CN109736584A - Super High concreting mobile protective device and its construction method - Google Patents

Super High concreting mobile protective device and its construction method Download PDF

Info

Publication number
CN109736584A
CN109736584A CN201910089000.6A CN201910089000A CN109736584A CN 109736584 A CN109736584 A CN 109736584A CN 201910089000 A CN201910089000 A CN 201910089000A CN 109736584 A CN109736584 A CN 109736584A
Authority
CN
China
Prior art keywords
protective device
super high
mobile protective
concreting
high concreting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910089000.6A
Other languages
Chinese (zh)
Inventor
龚剑
黄玉林
潘曦
左自波
占羿箭
吴联定
夏巨伟
杜晓燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction Group Co Ltd
Original Assignee
Shanghai Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction Group Co Ltd filed Critical Shanghai Construction Group Co Ltd
Priority to CN201910089000.6A priority Critical patent/CN109736584A/en
Publication of CN109736584A publication Critical patent/CN109736584A/en
Pending legal-status Critical Current

Links

Abstract

In order to solve the spillage generated in Super High outer framework concrete floor slab placement work progress, float slurry and falling object from high altitude the problems such as, enclosing is formed in construction operation area and carries out effective protection, and the invention proposes a kind of Super High concreting mobile protective device and its construction methods.A kind of Super High concreting mobile protective device, including movable stand, fixing piece, shielded frame, protection face board, hound, first axle and second hinge;A kind of Super High concreting mobile protective device of the invention; when use; Super High concreting mobile protective device is arranged in next layer of floor edge of the floor of build floor to be poured; adjust position of the pin shaft of hound in buckle; protection face board is set to stretch out floor edge; and the edge of build floor to be poured is made to fall into the protection scope of protection face board, to form protection enclosing.When treat pour build floor and poured when, just can effectively prevent spillage, float slurry and falling object from high altitude the problems such as.

Description

Super High concreting mobile protective device and its construction method
Technical field
The invention belongs to Construction Technology fields, are related to a kind of protection for super high-rise building concrete pouring construction Device, in particular to a kind of Super High concreting mobile protective device and its construction method.
Background technique
With the development of the city, land resource is increasingly in short supply, and super high-rise building becomes the inevitable choice of inner city construction, The quantity and height of China's super high-rise building are continuously available breakthrough.Super-high building structure form is frequently with frame Core Walls Structure knot Structure, wherein peripheral frame generally uses steel structure frame, the floor and roof system of Core Walls Structure periphery, using the profiled sheet of rolling Add the floor and roof system of cast-in-situ steel reinforced concrete.
When super high-rise building outer framework is constructed, every layer of floor is required to carry out concreting by pump line at the scene, And in the process, floor edge casting position be also easy to produce spillage, slurry problem of floaing, surrounding enviroment are polluted, and there are one Fixed security risk, construction height is higher, this adverse effect is bigger.
Summary of the invention
In order to solve, the spillage generated in above-mentioned Super High outer framework concrete floor slab placement work progress, float slurry and falling object from high altitude The problems such as, enclosing is formed in construction operation area and carries out effective protection, and the invention proposes a kind of Super High concreting shiftings Dynamic formula protective device and its construction method.
The technical solution of Super High concreting mobile protective device of the invention is as follows:
A kind of Super High concreting mobile protective device, including movable stand, fixing piece, shielded frame, protection face Plate, hound, first axle and second hinge;
The fixing piece at least one, movable stand side is vertically arranged at, if the fixing piece is from top to bottom spaced setting Dry buckle;
The first axle at least one, be set to movable stand fixing piece side top;
The side of the shielded frame is connected by the side top movable of first axle and movable stand, and shielded frame is with the One hinge rotates upwardly and downwardly for axle center;
The second hinge at least one, be set to the bottom of shielded frame, and with the position of fixing piece to corresponding;
The hound at least one, one end of hound is flexibly connected by second hinge with the bottom of shielded frame, Pin shaft is arranged in the other end, and the pin shaft is held on the buckle of the corresponding fixing piece of second hinge;
The protection face board is layed in shielded frame top.
A kind of Super High concreting mobile protective device of the invention, in use, by Super High concreting Mobile protective device is arranged in next layer of floor edge of the floor of build floor to be poured, and the pin shaft for adjusting hound is buckling In position, so that protection face board is stretched out floor edge, and the edge of build floor to be poured is made to fall into the protection scope of protection face board, from And form protection enclosing.When treat pour build floor and poured when, just can effectively prevent spillage, float slurry and falling object from high altitude etc. are asked Topic.
Further, in the Super High concreting mobile protective device, when the fixing piece is more than two, The fixing piece is horizontally spaced to be set to movable stand side, and the quantity of the second hinge is identical as fixing piece, described The quantity of hound is identical as fixing piece.More than two fixing pieces, hound, which is arranged, can further strengthen movable stand and protection Bonding strength between frame makes the more stable safety of Super High concreting mobile protective device.
Further, in the Super High concreting mobile protective device, the first axle is two or more When, the first axle is horizontally spaced to be set to movable stand side top.More than two first axles are arranged can be into One step reinforces the bonding strength between movable stand and shielded frame, keeps Super High concreting mobile protective device more steady Dingan County is complete.
Further, in the Super High concreting mobile protective device, the top of the movable stand be arranged to A few telescopic support.Telescopic support can be determined in the operating position of Super High concreting mobile protective device After be raised above, top-out structure is withstood, to play the role of fixed Super High concreting mobile protective device. Super High concreting mobile protective device in this way is not easy to shift in use, improves superelevation layer concrete and pours Build the safety in utilization of mobile protective device.
Further, in the Super High concreting mobile protective device, the telescopic support be two with When upper, telescopic support is spaced apart along the top periphery of the movable stand.Multiple telescopic supports, which are arranged, more effectively to be prevented The only displacement of Super High concreting mobile protective device further improves Super High concreting mobile protective The safety in utilization of device.
Further, in the Super High concreting mobile protective device, the top of the telescopic support 9 is set Set rubber slab.Rubber slab can increase the friction system between Super High concreting mobile protective device and top-out structure Number, more effectively prevents the displacement of Super High concreting mobile protective device, further improves superelevation layer concrete Pour the safety in utilization of mobile protective device.
Further, in the Super High concreting mobile protective device, if the bottom of the movable stand is arranged Dry universal wheel.Universal wheel is installed to adjust convenient for the position of Super High concreting mobile protective device.
Further, in the Super High concreting mobile protective device, the universal wheel is equipped with locking device. Locking device can be after the operating position of Super High concreting mobile protective device determines, fixed superelevation layer concrete Pour mobile protective device.Super High concreting mobile protective device in this way is not easy to shift in use, Improve the safety in utilization of Super High concreting mobile protective device.
Further, in the Super High concreting mobile protective device, the lateral section of the shielded frame is in L Shape.The L-shaped shielded frame in section can more effectively mortar leakage prevention, float slurry and falling object from high altitude etc. ask after being laid with protection face board Topic.
Further, in the Super High concreting mobile protective device, for ease of operation, the movable stand Inside is vertically-spaced to be arranged several walkway boards, and upper helper is arranged between the walkway board.
Further, in the Super High concreting mobile protective device, the protection face board be Dense mesh screen or Expanded metal lath or plank.In work progress, suitable protection face board can be used according to different needs.
Further, described for the ease of transporting, moving in the Super High concreting mobile protective device Shielded frame is scalable shielded frame or foldable shielded frame.
Further, convenient for the ease of transporting, moving in the Super High concreting mobile protective device On-site assembly disassembly, the movable stand be can splicing structure, the shielded frame be can splicing structure.
The present invention also provides a kind of construction methods of above-mentioned Super High concreting mobile protective device.
A kind of technical solution of the construction method of Super High concreting mobile protective device of the invention is as follows, packet Include following steps:
At least two Super High concreting mobile protective devices are arranged in the floor of build floor to be poured by the first step Next layer;
Super High concreting mobile protective device is moved to floor edge by second step;
Third step adjusts position of the pin shaft of hound in buckle, the edge of build floor to be poured is made to fall into protection face board (4) protection scope, and connect the both sides of the protection face board of adjacent Super High concreting mobile protective device closely Touching;
4th step, to be poured in the protection face board protection scope of first Super High concreting mobile protective device Build floor is poured;
5th step, when to be poured in the protection face board protection scope of first Super High concreting mobile protective device After the completion of build floor pours, first Super High concreting mobile protective device is moved to last platform superelevation layer concrete and is poured After building mobile protective device, and the edge of build floor to be poured is made to fall into the protection scope of its protection face board, protection face board On one side the protection face board with last platform Super High concreting mobile protective device while be in close contact;
6th step repeats the 4th step to the 5th step, until build floor to be poured pours completion.
A kind of construction method of Super High concreting mobile protective device of the invention, superelevation layer concrete is poured Next layer of the floor edge that mobile protective device is arranged in the floor of build floor to be poured is built, adjusts the pin shaft of hound in card Position in button makes protection face board stretch out floor edge, and the edge of build floor to be poured is made to fall into the protection scope of protection face board, To form protection enclosing.When treat pour build floor and poured when, just can effectively prevent spillage, float slurry and falling object from high altitude etc. Problem.
Further, in the construction method of the Super High concreting mobile protective device:
It is close on the both sides for the protection face board for making adjacent Super High concreting mobile protective device in third step After contact, locking is set to the universal wheel of the movable stand bottom of each Super High concreting mobile protective device, and will The telescopic support for being set to movable stand top rises, and withstands the bottom of build floor to be poured;
In 4th step, in the protection face board protection scope to first Super High concreting mobile protective device Before build floor to be poured is poured, the universal wheel of first Super High concreting mobile protective device is locked, and will be stretched Supporting element rises, and withstands the bottom of build floor to be poured;
In 5th step, before first Super High concreting mobile protective device of movement, it is mixed to unlock first Super High Solidifying soil pours the universal wheel of mobile protective device, and telescopic support is fallen.
The locking device of telescopic support and universal wheel can be in Super High concreting mobile protective device Play the role of fixed Super High concreting mobile protective device after determining in operating position.Superelevation layer concrete in this way pours It builds mobile protective device to be not easy to shift in use, improves Super High concreting mobile protective device Safety in utilization.After construction comes to an end, and the locking device that telescopic support can be put down, unlock universal wheel, it is convenient for superelevation Layer concrete pours mobile protective device and is moved to next designated position.
Detailed description of the invention
Fig. 1 is the schematic diagram of Super High concreting mobile protective device of the invention;
Fig. 2 is the side view of Super High concreting mobile protective device of the invention;
Fig. 3 is the schematic diagram of the fixing piece of Super High concreting mobile protective device of the invention.
Specific embodiment
The present invention is described in further detail below in conjunction with the drawings and specific embodiments.It is wanted according to following explanation and right Book is sought, advantages and features of the invention will become apparent from.It should be noted that attached drawing is all made of very simplified form and using non- Accurately ratio, only for the purpose of facilitating and clarifying the purpose of the embodiments of the invention.
Embodiment 1:
Referring to figs. 1 to Fig. 3, the technical solution of the Super High concreting mobile protective device of the present embodiment is as follows:
A kind of Super High concreting mobile protective device, including movable stand 1, fixing piece 2, shielded frame 3, protection Panel 4, hound 5, first axle 6 and second hinge 7;
The fixing piece 2 at least one, be vertically arranged at 1 side of movable stand, the fixing piece 2 is from top to bottom spaced setting Several buckle 2a;
The first axle 6 at least one, be set to 1 fixing piece of movable stand, 2 side top;
The side of the shielded frame 3 is connect by first axle 6 with the side top movable of movable stand 1, shielded frame 3 It is rotated upwardly and downwardly with first axle 6 for axle center;
The second hinge 7 at least one, be set to the bottom of shielded frame 3, and with the position of fixing piece 2 to corresponding;
The hound 5 at least one, one end of hound 5 is connected by the bottom activity of second hinge 7 and shielded frame 3 It connects, pin shaft 5a is arranged in the other end, and the pin shaft 5a is held on the buckle 2a of the corresponding fixing piece 2 of second hinge 7;
The protection face board 4 is layed in 3 top of shielded frame.
A kind of Super High concreting mobile protective device of the present embodiment, in use, superelevation layer concrete is poured Next layer of the floor edge that mobile protective device is arranged in the floor of build floor to be poured is built, the pin shaft 5a of hound 5 is adjusted Position in buckle 2a, makes protection face board 4 stretch out floor edge, and the edge of build floor to be poured is made to fall into protection face board 4 Protection scope, to form protection enclosing.When treat pour build floor and poured when, just can effectively prevent spillage, float slurry and The problems such as falling object from high altitude.
As preferable embodiment, in the Super High concreting mobile protective device, the fixing piece 2 is When more than two, the fixing piece 2 is horizontally spaced to be set to 1 side of movable stand, the quantity of the second hinge 7 and solid Determine that part 2 is identical, the quantity of the hound 5 is identical as fixing piece 2.More than two fixing pieces 2, hound 5 is arranged can be into one Step reinforces the bonding strength between movable stand 1 and shielded frame 3, keeps Super High concreting mobile protective device more steady Dingan County is complete.
As preferable embodiment, in the Super High concreting mobile protective device, the first axle 6 When for two or more, the first axle 6 is horizontally spaced to be set to 1 side top of movable stand.It is arranged more than two First axle 6 can further strengthen the bonding strength between movable stand 1 and shielded frame 3, keep Super High concreting mobile The more stable safety of formula protective device.
As preferable embodiment, in the Super High concreting mobile protective device, the movable stand 1 At least one telescopic support 9 is arranged in top.Telescopic support 9 can be in Super High concreting mobile protective device Operating position is raised above after determining, withstands top-out structure, so that it is anti-to play fixed Super High concreting movable type The effect of protection unit.Super High concreting mobile protective device in this way is not easy to shift in use, improves The safety in utilization of Super High concreting mobile protective device.
As preferable embodiment, in the Super High concreting mobile protective device, the retractable support When part 9 is more than two, telescopic support 9 is spaced apart along the top periphery of the movable stand 1.Multiple telescopic supports are set 9 can more effectively prevent the displacement of Super High concreting mobile protective device, further improve superelevation layer concrete Pour the safety in utilization of mobile protective device.
As preferable embodiment, in the Super High concreting mobile protective device, the retractable support Rubber slab is arranged in the top of part 9.Rubber slab can increase Super High concreting mobile protective device and top-out structure Between coefficient of friction, more effectively prevent the displacement of Super High concreting mobile protective device, further improve The safety in utilization of Super High concreting mobile protective device.
As preferable embodiment, in the Super High concreting mobile protective device, the movable stand 1 Several universal wheels 8 are arranged in bottom.Universal wheel 8 is installed to adjust convenient for the position of Super High concreting mobile protective device.
As preferable embodiment, in the Super High concreting mobile protective device, the universal wheel 8 is set There is locking device.Locking device can be fixed after the operating position of Super High concreting mobile protective device determines Super High concreting mobile protective device.Super High concreting mobile protective device is in use in this way It is not easy to shift, improves the safety in utilization of Super High concreting mobile protective device.
As preferable embodiment, in the Super High concreting mobile protective device, the shielded frame 3 Lateral section it is L-shaped.The L-shaped shielded frame 3 in section after being laid with protection face board 4 can more effectively mortar leakage prevention, float slurry with And the problems such as falling object from high altitude.
As preferable embodiment, in the Super High concreting mobile protective device, for ease of operation, 1 inside of movable stand is vertically-spaced to be arranged several walkway boards 10, and upper helper 11 is arranged between the walkway board 10.
As preferable embodiment, in the Super High concreting mobile protective device, the protection face board 4 For Dense mesh screen or expanded metal lath or plank.In work progress, suitable protection face board 4 can be used according to different needs.
As preferable embodiment, in the Super High concreting mobile protective device, for the ease of transporting, Mobile, the shielded frame 3 is scalable shielded frame or foldable shielded frame.
As preferable embodiment, in the Super High concreting mobile protective device, for the ease of transporting, It is mobile, facilitate on-site assembly to dismantle, the movable stand 1 be can splicing structure, the shielded frame 3 is can splicing structure.
Embodiment 2:
Referring to figs. 1 to Fig. 3, the present embodiment provides a kind of Super High concreting mobile protectives described in embodiment 1 The construction method of device.
A kind of technical solution of the construction method of Super High concreting mobile protective device of the present embodiment is as follows, Include the following steps:
At least two Super High concreting mobile protective devices are arranged in the floor of build floor to be poured by the first step Next layer;
Super High concreting mobile protective device is moved to floor edge by second step;
Third step adjusts position of the pin shaft 5a of hound 5 in buckle 2a, the edge of build floor to be poured is made to fall into protection The protection scope of panel 4, and keep the both sides of the protection face board 4 of adjacent Super High concreting mobile protective device close Contact;
4th step, in 4 protection scope of protection face board of first Super High concreting mobile protective device to Build floor is poured to be poured;
5th step, when in 4 protection scope of protection face board of first Super High concreting mobile protective device to After the completion of pouring concrete floor slab placement, first Super High concreting mobile protective device is moved to last platform superelevation layer concrete After pouring mobile protective device, and the edge of build floor to be poured is made to fall into the protection scope of its protection face board 4, protection face Plate 4 on one side the protection face board 4 with last platform Super High concreting mobile protective device while be in close contact;
6th step repeats the 4th step to the 5th step, until build floor to be poured pours completion.
The construction method of a kind of Super High concreting mobile protective device of the present embodiment, by superelevation layer concrete Next layer of the floor edge that mobile protective device is arranged in the floor of build floor to be poured is poured, the pin shaft of hound 5 is adjusted Position of the 5a in buckle 2a, makes protection face board 4 stretch out floor edge, and the edge of build floor to be poured is made to fall into protection face board 4 Protection scope, to form protection enclosing.When treat pour build floor and poured when, just can effectively prevent spillage, float slurry with And the problems such as falling object from high altitude.
As preferable embodiment, in the construction method of the Super High concreting mobile protective device:
It is tight on the both sides for the protection face board 4 for making adjacent Super High concreting mobile protective device in third step After touch, locking is set to the universal wheel 8 of 1 bottom of movable stand of each Super High concreting mobile protective device to contiguity, And rise the telescopic support 9 for being set to 1 top of movable stand, withstand the bottom of build floor to be poured;
In 4th step, in 4 protection scope of protection face board to first Super High concreting mobile protective device Build floor to be poured poured before, lock the universal wheel 8 of first Super High concreting mobile protective device, and will stretch Contracting supporting element 9 rises, and withstands the bottom of build floor to be poured;
In 5th step, before first Super High concreting mobile protective device of movement, it is mixed to unlock first Super High Solidifying soil pours the universal wheel 8 of mobile protective device, and telescopic support 9 is fallen.
The locking device of telescopic support 9 and universal wheel 8 can be in Super High concreting mobile protective device Operating position determine after play the role of fixed Super High concreting mobile protective device.Superelevation layer concrete in this way It pours mobile protective device to be not easy to shift in use, improves Super High concreting mobile protective device Safety in utilization.After construction comes to an end, and the locking device that telescopic support 9 can be put down, unlock universal wheel 8, it is convenient for Super High concreting mobile protective device is moved to next designated position.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Range.

Claims (15)

1. a kind of Super High concreting mobile protective device, which is characterized in that including movable stand (1), fixing piece (2), Shielded frame (3), protection face board (4), hound (5), first axle (6) and second hinge (7);
The fixing piece (2) at least one, be vertically arranged at movable stand (1) side, the fixing piece (2) is from top to bottom spaced and sets Set several buckles (2a);
The first axle (6) at least one, be set to movable stand (1) fixing piece (2) side top;
The side of the shielded frame (3) is connect by first axle (6) with the side top movable of movable stand (1), protective frame Frame (3) is rotated upwardly and downwardly with first axle (6) for axle center;
The second hinge (7) at least one, be set to the bottom of shielded frame (3), and with the position of fixing piece (2) to right It answers;
The hound (5) at least one, one end of hound (5) is living by the bottom of second hinge (7) and shielded frame (3) Pin shaft (5a) is arranged in dynamic connection, the other end, and the pin shaft (5a) is held on the buckle of the corresponding fixing piece (2) of second hinge (7) On (2a);
The protection face board (4) is layed in shielded frame (3) top.
2. Super High concreting mobile protective device as described in claim 1, which is characterized in that the fixing piece (2) when being more than two, the fixing piece (2) is horizontally spaced to be set to movable stand (1) side, the second hinge (7) quantity is identical as fixing piece (2), and the quantity of the hound (5) is identical as fixing piece (2).
3. Super High concreting mobile protective device as described in claim 1, which is characterized in that the first axle (6) when being more than two, the first axle (6) is horizontally spaced to be set to movable stand (1) side top.
4. Super High concreting mobile protective device as described in claim 1, which is characterized in that the movable stand (1) at least one telescopic support (9) is arranged in top.
5. Super High concreting mobile protective device as claimed in claim 4, which is characterized in that the retractable support When part (9) is more than two, telescopic support (9) is spaced apart along the top periphery of the movable stand (1).
6. Super High concreting mobile protective device as claimed in claim 4, which is characterized in that the retractable support Rubber slab is arranged in the top of part (9).
7. Super High concreting mobile protective device as described in claim 1, which is characterized in that the movable stand (1) several universal wheels (8) are arranged in bottom.
8. Super High concreting mobile protective device as claimed in claim 7, which is characterized in that the universal wheel (8) it is equipped with locking device.
9. Super High concreting mobile protective device as described in claim 1, which is characterized in that the shielded frame (3) lateral section is L-shaped.
10. Super High concreting mobile protective device as described in claim 1, which is characterized in that the movable stand (1) inside is vertically-spaced is arranged several walkway boards (10), and upper helper (11) are arranged between the walkway board (10).
11. Super High concreting mobile protective device as described in claim 1, which is characterized in that the protection face Plate (4) is Dense mesh screen or expanded metal lath or plank.
12. Super High concreting mobile protective device as described in claim 1, which is characterized in that the protective frame Frame (3) is scalable shielded frame or foldable shielded frame.
13. Super High concreting mobile protective device as described in claim 1, which is characterized in that the movable stand (1) for can splicing structure, the shielded frame (3) be can splicing structure.
14. the construction method of any one Super High concreting mobile protective device in a kind of such as claim 1 to 13, It is characterized by comprising the following steps:
At least two Super High concreting mobile protective devices are arranged under the floor of build floor to be poured by the first step One layer;
Super High concreting mobile protective device is moved to floor edge by second step;
Third step adjusts position of the pin shaft (5a) of hound (5) in buckle (2a), falls into the edge of build floor to be poured anti- The protection scope of protection slab (4), and make adjacent Super High concreting mobile protective device protection face board (4) two Side is in close contact;
4th step, to be poured in protection face board (4) protection scope of first Super High concreting mobile protective device Build floor is poured;
5th step, when to be poured in protection face board (4) protection scope of first Super High concreting mobile protective device After the completion of build floor pours, first Super High concreting mobile protective device is moved to last platform superelevation layer concrete and is poured After building mobile protective device, and the edge of build floor to be poured is made to fall into the protection scope of its protection face board (4), protection face Plate (4) on one side the protection face board (4) with last platform Super High concreting mobile protective device while be in close contact;
6th step repeats the 4th step to the 5th step, until build floor to be poured pours completion.
15. the construction method of Super High concreting mobile protective device as claimed in claim 14, it is characterised in that:
It is close on the both sides for the protection face board (4) for making adjacent Super High concreting mobile protective device in third step After contact, locking is set to the universal wheel of movable stand (1) bottom of each Super High concreting mobile protective device (8), and will be set to movable stand (1) top telescopic support (9) rise, withstand the bottom of build floor to be poured;
In 4th step, in protection face board (4) protection scope to first Super High concreting mobile protective device Before build floor to be poured is poured, the universal wheel (8) of first Super High concreting mobile protective device is locked, and will be stretched Contracting supporting element (9) rises, and withstands the bottom of build floor to be poured;
In 5th step, before first Super High concreting mobile protective device of movement, first superelevation layer concrete is unlocked The universal wheel (8) of mobile protective device is poured, and telescopic support (9) is fallen.
CN201910089000.6A 2019-01-30 2019-01-30 Super High concreting mobile protective device and its construction method Pending CN109736584A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910089000.6A CN109736584A (en) 2019-01-30 2019-01-30 Super High concreting mobile protective device and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910089000.6A CN109736584A (en) 2019-01-30 2019-01-30 Super High concreting mobile protective device and its construction method

Publications (1)

Publication Number Publication Date
CN109736584A true CN109736584A (en) 2019-05-10

Family

ID=66366705

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910089000.6A Pending CN109736584A (en) 2019-01-30 2019-01-30 Super High concreting mobile protective device and its construction method

Country Status (1)

Country Link
CN (1) CN109736584A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042140A (en) * 2020-02-11 2020-04-21 丁凤景 Passive protective device for slip form construction of hydraulic engineering and implementation method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201649678U (en) * 2010-03-24 2010-11-24 陕西建工集团总公司 Semi-automatic safety protective shed for high-rise building construction
CN205276913U (en) * 2016-01-07 2016-06-01 严星 Building construction safety protector
WO2016105319A1 (en) * 2014-12-26 2016-06-30 Cecen Haluk A protective shield against falling from constructions
CN107217862A (en) * 2017-06-19 2017-09-29 中国五冶集团有限公司 A kind of outer protection network supporting construction and outer protection net construction method
CN206801077U (en) * 2017-06-19 2017-12-26 中国五冶集团有限公司 A kind of external wall construction ballistic support structure
CN207406029U (en) * 2017-10-23 2018-05-25 穆壮尉 A kind of construction protective device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201649678U (en) * 2010-03-24 2010-11-24 陕西建工集团总公司 Semi-automatic safety protective shed for high-rise building construction
WO2016105319A1 (en) * 2014-12-26 2016-06-30 Cecen Haluk A protective shield against falling from constructions
CN205276913U (en) * 2016-01-07 2016-06-01 严星 Building construction safety protector
CN107217862A (en) * 2017-06-19 2017-09-29 中国五冶集团有限公司 A kind of outer protection network supporting construction and outer protection net construction method
CN206801077U (en) * 2017-06-19 2017-12-26 中国五冶集团有限公司 A kind of external wall construction ballistic support structure
CN207406029U (en) * 2017-10-23 2018-05-25 穆壮尉 A kind of construction protective device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
原建筑工程部华北工业设备安装公司: "油罐生漆防腐施工", 《建筑技术》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042140A (en) * 2020-02-11 2020-04-21 丁凤景 Passive protective device for slip form construction of hydraulic engineering and implementation method thereof

Similar Documents

Publication Publication Date Title
CN106907001A (en) Combined type heavy-duty self-crawling type tubular construction operation platform and construction method
CN209179535U (en) Basement reinforces support construction
CN207160062U (en) A kind of underground is without post overlapping wall station
CN105887685A (en) Railway high pier body template and scaffold integrated turnover formwork segmental construction method
CN105544587B (en) The construction method of tower crane is fixed using combined type foundation for tower crane
WO2015184476A1 (en) Precast concrete falsework bubbledeck element and process of manufacturing thereof
CN110273539A (en) A kind of combination set shaped steel formwork and its modeling method
CN205576955U (en) Raft foundation's reinforced structure is displaced into to strip footing
CN109736584A (en) Super High concreting mobile protective device and its construction method
CN110512719A (en) A kind of high residential building large span compartment vestibule high-altitude formwork steel platform construction
CN100362200C (en) Supporting displacement method for lifting component and supporting system thereof
CN107988918A (en) Concrete rolls up mould constructing device
CN109025275A (en) A kind of shear wall side regularization stair punching block and installation method
CN105113541B (en) Self-bearing type is without reversed construction method of the row without mould basement girderless floor
CN209603163U (en) A kind of tower crane bearing platform ruggedized construction
US3148434A (en) Means and method for constructing buildings
CN206376275U (en) A kind of construction elevator base apparatus on basement roof
CN206267519U (en) A kind of light engine position hydraulic climbing die block system
CN206887680U (en) A kind of removable type cover plate for foundation pit construction
CN206815379U (en) One kind assembling superposed type pipe gallery
CN208870416U (en) One kind exempting from the fixed device of pre-buried overhanging unloading platform
CN212356135U (en) Elevator platform
CN207469300U (en) A kind of double skin wall constructions of underground garage
CN109403674B (en) Assembled prefabrication factory for bridge construction and construction method thereof
CN106522542A (en) Single-station hydraulic formwork climbing system and climbing method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190510