CN109736274A - A kind of semi-underground well shaft type workshop of hydroelectric project - Google Patents

A kind of semi-underground well shaft type workshop of hydroelectric project Download PDF

Info

Publication number
CN109736274A
CN109736274A CN201910172338.8A CN201910172338A CN109736274A CN 109736274 A CN109736274 A CN 109736274A CN 201910172338 A CN201910172338 A CN 201910172338A CN 109736274 A CN109736274 A CN 109736274A
Authority
CN
China
Prior art keywords
room
auxiliary power
main building
semi
power house
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910172338.8A
Other languages
Chinese (zh)
Inventor
阮应宾
胡耀光
赵杰
孔伟
邵艳青
李海涛
郤婉洁
何猛
杨华广
李加瀚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 14 Co Ltd
Original Assignee
Sinohydro Bureau 14 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN201910172338.8A priority Critical patent/CN109736274A/en
Publication of CN109736274A publication Critical patent/CN109736274A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Abstract

The invention discloses a kind of semi-underground well shaft type workshop of hydroelectric project, the semi-underground well shaft type workshop of hydroelectric project includes main building, clipping room, water dispenser auxiliary power house, electrical auxiliary power house;Main building arrangement is in below ground, and corresponding with water (flow) direction, outer wall is pit shaft, is disposed between ball valve layer, turbine floor, cable interlayer, generator floor, host from the bottom to top in pit shaft;The right side that clipping room is arranged in below ground, flows to main building downstream is connected to by marching into the arena tunnel with outside;Water dispenser auxiliary power house is arranged in ground or more, water (flow) direction upstream side, including turbine grease chamber, oil purification room, air compressor chamber, fan house;Electrical auxiliary power house is arranged in more than ground, water (flow) direction downstream side, including Central Control Room, high-voltage switch gear room, station-service transformer room, switchgear house.The present invention enriches the selection of workshop arrangement form, can promote the raising of semi-underground powerhouse design level, also provides good reference function for the design of some reference.

Description

A kind of semi-underground well shaft type workshop of hydroelectric project
Technical field
The present invention is suitable for the arrangement of hydroelectric project workshop, and in particular to a kind of semi-underground well shaft type workshop.
Background technique
Powerhouse of hydropower station is the building that the hydraulic turbine, hydrogenerator and various ancillary equipments are installed in power station.Generally Be made of main building and auxiliary power house two parts, be the synthesis of hydraulic structure, mechanically and electrically equipment, but be operations staff into Row produces movable place.
According to the relative position and its structure feature of workshop and water retaining structure, three basic forms of it can be divided into: water channeling type Workshop, power house at dam toe, power house in river channel.According to workshop and ground relation of plane, and ground power house, underground power house can be divided into, this The arrangement form of two kinds of workshops, it is more mature at home and abroad, and semi-underground well shaft type workshop is then at the early-stage.
Relatively traditional ground power house, semi-underground well shaft type workshop are effectively reduced the length of pressure pipeline, save Investment.For opposite underground power house, reduces access tunnel, outlet hole, shorten tailrace tunnel, saved investment.Building ground Workshop and underground power house are again uneconomical, and in the case where making full use of water resource (head) again, semi-underground well shaft type workshop shows Its hugely advantage.
Summary of the invention
It is the problem of for background technique, rich the invention proposes a kind of semi-underground well shaft type workshop of hydroelectric project The rich selection of workshop arrangement form, can promote the raising of semi-underground powerhouse design level, also setting for some reference Meter provides good reference function.
To achieve the above object, the present invention adopts the following technical scheme: the semi-underground well shaft type workshop packet of the hydroelectric project Include main building, clipping room, water dispenser auxiliary power house, electrical auxiliary power house;
Main building arrangement is in below ground, and corresponding with water (flow) direction, outer wall is pit shaft, is disposed with ball valve from the bottom to top in pit shaft Between layer, turbine floor, cable interlayer, generator floor, host;
The right side that clipping room is arranged in below ground, flows to main building downstream is connected to by marching into the arena tunnel with outside;
Water dispenser auxiliary power house is arranged in ground or more, water (flow) direction upstream side, including turbine grease chamber, oil purification room, air compressor chamber, wind Machine room;
Electrical auxiliary power house is arranged in ground or more, water (flow) direction downstream side, including Central Control Room, high-voltage switch gear room, station-service transformer room, Switchgear house.
Preferably, main building upstream position arranges that air shaft, downstream position arrange elevator, air shaft and elevator bottom End is connected to ball valve layer, and air shaft top is connected to the fan house of water dispenser auxiliary power house.
Preferably, passing through upstream side stair and downstream side to generator floor, generator floor to turbine floor between host Stair connection, turbine floor to ball valve layer are connected to by right side stair with left side stair.
Preferably, the part that water dispenser auxiliary power house and electrical auxiliary power house are arranged in ground or more is all made of steel frame construction and takes It builds, is provided with steel roof on the upside of main building and clipping room.
Preferably, being provided with bridge crane at the top of main building, hanging object hole is equipped at the top of main building.
Beneficial effects of the present invention:
The present invention enriches the selection of workshop arrangement form, can promote the raising of semi-underground powerhouse design level, also for from now on The design of similar engineering provides good reference function.
Detailed description of the invention
Fig. 1 is major-minor workshop of the present invention (768.000 elevation) floor plan;
Fig. 2 is the A-A sectional view in Fig. 1;
Fig. 3 is the B-B sectional view in Fig. 1;
Fig. 4 is that major-minor workshop of the present invention installs interbed (757.700m elevation) layout drawing;
Fig. 5 (729.500m ~ 757.700m) layout drawing between host of the present invention;
Fig. 6 is generator floor of the present invention (729.500m elevation) layout drawing;
Fig. 7 is turbine floor of the present invention (721.450m is high-rise) layout drawing;
Fig. 8 is ball valve layer of the present invention (716.450 elevation) layout drawing;
In figure: 1-main building pit shaft, 2-clipping rooms, 3-hanging object holes, 4-air shafts, 5-elevators, 6-upstream side stair, 7-downstream side stair, 8-right side stair, 9-left side stair, 10-stair, 11-march into the arena tunnel, 12-clipping room frame columns, 13-main building frame columns, 14-ceilings, 15-water dispenser auxiliary power houses, 16-electrical auxiliary power houses.
Specific embodiment
In order to keep the purpose of the present invention, technical scheme and beneficial effects clearer, below in conjunction with attached drawing, to the present invention Preferred embodiment be described in detail, to facilitate the technical staff to understand.
As shown in figures 1-8, the semi-underground well shaft type workshop of the hydroelectric project includes main building, clipping room 2, water dispenser auxiliary power house 15, electrical auxiliary power house 16;Main building arrangement is in below ground, and corresponding with water (flow) direction, outer wall is pit shaft 1, and pit shaft 1 is interior under It is supreme to be disposed between ball valve layer, turbine floor, cable interlayer, generator floor, host, it is generator floor to clipping room between host Articulamentum, totally 7 layers, be concrete frame structure;Arrange that main building frame column 13 is used as support construction between each layer;In ball valve layer It is disposed with ball valve, leakage sump, circulating water pool, pump house;Ball valve hydraulic device, seepage drainage are disposed in turbine floor Pump, exciting transformer;It is disposed with generator in cable interlayer and draws bus, cable, neutral point device;It is disposed in generator floor Disk by governor, machine;Clipping room 2 is the place of units' installation and maintenance, the right side for being arranged in below ground, flowing to main building downstream Side, inside arrangement clipping room frame column 12 are used as braced frame, are connected to by marching into the arena tunnel 11 with outside;15 cloth of water dispenser auxiliary power house It is placed in ground or more, water (flow) direction upstream side, including turbine grease chamber, oil purification room, air compressor chamber, fan house;Electrical auxiliary power house 16 are arranged in ground or more, water (flow) direction downstream side, including Central Control Room, high-voltage switch gear room, station-service transformer room, switchgear house;Main factory Room upstream position arranges that air shaft 4, downstream position arrange elevator 5, and air shaft 4 and 5 bottom end of elevator are connected to ball valve layer, Air shaft top is connected to the fan house of water dispenser auxiliary power house 15;It is equal to generator floor, generator floor to turbine floor between host It is connected to by upstream side stair 6 with downstream side stair 7, turbine floor to ball valve layer is connected by right side stair 8 and left side stair 9 It is logical;The part that water dispenser auxiliary power house 15 and electrical auxiliary power house 16 are arranged in ground or more is all made of steel frame construction and builds, main building with Steel roof 14 is provided on the upside of clipping room 2;It is additionally provided on the upside of main building and is provided with bridge crane, be equipped at the top of main building Hanging object hole 3.
In the present embodiment, grade elevation 767.7m, indoor terrace elevation 768.0m, water dispenser auxiliary power house 15 and electrical Auxiliary power house 16 is arranged on 768.0m elevation, and clipping room is arranged in 757.7m elevation, with grade height difference 10m.Main building Pit shaft 1 diameter 25.5m, thick 1.5m, Bottom Altitude 714.95m, cope level 764.5m, total high 49.55m, pit shaft 1 are reinforcing bar Concrete structure.It is arranged between ball valve layer, turbine floor, cable interlayer, generator floor, host from the bottom to top in pit shaft 1, ball valve layer It is arranged in elevation 716.450m, turbine floor is arranged in elevation 721.450m, and cable interlayer is arranged in elevation 726.000m, power generation Machine layer arrangement is arranged in 729.500m to 757.700m elevation between elevation 729.500m elevation, host.
Wherein, the above 763.7~767.7m of elevation in 1 top of pit shaft and clipping room 2 use cubic metre of earth and stone open cut mode, form well Cylinder pilot shaft excavation construction platform.Cubic metre of earth and stone open cut uses the construction principle of " draining is advanced, controls explosion, and supporting is followed up in due course ", Side slope uses shotcrete support, it is ensured that stability of slope.Construction drainage, control explosion, side are properly carried out in implementation process Work such as slope supporting, and be considered as Pluvial influence, take the anti-collapse measure of flood control to Pluvial construction, it is ensured that engineering construction safety and apply Working medium amount.1 elevation 763.70m~714.95m of pit shaft is excavated, and by the way of well digging, excavates one temporarily from tailrace tunnel fork Access tunnel is to workshop excavation area as 1 bottom tap cinder construction channel of pit shaft.
1 excavation supporting implementation method of pit shaft with steps are as follows:
1 pilot shaft excavates: using the pilot shaft of drilling and blasting method digging diameter φ=2m, pilot shaft is excavated using stage excavation from top to bottom, is excavated Drilling depth controls within 2m, and using YT-28 hand air drill pore-creating, well head sets up hoisting frame, 2T electric hoist using channel steel or I-steel Slag is hung, personnel, material are transported by travelling bogie.
2 slag tap well excavation: well of slagging tap excavation digged using pilot shaft, using the quick-fried method of light dig to φ=4m diameter go out Slag well.It digs use " positive well method " and is layered from top to bottom and excavated, drilling depth control is excavated within 2.5m, using YT-28 hand Air drill pore-creating slips slag using pilot shaft, is slagged tap using side turn over loading machine cooperation 10t dumper to specified cinder field in shaft bottom.Every row It slags tap in time after big gun, prevents wellbore bottom accumulated slag from excessively causing blocking in well.
3 area pit shaft Zhu Wa excavation supportings: it is quick-fried that the area pit shaft Zhu Wa uses crawler belt hidden hole drilling and hand air drill to be layered brill from top to bottom To design sideline, II, III class surrounding rock excavates drilling depth control within 3m, and IV, V class surrounding rock excavates drilling depth control within 2m.It adopts With loading machine or bull-dozer collection slag, slag is sent, slag charge is excavated and is slipped by well of slagging tap to access tunnel, side turn over loading machine fills 10t certainly Automobile is unloaded to slag tap.
Carry out borehole wall supporting after the completion of 4 every layer of excavation in time: long anchor pole uses hidden hole drilling pore-creating, and Short bolt is using hand air drill Pore-creating, manually installed anchor pole, anchor rock mud filling machine slip casting;Pneumatically placed concrete applies spray using TK650 wet-spraying machine fragment, layering.To workshop The poor side wall of left and right sides geological conditions is segmented the supporting of pouring reinforcement concrete concealed beam.
Excavation between 5 elevation 714.95m~711.20m: by the way of slot digging.Main body rock excavation is latent using crawler belt Hole drill and hand air drill bore quick-fried, short-delay blasting, and design specification line uses the pore-creating of hand air drill, and presplit blasting or photoface exploision, corner are adopted It is quick-fried with hand air drill brill, it excavates rock ballast and is slagged tap using 1m3 excavator dress 10t dump truck, excavation of foundation pit sets pumping for water pump cooperation.
The present invention enriches the selection of workshop arrangement form, and Shaft Excavation is excavated by pilot shaft, well of slagging tap excavates and well Cylinder digs to be formed, and pit shaft buried depth is deeper, can effectively reduce the problem on deformation of factory building foundation, and preferable adaptation to the ground is saved engineering and thrown Money shortens the completion time of project, generates preferable economic results in society.
Finally, it is stated that preferred embodiment above is only used to illustrate the technical scheme of the present invention and not to limit it, although logical It crosses above preferred embodiment the present invention is described in detail, however, those skilled in the art should understand that, can be Various changes are made to it in form and in details, without departing from claims of the present invention limited range.

Claims (5)

1. a kind of semi-underground well shaft type workshop of hydroelectric project, it is characterised in that: including main building, clipping room (2), water dispenser pair factory Room (15), electrical auxiliary power house (16);
Main building arrangement is corresponding with water (flow) direction in below ground, and main building outer wall is pit shaft (1), in pit shaft (1) by down toward On be disposed between ball valve layer, turbine floor, cable interlayer, generator floor, host;
The right side that clipping room (2) is arranged in below ground, flows to main building downstream is connected to by tunnel of marching into the arena (11) with outside;
Water dispenser auxiliary power house (15) is arranged in ground or more, water (flow) direction upstream side, including turbine grease chamber, oil purification room, air compressor machine Room, fan house;
Electrical auxiliary power house (16) is arranged in ground or more, water (flow) direction downstream side, including Central Control Room, high-voltage switch gear room, unit transformer Electric room, switchgear house.
2. the semi-underground well shaft type workshop of hydroelectric project as described in claim 1, it is characterised in that: main building upstream position cloth It sets air shaft (4), downstream position arranges elevator (5), and air shaft (4) and elevator (5) bottom end are connected to ball valve layer, divulges information Vertical shaft top is connected to the fan house of water dispenser auxiliary power house (15).
3. the semi-underground well shaft type workshop of hydroelectric project as described in claim 1, it is characterised in that: to generator between host Layer, generator floor to turbine floor pass through upstream side stair (6) and are connected to downstream side stair (7), turbine floor to ball valve layer It is connected to by right side stair (8) with left side stair (9).
4. the semi-underground well shaft type workshop of hydroelectric project as described in claim 1, it is characterised in that: water dispenser auxiliary power house (15) and The part that electrical auxiliary power house (16) is arranged in ground or more is all made of steel frame construction and builds, and sets on the upside of main building and clipping room (2) It is equipped with steel roof (14).
5. the semi-underground well shaft type workshop of hydroelectric project as described in claim 1, it is characterised in that: be provided at the top of main building Bridge crane, main building top are equipped with hanging object hole (3).
CN201910172338.8A 2019-03-07 2019-03-07 A kind of semi-underground well shaft type workshop of hydroelectric project Pending CN109736274A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910172338.8A CN109736274A (en) 2019-03-07 2019-03-07 A kind of semi-underground well shaft type workshop of hydroelectric project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910172338.8A CN109736274A (en) 2019-03-07 2019-03-07 A kind of semi-underground well shaft type workshop of hydroelectric project

Publications (1)

Publication Number Publication Date
CN109736274A true CN109736274A (en) 2019-05-10

Family

ID=66369786

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910172338.8A Pending CN109736274A (en) 2019-03-07 2019-03-07 A kind of semi-underground well shaft type workshop of hydroelectric project

Country Status (1)

Country Link
CN (1) CN109736274A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863243A (en) * 2021-10-23 2021-12-31 中电建十一局工程有限公司 Construction method for quickly excavating underground powerhouse of hydropower station

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863243A (en) * 2021-10-23 2021-12-31 中电建十一局工程有限公司 Construction method for quickly excavating underground powerhouse of hydropower station

Similar Documents

Publication Publication Date Title
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN102454167B (en) The construction method of especially big & deep open caisson
CN102505695B (en) Construction method for deep foundation pit of three-dimensional garage
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
LU501539B1 (en) Pumping and drainage method for foundation pit bottom plate construction of deep foundation pit and pumping and drainage structure
CN111236957B (en) Mechanical pipe jacking construction process
CN103046931B (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN107514262A (en) The construction method of shield piping lane
CN102926392A (en) Foundation pit dewatering system and construction method thereof
CN109578014A (en) Anti- dash forward of one kind gushes back cover structure and construction method
CN109706945A (en) Come down fracture belt tunnel construction method
CN115182737A (en) Vertical orthogonal ejection type air duct structure of deep-buried subway station and construction method
CN109736274A (en) A kind of semi-underground well shaft type workshop of hydroelectric project
CN104763431A (en) Novel shaft construction method
CN201176596Y (en) Pipe well simultaneous for draining and pressure-reduction dewatering
CN112459834B (en) Water collecting well, counter-slope tunnel and counter-slope tunnel drainage method
CN209430204U (en) Anti- dash forward of one kind gushes back cover structure
CN209687506U (en) Wear river shallow buried covered excavation electric power tunnel constructing structure
CN113323722A (en) Water burst treatment method for extra-long tunnel
CN209760299U (en) light and shade of avoiding house to tear open and move is dug and is combined subway station structure
CN203475453U (en) Deeply-buried type bearing platform curtain structure of bridge
Hamberger Case history: Blowout at an LPG storage cavern in Sweden
CN113026757A (en) Rapid excavation and support construction method for complex stratum pipe-jacking comprehensive well
CN209873743U (en) Water and electricity engineering semi-underground shaft barrel type factory building
CN113107579B (en) Directional long drilling combined bottom plate cross drilling stereoscopic gas extraction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination