sizes, vertical section sequence of construction and the concrete formation of reinforced concrete combination batter post
Appearance quality requirement;2) people, machine, material prepare: with an appropriate number of construction according to the size of project amount and the factor of operating environment
Operating personnel is simultaneously equipped with corresponding administrative staff, prepares the resources such as the material needed in construction and Work tool;According to live practical
Situation is equipped with corresponding rapidoprint and installation tool:
(2) batter post positioning and joint bar: according to structure, architectural discipline design drawing, using Tekla software modeling, determine that batter post exists
The accurate positionin of plane;The construction of batter post joint bar is carried out after entry level column reinforcement installation, joint bar is certain by in-depth drawing bending
Angle carries out joint bar auxiliary positioning using mold;
(3) batter post bottom steel pipe support is set up and lower section taper pile shuttering is laid with: batter post being considered as Vierendeel girder 11, using building peace of siping tea
Full software for calculation is checked, and requires progress batter post steel pipe support to set up according to high-supported formwork according to calculated result, supporting erection is complete
Bi Hou carries out batter post end template 5 and is laid with, and the template 5 uses mirror surface formwork 5, the size of the mirror surface formwork 5 be 1830mm ×
915mm × 15mm, mirror surface formwork is big with rigidity, surface smoothness, smoothness are high, is conducive to concrete formation, has enough to meet the need the frequency
Height, in the bottom of template and docking it should be ensured that position is accurate for Vierendeel girder, opposite joint is tight;
(4) reinforcement installation: after batter post end template 5 is laid, batter post reinforcement installation is carried out, PVC is placed in time in installation process and slips
Slot 1 vibrates to concrete with ancillary vibration stick, in reinforcement fabrication and installation, pays attention to the reserved of cushion block of concrete bar protective layer
Be of the required size, concrete surface layer is easy to crack when protective layer is excessive, is unfavorable for the durability of structure when too small;
(5) PVC chute 1 is arranged: in batter post reinforcing bar process of binding, reserving 2 single u-shaped PVC chutes 1 in batter post and concrete is facilitated to shake
The insertion of tamper extracts PVC chute 1 with vibrating spear during concrete vibrating;
(6) lower section taper pile shuttering is reinforced: after reinforcement installation, carries out lower section taper pile shuttering 5 and reinforce, lower section batter post column bottom absolute altitude
4.700m, the high 8.700m of batter post top mark, the bed die of batter post support to 11 bottom of beam, and the backform and side form of batter post carry out segmentation support;
The top-side of the template 5 is provided with venthole 2, and venthole 2 is used for casting concrete, edge on the outer surface of the template 5
The length direction of template 5 is provided with several wooden a tree, used in making timber for boats 4, and the wooden a tree, used in making timber for boats 4 is used for the reinforcing of batter post secondary joist;Outside the bottom of the template 5
Surface is reinforced using double steel pipe 13 around surrounding, and middle and upper part is reinforced using tie 12, and tie 12 is added using finished product
Firmware, tie 12 are mainly used for the reinforcing of batter post main joist, are not necessarily to split bolt, reinforce comparatively fast, can guarantee the entirety of concrete
Property;The bed die side of the batter post is evenly arranged with several column bottoms cross bar 10, and column bottom cross bar 10 is close to double steel pipe 13 and column
The bottom of hoop 12, is provided with diagonal brace 9 on column bottom cross bar 10, and the other end of the diagonal brace 9 is by being set to the timber wedge 8 of base
It is fixed in base, after the completion of lower section taper pile shuttering 5 is reinforced, then carries out pouring for concrete;
(7) concrete optimum: adjustment concrete coarse-fine aggregate gradation determines concrete mix, the slump before concreting,
Optimised coagulation soil match ratio adjusts concrete slump;
(8) lower section batter post concreting: after the completion of template 5 is reinforced, carrying out watering to template 5 and moisten, carry out concreting,
It in concreting process, is vibrated by the chute 1 in setting template 5 with vibrating spear, makes coagulation rammed earth, finally will
Chute 1 is extracted with vibrating spear;
1) batter post maximum segment pours height no more than 2m, pours layered segmentation, check at any time the stability of the support of template 5,
Especially pay attention to the deformation of 5 reinforcement system of template herein;
2) it is carried out before batter post concreting in strict accordance with scheme, in the environment of hot weather, carries out template 5 and water, thus
It ensure that the water retention property of Surface Quality of Concrete and concrete;
3) after the completion of concreting, temporarily should not demoulding, guarantee that concrete obtains sufficient moisture-keeping maintaining;
(9) lower section batter post side form is removed: lower section batter post concreting completion reaches demoulding condition, carries out column top, side mould
5 Demolition Construction of plate, to observe the construction molding situation of concrete;Batter post after demoulding is carried out uniformly using curing compound
Sprinkling wraps up plastic film on its surface, to reach concrete wet curing function and effect;Batter post bed die waits for reaching with feeding intensity of test block
It can be removed to 100% side;
(10) upper section construction of inclined column: upper section construction of inclined column process is identical as lower section construction of inclined column process, repeats step (2) to (9);
In this step, before the reinforcing of upper section taper pile shuttering 5, it is additionally provided with the temporary ladder 6 convenient for constructing operation, it is described temporarily to climb
Ladder 6 is in being provided with operating platform on the same plane of completed batter post, the temporary ladder 6 and 5 top of upper section taper pile shuttering
Between plane on be also equipped with operating platform, the operating platform completely spreads template 5, and the ground of the template 5 is evenly arranged with
Several brace a tree, used in making timber for boats 4;The two sides of the temporary ladder 6 are respectively arranged with ladder handrail 3, and the ladder handrail 3 is to guarantee
The safety of construction personnel;The bottom end of the temporary ladder 6 is provided with cushion block 7;Before the reinforcing of upper section taper pile shuttering 5, upper section is oblique
The backform and side form of column support to docking for 11 bottom of beam, conscientious detection template and top and beam, it is ensured that position is accurate, and opposite joint is tight
It is close.
The present invention is suitable for the gymnasium of Shucheng County, Anhui Province sports center construction project first stage of the project and the whole people are good for
Good application has been obtained in body shop, achieves certain economic interests;Shucheng County, Anhui Province sports center construction project
First stage of the project is located to the west of Wan Folu, to the north of seven roads Men Yan, is made of that (one is stadium, two shops are body " one, two shops "
Educate shop and nationwide fitness programs shop);Total land area 320216 ㎡, 84495 ㎡ of overall floorage;2 layers on the ground of gymnasium, underground part
1 layer, a circle is 24 groups of reinforced concrete combination batter posts on the outside of grandstand layer, 3 pillars of every group of batter post, wherein 2 are two-way to incline
Tiltedly (batter post sectional dimension 400mm × 800mm, 66.1 ° of circumferential tilt angle, 56.2 ° of radial angular orientation), 1 be unidirectionally to incline
Tiltedly (batter post sectional dimension 700mm × 800mm, 72.8 ° of circumferential tilt angle);5 layers on the ground of nationwide fitness programs shop, 2 layers of underground part,
Position shares four armored concrete batter posts (batter post sectional dimension 600mm × 600mm, tilt angle among its north and south side
82.87 °);In this project, the molding of reinforced concrete combination batter post cast-in-place structural preferably, has obtained designing unit, construction unit
Favorable comment consistent with supervisor, bring economic benefit mainly consider that the tie that batter post is reinforced is replaced using finished product reinforcing member
Conventional steel fastener, taper pile shuttering are decorated using mirror surface formwork, and when finishing exempts from bring benefit of plastering.
(1) batter post, which is reinforced, replaces conventional steel fastener using finished product reinforcing member
It is reinforced according to conventional steel fastener, steel tube fastener needs additional increase to support, and every group batter post (three) need additional increase
Add about 2400 yuan of labour cost, finished product reinforcing member needs additional branch relative to the average every group of batter post of conventional steel fastener lease expenses
About 600 yuan out, amount to 24 groups of batter posts, it is contemplated that save the cost (2400-600) × 24=43200 yuan.
(2) exempt to plaster when taper pile shuttering uses mirror surface formwork decorations
Batter post plastering is more complicated than the plastering of general column, and plaster about 35 Yuan/㎡ of price in this position market, this engineering batter post lateral area is total
About 2200 ㎡ exempt from 77000 yuan of estimated saving expense of plastering using mirror surface formwork decorations.
To sum up, amount to and bring about 12.02 ten thousand yuan of benefit.
In addition, the present invention has many advantages, such as suitable for actual items:
1. the present invention carries out simulator locating using softwares such as Tekla, two-dimension plane structure is converted by three-D space structure, just
It constructs on site.
2. armored concrete batter post is considered as Vierendeel girder by the present invention, formwork system calculating is carried out.
3. hole is not present without screw rod eye in template of the present invention, without part bee caused by spillage after the completion of concreting
Nest pitted skin, without cutting off the Screw arbor with nut at both-ends deformed in column, the mould bases that batter post can be improved in easy demoulding is used in turn rate.
4. the present invention is not easy the case where vibrating according to batter post concrete, optimised coagulation soil match ratio adjusts Control Measures for Concrete Slump
Degree is vibrated using the assistance of PVC chute when concrete vibrating, and the molding of batter post reinforced concrete structure is good.
5. using sizing reinforcing member the proportion of goods damageds of material are effectively reduced, in similar construction process in tie of the present invention
In may be reused, meet the requirement of green construction.
As described above, must not be explained although the present invention has been indicated and described referring to specific preferred embodiment
For the limitation to invention itself.It without prejudice to the spirit and scope of the invention as defined in the appended claims, can be right
Various changes can be made in the form and details for it.
Claims (5)
1. a kind of construction method of reinforced concrete combination batter post, it is characterised in that include the following steps:
(1) preparation of construction: 1) technique preparation: design drawing is familiar with before construction, detailed reinforced concrete combination batter post is worked out and applies
Work method is specified outside quantity, cross-sectional sizes, vertical section sequence of construction and the concrete formation of reinforced concrete combination batter post
Appearance quality requirement;2) people, machine, material prepare: with an appropriate number of construction according to the size of project amount and the factor of operating environment
Operating personnel is simultaneously equipped with corresponding administrative staff, prepares the resources such as the material needed in construction and Work tool;According to live practical
Situation is equipped with corresponding rapidoprint and installation tool:
(2) batter post positioning and joint bar: according to structure, architectural discipline design drawing, using Tekla software modeling, determine that batter post exists
The accurate positionin of plane;The construction of batter post joint bar is carried out after entry level column reinforcement installation, joint bar is certain by in-depth drawing bending
Angle carries out joint bar auxiliary positioning using mold;
(3) batter post bottom steel pipe support is set up and lower section taper pile shuttering is laid with: batter post being considered as Vierendeel girder, using building safety of siping tea
Software for calculation is checked, and requires progress batter post steel pipe support to set up according to high-supported formwork according to calculated result, supporting erection finishes
Afterwards, the laying of batter post end template is carried out;
(4) reinforcement installation: after batter post end template is laid, batter post reinforcement installation is carried out, PVC is placed in time in installation process and slips
Slot vibrates to concrete with ancillary vibration stick;
(5) PVC chute is arranged: in batter post reinforcing bar process of binding, reserving 2 single u-shaped PVC chutes in batter post and facilitates concrete vibrating
The insertion of stick extracts PVC chute with vibrating spear during concrete vibrating;
(6) lower section taper pile shuttering is reinforced: after reinforcement installation, carrying out the reinforcing of lower section taper pile shuttering, lower section batter post column bottom absolute altitude
4.700m, the high 8.700m of batter post top mark, the bed die of batter post support to beam bottom, and the backform and side form of batter post carry out segmentation support;Institute
The top-side for stating template is provided with venthole, and the length direction on the outer surface of the template along template is provided with several wood
The outer surface of a tree, used in making timber for boats, the bottom of the template is reinforced using double steel pipe around surrounding, and middle and upper part is reinforced using tie,
The bed die side of the batter post is evenly arranged with several column bottoms cross bar, and column bottom cross bar is close to the bottom of double steel pipe and tie,
Diagonal brace is provided on the cross bar of the column bottom, the other end of the diagonal brace is fixed in base by being set to the timber wedge of base, under
After the completion of section taper pile shuttering is reinforced, then carry out pouring for concrete;
(7) concrete optimum: adjustment concrete coarse-fine aggregate gradation determines concrete mix, the slump before concreting;
(8) lower section batter post concreting: after the completion of formwork reinforcement, carrying out watering to template and moisten, carry out concreting,
In concreting process, is vibrated by the chute in setting template with vibrating spear, make coagulation rammed earth, finally by chute
It is extracted with vibrating spear;
1) batter post maximum segment pours height no more than 2m, pours layered segmentation, check at any time the stability of shuttering supporting, especially
It pays attention to the deformation of formwork reinforcement system herein;
2) it is carried out before batter post concreting in strict accordance with scheme, in the environment of hot weather, template watering is carried out, to protect
The water retention property of Surface Quality of Concrete and concrete is demonstrate,proved;
3) after the completion of concreting, temporarily should not demoulding, guarantee that concrete obtains sufficient moisture-keeping maintaining;
(9) lower section batter post side form is removed: lower section batter post concreting completion reaches demoulding condition, carries out at the top of batter post, side
Form removable construction, to observe the construction molding situation of concrete;Batter post after demoulding is carried out using curing compound
Even sprinkling wraps up plastic film on its surface, to reach concrete wet curing function and effect;Batter post bed die is waited for feeding intensity of test block
Reaching 100% side can remove;
(10) upper section construction of inclined column: upper section construction of inclined column process is identical as lower section construction of inclined column process, repeats step (2) to (9).
2. a kind of construction method of reinforced concrete combination batter post according to claim 1, it is characterised in that: the step
(10) in, before the reinforcing of upper section taper pile shuttering, it is additionally provided with the temporary ladder convenient for constructing operation, the temporary ladder is in
Operating platform, the plane between the temporary ladder and upper section taper pile shuttering top are provided on the same plane of the batter post of completion
On be also equipped with operating platform, the operating platform completely spreads template, and the ground of the template is evenly arranged with several brace a tree, used in making timber for boats;
The two sides of the temporary ladder are respectively arranged with ladder handrail, and the ladder handrail is the safety in order to guarantee construction personnel;Institute
The bottom end for stating temporary ladder is provided with cushion block.
3. a kind of construction method of reinforced concrete combination batter post according to claim 2, it is characterised in that: the step
(10) in, before the reinforcing of upper section taper pile shuttering, the backform and side form of upper section batter post support to beam bottom.
4. a kind of construction method of reinforced concrete combination batter post according to claim 1, it is characterised in that: the mould
Plate uses mirror surface formwork, and the size of the mirror surface formwork is 1830mm × 915mm × 15mm.
5. a kind of construction method of reinforced concrete combination batter post according to claim 1, it is characterised in that: the tie
Using finished product reinforcing member.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910066583.0A CN109763606B (en) | 2019-01-24 | 2019-01-24 | Construction method of reinforced concrete combined batter post |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910066583.0A CN109763606B (en) | 2019-01-24 | 2019-01-24 | Construction method of reinforced concrete combined batter post |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109763606A true CN109763606A (en) | 2019-05-17 |
CN109763606B CN109763606B (en) | 2021-05-28 |
Family
ID=66454203
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910066583.0A Active CN109763606B (en) | 2019-01-24 | 2019-01-24 | Construction method of reinforced concrete combined batter post |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109763606B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112609986A (en) * | 2020-12-11 | 2021-04-06 | 上海宝冶集团有限公司 | Method for controlling pouring forming quality of concrete batter post |
CN113958123A (en) * | 2021-11-04 | 2022-01-21 | 中国十七冶集团有限公司 | Manufacturing method of concrete batter post template inclination control device |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1071045A (en) * | 1911-05-27 | 1913-08-26 | Henri Edouard Graa | Reinforced-concrete column or pole. |
CN103526930A (en) * | 2013-10-14 | 2014-01-22 | 成军 | Multi-directional intersection reinforced bare concrete inclined column construction method |
CN106088475A (en) * | 2016-06-23 | 2016-11-09 | 青岛海川建设集团有限公司 | Steel pipe self-compacting concrete tilt column construction technology |
-
2019
- 2019-01-24 CN CN201910066583.0A patent/CN109763606B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1071045A (en) * | 1911-05-27 | 1913-08-26 | Henri Edouard Graa | Reinforced-concrete column or pole. |
CN103526930A (en) * | 2013-10-14 | 2014-01-22 | 成军 | Multi-directional intersection reinforced bare concrete inclined column construction method |
CN106088475A (en) * | 2016-06-23 | 2016-11-09 | 青岛海川建设集团有限公司 | Steel pipe self-compacting concrete tilt column construction technology |
Non-Patent Citations (2)
Title |
---|
刘波: "现浇钢筋混凝土大直径写圆柱施工工艺探讨", 《劳动保障世界》 * |
裘一峰: "上海八万人体育场大斜柱的施工", 《建筑施工》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112609986A (en) * | 2020-12-11 | 2021-04-06 | 上海宝冶集团有限公司 | Method for controlling pouring forming quality of concrete batter post |
CN113958123A (en) * | 2021-11-04 | 2022-01-21 | 中国十七冶集团有限公司 | Manufacturing method of concrete batter post template inclination control device |
Also Published As
Publication number | Publication date |
---|---|
CN109763606B (en) | 2021-05-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104846744B (en) | Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode | |
CN108265885B (en) | Construction method of high-large non-orthogonal large-inclination-angle special-shaped concrete inclined column | |
CN102392549B (en) | Construction working method for seamless prestressed-concrete self-waterproof clean water reservoir | |
CN102493341A (en) | Construction method for hollow thin-walled high pier non-bracket formwork turnover of railway | |
CN105040970A (en) | Comprehensive gymnasium high formwork support system and construction method of comprehensive gymnasium high formwork support system | |
CN106639349A (en) | Construction method for partial replacement of concrete column | |
CN105350777A (en) | Device and method for one-time pouring molding of ultra-high concrete column | |
CN104088461A (en) | Y-type cast-in-place concrete column formwork system and construction method thereof | |
CN104894954A (en) | Overall mounting and constructing method of pier stud reinforcing steel bars of urban bridge | |
CN107419802A (en) | A kind of Precast Concrete Frame and construction method | |
CN103590603A (en) | Large-span multi-curvature thin shell reinforced concrete structure construction method | |
CN109763606A (en) | A kind of construction method of reinforced concrete combination batter post | |
CN110284702A (en) | A kind of constructing device and construction method of hyperboloid arc mixed mud wall | |
CN106351376A (en) | Construction method of garage roof | |
CN108005255A (en) | A kind of construction method of wall | |
CN107575023A (en) | A kind of sliding formwork component and apply its caisson cutting edge layer slding form operation method | |
CN113829493A (en) | Processing method of prefabricated greening retaining wall | |
CN109112903A (en) | Solid concrete roabed trackless construction technology is cheated in a kind of phase library inner column formula inspection | |
CN205558264U (en) | Space reentrant corner system of clear water inclined wall switching clear water swash plate | |
CN209293068U (en) | A kind of open trench tunnel falsework system | |
CN106677558A (en) | Construction method for deep foundation pit assembling type stairway used for people | |
CN108979137A (en) | The assembling and disassembling construction method of Round Concrete column composite wooden template | |
CN114277672B (en) | Large-span prestressed concrete bent cap structure and construction method thereof | |
CN208415925U (en) | A kind of PVC column-form | |
CN105984015A (en) | Method for manufacturing prefabricated concrete components of bracket set of antique building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |