Prior art keywords
arm
cross
support
pipeline
assembled suspension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910098683.1A
Other languages
Chinese (zh)
Inventor
乔小博
杨建学
同庆
欧阳黎煊
邓保顺
郭永桢
张毓斌
张海
鱼晟睿
樊航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN201910098683.1A priority Critical patent/CN109755907A/en
Publication of CN109755907A publication Critical patent/CN109755907A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The present invention relates to subway station comprehensive pipeline assembled suspension and support and its construction method, the assembled suspension and support is set up in below the beam body in subway station between the wallboard of two sides, including cross-arm beam, laterallys secure arm, vertical columns and diagonal brace;Cross-arm beam is horizontally disposed between the wallboard of two sides, and the vertical arm that laterallys secure is fixedly connected with above both ends, and vertical vertical columns are fixedly connected with above middle part, and the symmetrical diagonal brace in front and back is also fixedly connected with above middle part;It laterallys secure arm bottom end, vertical columns bottom end and diagonal brace bottom end to be fixedly connected in cross-arm beam, each component is connected integral by prefabrication;It laterallys secure and is fixedly installed to wallboard on the outside of arm, vertical columns and diagonal brace top are fixedly installed to beam body.Each component factory customization processing of the present invention, it is a little more can to solve the problems, such as that subway station device systems pipeline sunpender, finishing furred ceiling sunpender and civil engineering concrete panel or beam are connected and fixed, and effectively save pipeline installation space.

Description

Subway station comprehensive pipeline assembled suspension and support and its construction method
Technical field
The present invention relates to subway engineering electromechanics mounting technique fields, and in particular to a kind of subway station comprehensive pipeline assembled Suspension and support and its construction method.
Background technique
Subway station device systems pipeline type is more, and the fixation of the independently installed sunpender of each pipeline, station finishing furred ceiling is hung Bar quantity is thousands of, when all sunpenders are both needed to carry out punching fixed on civil engineering concrete panel or beam, then makes civil engineering Concrete panel or beam become riddled with gaping wounds, and each pipeline is independently installed need to occupy biggish installation space.
Though being still classification currently, there are some various forms of assembled combination suspension and supports and laying, pipeline branch is hung Frame and finishing furred ceiling sunpender are still combination, and pipeline is either that arrangement stacked on top of one another occupies height space greatly or flat raft Arrangement increases the fixation upright bar connecting with civil engineering concrete panel or beam, still fails thoroughly to solve to reduce upright bar quantity, save The problem of space.
Summary of the invention
The object of the present invention is to provide a kind of subway station comprehensive pipeline assembled suspension and support and its construction method, factory are fixed System processing can solve subway station device systems pipeline sunpender, finishing furred ceiling sunpender is connect admittedly with civil engineering concrete panel or beam Pinpoint more problem, and effectively save pipeline installation space.
The technical scheme adopted by the invention is as follows:
Subway station comprehensive pipeline assembled suspension and support, it is characterised in that:
The assembled suspension and support is set up in subway station the structural slab subjacent between both walls or beam, including cross-arm Beam laterallys secure arm, vertical columns and diagonal brace;
Cross-arm beam is horizontally disposed between the wallboard of two sides, and cross-arm beam both ends are fixedly connected with the vertical arm that laterallys secure, cross-arm beam It is fixedly connected with vertical vertical columns above middle part, is also fixedly connected at least one diagonal brace in the middle part of cross-arm beam;
Arm lower part, vertical columns bottom end and diagonal brace bottom end is laterallyd secure to be fixedly connected on cross-arm beam;
It laterallys secure and is fixedly installed to metope or beam sides on the outside of arm, vertical columns and diagonal brace top are fixedly installed to beam body;
For each component by prefabrication at finished product member, assembly fixation in erecting bed is integral.
It is fixedly connected with vertical line holder column above cross-arm beam, line holder column and laterallys secure arm or fixation At least one set of line holder cross-arm is connected between column.
Locating pipeling part or pipe clamp are provided on cross-arm beam or line holder cross-arm.
Line holder cross-arm or cross-arm soffit are provided with pipeline sunpender.
Cross-arm soffit is provided with finishing furred ceiling sunpender.
Cross-arm beam laterallys secure arm, vertical columns, line holder column and line holder cross-arm as single or double spelling C-shaped channel Steel or I-steel.
The construction method of subway station comprehensive pipeline assembled suspension and support, it is characterised in that:
The following steps are included:
A, each component of assembled suspension and support determined according to pipeline installation arrangement drawing and BIM setting-out, scene inspection unwrapping wire Fixation position of the assembled suspension and support on wallboard described in determination need to install first first group, and the successively punching peace on wallboard Dress laterallys secure arm;Then with laterally secure arm and connect installation cross-arm beam, then along pipeline installation direction longitudinal probing and adjust cross Spreader beam is lateralling secure the accurate fixed height on arm, locks cross-arm depth of beam after guaranteeing whole pipe space collisionless conflict; Fixation position of the vertical columns in beam body is repositioned, and punching installs and is fastened and fixed the top of column in beam body, then Vertical columns bottom end is connect fastening with cross-arm beam, be finally linked in sequence fixed diagonal brace like this;Again along the maximum for needing multilayer to install Pipeline width spaces longitudinal probing simultaneously adjusts accurate positioning of the line holder column on cross-arm beam, guarantee whole pipe space without Line holder column is locked after collision conflict, finally sequential connection fixed pipelines support cross-arm like this;
B, according to the process of step A, successively assembled suspension and support described in the subsequent each group of construction and installation;
C, after completing step B, start sectionally smooth join pipeline or cable bridge on the mounted assembled suspension and support, and Arrangement drawing is installed according to pipeline and site space is checked in time, it is ensured that after not influencing subsequent other pipelinings installation, is used Locating pipeling part or pipe clamp are fastened and fixed or are directly locked;
D, according to the process of step C, successively each pipeline of construction and installation or cable bridge, until whole pipelines and cable bridge installation It completes;
E, according to the design of finishing furred ceiling or the cross-arm of arrangement in-depth drawing and the assembled suspension and support of live completion of having constructed Beam physical location, carry out positioning verify finishing furred ceiling sunpender accurate location, determine it is errorless after install and fix locking finishing hang Push up sunpender;
F, after completing step E, start successively installation connection finishing ceiling joist, and carry out finishing installation of ceiling.
The invention has the following advantages that
(1) by each device systems pipeline consolidation centralized arrangement in subway station on the assembled suspension and support while also by subway Stand finishing furred ceiling sunpender be directly fixed on the assembled suspension and support cross-arm beam, be greatly decreased directly in civil engineering concrete panel Or the sunpender quantity of fixation and the secondary punching destruction to civil engineering structure on beam.
(2) by flat raft, the combination of stacking in the confined space, space layout of making rational planning for saves pipeline installation Space plays the sharpest edges of the assembled suspension and support.
(3) by lateralling secure being connected and fixed for arm, diagonal brace and civil engineering concrete panel or beam, when can avoid earthquake and occurring Significantly lateral or vertical equity displacement occurs for the assembled suspension and support system.
(4) it can reduce waste of material by BIM technology setting-out blanking, factory's customization processing, overcome live processing and fabricating tired It is difficult.
(5) by reasonable process and construction method, whole unified construction installation avoids pipeline from tearing down and reconstructing or do over again, mentions High installation effectiveness reduces installation cost.
Detailed description of the invention
Fig. 1 is front view of the present invention.
Fig. 2 is top view of the present invention.
Fig. 3 is construction procedure figure of the present invention.
In figure, 1- cross-arm beam, 2- laterallys secure arm, 3- vertical columns, 4- diagonal brace, 5- line holder column, 6- pipeline branch Frame cross-arm, 7- connector, 8- fastener, 91- finishing furred ceiling sunpender, 92- pipeline sunpender, 10- pipe clamp, 11- locating pipeling part, 12- civil engineering concrete panel or beam.
Specific embodiment
The present invention will be described in detail With reference to embodiment.
The present invention relates to a kind of subway station comprehensive pipeline assembled support hanger structures, pass through BIM technology setting-out blanking, work Factory's customization processing, final each component need to only assemble assembly at construction and installation scene.
The assembled suspension and support is set up in subway station the structural slab subjacent between both walls or beam, including cross Spreader beam 1 laterallys secure arm 2, vertical columns 3 and diagonal brace 4.Cross-arm beam 1 is horizontally disposed between both walls or beam, and 1 liang of cross-arm beam End be fixedly connected with it is vertical laterally secure arm 2,1 middle part top of cross-arm beam is fixedly connected with vertical vertical columns 3, cross-arm beam 1 middle part is also fixedly connected at least one diagonal brace 4, and assembled suspension and support system when earthquake occurs that can avoid occurs significantly Vertical equity displacement.2 lower part of arm, 3 bottom end of vertical columns and 4 bottom end of diagonal brace is laterallyd secure to be fixedly connected on cross-arm beam 1. It laterallys secure 2 outside of arm to be directly fixedly mounted on side wall panel or beam, can avoid assembled suspension and support body when earthquake occurs Significantly side horizontal displacement occurs for system.Vertical columns 3 and 4 top of diagonal brace are fixedly installed to beam or structural slab bottom surface.
For each component by prefabrication at finished product member, assembly fixation in erecting bed is integral.It is only described to laterally secure arm 2 With pass through connector 7 totally at the tops of vertical columns 3 and the top of diagonal brace 4 three respectively and fastener 8 to be directly fixed on civil engineering mixed On solidifying cob wall plate or beam 12.It is interconnected and fixed by connector 7 and fastener 8 between remaining each component.
The bottom end for lateralling secure 2 lower part of arm, the bottom end of vertical columns 3 and diagonal brace 4 passes through 8 phase of connector 7 and fastener Connect fixation, is not attached fixation with civil engineering concrete panel or beam 12.Connector is interconnected small between component Part, fastener are bolt.
The vertical line holder column 5 of at least one is fixedly connected with by connector 7 and fastener 8 above cross-arm beam 1, It line holder column 5 and laterallys secure and is fixedly connected at least one by connector 7 and fastener 8 between arm 2 or vertical columns 3 Group line holder cross-arm 6.Locating pipeling part 11 or pipe clamp 10 are provided on cross-arm beam 1 or line holder cross-arm 6.
Line holder cross-arm 6 or 1 bottom surface of cross-arm beam are provided with pipeline sunpender 92.1 bottom surface of cross-arm beam is provided with finishing furred ceiling Sunpender 91.
Finishing furred ceiling sunpender 91 is directly connected to be fixed on side below cross-arm beam 1 by connector 7 and fastener 8.Pipeline Sunpender 92, pipe clamp 10 are individually fixed on cross-arm beam 1 or line holder cross-arm 6 by connector 7 and the connection of fastener 8.Pipeline Locating piece 11 is attached by fastener 8 with cross-arm beam 1 or line holder cross-arm 6, prevents pipeline or so from laterally moving horizontally.
Cross-arm beam 1 laterallys secure arm 2, vertical columns 3, line holder column 5 and line holder cross-arm 6 as single or double spelling C Type groove steel or I-steel facilitate the connector 7 that can flexibly move on it, adjust relative position, to meet live pipeline peace Set a fine position.
By the differences such as specific station civil engineering steric requirements and each device systems pipeline specification quantity, cross-arm beam 1 is laterallyd secure Arm 2, vertical columns 3, diagonal brace 4, line holder column 5, line holder cross-arm 6 etc. need to be designed or be arranged according to specific pipeline layout Deepen drawing to carry out under BIM technology three-dimensional modeling and collision detection, Force Calculation and analysis, specification type selecting, material generation, setting-out After the links such as material, then factory's customization processing is carried out, other each components in addition to above-mentioned component are (containing connector 7, fastener 8, finishing Furred ceiling sunpender 91, pipeline sunpender 92, pipe clamp 10, locating pipeling part 11 etc.) it can directly carry out trimmed size type selecting.
The construction method of above-mentioned subway station comprehensive pipeline assembled suspension and support, comprising the following steps:
A, each component of assembled suspension and support determined according to pipeline installation arrangement drawing and BIM setting-out, scene inspection unwrapping wire Fixation position of the assembled suspension and support on wallboard described in determination need to install first first group, and the successively punching peace on wallboard Dress laterallys secure arm 2;Then with laterally secure arm 2 and connect installation cross-arm beam 1, then along pipeline installation direction longitudinal probing and adjust Cross-arm beam 1 is lateralling secure the accurate fixed height on arm 2, locks cross-arm beam 1 after guaranteeing whole pipe space collisionless conflict Highly;Fixation position of the vertical columns 3 in beam body is repositioned, and punching installs and is fastened and fixed the top of column 3 in beam body End, then connect fastening with cross-arm beam 1 for 3 bottom end of vertical columns, and be finally linked in sequence fixed diagonal brace 4 like this;It is suitable again to need multilayer The largest tube line width space longitudinal probing of installation simultaneously adjusts accurate positioning of the line holder column 5 on cross-arm beam 1, guarantees whole Line holder column 5 is locked after the conflict of fluid line space collisionless, finally sequential connection fixed pipelines support cross-arm 6 like this;
B, according to the process of step A, successively assembled suspension and support described in the subsequent each group of construction and installation;
C, after completing step B, start sectionally smooth join pipeline or cable bridge on the mounted assembled suspension and support, and Arrangement drawing is installed according to pipeline and site space is checked in time, it is ensured that after not influencing subsequent other pipelinings installation, is used Locating pipeling part 11 or pipe clamp 10 are fastened and fixed or are directly locked;
D, according to the process of step C, successively each pipeline of construction and installation or cable bridge, until whole pipelines and cable bridge installation It completes;
E, according to the design of finishing furred ceiling or the cross-arm of arrangement in-depth drawing and the assembled suspension and support of live completion of having constructed 1 physical location of beam, carry out positioning verify finishing furred ceiling sunpender 91 accurate location, determine it is errorless after install and fix locking finishing Furred ceiling sunpender 91;
F, after completing step E, start successively installation connection finishing ceiling joist, and carry out finishing installation of ceiling.
The contents of the present invention are not limited to cited by embodiment, and those of ordinary skill in the art are by reading description of the invention And to any equivalent transformation that technical solution of the present invention is taken, all are covered by the claims of the invention.

Claims (7)

1. subway station comprehensive pipeline assembled suspension and support, it is characterised in that:
The assembled suspension and support is set up in below the beam body in subway station between the wallboard of two sides, including cross-arm beam (1), lateral Fixed arm (2), vertical columns (3) and diagonal brace (4);
Cross-arm beam (1) is horizontally disposed between the wallboard of two sides, is fixedly connected with vertical laterally secure above cross-arm beam (1) both ends Arm (2), cross-arm beam (1) middle part top are fixedly connected with vertical vertical columns (3), the also fixed company in top in the middle part of cross-arm beam (1) It is connected to the symmetrical diagonal brace (4) in front and back;
Arm (2) bottom end, vertical columns (3) bottom end and diagonal brace (4) bottom end is laterallyd secure to be fixedly connected in cross-arm beam (1), each portion Part is connected integral by prefabrication;
It laterallys secure and is fixedly installed to wallboard on the outside of arm (2), vertical columns (3) and diagonal brace (4) top are fixedly installed to beam body.
2. comprehensive pipeline assembled suspension and support in subway station according to claim 1, it is characterised in that:
It is fixedly connected with vertical line holder column (5) above cross-arm beam (1), line holder column (5) and laterallys secure arm (2) or between vertical columns (3) it is connected with line holder cross-arm (6).
3. comprehensive pipeline assembled suspension and support in subway station according to claim 2, it is characterised in that:
Locating pipeling part (11) or pipe clamp (10) are provided on cross-arm beam (1) or line holder cross-arm (6).
4. comprehensive pipeline assembled suspension and support in subway station according to claim 2, it is characterised in that:
Line holder cross-arm (6) bottom surface is provided with pipeline sunpender (92).
5. comprehensive pipeline assembled suspension and support in subway station according to claim 1, it is characterised in that:
Cross-arm beam (1) bottom surface is provided with finishing furred ceiling sunpender (91).
6. comprehensive pipeline assembled suspension and support in subway station according to claim 2, it is characterised in that:
Cross-arm beam (1) laterallys secure arm (2), vertical columns (3), line holder column (5) and line holder cross-arm (6) as list Or Two bors d's oeuveres C-shaped channel steel or I-steel.
7. the construction method of subway station comprehensive pipeline assembled suspension and support, it is characterised in that:
The following steps are included:
A, each component of assembled suspension and support determined according to pipeline installation arrangement drawing and BIM setting-out, scene inspection unwrapping wire Fixation position of the assembled suspension and support on wallboard described in determination need to install first first group, and the successively punching peace on wallboard Dress laterallys secure arm (2);Then with laterally secure arm (2) and connect installation cross-arm beam (1), then along pipeline installation direction longitudinal probing And adjust cross-arm beam (1) and lateralling secure the accurate fixed height on arm (2), it is locked after guaranteeing whole pipe space collisionless conflict Tight cross-arm beam (1) height;The fixation position of vertical columns (3) in beam body is repositioned, and punching installation and fastening in beam body Then vertical columns (3) bottom end is connect fastening with cross-arm beam (1) by the top of vertical columns (3), be finally linked in sequence like this solid Determine diagonal brace (4);Again along need multilayer install largest tube line width space longitudinal probing and adjust line holder column (5) in cross-arm Accurate positioning on beam (1) locks line holder column (5) after guaranteeing whole pipe space collisionless conflict, finally suitable like this Sequence is connected and fixed line holder cross-arm (6);
B, according to the process of step A, successively assembled suspension and support described in the subsequent each group of construction and installation;
C, after completing step B, start sectionally smooth join pipeline or cable bridge on the mounted assembled suspension and support, and Arrangement drawing is installed according to pipeline and site space is checked in time, it is ensured that after not influencing subsequent other pipelinings installation, is used Locating pipeling part (11) or pipe clamp (10) are fastened and fixed or are directly locked;
D, according to the process of step C, successively each pipeline of construction and installation or cable bridge, until whole pipelines and cable bridge installation It completes;
E, according to the design of finishing furred ceiling or the cross-arm of arrangement in-depth drawing and the assembled suspension and support of live completion of having constructed Beam (1) physical location, carry out positioning verify finishing furred ceiling sunpender (91) accurate location, determine it is errorless after install and fix locking It fits up furred ceiling sunpender (91);
F, after completing step E, start successively installation connection finishing ceiling joist, and carry out finishing installation of ceiling.
CN201910098683.1A 2019-01-31 2019-01-31 Subway station comprehensive pipeline assembled suspension and support and its construction method Pending CN109755907A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910098683.1A CN109755907A (en) 2019-01-31 2019-01-31 Subway station comprehensive pipeline assembled suspension and support and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910098683.1A CN109755907A (en) 2019-01-31 2019-01-31 Subway station comprehensive pipeline assembled suspension and support and its construction method

Publications (1)

Publication Number Publication Date
CN109755907A true CN109755907A (en) 2019-05-14

Family

ID=66407246

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910098683.1A Pending CN109755907A (en) 2019-01-31 2019-01-31 Subway station comprehensive pipeline assembled suspension and support and its construction method

Country Status (1)

Country Link
CN (1) CN109755907A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111692434A (en) * 2020-06-29 2020-09-22 北京城建七建设工程有限公司 Adjustable electromechanical pipeline comprehensive support and hanger system and construction method thereof
CN113566021A (en) * 2021-06-04 2021-10-29 中铁电气化局集团北京建筑工程有限公司 Construction method for suspended-ceiling-free comprehensive pipeline at entrance and exit of subway station
CN114215323A (en) * 2021-12-27 2022-03-22 广州地铁设计研究院股份有限公司 Civil engineering and mechanical-electrical integration assembly type maintenance platform and construction method thereof
CN114673834A (en) * 2022-04-13 2022-06-28 广州地铁设计研究院股份有限公司 Integrated comprehensive bearing anti-seismic system
CN115163924A (en) * 2022-08-05 2022-10-11 福州轨道交通设计院有限公司 Integrated support combined with subway assembled wallboard body system and anti-seismic support

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090229203A1 (en) * 2008-03-14 2009-09-17 Mclaughlin Jr Donald James Floor Joist Raceway
CN206571029U (en) * 2016-12-29 2017-10-20 中铁电气化局集团北京建筑工程有限公司 Branch, which is integrated, without furred ceiling hangs system
CN107620832A (en) * 2016-07-14 2018-01-23 河南大森机电股份有限公司 It is a kind of to integrate suspension and support without furred ceiling
CN209344717U (en) * 2019-01-31 2019-09-03 中铁第一勘察设计院集团有限公司 A kind of subway station comprehensive pipeline assembled suspension and support

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090229203A1 (en) * 2008-03-14 2009-09-17 Mclaughlin Jr Donald James Floor Joist Raceway
CN107620832A (en) * 2016-07-14 2018-01-23 河南大森机电股份有限公司 It is a kind of to integrate suspension and support without furred ceiling
CN206571029U (en) * 2016-12-29 2017-10-20 中铁电气化局集团北京建筑工程有限公司 Branch, which is integrated, without furred ceiling hangs system
CN209344717U (en) * 2019-01-31 2019-09-03 中铁第一勘察设计院集团有限公司 A kind of subway station comprehensive pipeline assembled suspension and support

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111692434A (en) * 2020-06-29 2020-09-22 北京城建七建设工程有限公司 Adjustable electromechanical pipeline comprehensive support and hanger system and construction method thereof
CN113566021A (en) * 2021-06-04 2021-10-29 中铁电气化局集团北京建筑工程有限公司 Construction method for suspended-ceiling-free comprehensive pipeline at entrance and exit of subway station
CN113566021B (en) * 2021-06-04 2022-12-13 中铁电气化局集团北京建筑工程有限公司 Construction method for suspended-ceiling-free comprehensive pipeline at entrance and exit of subway station
CN114215323A (en) * 2021-12-27 2022-03-22 广州地铁设计研究院股份有限公司 Civil engineering and mechanical-electrical integration assembly type maintenance platform and construction method thereof
CN114673834A (en) * 2022-04-13 2022-06-28 广州地铁设计研究院股份有限公司 Integrated comprehensive bearing anti-seismic system
CN114673834B (en) * 2022-04-13 2022-10-21 广州地铁设计研究院股份有限公司 Integrated comprehensive bearing anti-seismic system
CN115163924A (en) * 2022-08-05 2022-10-11 福州轨道交通设计院有限公司 Integrated support combined with subway assembled wallboard body system and anti-seismic support
CN115163924B (en) * 2022-08-05 2024-05-28 福州轨道交通设计院有限公司 Comprehensive support combined with subway assembled wallboard system and anti-seismic support

Similar Documents

Publication Publication Date Title
CN109755907A (en) Subway station comprehensive pipeline assembled suspension and support and its construction method
KR20070005021A (en) Two-way architectural structural system and modular support member
CN106193402B (en) Girder truss integrated form flooring module and its installation method
CN110306658A (en) Steel construction for assembled architecture assembles system and construction method
CN204475846U (en) A kind of conversion support system for socket joint dish button steel tube frame
CN209344717U (en) A kind of subway station comprehensive pipeline assembled suspension and support
CN107268885A (en) Saving steels type H profile steel beam
CA3029674A1 (en) Quad v-panel assembly
KR20200051313A (en) Construction Method of Pipe Rack Structure
CN208899928U (en) Stage building structure
CN106870827A (en) Line holder structure and installation method in concrete structure
CN109555313A (en) A kind of adjustable gib truss for assembled floor
CN203213348U (en) Large space NALC (Autoclaved Lightweight Concrete) wall board structure
CN115637810A (en) Large-space special-shaped honeycomb aluminum plate ceiling structure and construction method
CN206667572U (en) A kind of modified quickly connects prefabricated thermal insulation building block
CN103046648B (en) Combination construction steel bar connecting joints
CN105839830A (en) Movable locator for transfer floor hyperboloidalceiling joist, ceiling system and construction method thereof
CN204676757U (en) Suspended-ceiling suspension device
JP2010048398A (en) Piping unit and connection structure of the same
CN208078566U (en) A kind of city integrated piping lane intersection pipeline portal structure and city integrated piping lane system
CN209046168U (en) A kind of high-tension cable console mode steel framed bent
CN208472978U (en) A kind of roofing of reinforced concrete roof hangs Foundation fixing device
CN110030005A (en) The light-duty guarantor's circle support system of shield tunnel and its construction method
CN208074291U (en) Prefabricated for pipeline ensemble, installation precast combined holder
JP2607701B2 (en) Unit coupling device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination