A kind of high-low pressure is two-sided to rush shoe manifold apparatus
Technical field
The invention belongs to technology maritime platform pile punching apparatus fields, and in particular to a kind of high-low pressure is two-sided to rush shoe manifold dress
It sets.
Background technique
Be supported on seabed by three legs and its shoe when jack up maritime platform operation, just need to rush when needing to shift stake and
Pile pulling, the power gear device first passed through between main hull and spud leg drop to sea by main hull, by rushing stake and pile pulling, receive
It returns spud leg and shoe is equal with main hull bottom to bottom, next operating location then can be dragged to by towboat.
Existing technology has the following problems:
1, existing maritime platform rushes stake design arrangement, and high pressure rushes pile pipe all the way and low pressure rushes pile pipe all the way for setting, respectively
It is independent, can not mutual backup, and two-way bottom rushes pile pipe and its nozzle, in certain sea area shoes upper surface deeper Shi Wufa of mud
Stake is rushed, pile pulling is difficult;
2, existing maritime platform rushes shoe manifold apparatus, rushes pile pipe using common u-shaped pipe clamp, rushes stake Shi Yizhen in high pressure
Dynamic, bolt and nut, which easily loosens, to be fallen, it is often necessary to be safeguarded.
Summary of the invention
To solve the problems mentioned above in the background art.The present invention provides a kind of two-sided shoe manifolds that rushes of high-low pressure to fill
It sets, it is time saving and energy saving to have, and rushes the feature that stake effect is good and maintenance is few.
To achieve the above object, the invention provides the following technical scheme: a kind of high-low pressure is two-sided to rush shoe manifold apparatus, packet
Shoe is included, the upper surface of the shoe is equipped with spud leg, and the lateral wall of the spud leg is fixed with main hull, and the main hull leans on
The side of the nearly spud leg is fixed with climbing gear, and the main hull connects by the way that the climbing gear and the spud leg are fixed
It connects, the upper surface of the main hull is fixed with main deck, and the upper surface of the main deck is fixed with from high pressure slurry pump, institute
It states from the efferent duct of high pressure slurry pump and is fixedly connected with the first connecting tube, first connecting tube is far from described from high pressure slurry pump
One end be fixed with the second high pressure valve, the output end of second high pressure valve is fixedly connected with the second connecting tube, described second
First pressure gauge is fixed in connecting tube, second connecting tube is fixed with first far from one end of second high pressure valve
High pressure valve, the output end of first high pressure valve are fixedly connected with third connecting tube, and the third connecting tube is far from described first
One end of high pressure valve is equipped with the first water supplying pipe, and one end of first water supplying pipe is fixedly connected with the third connecting tube, described
The other end of third connecting tube is fixedly connected with the first hose, and first hose is fixed far from one end of first water supplying pipe
It is connected with the second water supplying pipe, second water supplying pipe is fixedly connected with the shoe, and second water supplying pipe is far from described first
One end of hose is fixedly connected with upper surface nozzle, and the upper surface nozzle is located at the upper surface of the spud leg, the main deck
It is equipped with from the side of high pressure slurry pump from low pressure slush pump far from described, it is described to be connected from high pressure slurry pump far from described first
The side of pipe is fixedly connected with the 4th connecting tube, and the 4th connecting tube is fixed with far from described from one end of high pressure slurry pump
4th high pressure valve, the 4th high pressure valve are fixedly connected with the 5th connecting tube far from the side lateral wall of the 4th connecting tube,
5th connecting tube is fixedly connected with described from low pressure slush pump, and the efferent duct from low pressure slush pump is fixedly connected with
Six connecting tubes, the 6th connecting tube are fixedly connected with check-valves, the check-valves from one end of low pressure slush pump far from described
Output end be fixedly connected with the 7th connecting tube, be fixed with second pressure gauge in the 7th connecting tube, the 7th connection
It manages one end far from the check-valves and is fixedly connected with third high pressure valve, the third high pressure valve is far from the 7th connecting tube
Side is fixedly connected with the 8th connecting tube, and the described one end of 8th connecting tube far from the third high pressure valve is supplied water equipped with third
Pipe, one end of the third water supplying pipe are fixedly connected with the 8th connecting tube, and the other end of the third water supplying pipe is fixed to be connected
It is connected to the second hose, second hose is fixedly connected with the 4th water supplying pipe far from one end of the third water supplying pipe, and described
Four water supplying pipes are fixedly connected with the spud leg, and the 4th water supplying pipe runs through the spud leg simultaneously far from one end of second hose
It is fixedly connected with lower surface nozzle, the lower surface nozzle is located at the lower surface of the spud leg, and the 4th water supplying pipe is far from institute
The one end for stating the second hose is fixedly connected with first jet branch pipe, and the lateral wall of the first jet branch pipe is fixed with first and wears
Bulkhead casing, the first crossing cabin wall casing run through the shoe, the lower surface nozzle by the first jet branch pipe and
The first crossing cabin wall casing is fixedly connected with the shoe, and the shoe is set close to the lateral wall fixation of the lower surface nozzle
There is a protective plate, second water supplying pipe is fixedly connected with second nozzle branch pipe far from one end of first hose, and described second
The lateral wall of nozzle branch pipe is fixed with the second crossing cabin wall casing, and the second crossing cabin wall casing runs through the shoe, it is described on
Surface nozzle is fixedly connected by the second nozzle branch pipe and the second crossing cabin wall casing with the shoe, and the shoe is leaned on
The lateral wall of the nearly upper surface nozzle is fixed with pipe cap, one end lateral wall of the first jet branch pipe close to the shoe
It is fixed with pipe clamp, the inner sidewall of the pipe clamp is fixed with lining, and the lateral wall of the pipe clamp is fixed with support tube, described
Pipe clamp is fixedly connected by the support tube with the shoe, it is described from high pressure slurry pump and it is described from low pressure slush pump and outside
Portion's power supply is electrically connected.
Preferably, the protective plate is semi-circular shape, the quantity phase of the quantity of the protective plate and the lower surface nozzle
Deng.
Preferably, the surface of the pipe cap offers open-work, and the quantity of the open-work is three, and three open-works are uniform
It is distributed in the surface of the pipe cap.
Preferably, the quantity of the lower surface nozzle is 12, the injection direction of lower surface nozzle described in six of them
At a great circle, every 60 degree be equipped with a lower surface nozzle, in addition the injection direction of six lower surface nozzles at
One ringlet, every 60 degree are equipped with a lower surface nozzle, and the quantity and distribution mode of the upper surface nozzle are and institute
It is identical to state lower surface nozzle.
Preferably, the lateral wall of second water supplying pipe is fixed with union female connector, the inside of the union female connector
Wall is equipped with union pin end, and first hose is fixedly connected by the union female connector with second water supplying pipe, institute
It is identical with the structure of the 4th water supplying pipe to state the second water supplying pipe.
Preferably, the pipe clamp is mainly made of first clamping plate and second clamping plate and screw, the first clamping plate and described
Second clamping plate is U-shaped.
Preferably, the lateral wall of the second nozzle branch pipe is equipped with the pipe clamp, and the second nozzle branch pipe passes through described
Pipe clamp is fixedly connected with the shoe.
Compared with prior art, the beneficial effects of the present invention are:
1, high-low pressure manifold is set in main deck, the 4th high pressure valve is intermediate isolating valve, and then realizes that high pressure and low pressure are mutual
Be it is spare, do not have to dismounting hose, time saving and energy saving, two-way rushes pile pipe and is respectively connected to shoe upper and lower surfaces, upper surface nozzle
For washing out the mud of accumulation, it is easier pile pulling, because protective plate is semi-circular shape, is protected conducive to first jet branch pipe
And there is diversion function, it is not easy to damage and blocking, because the quantity of lower surface nozzle is 12, six of them lower surface nozzle
For injection direction at a great circle, every 60 degree are equipped with a lower surface nozzle, in addition the injection direction of six lower surface nozzles at
One ringlet, every 60 degree are equipped with a lower surface nozzle, and then form annular water conservancy diversion, and it is good to rush stake effect, because of lower surface nozzle
Quantity and distribution mode it is identical as upper surface nozzle, lower surface nozzle cooperation pipe cap and open-work jet stream be injected into mud,
Be conducive to break up and remove mud, be conducive to pile pulling.
2, it is equipped with pipe clamp in first jet branch pipe and second nozzle branch pipe lateral wall, and is set respectively in pipe clamp outboard sidewalls
There are lining and support tube, in fixed first jet branch pipe and second nozzle branch pipe, because pipe clamp is mainly by first clamping plate and second
Clamping plate and screw composition, first clamping plate and second clamping plate are U-shaped, double-U-shaped pipe clamp, so that pipe clamp and first jet branch pipe
Stable connection between second nozzle branch pipe, lining reduces the gap between pipe clamp and nozzle branch pipe, and lining is with good
Good damping effect so that when high pressure rushes stake nozzle branch pipe be not easy to shake and pipe clamp on bolt and nut be not easy pine
Dynamic to fall, maintenance is few.
Detailed description of the invention
Attached drawing is used to provide further understanding of the present invention, and constitutes part of specification, with reality of the invention
It applies example to be used to explain the present invention together, not be construed as limiting the invention.In the accompanying drawings:
Fig. 1 is prior art construction figure;
Fig. 2 is enlarged diagram at the A in Fig. 1;
Fig. 3 is structural schematic diagram of the invention;
Fig. 4 is highest operation sponge structures schematic diagram of the invention;
Fig. 5 is enlarged diagram at B in Fig. 3, Fig. 4 of the present invention;
Fig. 6 is flow chart of the invention;
Fig. 7 is shoe and lower surface nozzle installation diagram in the present invention;
Fig. 8 is shoe and upper surface nozzle installation diagram in the present invention;
Fig. 9 is union female connector and the second water supplying pipe connection figure in the present invention;
Figure 10 is the union pin end structural schematic diagram in the present invention;
Figure 11 is the first jet branch pipe and protective plate figure in the present invention;
Figure 12 is the left view of Fig. 8 in the present invention;
Figure 13 is the pipe cap and shoe installation diagram in the present invention;
Figure 14 is the top view of Figure 10 in the present invention;
Figure 15 is the pipe clamp and first jet branch pipe installation diagram in the present invention;
Figure 16 is the support tube and shoe installation diagram in the present invention;
In figure: 1- shoe, 2- spud leg, 3- main hull, 4- climbing gear, 5- main deck, 6- are from high pressure slurry pump, 7- first
Connecting tube, the second high pressure valve of 8-, the second connecting tube of 9-, 10- first pressure gauge, the first high pressure valve of 11-, 12- third connecting tube,
The first water supplying pipe of 13-, the first hose of 14-, the second water supplying pipe of 15-, the upper surface 16- nozzle, the 4th connecting tube of 17-, 18- the 4th are high
Pressure valve, the 5th connecting tube of 19-, 20- are from low pressure slush pump, the 6th connecting tube of 21-, 22- check-valves, the 7th connecting tube of 23-, 24-
Second pressure gauge, 25- third high pressure valve, the 8th connecting tube of 26-, 27- third water supplying pipe, the second hose of 28-, 29- the 4th supply water
Pipe, the lower surface 30- nozzle, 31- first jet branch pipe, 32- the first crossing cabin wall casing, 33- protective plate, 34- second nozzle branch pipe,
35- the second crossing cabin wall casing, 36- pipe cap, 37- pipe clamp, 38- lining, 39- support tube, 40- open-work, 41- union female connector, 42-
Union pin end.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that term " up/down end ", "inner", "outside" " front end ", " rear end ",
The orientation or positional relationship of the instructions such as " both ends ", " one end ", " other end " is to be based on the orientation or positional relationship shown in the drawings, only
It is that for the convenience of describing the present invention and simplifying the description, rather than the device or element of indication or suggestion meaning must have specifically
Orientation is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.In addition, term " first ", " the
Two " are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation " " is set
Set/be arranged with ", " socket ", " connection " etc., shall be understood in a broad sense, such as " connection ", may be a fixed connection, being also possible to can
Dismantling connection, or be integrally connected;It can be mechanical connection, be also possible to be electrically connected;It can be directly connected, can also pass through
Intermediary is indirectly connected, and can be the connection inside two elements.For the ordinary skill in the art, can have
Body situation understands the concrete meaning of above-mentioned term in the present invention.
Embodiment 1
Please referring to Fig. 1-16, the present invention rushes shoe manifold apparatus the following technical schemes are provided: a kind of high-low pressure is two-sided, including
Shoe 1, the upper surface of shoe 1 are equipped with spud leg 2, and the lateral wall of spud leg 2 is fixed with main hull 3, and main hull 3 is close to spud leg 2
Side be fixed with climbing gear 4, main hull 3 is fixedly connected by climbing gear 4 with spud leg 2, and the upper surface of main hull 3 is consolidated
Surely it is equipped with main deck 5, the upper surface of main deck 5 is fixed with from high pressure slurry pump 6, fixes from the efferent duct of high pressure slurry pump 6
It is connected with the first connecting tube 7, the first connecting tube 7 is far from being fixed with the second high pressure valve 8 from one end of high pressure slurry pump 6, and second
The output end of high pressure valve 8 is fixedly connected with the second connecting tube 9, and first pressure gauge 10 is fixed in the second connecting tube 9, and second connects
Adapter tube 9 is fixed with the first high pressure valve 11 far from one end of the second high pressure valve 8, and the output end of the first high pressure valve 11 is fixedly connected with
Third connecting tube 12, third connecting tube 12 are equipped with the first water supplying pipe 13, the first water supplying pipe 13 far from one end of the first high pressure valve 11
One end be fixedly connected with third connecting tube 12, the other end of third connecting tube 12 is fixedly connected with the first hose 14, and first is soft
Pipe 14 is fixedly connected with the second water supplying pipe 15 far from one end of the first water supplying pipe 13, and the second water supplying pipe 15 is fixedly connected with shoe 1,
Second water supplying pipe 15 is fixedly connected with upper surface nozzle 16 far from one end of the first hose 14, and upper surface nozzle 16 is located at spud leg 2
Upper surface, main deck 5 from the side of high pressure slurry pump 6 far from being equipped with from low pressure slush pump 20, far from high pressure slurry pump 6
The side of first connecting tube 7 is fixedly connected with the 4th connecting tube 17, and the 4th connecting tube 17 is far from solid from one end of high pressure slurry pump 6
Surely it is equipped with the 4th high pressure valve 18, the 4th high pressure valve 18 is fixedly connected with the 5th connection far from the side lateral wall of the 4th connecting tube 17
Pipe 19, the 5th connecting tube 19 are fixedly connected with from low pressure slush pump 20, are fixedly connected with from the efferent duct of low pressure slush pump 20
Six connecting tubes 21, the 6th connecting tube 21 far from being fixedly connected with check-valves 22 from one end of low pressure slush pump 20, check-valves 22
Output end is fixedly connected with the 7th connecting tube 23, and second pressure gauge 24, the 7th connecting tube 23 are fixed in the 7th connecting tube 23
One end far from check-valves 22 is fixedly connected with third high pressure valve 25, and side of the third high pressure valve 25 far from the 7th connecting tube 23 is solid
Surely it is connected with the 8th connecting tube 26, the 8th connecting tube 26 is equipped with third water supplying pipe 27, third far from one end of third high pressure valve 25
One end of water supplying pipe 27 is fixedly connected with the 8th connecting tube 26, and the other end of third water supplying pipe 27 is fixedly connected with the second hose
28, the second hose 28 is fixedly connected with the 4th water supplying pipe 29, the 4th water supplying pipe 29 and spud leg 2 far from one end of third water supplying pipe 27
It being fixedly connected, the one end of the 4th water supplying pipe 29 far from the second hose 28 is through spud leg 2 and is fixedly connected with lower surface nozzle 30, under
Surface nozzle 30 is located at the lower surface of spud leg 2, and the 4th water supplying pipe 29 is fixedly connected with the first spray far from one end of the second hose 28
Mouth branch pipe 31, the lateral wall of first jet branch pipe 31 are fixed with the first crossing cabin wall casing 32, and the first crossing cabin wall casing 32 runs through
Shoe 1, lower surface nozzle 30 are fixedly connected by first jet branch pipe 31 and the first crossing cabin wall casing 32 with shoe 1, and shoe 1 is leaned on
The lateral wall of nearly lower surface nozzle 30 is fixed with protective plate 33, and the one end of the second water supplying pipe 15 far from the first hose 14 is fixed to be connected
It is connected to second nozzle branch pipe 34, the lateral wall of second nozzle branch pipe 34 is fixed with the second crossing cabin wall casing 35, the second crossing cabin wall
Casing 35 runs through shoe 1, and upper surface nozzle 16 passes through second nozzle branch pipe 34 and the second crossing cabin wall casing 35 and the fixed company of shoe 1
It connects, shoe 1 is fixed with pipe cap 36 close to the lateral wall of upper surface nozzle 16, and first jet branch pipe 31 is close to one end of shoe 1
Lateral wall is fixed with pipe clamp 37, and the inner sidewall of pipe clamp 37 is fixed with lining 38, and the lateral wall of pipe clamp 37 is fixed with support
Pipe 39, pipe clamp 37 are fixedly connected by support tube 39 with shoe 1, from high pressure slurry pump 6 and from low pressure slush pump 20 with outside
Power supply is electrically connected.
In the present embodiment: the water supplying pipe P1 in attached drawing 3,4 and 5 is the first water supplying pipe 13 of attached drawing 6, attached drawing 3,4 and 5
The first hose 14 and the second hose 28 that stake hose is attached drawing 6 are rushed, the nozzle supplies water pipe P1 in attached drawing 3,4 and 5 is attached drawing 6
The second water supplying pipe 15, attached drawing 3,4 and 5 water supplying pipe P2 are the third water supplying pipe 27 of attached drawing 6, and the nozzle in attached drawing 3,4 and 5 supplies
Water pipe P2 is the 4th water supplying pipe 29 of attached drawing 6, high pressure valve 1, high pressure valve 2, high pressure valve 3,4 and of high pressure valve in attached drawing 3,4 and 5
High-pressure stop check-valves 1 is the first high pressure valve 11, the second high pressure valve 8, the third high pressure valve 25, the 4th high pressure valve 18 of attached drawing 6
With check-valves 22.
In the present embodiment: from the model ZJQ100-25-22 of high pressure slurry pump 6, from the model of low pressure slush pump 20
NSQ800-45-200 provides power resources for pipe flushing mud.
In the present embodiment: the first high pressure valve 11, the second high pressure valve 8, third high pressure valve 25, the model of the 4th high pressure valve 18 are equal
For Y42X-16P, control from 6 pipeline of high pressure slurry pump and opening or closing from 20 pipeline of low pressure slush pump.
In the present embodiment: the model HC42X of check-valves 22 avoids high pressure water from misleading into from 20 pipeline of low pressure slush pump,
Damage its pipeline.
In the present embodiment: the model of first pressure gauge 10 and second pressure gauge 24 is YTX-160B, passes through first pressure
Table 10 checks that the pressure value from 6 pipeline of high pressure slurry pump, second pressure gauge 24 are used to check the pressure from 20 pipeline of low pressure slush pump
Force value.
In the present embodiment: lining 38 is three mm of thickness graphite resilient cushions, has good damping effect, so that
When high pressure rushes stake, first jet branch pipe 31 and second nozzle branch pipe 34 are not easy to shake.
In the present embodiment: the first clamping plate and second clamping plate of pipe clamp 37 are the zinc-plated material of steel, have good corrosion resistant
Property, it is conducive to improve its service life.
In the present embodiment: when carrying out rushing stake work, because the 4th high pressure valve 18 is intermediate isolating valve, closing can be passed through
First high pressure valve 11, opens third high pressure valve 25, and the 4th high pressure valve 18 is realized from 6 pipeline of high pressure slurry pump to from low pressure slush pump
20 pipelines can also be realized and be supplied water from 20 pipeline of low pressure slush pump to from 6 pipeline of high pressure slurry pump for high pressure water, and then be realized
High pressure and low pressure mutual backup do not have to dismounting hose, time saving and energy saving, pass through the 6th connecting tube 21 and the 7th from low pressure slush pump 20
Check-valves 22 is arranged in connecting tube 23, avoids high pressure water from misleading into from 20 pipeline of low pressure slush pump, damages its pipeline, the first water supplying pipe
13, the connection between the first hose 14 and the second water supplying pipe 15 and third water supplying pipe 27, the second hose 28 and the 4th water supplying pipe
29 are all made of union female connector 41 and the connection of union pin end 42, as hit union connection, hammering union connection, with hammer
Operation, connection is simple and reliable, time saving and energy saving, needs to dismount many and diverse operation of eight groups of bolt and nuts instead of original every group of valve, because
First water supplying pipe 13, the first hose 14, the second water supplying pipe 15, second nozzle branch pipe 34, the second crossing cabin wall casing 35 and upper surface
Nozzle 16, can be rinsed work to 1 upper surface of shoe, and upper surface nozzle 16 is used to wash out the mud of accumulation, holds that pile pulling more
Easily, because protective plate 33 be semi-circular shape, conducive to being protected first jet branch pipe 31 and having diversion function, it is not easy to damage and
Blocking, because third water supplying pipe 27, the second hose 28, the 4th water supplying pipe 29, first jet branch pipe 31, the first crossing cabin wall casing 32 are matched
Lower surface nozzle 30 is closed, work can be rinsed to 1 lower surface of shoe, because the quantity of lower surface nozzle 30 is 12, wherein
For the injection direction of six lower surface nozzles 30 at a great circle, every 60 degree are equipped with a lower surface nozzle 30, in addition under six
For the injection direction of surface nozzle 30 at a ringlet, every 60 degree are equipped with a lower surface nozzle 30, and then form annular water conservancy diversion,
Rush that stake effect is good, because the quantity and distribution mode of lower surface nozzle 30 are identical as upper surface nozzle 16, lower surface nozzle 30 is matched
It closes pipe cap 36 and 40 jet stream of open-work is injected into mud, be conducive to break up and remove mud, be conducive to pile pulling, in fixed first jet
When branch pipe 31 and second nozzle branch pipe 34, because pipe clamp 37 is mainly made of first clamping plate and second clamping plate and screw, first clamping plate
It is U-shaped with second clamping plate, double-U-shaped pipe clamp 37, so that pipe clamp 37 and first jet branch pipe 31 and second nozzle branch pipe 34
Between stable connection, and first jet branch pipe 31 and second nozzle branch pipe 34 are fixed to by the upper of shoe 1 by support tube 39
Stability is improved on surface, and lining 38 reduces the gap between pipe clamp 37 and nozzle branch pipe, and lining 38 has good damping
Effect so that when high pressure rushes stake, first jet branch pipe 31 and second nozzle branch pipe 34 be not easy to shake and pipe clamp 37 on
Bolt and nut be not easy to loosen and fall, maintenance is few.
Specifically, protective plate 33 is semi-circular shape, the quantity of protective plate 33 and the quantity of lower surface nozzle 30 are equal;Pass through
Protective plate 33 is conducive to protect first jet branch pipe 31, and has diversion function, it is not easy to damage and blocking, conducive to stake is rushed,
Each protective plate 33 protects each lower surface nozzle 30.
Specifically, the surface of pipe cap 36 offers open-work 40, the quantity of open-work 40 is three, and three open-works 40 are uniformly distributed
On the surface of pipe cap 36;The diameter of three open-works 40 is 25 millimeters, is injected into mud by 40 jet stream of open-work, favorably
In breaking up and remove mud.
Specifically, the quantity of lower surface nozzle 30 is 12, the injection direction of six of them lower surface nozzle 30 is at one
A great circle, every 60 degree are equipped with a lower surface nozzle 30, and in addition the injection direction of six lower surface nozzles 30 is at a ringlet,
Every 60 degree be equipped with a lower surface nozzle 30, the quantity and distribution mode of upper surface nozzle 16 with 30 phase of lower surface nozzle
Together;So that lower surface nozzle 30 forms two annular water conservancy diversion, conducive to uniformly mud is broken up, it is good to rush stake effect, upper surface
The diversion effect of nozzle 16 is identical as lower surface nozzle 30, reaches identical purpose.
Specifically, the lateral wall of the second water supplying pipe 15 is fixed with union female connector 41, the inner sidewall of union female connector 41
Union pin end 42 is installed, the first hose 14 is fixedly connected by union female connector 41 with the second water supplying pipe 15, and second supplies water
Pipe 15 is identical with the structure of the 4th water supplying pipe 29;It in proper height, is usually blocked with plug, sea removes when rushing stake, connection the
One hose 14 or the second hose 28, can be operated with hammer, and connection is simple and reliable, time saving and energy saving.
Specifically, pipe clamp 37 is mainly made of first clamping plate and second clamping plate and screw, first clamping plate and second clamping plate are equal
For U-shaped;The first clamping plate and second clamping plate of U-shaped, so that pipe clamp 37 is close to first jet branch pipe 31 and second nozzle branch pipe
34 lateral wall is conducive to stable connection.
Specifically, the lateral wall of second nozzle branch pipe 34 is equipped with pipe clamp 37, second nozzle branch pipe 34 passes through pipe clamp 37 and stake
Boots 1 are fixedly connected;The connection side of second nozzle branch pipe 34 and the connection type of shoe 1 with first jet branch pipe 31 and shoe 1
Formula is identical, in order to enable being less prone to the case where second nozzle branch pipe 34 loosens when high pressure rushes stake.
The working principle of the invention and process for using: when rush stake work, because main hull 3 by climbing gear 4 with
Spud leg 2 is fixed, drives spud leg 2 and shoe 1 mobile by main hull 3, by the 4th connecting tube 17 and the 5th connecting tube 19, passes through
8th connecting tube 26 connects 25 He of third high pressure valve, by the 4th high pressure valve 18 and from high pressure slurry pump 6 and from low pressure slush pump 20
Third water supplying pipe 27 is connected, because the 4th high pressure valve 18 is intermediate isolating valve, third can be opened by closing the first high pressure valve 11
High pressure valve 25, the 4th high pressure valve 18 realize from 6 pipeline of high pressure slurry pump to from 20 pipeline of low pressure slush pump for high pressure water, otherwise
It can be achieved to supply water from 20 pipeline of low pressure slush pump to from 6 pipeline of high pressure slurry pump, and then realize high pressure and low pressure mutual backup, no
It is time saving and energy saving with dismounting hose, from low pressure slush pump 20 by the 6th connecting tube 21 and the 7th connecting tube 23, check-valves 22 is set,
It avoids high pressure water from misleading into from 20 pipeline of low pressure slush pump, damages its pipeline, pass through the first connecting tube 7, the second connecting tube 9 and
Three connecting tubes 12 for the second high pressure valve 8 and the first high pressure valve 11 to be connect with from high pressure slurry pump 6, and pass through first pressure
Table 10 checks the pressure value from 6 pipeline of high pressure slurry pump, likewise, second pressure gauge 24 is managed for checking from low pressure slush pump 20
The pressure value on road, connection and third water supplying pipe 27 between the first water supplying pipe 13, the first hose 14 and the second water supplying pipe 15,
Two hoses 28 and the 4th water supplying pipe 29 are all made of union female connector 41 and union pin end 42 connects, and as hit union connection, hammer
Union connection to be hit, can be operated with hammer, connection is simple and reliable, and it is time saving and energy saving, need to dismount eight groups instead of original every group of valve
Many and diverse operation of bolt and nut, because of the first water supplying pipe 13, the first hose 14, the second water supplying pipe 15, second nozzle branch pipe 34, second
Crossing cabin wall casing 35 and upper surface nozzle 16 can be rinsed work to 1 upper surface of shoe, and upper surface nozzle 16 is for washing out heap
Long-pending mud, is easier pile pulling, because protective plate 33 is semi-circular shape, is protected and is led conducive to first jet branch pipe 31
Flow function, it is not easy to damage and blocking, because of third water supplying pipe 27, the second hose 28, the 4th water supplying pipe 29, first jet branch pipe
31, the first crossing cabin wall casing 32 cooperates lower surface nozzle 30, work can be rinsed to 1 lower surface of shoe, because of lower surface nozzle
30 quantity is 12, and at a great circle, every 60 degree are equipped under one the injection direction of six of them lower surface nozzle 30
Surface nozzle 30, in addition for the injection direction of six lower surface nozzles 30 at a ringlet, every 60 degree are equipped with a lower surface spray
Mouth 30, and then form annular water conservancy diversion, rushes that stake effect is good, because lower surface nozzle 30 quantity and distribution mode with upper surface nozzle
16 is identical, and lower surface nozzle 30 cooperates pipe cap 36 and 40 jet stream of open-work to be injected into mud, is conducive to break up and remove mud, benefit
In pile pulling, in fixed first jet branch pipe 31 and second nozzle branch pipe 34, because pipe clamp 37 is mainly pressed from both sides by first clamping plate and second
Plate and screw composition, first clamping plate and second clamping plate are U-shaped, double-U-shaped pipe clamp 37, so that pipe clamp 37 and first jet branch
Stable connection between pipe 31 and second nozzle branch pipe 34, and pass through support tube 39 for first jet branch pipe 31 and second nozzle branch
Pipe 34 is fixed to the upper surface of shoe 1, improves stability, and lining 38 reduces the gap between pipe clamp 37 and nozzle branch pipe, and
Lining 38 has good damping effect, so that when high pressure rushes stake, first jet branch pipe 31 and second nozzle branch pipe 34
Be not easy to shake and pipe clamp 37 on bolt and nut be not easy to loosen and fall, maintenance is few.
Finally, it should be noted that the foregoing is only a preferred embodiment of the present invention, it is not intended to restrict the invention,
Although the present invention is described in detail referring to the foregoing embodiments, for those skilled in the art, still may be used
To modify the technical solutions described in the foregoing embodiments or equivalent replacement of some of the technical features.
All within the spirits and principles of the present invention, any modification, equivalent replacement, improvement and so on should be included in of the invention
Within protection scope.