CN109740786A - A kind of multiterminal flexible interconnection distribution network planning method and system - Google Patents

A kind of multiterminal flexible interconnection distribution network planning method and system Download PDF

Info

Publication number
CN109740786A
CN109740786A CN201811363158.XA CN201811363158A CN109740786A CN 109740786 A CN109740786 A CN 109740786A CN 201811363158 A CN201811363158 A CN 201811363158A CN 109740786 A CN109740786 A CN 109740786A
Authority
CN
China
Prior art keywords
power
cost
ess
node
mbvh
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811363158.XA
Other languages
Chinese (zh)
Inventor
韩华春
葛乐
张伟
李强
吕振华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changzhou Power Supply Branch Jiangsu Electric Power Co Ltd
State Grid Corp of China SGCC
Nanjing Institute of Technology
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
Changzhou Power Supply Branch Jiangsu Electric Power Co Ltd
State Grid Corp of China SGCC
Nanjing Institute of Technology
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changzhou Power Supply Branch Jiangsu Electric Power Co Ltd, State Grid Corp of China SGCC, Nanjing Institute of Technology, Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd filed Critical Changzhou Power Supply Branch Jiangsu Electric Power Co Ltd
Priority to CN201811363158.XA priority Critical patent/CN109740786A/en
Publication of CN109740786A publication Critical patent/CN109740786A/en
Pending legal-status Critical Current

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a kind of multiterminal flexible interconnection distribution network planning method and system, meter and source, net, lotus, the interaction between Chu Sizhe, coordinate distributed generation resource operator, grid company and the respective interests demand of power consumer, systems organization and running optimizatin are combined, propose three layers of coordinated planning model of multiterminal flexible interconnection power distribution network " source-net-lotus-storage ", using the uncertain problem of scene analysis method processing distributed generation resource and load, using the hybrid algorithm solving model based on simulated annealing and interior point method composition.The present invention takes into account the interests demand of different subjects, promote source, net, lotus, storage friendly interaction, ensure DG operator and power consumer respectively interests while, moreover it is possible to improve system operation level, improve the power supply quality and economy of system operation.

Description

A kind of multiterminal flexible interconnection distribution network planning method and system
Technical field
The invention belongs to active distribution network planning technology fields, and in particular to a kind of multiterminal flexible interconnection distribution network planning side Method and system.
Background technique
With the development of back-to-back flexible direct current (Back-to-Back VSC-HVDC) technology, flexible electric electronics is utilized Technological transformation power distribution network becomes an important trend.Back-to-back soft straight technology is applied to AC distribution net, can be changed " closed loop design, open loop operation " mode that China's power distribution network is carried out for a long time, not only may be implemented any feeder line of power distribution network and pacifies for a long time Full Electromagnetic coupling, and can the distribution of accuracy controlling electric network swim.The operation of power distribution network flexible interconnection is to promote power supply reliability and rush The important channel dissolved into Thief zone DG close friend.
In order to meet the power supply reliability demand of customer charge continuous improvement, Modern power distribution network planning is drawn in direction and is had begun It is a large amount of it is standby for one using two, three directly got in touch with for multi-thread powering mode, a plurality of feeder line such as standby by the loop networks switch of end Scene generally occurs.Therefore, using multiterminal back-to-back it is soft it is straight (multi-terminal back-to-back VSC-HVDC, MBVH) loop networks switch is replaced to further realize a plurality of feeder line flexible interconnection, forms multiterminal flexible interconnection power distribution network, just can in this way The flexible interconnection demand under multi-thread power supply scene is adapted to, scrap build cost and workload are reduced.But directly it is with soft back-to-back The flexible power flowcontrol technology of representative, is substantially still the regulation of power level, high when interconnection feeder line variable capacity is lower Infiltration DG access still will affect system safe and stable operation.
In recent years, the controllable devices such as energy storage and flexible load are grown rapidly, and provide more supplies to power distribution network Side and Demand-side resource can provide the regulation of timing energy level for power grid, therefore, if can unite in distribution network planning and operation It raises and considers influencing each other for all kinds of controllable flexible resources, coordinate the interests between each investment subject, just can further promote distribution The economy and safety of operation.
At this stage, DG operator fails to fully consider the planning and development situation of power distribution network in planning, by trend section The limitation of capacity causes abandonment to abandon optical issue serious;Grid company does not fully consider the possible planning of DG in investment construction Situation, but also distribution network planning is unreasonable, it is difficult to receive DG largely to network, can not achieve maximizing the benefits;Grid company is removed Outside investment construction, also implementable all kinds of Demand Side Responses (demand side response, DSR) project, motivates ESS and FL Equal power consumers adjust electricity consumption behavior, this equally also will affect distribution investment construction and DG access amount.It therefore, is realization DG operation Interests between quotient, grid company and power consumer tripartite's main body, the coordinated planning for carrying out " source-net-lotus-storage " have important meaning Justice.
Summary of the invention
Goal of the invention: in order to overcome the deficiencies in the prior art, the present invention provides a kind of multiterminal flexible interconnection distribution Net method and system for planning can ensure distributed generation resource operator and power consumer respectively interests, and can improve system operation water It is flat, improve the power supply quality and economy of system operation.
Technical solution: a kind of multiterminal flexible interconnection distribution network planning method of the present invention the following steps are included:
(1) power grid operator, flexible load user and the respective year comprehensive income of energy storage user are up in a distributed manner Target, using simulated annealing to the addressing constant volume model of distributed generation resource, flexible load and the energy-storage system pre-established It is solved;
(2) with the minimum target of grid company year overall cost, the multiterminal pre-established are carried on the back using simulated annealing The soft straight constant volume model of backrest is solved;
(3) according to the operation result of step (1), step (2), with the minimum target of system annual operating and maintenance cost, using interior point Method solves the optimal operation model pre-established;
(4) by the operation result of step (3) feedback into step (1) and step (2), and by the operation result of step (1) It is transmitted in step (2), forms iteration optimization, when reaching maximum number of iterations, terminate optimization, form optimum programming scheme;When Not up to maximum number of iterations, return step (1) optimize into a new round.
The objective function of the addressing constant volume model of the distributed power supply system is as follows:
Wherein:Respectively the year sale of electricity income of DG operator, year subsidy are received Benefit, ancillary service annual earnings, annual operating cost and year investment cost;T is the optimization period, and s is optimization scene, NsFor scene number; ΩDGFor DG upgrading node collection;psFor scene probability;Δ t is Period Length;The online sale of electricity electricity of respectively DG Valence and policy subsidize electricity price;The Reactive Power Price of ancillary service is provided for DG under t period scene s;Respectively DG The operation expense and cost of investment of unit capacity;Output for DG at t period scene s lower node i is active Power and reactive power;For the installed capacity of DG at node i;D is discount rate;yDGFor the Economic Life of DG;Allow the DG maximum capacity upper limit installed for node i;aiFor nonnegative integer;SDG,0For DG unit rated capacity;
The objective function of the addressing constant volume model of the flexible load system is as follows:
Wherein:Respectively flexible load participates in the electricity cost of reduction and the compensation income of acquisition after DSR; The respectively annual operating cost of flexible load and year investment cost;ΩFLFor flexible load upgrading node collection; The respectively ancillary service electricity price, maintenance cost and unit capacity cost of investment of flexible load;When for t The original loads power of flexible load at section scene s lower node i;It is soft at respectively t period scene s lower node i Property load power and flexible load regulating power, wherein increase power be positive, reduce power be negative;ΔPi FL, max、ΔPi FL ,minThe bound of flexible load regulating power respectively at node i;psFor scene probability;ct,sFor power grid under t period scene s Purchase electricity price;Δ t is the time span of each period in an optimizing cycle;yFLFor flexible load utilization periods;For section Flexible load rated power at point i;
The objective function of the addressing constant volume model of the energy-storage system is as follows:
Wherein:Year the online income, year power purchase expense, annual running cost of respectively ESS With with year investment cost;ΩESSFor ESS upgrading node collection;For the charge and discharge electric work of ESS at t period scene s lower node i Rate, charging are negative, and electric discharge is positive;The operation and maintenance of online the sale of electricity electricity price, unit capacity of respectively ESS Cost and cost of investment;ct,sFor grid company sale of electricity electricity price;Respectively ESS unit power cost and unit Capacity Cost;Respectively rated power ESS to be installed at node i and rated capacity;yESSFor the warp of ESS It helps service life;Respectively node i allow install the ESS maximum power upper limit and the maximum capacity upper limit; eiFor nonnegative integer;PESS,0、SESS,0Respectively ESS specific power ratings and unit rated capacity.
The back-to-back soft straight constant volume model of step (2) described multiterminal:
Wherein:For power distribution network superior power grid purchases strategies,Operating cost is invested for MBVH,For Web-based exercise,For emission reduction benefit;ΩgridIt is coupled point set with upper network for distribution,For the purchase of distribution superior power grid Electrical power,For superior power grid purchase electricity price at t period scene s lower node i;ΩMBVHFor the position MBVH collection, ηMBVH、 yMBVHThe respectively Economic Life of MBVH, year operation and maintenance cost coefficient, unit capacity cost of investment,For MBVH capacity to be installed;Pt,s,iFor the i-node injecting power under scene s in the t period, AMBVH,iFor MBVH current transformer at node i Loss factor,For the active power of output of MBVH current transformer at t period scene s lower node i;cemiFor the discharge of higher level's power grid Cost;Allow the MBVH maximum capacity upper limit installed for node i;miFor nonnegative integer;SMBTB,0For MBVH unit volume Constant volume;N indicates distribution number of nodes;ct,sFor power grid purchase electricity price under t period scene s;At t period scene s lower node i Distributed power source output power.
Step (3) described optimal operation model includes that FL optimal operation model, ESS optimal operation model and system operation are excellent Change model.
The step (3) the following steps are included:
(31) FL optimal operation model be meet FL operation constraint while, using FL run Income Maximum as target, The output power of decision FL, objective function are as follows:
(32) ESS optimal operation model is while meeting ESS operation constraint, using ESS operation Income Maximum as mesh Mark, the output power of decision ESS, objective function are as follows:
(33) solving result based on FL optimal operation model and ESS optimal operation model, running Optimization model are System annual operating and maintenance cost, the operating status of optimization system, decision DG are minimized while meeting power distribution network various constraint conditions With the output of MBVH it is active/reactive power, objective function is as follows:
A kind of multiterminal flexible interconnection distribution network planning system of the present invention, including upper layer planning module, middle layer planning Module, lower layer's planning module and calculating feedback module;The upper layer planning module in a distributed manner use by power grid operator, flexible load Family and the respective year comprehensive income of energy storage user are up to target, using simulated annealing to the distributed electrical pre-established The addressing constant volume model in source, flexible load and energy-storage system is solved;The middle layer planning module is comprehensive with grid company year Cost minimization is target, and using simulated annealing, to the multiterminal pre-established, soft straight constant volume model is solved back-to-back; Lower layer's planning module is with the minimum target of system annual operating and maintenance cost, using interior point method to the optimal operation model pre-established It is solved;The feedback module that calculates plans the operation result feedback of lower layer's planning module to upper layer planning module and middle layer In module, and the operation result of upper layer planning module is transmitted in the planning module of middle layer, when reaching maximum number of iterations, is terminated It calculates;When not up to maximum number of iterations, return upper layer planning module recalculate.
The utility model has the advantages that compared with prior art, the invention has the benefit that taking into account the interests demand of different subjects, promoting Into source, net, lotus, storage friendly interaction, ensure distributed generation resource operator and power consumer respectively interests while, moreover it is possible to improve System operation level improves the power supply quality and economy of system operation.
Detailed description of the invention
Fig. 1 is three layers of coordinated planning relational graph;
Fig. 2 is " source, net, lotus, storage " flexible power distribution network figure;
Fig. 3 is that the present invention solves flow chart;
Fig. 4 is 33 node example system diagrams;
Fig. 5 is system per period minimum node voltage pattern under four kinds of schemes;
Fig. 6 is energy storage power graph;
Fig. 7 is energy storage electric quantity curve figure;
Fig. 8 is flexible load power graph.
Specific embodiment
The present invention will be further explained with reference to the accompanying drawing.A kind of multiterminal flexible interconnection distribution network planning method, Include the following steps:
1, power grid operator, flexible load user and the respective year comprehensive income of energy storage user are up to mesh in a distributed manner Mark, using simulated annealing to the addressing constant volume model of distributed generation resource, flexible load and the energy-storage system pre-established into Row solves.
From economy, the year comprehensive income of power supply (DG) operator is up to target in a distributed manner, determines the peace of DG Holding position and capacity, objective function are as follows:
In formula:Respectively the year sale of electricity income of DG operator, year subsidy are received Benefit, ancillary service annual earnings, annual operating cost and year investment cost;T is the optimization period, and s is optimization scene, NsFor scene number; ΩDGFor DG upgrading node collection;psFor scene probability;Δ t is Period Length;The online sale of electricity electricity of respectively DG Valence and policy subsidize electricity price;The Reactive Power Price of ancillary service is provided for DG under t period scene s;Respectively DG The operation expense and cost of investment of unit capacity;Output for DG at t period scene s lower node i is active Power and reactive power;For the installed capacity of DG at node i;D is discount rate;yDGFor the Economic Life of DG;Allow the DG maximum capacity upper limit installed for node i;aiFor nonnegative integer;SDG,0For DG unit rated capacity.
Consider that user participates in demand response, it is believed that user can determine response policy so as to adjust its electricity consumption based on number one Behavior.The price type DSR project that user may participate in is tou power price, and user is transferred out of load in electricity price peak period, in electricity price Pinggu period is transferred into load.DSR acquisition year comprehensive income is participated in flexible load user and is up to target, determines the transformation of FL Position and transformation capacity, objective function are as follows:
In formula:Respectively flexible load participates in the electricity cost of reduction and the compensation income of acquisition after DSR; The respectively annual operating cost of flexible load and year investment cost;ΩFLFor flexible load upgrading node collection; The respectively ancillary service electricity price, maintenance cost and unit capacity cost of investment of flexible load;When for t The original loads power of flexible load at section scene s lower node i;It is soft at respectively t period scene s lower node i Property load power and flexible load regulating power, wherein increase power be positive, reduce power be negative;ΔPi FL, max、ΔPi FL , minThe bound of flexible load regulating power respectively at node i.
Energy storage user realizes arbitrage according to grid company tou power price and energy storage rate for incorporation into the power network difference, maximum with year comprehensive income For target, the installation site and capacity of ESS are determined, objective function is as follows:
In formula:Year the online income, year power purchase expense, annual running cost of respectively ESS With with year investment cost;ΩESSFor ESS upgrading node collection;For the charge and discharge electric work of ESS at t period scene s lower node i Rate, charging are negative, and electric discharge is positive;The operation and maintenance of online the sale of electricity electricity price, unit capacity of respectively ESS Cost and cost of investment;ct,sFor grid company sale of electricity electricity price;Respectively ESS unit power cost and unit Capacity Cost;Respectively rated power ESS to be installed at node i and rated capacity;yESSFor the warp of ESS It helps service life;Respectively node i allow install the ESS maximum power upper limit and the maximum capacity upper limit; eiFor nonnegative integer;PESS,0、SESS,0Respectively ESS specific power ratings and unit rated capacity.
Storage energy operation constraint is needed comprising the following:
1) ESS discharge power constrains
2) ESS charge power constrains
3) ESS state-of-charge SOC is constrained
In formula: SOCt,s,iFor the SOC value of ESS at t period scene s lower node i;WithRespectively node i Locate the SOC value bound of ESS;ξchAnd ξdisRespectively ESS efficiency for charge-discharge.
2, with the minimum target of grid company year overall cost, the multiterminal pre-established are leaned against using simulated annealing The constant volume model for carrying on the back soft straight (MBVH) is solved.
In using minimize grid company year overall cost as target, obtain the constant volume model of optimal MBVH:
In formula:For power distribution network superior power grid purchases strategies,Operating cost is invested for MBVH,For Web-based exercise,For emission reduction benefit;ΩgridIt is coupled point set with upper network for distribution,For the purchase of distribution superior power grid Electrical power,For superior power grid purchase electricity price at t period scene s lower node i;ΩMBVHFor the position MBVH collection, ηMBVH、 yMBVHThe respectively Economic Life of MBVH, year operation and maintenance cost coefficient, unit capacity cost of investment,For MBVH capacity to be installed;Pt,s,iFor the i-node injecting power under scene s in the t period, AMBVH,iFor MBVH current transformer at node i Loss factor,For the active power of output of MBVH current transformer at t period scene s lower node i;cemiFor the discharge of higher level's power grid Cost;Allow the MBVH maximum capacity upper limit installed for node i;miFor nonnegative integer;SMBTB,0For MBVH unit volume Constant volume.
One end current transformer is controlled using constant voltage in MBVH, and other each end current transformers use constant dc power control, is considered certain Loss factor, MBVH operation constraint it is as follows:
1) active power balance constraint
2) current transformer reactive power constrains
3) Converter Capacity constrains
In formula:WithIn respectively period t at scene s lower node i MBVH current transformer active power of output And reactive power, and provide that flowing into feeder line is positive direction;μ is reactive power limit coefficient;For MBVH unsteady flow at node i The access capacity of device.
3, with the minimum target of system annual operating and maintenance cost, the optimal operation model pre-established is asked using interior point method Solution;
Optimal operation model includes flexible load (FL) optimal operation model, energy storage (ESS) optimal operation model and system Three submodels of optimal operation model.
FL optimal operation model be meet FL operation constraint while, using FL run Income Maximum as target, decision The output power of FL, objective function are as follows:
ESS optimal operation model is while meeting ESS operation constraint, using ESS operation Income Maximum as target, certainly The output power of plan ESS, objective function are as follows:
Solving result based on FL optimal operation model and ESS optimal operation model, running Optimization model are full Minimize system annual operating and maintenance cost while sufficient power distribution network various constraint conditions, the operating status of optimization system, decision DG and The output of MBVH is active/reactive power, objective function is as follows:
Constraint condition removes formula (3), formula (24)~formula (26), comprising: constraint, node electricity are sent in system load flow constraint, trend Pressure constraint and line power constraint.Constraint condition is as follows:
In formula: i, j are system node number;Ut,s,i、Ut,s,jIt (t) is the voltage magnitude of t period node i and node j;Gij、Bij Transconductance and mutual susceptance respectively between node i and node j;δt,s,ijFor the phase difference between t period node i and node j; Pt,s,ijFor the line power between t period node i and node j;WithFor node voltage bound;Line power The upper limit.
4, by the operation result feedback of step 3 into step 1 and step 2, and the operation result of step 1 is transmitted to step In 2, iteration optimization is formed, when reaching maximum number of iterations, terminates optimization, forms optimum programming scheme;When not up to maximum changes Generation number, return step 1 optimize into a new round.
A kind of multiterminal flexible interconnection distribution network planning system, including upper layer module, middle layer module, lower module and calculating are anti- Present module;The upper layer module in a distributed manner receive by power grid operator, flexible load user and the respective year synthesis of energy storage user Benefit is up to target, the addressing using simulated annealing to the distributed generation resource, flexible load and the energy-storage system that pre-establish Constant volume model is solved;The middle layer module is with the minimum target of grid company year overall cost, using simulated annealing To the multiterminal pre-established, soft straight constant volume model is solved back-to-back;The lower module is minimum with system annual operating and maintenance cost For target, the optimal operation model pre-established is solved using interior point method;The calculating feedback module is by lower module Operation result feedback into upper layer module and middle layer module, and the operation result of upper layer module is transmitted in the module of middle layer, When reaching maximum number of iterations, terminate to calculate;When not up to maximum number of iterations, return upper layer module recalculate.
Programme is passed to middle lower layer by upper layer model, and programme is passed to lower layer, underlying model by middle layer model It respectively runs Income Maximum year using flexible load and energy-storage system and carries out running optimizatin, the output work of flexibility in decision load as target Rate and energy-storage system output power, then with the minimum target of distribution annual operating and maintenance cost, decision multiterminal are soft straight and distributed back-to-back The output of power supply is active or reactive power, and distributed generation resource that decision obtains, flexible load, energy-storage system, multiterminal are leaned against It carries on the back soft straight four optimized operation and goes out force feedback to middle layer and upper layer.
" source, net, lotus, storage " flexibility power distribution network as shown in Fig. 2, in the case where electricity market background and policy are encouraged, DG operator, Energy storage user and flexible load user have a motivation and power preferentially to make a policy, different interests main body decision problem need into Row layered shaping.Upper layer planning is up to target, decision with DG operator, FL user and the respective year comprehensive income of ESS user The installation site and capacity of DG, ESS, FL three;It plans with the minimum target of grid company year overall cost, decision MBVH in middle layer Installed capacity;Lower layer is respectively run Income Maximum year using FL and ESS first and carries out running optimizatin, the output of decision FL as target Power and ESS output power, then again with the minimum target of distribution annual operating and maintenance cost, the output of decision MBVH and DG have system Function/reactive power.DG, FL, ESS installation site and capacity are passed to middle lower layer by upper layer, and then, middle layer holds the installation of MBVH Amount and DG and each scene power transfer of load are to lower layer, and later, lower layer is according to the program results in upper layer and middle layer to run warp Ji property is objective optimization system running state, and DG, FL, ESS, MBVH optimized operation that decision obtains are gone out force feedback and arrived Middle layer and upper layer.
Consider that systems organization and operation combined optimization, each layer model mutually transmit data and variable, alternating iteration, lower layer's root According to the program results in upper middle layer using performance driving economy as objective optimization system, upper middle layer is then again excellent according to the operation result of lower layer Change itself decision, and then start next round loop optimization, the relationship of three layers of coordinated planning is as shown in Figure 1.Above-mentioned three layers of coordination rule Draw model be difficult to by single method solve, the present invention using simulated annealing algorithm (SA) and interior point method composition hybrid algorithm into Row solves, and specific solution procedure is as shown in figure 3, wherein SA is used to obtain addressing constant volume scheme and the middle layer of upper layer DG, FL, ESS The constant volume scheme of MBVH, interior point method is used to solve the running optimizatin problem of lower layer FL, ESS and system, when the number of iterations reaches most The maximum number of iterations being just arranged 10000 times, optimization process terminate, and form optimum programming scheme.
In order to verify the feasibility and validity of the proposed coordinated planning method of the present invention, using 33 nodes as shown in Figure 4 Example system carries out analysis verifying to the three-level programming model of proposition, and the system is logical for 4 feeder lines from 4 different substations It crosses MBVH and is connected to form a closed-loop system.System nominal voltage is 10kV, and total burden with power is 7.43MW, and load or burden without work is 4.6Mvar.DG, FL, ESS and MBVH relative parameters setting are shown in Table 1~table 4, and electricity price relevant parameter is shown in Table 5.Set complete one A dispatching cycle is sampling time interval 15min for 24 hours, totally 96 periods.The sample number of photovoltaic and load is after reduction 3,9 kinds of total Run-time scenarios are obtained after joint mapping, corresponding scene probability of happening and PV and load power are calculated, and will PV and load power are normalized.Simulation Example Program under MATLAB R2014a environment.
The present invention set 4 kinds of programmes: 1. plan do not have the DG of Reactive-power control ability, do not consider MBVH, ESS and FL;2. planning has the DG of Reactive-power control ability, MBVH, ESS and FL are not considered;3. planning have Reactive-power control ability DG with MBVH does not consider ESS and FL;4. planning has Reactive-power control ability DG, MBVH, ESS and FL, using three layers of Optimized model, obtain The program results arrived are as shown in 6~table of table 9, it can be deduced that draw a conclusion:
1) compared with original system, the DG annual earnings of scheme 1,2,3 are respectively 96.10 ten thousand yuan, 111.08 ten thousand yuan and 154.78 Wan Yuan, DG installed capacity are respectively 3.7MW, 3.9MW, 5.6MW, distribution year comprehensive power supply cost reduce respectively 335.26 ten thousand yuan, 359.73 ten thousand yuan and 596.00 ten thousand yuan, decreasing loss rate is respectively 27.31%, 35.24%, 40.55%.Illustrate to configure DG in systems Obvious income can be brought for DG operator and grid company, and grid company investment MBVH improves the regulating power of system, energy DG consumption rate is enough further increased, the requirement of both sides is met.
2) compared to scheme 3, after scheme 4 considers power consumer coordinated planning, energy storage user and flexible load annual earnings point Wei not be 8.07 ten thousand yuan and 152.31 ten thousand yuan, the annual earnings of DG operator increase 33.52 ten thousand yuan, and DG installed capacity increases 0.4MW, grid company year, comprehensive power supply cost again reduced 31.22 ten thousand yuan, and decreasing loss rate is up to 48.23%.Illustrate, using this hair After " source-net-lotus-storage " coordinated planning model of bright proposition, DG operator and power consumer have certain net profit, and power grid The power supply cost of company is significantly reduced, i.e. coordinated planning has ensured the interests of tripartite simultaneously.
3) it compares scheme 1 and scheme 2, DG installed capacity increases 0.2MW, DG operator annual earnings increase 14.98 ten thousand Member, grid company year, comprehensive power supply cost reduced 24.67 ten thousand yuan.Illustrate that grid company is certain by providing according to power grid demand Reactive Power Ancillary Services electricity price has increase accordingly DG configuration capacity after DG operator active response electricity price, increases the same of sale of electricity income When, extra returns are also obtained come responsive electricity grid demand by gird-connected inverter residual capacity in the Reactive Power Ancillary Services period.Power grid Although the certain ancillary service cost of company's pay this extra, superior power grid purchases strategies and Web-based exercise reduce more, Total power supply cost is still reduced.As long as therefore reasonably introducing DSR, so that it may improve system operation and reduce system and throw Money, to improve distribution construction economy.
4) as can be seen from Table 6, grid company is greatly reduced from the purchases strategies of higher level's power grid.The reason is as follows that: 1, it connects The power purchase approach for entering power distribution network after DG increases, be no longer it is single can be commercially available from local DG operation from higher level's power grid power purchase Electricity;2, on the one hand the MBVH of grid company investment operation can select cost in real time according to bus nodes electricity price and workload demand Minimum scheme carries out power purchase, and the installation of another aspect MBVH improves the power flow regulating ability of system, increases the consumption of DG Ability reduces purchases strategies indirectly;3, after implementing DSR, energy storage and flexible load release electric energy in electricity price peak period respectively With reduction electricity consumption, the purchases strategies of grid company are again reduced.
5) system per period minimum node voltage is as shown in Figure 5 under four kinds of schemes, it can be seen that scheme 1 compares original system Daytime photovoltaic there is power output period node voltage to get over lower limit situation and make moderate progress, but load peak period voltage is still more at night Limit is serious.After 17:00~21:00 introduces the participation ancillary service of Reactive Power Price excitation PV operator, system voltage obtains scheme 2 Effective improvement, but still constrained lower than lower voltage limit within multiple periods.Under scheme 3 and scheme 4, system node voltage More Lower Boundary has obtained comprehensive solution, and scheme 4 is smaller compared to 3 maximum node voltage deviation of scheme.Thus illustrate, The coordinated planning of four kinds of flexible resources can give full play to voltage regulation capability, and MBVH provides a large amount of reactive power support effectively System voltage is improved, energy storage and the application of flexible load have then further reduced voltage deviation, thus the power supply of whole system Quality has obtained effective raising, ensure that power supply quality is optimal.
6) by taking energy storage at node 14 and the flexible load at node 25 as an example, corresponding operation curve, can as shown in Fig. 6,7,8 To find out, in the load peak period, energy storage releases electric energy as load power supply, and flexible load reduces electricity consumption and reduces system loading. Illustrate, grid company can motivate power consumer to participate in the optimization operation of power grid, realize soft by implementing reasonable DSR The coordinated operation of property resource.
1 PV relevant parameter of table
2 MBVH relevant parameter of table
3 energy storage relevant parameter of table
4 flexible load relevant parameter of table
5 electric price parameter of table
Remarks: the peak period: section when 10:00-12:00,17:00-20:00 is flat: 6:00-9:00,13:00-16:00,21: The 00-24:00 paddy period: 1:00-5:00
6 DG program results of table
7 power grid of table (MBVH) program results
8 flexible load program results of table
9 energy storage program results of table
The above is only a preferred embodiment of the present invention, it should be pointed out that: for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (6)

1. a kind of multiterminal flexible interconnection distribution network planning method, which comprises the following steps:
(1) power grid operator, flexible load user and the respective year comprehensive income of energy storage user are up to target in a distributed manner, It is asked using addressing constant volume model of the simulated annealing to distributed generation resource, flexible load and the energy-storage system pre-established Solution;
(2) back-to-back to the multiterminal pre-established using simulated annealing with the minimum target of grid company year overall cost Soft straight constant volume model is solved;
(3) according to the operation result of step (1), step (2), with the minimum target of system annual operating and maintenance cost, using interior point method pair The optimal operation model pre-established is solved;
(4) the operation result feedback of step (3) is transmitted into step (1) and step (2), and by the operation result of step (1) To in step (2), iteration optimization is formed, when reaching maximum number of iterations, terminates optimization, forms optimum programming scheme;When not reaching To maximum number of iterations, return step (1) optimizes into a new round.
2. a kind of multiterminal flexible interconnection distribution network planning method according to claim 1, which is characterized in that step (1) institute The objective function of the addressing constant volume model for the distributed power supply system stated are as follows:
Wherein:Respectively the year sale of electricity income of DG operator, year subsidy income, auxiliary Help service annual earnings, annual operating cost and year investment cost;T is the optimization period, and s is optimization scene, NsFor scene number;ΩDGFor DG upgrading node collection;psFor scene probability;Δ t is Period Length;The online sale of electricity electricity price of respectively DG and Policy subsidizes electricity price;The Reactive Power Price of ancillary service is provided for DG under t period scene s;Respectively DG unit The operation expense and cost of investment of capacity;For DG at t period scene s lower node i active power of output and Reactive power;For the installed capacity of DG at node i;D is discount rate;yDGFor the Economic Life of DG;For section Point i allows the DG maximum capacity upper limit installed;aiFor nonnegative integer;SDG,0For DG unit rated capacity;
The objective function of the addressing constant volume model of flexible load system is as follows:
Wherein:Respectively flexible load participates in the electricity cost of reduction and the compensation income of acquisition after DSR;The respectively annual operating cost of flexible load and year investment cost;ΩFLFor flexible load upgrading node collection;The respectively ancillary service electricity price, maintenance cost and unit capacity cost of investment of flexible load;For t The original loads power of flexible load at period scene s lower node i; It is soft at respectively t period scene s lower node i Property load power and flexible load regulating power, wherein increase power be positive, reduce power be negative;ΔPi FL,max、ΔPi FL ,minThe bound of flexible load regulating power respectively at node i;psFor scene probability;ct,sFor power grid under t period scene s Purchase electricity price;Δ t is the time span of each period in an optimizing cycle;yFLFor flexible load utilization periods;For section Flexible load rated power at point i;
The scalar functions of the addressing constant volume model of energy-storage system are as follows:
Wherein:Respectively ESS year online income, year power purchase expense, annual operating cost and Year investment cost;ΩESSFor ESS upgrading node collection;For the charge-discharge electric power of ESS at t period scene s lower node i, Charging is negative, and electric discharge is positive;Respectively ESS online sale of electricity electricity price, unit capacity operation and maintenance at Sheet and cost of investment;ct,sFor grid company sale of electricity electricity price;Respectively ESS unit power cost and unit are held Measure cost;Respectively rated power ESS to be installed at node i and rated capacity;yESSMake for the economy of ESS Use the time limit;Respectively node i allow install the ESS maximum power upper limit and the maximum capacity upper limit;eiFor Nonnegative integer;PESS,0、SESS,0Respectively ESS specific power ratings and unit rated capacity.
3. a kind of multiterminal flexible interconnection distribution network planning method according to claim 1, which is characterized in that step (2) institute State multiterminal soft straight constant volume model back-to-back:
Wherein:For power distribution network superior power grid purchases strategies,Operating cost is invested for MBVH,For network loss Cost,For emission reduction benefit;ΩgridIt is coupled point set with upper network for distribution,For distribution superior power grid power purchase function Rate,For superior power grid purchase electricity price at t period scene s lower node i;ΩMBVHFor the position MBVH collection, ηMBVH、yMBVHThe respectively Economic Life of MBVH, year operation and maintenance cost coefficient, unit capacity cost of investment,For MBVH Capacity to be installed;Pt,s,iFor the i-node injecting power under scene s in the t period, AMBVH,iFor the loss of MBVH current transformer at node i Coefficient,For the active power of output of MBVH current transformer at t period scene s lower node i;cemiFor higher level's power grid discharge at This;Allow the MBVH maximum capacity upper limit installed for node i;miFor nonnegative integer;SMBTB,0It is specified for MBVH unit Capacity;N indicates distribution number of nodes;ct,sFor power grid purchase electricity price under t period scene s;At t period scene s lower node i Distributed power source output power.
4. a kind of multiterminal flexible interconnection distribution network planning method according to claim 1, which is characterized in that step (3) institute Stating optimal operation model includes flexible load optimal operation model, storage energy operation Optimized model and running Optimization model.
5. a kind of multiterminal flexible interconnection distribution network planning method according to claim 4, which is characterized in that the step (3) the following steps are included:
(31) flexible load optimal operation model is while meeting operation constraint, using year operation Income Maximum as target, certainly The output power of plan flexible load operation, objective function are as follows:
(32) storage energy operation Optimized model is while meeting operation constraint, and using year operation Income Maximum as target, decision is stored up The output power that can be run, objective function are as follows:
(33) solving result based on flexible load optimal operation model and storage energy operation Optimized model, running Optimization model It is that system annual operating and maintenance cost, the operating status of optimization system, decision are minimized while meeting power distribution network various constraint conditions Distributed generation resource and multiterminal back-to-back soft straight output it is active/reactive power, objective function is as follows:
6. a kind of multiterminal flexible interconnection distribution network planning system, which is characterized in that the system comprises upper layer planning modules, middle layer Planning module, lower layer's planning module and calculating feedback module;Power grid operator, flexibility are negative in a distributed manner for the upper layer planning module Lotus user and the respective year comprehensive income of energy storage user are up to target, the distribution using simulated annealing to pre-establishing The addressing constant volume model of formula power supply, flexible load and energy-storage system is solved;The middle layer planning module is with grid company year The minimum target of overall cost, using simulated annealing, to the multiterminal pre-established, soft straight constant volume model is asked back-to-back Solution;Lower layer's planning module runs the optimization pre-established with the minimum target of system annual operating and maintenance cost, using interior point method Model is solved;The feedback module that calculates is by the operation result feedback of lower layer's planning module to upper layer planning module and middle layer In planning module, and the operation result of upper layer planning module is transmitted in the planning module of middle layer, when reaching maximum number of iterations, Terminate to calculate;When not up to maximum number of iterations, return upper layer planning module recalculate.
CN201811363158.XA 2018-11-15 2018-11-15 A kind of multiterminal flexible interconnection distribution network planning method and system Pending CN109740786A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811363158.XA CN109740786A (en) 2018-11-15 2018-11-15 A kind of multiterminal flexible interconnection distribution network planning method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811363158.XA CN109740786A (en) 2018-11-15 2018-11-15 A kind of multiterminal flexible interconnection distribution network planning method and system

Publications (1)

Publication Number Publication Date
CN109740786A true CN109740786A (en) 2019-05-10

Family

ID=66355628

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811363158.XA Pending CN109740786A (en) 2018-11-15 2018-11-15 A kind of multiterminal flexible interconnection distribution network planning method and system

Country Status (1)

Country Link
CN (1) CN109740786A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110556847A (en) * 2019-09-19 2019-12-10 山东大学 Energy storage system planning operation joint optimization method and system in photovoltaic-containing power distribution network
CN110569555A (en) * 2019-08-14 2019-12-13 上海电力设计院有限公司 Computer-aided planning method based on three-layer planning model of power distribution network transition scheme
CN110912168A (en) * 2019-11-29 2020-03-24 国网江苏省电力有限公司常州供电分公司 Optimization planning method for energy storage in back-to-back flexible interconnected power distribution network
CN111612248A (en) * 2020-05-20 2020-09-01 云南电网有限责任公司电力科学研究院 Power distribution network side source-load coordination method and system
CN111626633A (en) * 2020-06-04 2020-09-04 南京工程学院 Self-energy-storage flexible interconnected power distribution network expansion planning method based on comprehensive evaluation indexes
CN112149875A (en) * 2020-08-27 2020-12-29 国网能源研究院有限公司 Optimal configuration method and device for distributed energy storage system of active power distribution network
CN112713618A (en) * 2020-12-29 2021-04-27 天津大学合肥创新发展研究院 Active power distribution network source network load storage cooperative optimization operation method based on multi-scene technology
CN112886624A (en) * 2021-02-05 2021-06-01 国网新疆电力有限公司经济技术研究院 Planning and designing system and method for energy storage device of three-station-in-one transformer substation
CN113393172A (en) * 2021-07-15 2021-09-14 华北电力大学 Source network storage planning method considering power distribution network multi-device time sequence operation
CN113964828A (en) * 2021-10-28 2022-01-21 国网宁夏电力有限公司经济技术研究院 Power distribution network collaborative planning method based on interval probability statistical model
CN114301089A (en) * 2021-12-17 2022-04-08 国核电力规划设计研究院有限公司 Energy storage capacity configuration optimization method for wind-solar combined power generation system
CN114358447A (en) * 2022-03-21 2022-04-15 中国长江三峡集团有限公司 Flexible interconnection device configuration method and device, electronic equipment and storage medium
CN117039884A (en) * 2023-08-22 2023-11-10 四川大学 Flexible interconnection planning method of low-voltage distribution network suitable for improving power supply capacity of multiple scenes

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110569555A (en) * 2019-08-14 2019-12-13 上海电力设计院有限公司 Computer-aided planning method based on three-layer planning model of power distribution network transition scheme
CN110569555B (en) * 2019-08-14 2023-04-18 上海电力设计院有限公司 Computer-aided planning method based on three-layer planning model of power distribution network transition scheme
CN110556847A (en) * 2019-09-19 2019-12-10 山东大学 Energy storage system planning operation joint optimization method and system in photovoltaic-containing power distribution network
CN110912168B (en) * 2019-11-29 2022-12-06 国网江苏省电力有限公司常州供电分公司 Optimization planning method for energy storage in back-to-back flexible interconnected power distribution network
CN110912168A (en) * 2019-11-29 2020-03-24 国网江苏省电力有限公司常州供电分公司 Optimization planning method for energy storage in back-to-back flexible interconnected power distribution network
CN111612248A (en) * 2020-05-20 2020-09-01 云南电网有限责任公司电力科学研究院 Power distribution network side source-load coordination method and system
CN111612248B (en) * 2020-05-20 2023-09-08 云南电网有限责任公司电力科学研究院 Power distribution network side source-load coordination method and system
CN111626633A (en) * 2020-06-04 2020-09-04 南京工程学院 Self-energy-storage flexible interconnected power distribution network expansion planning method based on comprehensive evaluation indexes
CN111626633B (en) * 2020-06-04 2023-10-03 南京工程学院 Self-energy-storage flexible interconnected power distribution network expansion planning method based on comprehensive evaluation index
CN112149875A (en) * 2020-08-27 2020-12-29 国网能源研究院有限公司 Optimal configuration method and device for distributed energy storage system of active power distribution network
CN112713618A (en) * 2020-12-29 2021-04-27 天津大学合肥创新发展研究院 Active power distribution network source network load storage cooperative optimization operation method based on multi-scene technology
CN112713618B (en) * 2020-12-29 2023-04-07 天津大学合肥创新发展研究院 Active power distribution network source network load storage cooperative optimization operation method based on multi-scene technology
CN112886624B (en) * 2021-02-05 2023-05-05 国网新疆电力有限公司经济技术研究院 Three-station-in-one substation energy storage device planning and designing system and method
CN112886624A (en) * 2021-02-05 2021-06-01 国网新疆电力有限公司经济技术研究院 Planning and designing system and method for energy storage device of three-station-in-one transformer substation
CN113393172A (en) * 2021-07-15 2021-09-14 华北电力大学 Source network storage planning method considering power distribution network multi-device time sequence operation
CN113393172B (en) * 2021-07-15 2023-10-10 华北电力大学 Source network storage planning method considering multi-equipment time sequence operation of power distribution network
CN113964828A (en) * 2021-10-28 2022-01-21 国网宁夏电力有限公司经济技术研究院 Power distribution network collaborative planning method based on interval probability statistical model
CN113964828B (en) * 2021-10-28 2024-05-03 国网宁夏电力有限公司经济技术研究院 Power distribution network collaborative planning method based on interval probability statistical model
CN114301089A (en) * 2021-12-17 2022-04-08 国核电力规划设计研究院有限公司 Energy storage capacity configuration optimization method for wind-solar combined power generation system
CN114301089B (en) * 2021-12-17 2023-11-03 国核电力规划设计研究院有限公司 Energy storage capacity configuration optimization method for wind-solar combined power generation system
CN114358447A (en) * 2022-03-21 2022-04-15 中国长江三峡集团有限公司 Flexible interconnection device configuration method and device, electronic equipment and storage medium
CN117039884A (en) * 2023-08-22 2023-11-10 四川大学 Flexible interconnection planning method of low-voltage distribution network suitable for improving power supply capacity of multiple scenes

Similar Documents

Publication Publication Date Title
CN109740786A (en) A kind of multiterminal flexible interconnection distribution network planning method and system
CN104734168B (en) Microgrid running optimization system and method based on power and heat combined dispatching
Li et al. Emission-concerned wind-EV coordination on the transmission grid side with network constraints: Concept and case study
CN104135025B (en) Microgrid connection economic optimization method based on fuzzy particle swarm algorithm
CN109149651B (en) Optimal operation method of light storage system considering voltage-regulating auxiliary service income
CN106026152A (en) Charging and discharging scheduling method for electric vehicles connected to micro-grid
CN105262129A (en) Multi-objective optimization system and multi-objective optimization method containing composite energy storage micro grid
CN109066822A (en) A kind of multi-point dispersion formula distribution system dispatching method based on electric power electric transformer
CN107749635A (en) A kind of closed loop network running optimizatin method
CN110350512A (en) A kind of Itellectualized uptown generation of electricity by new energy station method for optimizing scheduling and system
Arab et al. Suitable various-goal energy management system for smart home based on photovoltaic generator and electric vehicles
CN110165666A (en) A kind of active distribution network dispatching method based on IGDT
CN109599864A (en) Active power distribution network the safe and economic operation method
CN109494813A (en) A kind of power dispatching method, electronic equipment and storage medium
Zhang et al. Bi-layer economic scheduling for integrated energy system based on source-load coordinated carbon reduction
Yang et al. Enhancing utilization of PV energy in building microgrids via autonomous demand response
CN105226649B (en) One kind predicting improved provincial power network power generation dispatching optimization method based on bus load
CN112734116A (en) Optimal scheduling method for active power distribution network containing distributed energy storage
CN107171333B (en) The real-time control method of virtual battery model based on intelligent load
CN106253356B (en) Alternating current-direct current mixing microgrid Real-time Economic Dispatch method based on energy storage electricity value assessment
YUEQI et al. Coordinated dispatch between active distribution network and main network
Liu et al. Hierarchical optimal dispatching strategy for microgrid system considering user-side resources
Ni et al. Featured town energy internet design based on the flexible demand response resources
Guo et al. Optimal configuration of multi-energy storage for load aggregators considering user behavior
CN110198053A (en) It is a kind of to concentrate with the micro-capacitance sensor real-time voltage control method and system combined on the spot

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190510

RJ01 Rejection of invention patent application after publication