CN109736825A - 超硬质岩隧道水钻配合液压劈裂开挖施工方法 - Google Patents

超硬质岩隧道水钻配合液压劈裂开挖施工方法 Download PDF

Info

Publication number
CN109736825A
CN109736825A CN201811579183.1A CN201811579183A CN109736825A CN 109736825 A CN109736825 A CN 109736825A CN 201811579183 A CN201811579183 A CN 201811579183A CN 109736825 A CN109736825 A CN 109736825A
Authority
CN
China
Prior art keywords
rock
excavation
construction
splitting
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811579183.1A
Other languages
English (en)
Inventor
孙中华
李鹏翱
李彩红
李傲龙
孙伯乐
郝鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Six Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Six Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co Ltd, Six Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd filed Critical China Railway No 3 Engineering Group Co Ltd
Priority to CN201811579183.1A priority Critical patent/CN109736825A/zh
Publication of CN109736825A publication Critical patent/CN109736825A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

本发明型属于跨线大型桥梁施工技术领域,为了解决现有设置边跨现浇和合拢段对营业线干扰大、施工风险高等问题,提出了一种超浅埋穿越敏感建筑物地区硬质岩隧道开挖施工方法。跨线桥梁采用平行线路方向悬臂法或支架现浇法浇筑梁体,转动到位的施工方法,该发明型取消常规转体设置边跨现浇段和合拢段,避免了线路上方或邻近既有线施工风险大的问题,梁体转动前现实整梁体带支座浇筑,边墩设置高低台时,高承台等转体到位后进行浇筑施工,低承台在转体施工前浇筑完成,但支座垫石需转动到位后再进行浇筑施工,该施工方法克服了既有线上方或邻近既有线施工等问题,保证了营业线路的运行安全,降低了施工风险,保证了施工安全,提高施工效率。

Description

超硬质岩隧道水钻配合液压劈裂开挖施工方法
技术领域
本发明型属于隧道施工的技术领域,具体涉及一种超浅埋穿越敏感建筑物地区硬质岩隧道开挖施工方法。
背景技术
随着城市轨道交通的迅速发展,岩石隧道施工日益增加,复杂的施工工况不断涌现,对施工技术提出更高要求,目前针对超浅埋及穿越敏感建筑物、临近重要建筑物地区的隧道施工,对扰动及震动要求高,不允许爆破施工,对于超硬质岩隧道开挖仍未有较好的施工方法,因此提出一种超硬质岩隧道水钻配合液压劈裂开挖施工方法,降低了对周围围岩的扰动,提高了隧道掘进速度,提高了施工工效,降低施工风险。
发明内容
本发明型为了解决超硬质岩、超浅埋、穿越敏感建筑物隧道开挖工效低下,施工成本高,对周围建筑物及构造物影响大等难题,故提出了一种超硬质岩隧道水钻配合液压劈裂开挖施工方法。
本发明采用如下技术方案:
一种超硬质岩隧道水钻配合液压劈裂开挖施工方法,其特征在于,是采用周边利用水磨钻钻孔取芯+中心打孔液压劈裂开挖上断面,岩石切割锯分段拉槽开挖下段面的方法进行隧道开挖,具体施工过程如下:
先采用水磨钻沿开挖轮廓线以相临圆方式按水平方向施钻取芯,在周边形成连续槽道,为上断面岩体开挖提供临空面;
在上断面岩体开挖区域内使用风钻在水平方向钻劈裂孔,再利用周边槽道开挖形成的临空面,用液压劈裂机自周边向内逐层进行劈裂岩体;
上断面开挖完成后,利用岩石切割机拉槽、切割,开挖下断面岩体。
利用岩石切割机开挖下断面岩体时,先沿隧道侧墙开挖线切割岩石,使中部岩体与基岩分离,然后在平行于线路方向,按等间距依次进行切割,将中部开挖岩体平均切分成若干等份,切割完成后对中部岩体进行钻孔劈裂处理。
中部岩体按每隔50cm进行一次切割,每次切割深度50cm。
水磨钻施钻取芯时,每个周向循环的取芯孔数为45-60个,相邻取芯点搭接设置。
在上断面岩体开挖区域内钻劈裂孔时,相邻孔间距40cm,孔径4.2cm,钻孔数45~50个。
一种超硬质岩隧道开挖用水磨钻取芯作业装置,包括脚手架、电机、钻头和滑轮行走机构,滑轮行走机构包括滑轮、调节滑链、转轴和行走杆,转轴由脚手架支撑沿隧道纵向设置于隧道开挖轮廓线中心,行走杆和转轴平行设置并通过支撑杆连接固定,钻头安装于行走杆上并和电机相连,钻头由电机驱动沿行走杆垂直推进钻孔取芯;调节滑链的两端分别与滑轮和行走杆相连,滑轮固定于脚手架上,行走杆以及安装于行走杆上的钻头、电机在调节滑链作用下整体绕转轴旋转定位旋转钻孔取芯点。
本发明是利用水钻配合液压劈裂开挖的施工方法,来降低了对周围围岩的扰动,提高了隧道掘进速度,提高了施工工效,降低施工风险。且水钻取芯施工时采用了特定的水磨钻取芯作业装置,通过该装置可快速准确的选取钻孔取芯位置,且该装置的行走杆具有导向作用,钻孔质量更精确。
附图说明
图1为孔位布置图;
图2为水磨钻取芯作业示意图;
图3为水磨钻支撑结构立面图;
图中:1-水磨钻孔位(取芯点)、2-劈裂临空孔孔位、3-滑轮、4-脚手架、5-开挖轮廓线、6-水磨钻支撑架、7-调节滑链、8-电机、9-钻头、10-进水孔、11-支撑杆、12-转轴、13-行走杆。
具体实施方式
本发明的施工原理是:水钻+液压劈裂开挖上断面,岩石切割锯开挖下断面开挖方案是采用“周边钻孔取芯+中心打孔液压劈裂开挖上断面,岩石切割锯分段拉槽开挖下段面”的方法进行隧道开挖。采用水磨钻沿开挖轮廓线以相临圆方式按水平方向施钻取芯,在周边形成连续槽道,为上断面岩体开挖提供临空面。在上断面岩体开挖区域内使用风钻按一定间距在水平方向钻劈裂孔,利用周边槽道开挖形成的临空面,用液压劈裂机自周边向内进行劈裂岩体。上断面开挖完成后,利用岩石切割机拉槽、切割,开挖下断面岩体。先沿隧道侧墙开挖线切割岩石,使中部岩体与基岩分离,然后在平行于线路方向,每隔50cm进行一次切割,将中部开挖岩体平均切分成若干等份,每次切割深度50cm,切割完成后对中部岩体进行钻孔劈裂处理。
开挖施工流程如下:
测量放样→超前支护→搭设施工平台→布孔→钻孔→上半断面液压劈裂出渣→岩石切割锯分层切割→液压劈裂出渣→循环至开挖完成→施作初期支护。
具体施工过程如下:
①测量放线
施工前由测量班组对开挖断面轮廓线进行放样,将放样点位标识清晰,并设置放样桩,固定牢固,以便过程中检查。
②超前支护
隧道拱部设置φ42mm,壁厚3.5mm,L=3.0m超前小导管,小导管环向间距0.4m,纵向间距1.5m,外插角5~10度。
小导管在钢筋加工场集中加工制作,准确测量放样出小导管位置,采用TY-28钻机钻孔并清理干净虚碴,插打小导管并注射水泥浆液,稳固前方围岩。
③搭设施工平台
水钻钻孔和劈裂的平台采用脚手架搭设。平台顶部距开挖区高80cm、宽2m(左右侧各1m),以便于人员操作和水磨钻悬吊。平台搭设应牢固,强度和稳定性满足要求,尽量减少作业的晃动,保证施工安全和钻进精度。
④布孔
根据测量放样点位,沿开挖轮廓线布孔,布孔原则是保证结构净空,且能够连续钻孔形成整体临空面。
⑤钻孔
水磨钻钻孔:水磨钻钻杆直径15cm,机带钻头长60cm,有效成孔深度约50cm,为减少钻机接杆时间,钻孔开挖循环进尺按50cm控制。水磨钻钻孔时设置一定外插角,保证钻孔后净空满足要求。
液压劈裂孔:液压劈裂孔采用TY-28风钻钻孔,孔横纵间距40cm,沿隧道中线呈梅花形左右对称布置。
具体水磨钻、液压劈裂孔布置详见图1:
将水磨钻利用倒链悬吊在作业台架上,并安装调节水磨钻位置的支撑架,可以上下左右调整水磨钻位置,检查水磨钻能否顺利到位。水磨钻取芯作业装置见图2、图3,包括脚手架、电机、钻头和滑轮行走机构,滑轮行走机构包括滑轮、调节滑链、转轴和行走杆,转轴由脚手架支撑沿隧道纵向设置于隧道开挖轮廓线中心,行走杆和转轴平行设置并通过支撑杆连接固定,钻头安装于行走杆上并和电机相连,钻头由电机驱动沿行走杆垂直推进钻孔取芯;调节滑链的两端分别与滑轮和行走杆相连,滑轮固定于脚手架上,行走杆以及安装于行走杆上的钻头、电机在调节滑链作用下整体绕转轴(旋转定位旋转钻孔取芯点。该装置的工作原理是将行走杆作为钻头的行进导向杆,保证钻孔精度,同时将导向行走杆、电机、钻头作为整体通过调节滑链和滑轮实现对取芯点的快速选择定位,当取芯数量、孔径及间距均设计确定后,可通过取芯点之间的角度及弦长数据换算为调节滑链的滑动量,进而精确控制取芯位置,且施工更便捷。
开机检查水磨钻运转是否正常,然后人工手持取芯钻在隧道轮廓线上钻孔取芯,采用以相割圆方式按水平方向施钻取芯,在周边形成连续槽道临空面。
为了同时保证取芯效率和较小的超挖量,相邻钻孔中心间距13cm,两孔搭接2cm,每循环取芯孔数在45~60个。2~3台钻机,每台钻机需2~3人操作。取芯时一个孔钻进时间约为5~10分钟。
水磨钻取芯到位时,缓慢拉出水磨钻,轻轻敲击芯体,使其与母岩断开,然后将其取出,水磨钻移至下一个孔位处钻孔。
在开挖区域轮廓线取芯的中间部分用YT-28凿岩钻机钻孔,相邻孔间距40cm,孔径4.2cm,钻孔数45~50个;钻劈裂孔也可在搭设简易台架前进行,为方便施工劈裂孔可一次钻进2~4m,满足4~8个劈裂循环作业(一个开挖循环约1.5米,每劈裂循环约0.5米)。
⑥液压劈裂机分裂核心岩体
取芯孔完成后,然后以周边槽道形成的临空面,用液压劈裂机自周边向内进行分裂开挖岩体,劈裂自上而下分裂岩块,人工撬落。
劈裂采用一台劈裂机,3个操作人员,根据围岩裂隙发育情况,小导洞劈裂每循环约1小时。
⑦人工清除劈裂岩体
为保证台架和液压劈裂机管线和下部工作面安全,劈裂机将岩体分裂后,分裂岩块随时由人工用手推车运至距离掌子面10m以外临时堆放,根据现场条件约3个运作人员,开挖完一个循环后用装载机配合大车出渣至弃渣场。
⑧岩石切割机切割,开挖下断面岩体
由测量人员使用全站仪放出岩石切割机切割的位置线。
搭设好岩石切割机导轨,接上主电源,将岩石切割机锯盘底部对准开挖岩体周边控制线,沿开挖位置线进行切割。先沿侧墙开挖线一端缓慢切入岩体,根据岩体硬度按0.5~1米/分钟切割速度进行水平前进切割,使开挖岩体与周边岩体竖向分离。然后在平行于线路方向,按50cm一道将开挖岩体平均切分成若干等份。每次切割深度50cm,再对中部开挖岩体进行钻孔劈裂处理,每取出深50cm的岩石后,循环使用该方法直至开挖完成。
本发明型实施应用降低了隧道开挖对围岩的扰动,降低对上部建筑物及构造物的影响,提高施工工效,降低施工成本。

Claims (6)

1.一种超硬质岩隧道水钻配合液压劈裂开挖施工方法,其特征在于,是采用周边利用水磨钻钻孔取芯+中心打孔液压劈裂开挖上断面,岩石切割锯分段拉槽开挖下段面的方法进行隧道开挖,具体施工过程如下:
先采用水磨钻沿开挖轮廓线以相临圆方式按水平方向施钻取芯,在周边形成连续槽道,为上断面岩体开挖提供临空面;
在上断面岩体开挖区域内使用风钻在水平方向钻劈裂孔,再利用周边槽道开挖形成的临空面,用液压劈裂机自周边向内逐层进行劈裂岩体;
上断面开挖完成后,利用岩石切割机拉槽、切割,开挖下断面岩体。
2.根据权利要求1所述的超硬质岩隧道水钻配合液压劈裂开挖施工方法,其特征在于,利用岩石切割机开挖下断面岩体时,先沿隧道侧墙开挖线切割岩石,使中部岩体与基岩分离,然后在平行于线路方向,按等间距依次进行切割,将中部开挖岩体平均切分成若干等份,切割完成后对中部岩体进行钻孔劈裂处理。
3.根据权利要求1所述的超硬质岩隧道水钻配合液压劈裂开挖施工方法,其特征在于,中部岩体按每隔50cm进行一次切割,每次切割深度50cm。
4.根据权利要求1所述的超硬质岩隧道水钻配合液压劈裂开挖施工方法,其特征在于,水磨钻施钻取芯时,每个周向循环的取芯孔数为45-60个,相邻取芯点搭接设置。
5.根据权利要求1所述的超硬质岩隧道水钻配合液压劈裂开挖施工方法,其特征在于,在上断面岩体开挖区域内钻劈裂孔时,相邻孔间距40cm,孔径4.2cm,钻孔数45~50个。
6.一种超硬质岩隧道开挖用水磨钻取芯作业装置,其特征在于,包括脚手架(4)、电机(8)、钻头(9)和滑轮行走机构,滑轮行走机构包括滑轮(3)、调节滑链(7)、转轴(12)和行走杆(13),转轴(12)由脚手架(4)支撑沿隧道纵向设置于隧道开挖轮廓线中心,行走杆(13)和转轴(12)平行设置并通过支撑杆(11)连接固定,钻头(9)安装于行走杆(13)上并和电机(8)相连,钻头(9)由电机(8)驱动沿行走杆(13)垂直推进钻孔取芯;调节滑链(7)的两端分别与滑轮(3)和行走杆(13)相连,滑轮(3)固定于脚手架(4)上,行走杆(13)以及安装于行走杆(13)上的钻头(9)、电机(8)在调节滑链(7)作用下整体绕转轴(12)旋转定位旋转钻孔取芯点。
CN201811579183.1A 2018-12-24 2018-12-24 超硬质岩隧道水钻配合液压劈裂开挖施工方法 Pending CN109736825A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811579183.1A CN109736825A (zh) 2018-12-24 2018-12-24 超硬质岩隧道水钻配合液压劈裂开挖施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811579183.1A CN109736825A (zh) 2018-12-24 2018-12-24 超硬质岩隧道水钻配合液压劈裂开挖施工方法

Publications (1)

Publication Number Publication Date
CN109736825A true CN109736825A (zh) 2019-05-10

Family

ID=66361095

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811579183.1A Pending CN109736825A (zh) 2018-12-24 2018-12-24 超硬质岩隧道水钻配合液压劈裂开挖施工方法

Country Status (1)

Country Link
CN (1) CN109736825A (zh)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110219653A (zh) * 2019-07-11 2019-09-10 中铁隧道集团三处有限公司 一种矿山法隧道矩阵状液压劈裂开挖方法
CN110295912A (zh) * 2019-07-18 2019-10-01 中铁隧道集团一处有限公司 敏感地段完整性良好硬岩大断面隧道非爆高效开挖法
CN110410097A (zh) * 2019-06-28 2019-11-05 重庆宏工工程机械股份有限公司 一种工程隧道施工方法
CN110513038A (zh) * 2019-08-27 2019-11-29 中铁六局集团有限公司 临近营业线岩石地质桩基水磨钻施工工法
CN110685596A (zh) * 2019-09-30 2020-01-14 宜昌鄂奥图机械制造有限公司 钻孔劈裂一体机
CN110748355A (zh) * 2019-11-28 2020-02-04 中建四局土木工程有限公司 一种大断面隧道导洞的洞门施工方法
CN110905543A (zh) * 2019-10-22 2020-03-24 中冶交通建设集团有限公司 隧道挖掘方法
CN110924972A (zh) * 2019-12-23 2020-03-27 中国铁建重工集团股份有限公司 一种硬岩隧道施工工法
CN112096410A (zh) * 2020-08-13 2020-12-18 中国地质大学(武汉) 一种取心和静态破裂结合的全断面激光掘进系统及方法
CN112096402A (zh) * 2020-08-13 2020-12-18 中国地质大学(武汉) 周缘熔融气化和静态破裂相结合的全断面激光掘进方法
CN112228070A (zh) * 2020-10-13 2021-01-15 中国电建集团成都勘测设计研究院有限公司 一种圆弧形钻孔劈裂法开挖洞室的方法
CN113356847A (zh) * 2021-07-14 2021-09-07 中铁工程装备集团有限公司 一种涨压破岩设备和隧道涨压破岩施工方法
CN113586076A (zh) * 2021-08-03 2021-11-02 武汉大学 隧洞硬岩非爆破开挖方法
CN114320315A (zh) * 2022-01-11 2022-04-12 湖南省通盛工程有限公司 一种用于隧道掘进施工中的预裂法
CN114790894A (zh) * 2022-04-28 2022-07-26 中交第一公路勘察设计研究院有限公司 一种大断面硬岩竖井钻孔胀裂开挖方法
WO2024077841A1 (zh) * 2022-10-14 2024-04-18 中国矿业大学 沿空留巷低位切顶与高位定向压裂应力转移方法及装备

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392650A (zh) * 2011-11-02 2012-03-28 中铁隧道集团有限公司 一种隧道非爆开挖施工方法
CN204152517U (zh) * 2014-10-13 2015-02-11 福州市规划设计研究院 一种硬岩隧道非爆破开挖掌子面分块结构
CN106869939A (zh) * 2015-12-10 2017-06-20 中铁隧道勘测设计院有限公司 一种高压水劈裂成型与钻爆法联合应用开挖隧道的施工方法
CN107269284A (zh) * 2017-08-18 2017-10-20 徐工集团工程机械有限公司 硬岩隧道开挖施工方法
CN109026019A (zh) * 2018-08-03 2018-12-18 中水电第十工程局(郑州)有限公司 水磨钻非爆破石方洞挖施工的方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392650A (zh) * 2011-11-02 2012-03-28 中铁隧道集团有限公司 一种隧道非爆开挖施工方法
CN204152517U (zh) * 2014-10-13 2015-02-11 福州市规划设计研究院 一种硬岩隧道非爆破开挖掌子面分块结构
CN106869939A (zh) * 2015-12-10 2017-06-20 中铁隧道勘测设计院有限公司 一种高压水劈裂成型与钻爆法联合应用开挖隧道的施工方法
CN107269284A (zh) * 2017-08-18 2017-10-20 徐工集团工程机械有限公司 硬岩隧道开挖施工方法
CN109026019A (zh) * 2018-08-03 2018-12-18 中水电第十工程局(郑州)有限公司 水磨钻非爆破石方洞挖施工的方法

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110410097B (zh) * 2019-06-28 2021-02-26 重庆宏工工程机械股份有限公司 一种工程隧道施工方法
CN110410097A (zh) * 2019-06-28 2019-11-05 重庆宏工工程机械股份有限公司 一种工程隧道施工方法
CN110219653A (zh) * 2019-07-11 2019-09-10 中铁隧道集团三处有限公司 一种矿山法隧道矩阵状液压劈裂开挖方法
CN110295912A (zh) * 2019-07-18 2019-10-01 中铁隧道集团一处有限公司 敏感地段完整性良好硬岩大断面隧道非爆高效开挖法
CN110513038A (zh) * 2019-08-27 2019-11-29 中铁六局集团有限公司 临近营业线岩石地质桩基水磨钻施工工法
CN110685596A (zh) * 2019-09-30 2020-01-14 宜昌鄂奥图机械制造有限公司 钻孔劈裂一体机
CN110685596B (zh) * 2019-09-30 2021-11-26 宜昌鄂奥图机械制造有限公司 钻孔劈裂一体机
CN110905543A (zh) * 2019-10-22 2020-03-24 中冶交通建设集团有限公司 隧道挖掘方法
CN110748355A (zh) * 2019-11-28 2020-02-04 中建四局土木工程有限公司 一种大断面隧道导洞的洞门施工方法
CN110924972A (zh) * 2019-12-23 2020-03-27 中国铁建重工集团股份有限公司 一种硬岩隧道施工工法
CN112096410A (zh) * 2020-08-13 2020-12-18 中国地质大学(武汉) 一种取心和静态破裂结合的全断面激光掘进系统及方法
CN112096402A (zh) * 2020-08-13 2020-12-18 中国地质大学(武汉) 周缘熔融气化和静态破裂相结合的全断面激光掘进方法
CN112228070A (zh) * 2020-10-13 2021-01-15 中国电建集团成都勘测设计研究院有限公司 一种圆弧形钻孔劈裂法开挖洞室的方法
CN113356847A (zh) * 2021-07-14 2021-09-07 中铁工程装备集团有限公司 一种涨压破岩设备和隧道涨压破岩施工方法
CN113586076A (zh) * 2021-08-03 2021-11-02 武汉大学 隧洞硬岩非爆破开挖方法
CN114320315A (zh) * 2022-01-11 2022-04-12 湖南省通盛工程有限公司 一种用于隧道掘进施工中的预裂法
CN114790894A (zh) * 2022-04-28 2022-07-26 中交第一公路勘察设计研究院有限公司 一种大断面硬岩竖井钻孔胀裂开挖方法
WO2024077841A1 (zh) * 2022-10-14 2024-04-18 中国矿业大学 沿空留巷低位切顶与高位定向压裂应力转移方法及装备

Similar Documents

Publication Publication Date Title
CN109736825A (zh) 超硬质岩隧道水钻配合液压劈裂开挖施工方法
CN104265307B (zh) 软硬不均地层土压平衡盾构隧道下穿铁路既有线施工方法
CN102392650B (zh) 一种隧道非爆开挖施工方法
CN109653755B (zh) 一种大直径泥水盾构零沉降穿越无砟轨道路基的施工方法
CN110700841B (zh) 用于隧道开挖的双侧壁导坑式开挖方法
Gong et al. TBM tunneling in marble rock masses with high in situ stress and large groundwater inflow: a case study in China
CN106285715A (zh) 土压平衡盾构机近距离侧穿初支暗挖隧道的施工方法
CN110259467A (zh) 泥水平衡盾构下穿江河施工方法
CN109707388B (zh) 防止盾构机始发即下穿既有盾构隧道时地面塌陷的方法
CN107083932A (zh) 钻孔清洗循环设备及导洞内钢管柱的安装方法
CN108425682A (zh) 一种盾构换刀地连墙加固结构及加固施工方法
CN102562087B (zh) 水钻跟进管棚施工方法
CN110984132B (zh) 复杂地质条件下地下连续墙成槽的施工方法
CN109356193B (zh) 一种预制管廊推送施工装置
CN112610224B (zh) 陡壁隧道掏心洞施工工艺
CN109723450A (zh) 一种复合式tbm隧道掘进施工方法
CN206129278U (zh) 土压平衡盾构机近距离侧穿初支暗挖隧道的施工结构
CN108755660A (zh) 一种紧邻地铁入岩30米地下连续墙施工方法
CN114483054A (zh) 上软下硬地层导洞非爆开挖施工方法
Wang et al. Study on Technology of Surface Pre-grouting for Vertical Shaft in Broken and Water-rich Granite Strata of Gaoligong Mountain Tunnel of Dali-Ruili Railway
Zhu et al. Technologies of Shield Tunneling Along Special Alignment
Tan et al. Deep intervention shaft excavation in Kuala Lumpur limestone formation with pre-tunnelling construction method
CN112253155B (zh) 一种基于cd功法的平衡顶管施工方法
Shi Study on safety analysis of raw water pipe under large section bored tunnel of shallow buried excavation
Sunuwar Challenges of shaft excavation in Nepal Himalaya: case study from hydropower projects

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190510