CN109720781A - Deep Foundation Pit Excavation vertically takes indigenous equipment - Google Patents

Deep Foundation Pit Excavation vertically takes indigenous equipment Download PDF

Info

Publication number
CN109720781A
CN109720781A CN201910022571.8A CN201910022571A CN109720781A CN 109720781 A CN109720781 A CN 109720781A CN 201910022571 A CN201910022571 A CN 201910022571A CN 109720781 A CN109720781 A CN 109720781A
Authority
CN
China
Prior art keywords
hopper
foundation pit
haulage chain
roller
deep foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910022571.8A
Other languages
Chinese (zh)
Inventor
王辉
陈凯
李继承
王星
魏倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN201910022571.8A priority Critical patent/CN109720781A/en
Publication of CN109720781A publication Critical patent/CN109720781A/en
Pending legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a kind of Deep Foundation Pit Excavations vertically to take indigenous equipment, including the attachment being fixed in foundation pit support construction or building enclosure, the frame for vertically protruding into foundation pit and being mounted on attachment, the lower roller for being located at base of frame, two be located at the upper roller in foundation pit exit, the driving mechanism of the upper roller rotation of driving, the closed haulage chain being wound on lower roller and two on rollers, the hopper being evenly arranged on haulage chain, positioned at two chutes gone up between rollers, the collection soil case being connect with chute tail end;Upper roller can drive haulage chain mobile when rotating, hopper open edge and haulage chain are hinged, haulage chain uplifted side hopper is opening up, decline side hopper is opening down, and the earthwork of taking-up can be poured into chute when can take the earthwork when bypassing lower roller, go up roller around first by hopper.This device achieves that the efficient vertical transport of Deep Foundation Pit Excavation, required work surface is small, and conevying efficiency is high, and structure is simple, easy for installation.

Description

Deep Foundation Pit Excavation vertically takes indigenous equipment
Technical field
The invention belongs to deep foundation pit construction fields, and in particular to a kind of Deep Foundation Pit Excavation vertically takes indigenous equipment.
Background technique
Along with building foundation pit constantly to overlarge area, super large depth development, take soil to closing after deep foundation pit earthwork digging It is important, directly affect deep-foundation pit engineering progress and economic cost, current Deep Foundation Pit Excavation take indigenous equipment include long-armed digging machine, Shell bucket telescopic arm digging machine, clamp excavator etc., these equipment uniformly have that required operating surface is big, the low problem of construction efficiency.
Summary of the invention
The object of the present invention is to provide a kind of Deep Foundation Pit Excavations vertically to take indigenous equipment, this device achieves that Deep Foundation Pit Excavation Efficient vertical transport, required work surface is small, and conevying efficiency is high, and structure is simple, easy for installation.
The technical scheme adopted by the invention is that:
A kind of Deep Foundation Pit Excavation vertically takes indigenous equipment, including the attachment being fixed in foundation pit support construction or building enclosure Part, vertically protrude into the frame in foundation pit and being mounted on attachment, the lower roller for being located at base of frame, two be located at foundation pit outlet The upper roller at place, the driving mechanism of the upper roller rotation of driving, closed lower roller and two haulage chains gone up on rollers, equal of being wound on Cloth is in the hopper on haulage chain, the chute between two upper rollers, the collection soil case connecting with chute tail end;Upper roller rotation When haulage chain can be driven mobile, hopper open edge and haulage chain are hinged, and haulage chain uplifted side hopper is opening up, decline side is expected Downward, the earthwork of taking-up can be poured into chute when can take the earthwork when bypassing lower roller, go up roller around first to hopper opening by hopper.
Further, first upper roller is located at right above lower roller, and haulage chain uplifted side is vertical.
Further, one layer of flexible pocket is equipped in hopper, hopper is around flexible pocket when first upper roller with taking-up The earthwork take off together, hopper bypass lower roller when flexible pocket be close to hopper under the pressure of the earthwork.
Further, it is equipped with positive stop strip above chute, Open Side Down that overturning is straight around hopper when first upper roller for hopper To item limit is limited, when hopper is limited item limit, hopper is opening down and does not overturn excessively.
Further, frame can be with the intensification of foundation pit and downward spreading, haulage chain can be with lower rollers when frame spreading Move down and spreading.
Further, hopper include the stocking space that is surrounded by the trapezoidal plate on front and back both sides and the rectangular slab of the right and left with And the liner plate positioned at the ipsilateral both sides in stocking space outside, liner plate edge and haulage chain are hinged.
The beneficial effects of the present invention are:
Hopper is transported to chute after vertically taking the earthwork, is concentrated to native case again when work, this device achieves that Deep Foundation Pit Excavation Efficient vertical transport, required work surface is small, and conevying efficiency is high;The device structure is simple, easy for installation, by frame and can lead Draw the vertical transport of the earthwork of the spreading completion foundation pit difference cutting depth of chain, the outfit quantity of the equipment can be according to pit earthwork Freight volume setting.
Detailed description of the invention
Fig. 1 is the operation schematic diagram of the embodiment of the present invention.
Fig. 2 is schematic diagram when haulage chain uplifted side hopper is opening up in the embodiment of the present invention.
Fig. 3 is the schematic diagram that hopper bypasses when roller rear hopper is opening down on first in the embodiment of the present invention.
Fig. 4 is the schematic view of the mounting position of positive stop strip in the embodiment of the present invention.
In figure: 1- frame;2- attachment;3- haulage chain;4- driving mechanism;The upper roller of 5-;6- hopper;7- positive stop strip;8- Foundation pit support construction or building enclosure;9- lower roller;10- chute;11- positive stop strip.
Specific embodiment
Present invention will be further explained below with reference to the attached drawings and examples.
As shown in Figure 1 to Figure 3, a kind of Deep Foundation Pit Excavation vertically takes indigenous equipment, including is fixed on foundation pit support construction or encloses Attachment 2 on protection structure 8 vertically protrudes into foundation pit and the frame 1 being mounted on attachment 2, the lower rolling for being located at 1 bottom of frame Son 9, two is located at the upper roller 5 in foundation pit exit, the driving mechanism 4 of the rotation of roller 5 in driving, closed is wound on lower roller 9 And haulage chains 3 on two upper rollers 5, the hopper 6 being evenly arranged on haulage chain 3, the chutes 10 between two upper rollers 5, The collection soil case being connect with 10 tail end of chute;Upper roller 5 can drive haulage chain 3 mobile when rotating, 6 open edge of hopper and haulage chain 3 is hinged, and 3 uplifted side hopper of haulage chain is 6 opening up, decline side hopper 6 is opening down, and hopper 6 can take soil when bypassing lower roller 9 Just, the earthwork of taking-up can be poured into chute 10 when around first upper roller 5.Hopper 6 vertically takes to be transported to after the earthwork and slip when work Slot 10 is concentrated to native case again, this device achieves that the efficient vertical transport of Deep Foundation Pit Excavation, required work surface is small, Transportation Efficiency Rate is high;The device structure is simple, easy for installation, can complete foundation pit difference cutting depth by frame 1 and the spreading of haulage chain 3 The vertical transport of the earthwork, the outfit quantity of the equipment can be arranged according to pit earthwork freight volume.
As shown in Figure 1, in the present embodiment, first upper roller 5 is located at right above lower roller 9, and 3 uplifted side of haulage chain is Vertically, so that the small minimum of required work surface.
As shown in Figures 2 and 3, in the present embodiment, hopper 6 includes the square of the trapezoidal plate and the right and left by front and back both sides The stocking space that shape plate surrounds and the liner plate positioned at the ipsilateral both sides in stocking space outside, liner plate edge and haulage chain 3 are hinged.Ladder The effect of shape plate is that overturning surplus is provided for hopper 6, and the effect of liner plate is by own dimensions and Position Design hopper 6 to be turned over The angle for maintaining the opening of hopper 6 suitable after turning, e.g., in 3 uplifted side of haulage chain, AB is horizontal while perpendicular to chain bucket, CD, hopper 6 After first upper roller 5, AC is greater than 60 degree with horizontal angle in level, A1B1.
As shown in figure 4, in the present embodiment, positive stop strip 11 is equipped with above chute 10, hopper 6 is around first upper roller 5 When hopper 6 Open Side Down overturning until be limited item 11 limit, hopper 6 be limited item 11 limit when, hopper 6 is opening down and does not have There is excessive overturning.When in the overturning to positive stop strip 11 of hopper 6, the vibration of generation facilitates blanking, and positive stop strip 11 can prevent from expecting The excessively overturning of bucket 6, avoiding the earthwork could not topple over completely.
In the present embodiment, one layer of flexible pocket is equipped in hopper 6, hopper 6 is around flexible pocket when first upper roller 5 It is taken off together with the earthwork of taking-up, flexible pocket is close to hopper 6 under the pressure of the earthwork when hopper 6 bypasses lower roller 9, prevents soil Square viscosity is big, is bonded in hopper 6, influences freight volume.
In the present embodiment, frame 1 can with the intensification of foundation pit downward spreading, when haulage chain 3 can be with 1 spreading of frame Lower roller 9 moves down and spreading.
It should be understood that for those of ordinary skills, it can be modified or changed according to the above description, And all these modifications and variations should all belong to the protection domain of appended claims of the present invention.

Claims (6)

1. a kind of Deep Foundation Pit Excavation vertically takes indigenous equipment, it is characterised in that: including being fixed on foundation pit support construction or building enclosure On attachment, vertically protrude into the frame in foundation pit and being mounted on attachment, the lower roller for being located at base of frame, two be located at The driving mechanism of roller rotation on the upper roller in foundation pit exit, driving closed is wound on lower roller and two upper rollers Haulage chain, the hopper being evenly arranged on haulage chain, the chute between two upper rollers, the collection soil case being connect with chute tail end; Upper roller can drive haulage chain mobile when rotating, hopper open edge and haulage chain are hinged, haulage chain uplifted side hopper opening court Upper and lower drop side hopper is opening down, and hopper can be by the soil of taking-up when can take the earthwork when bypassing lower roller, go up roller around first Chute pours into side.
2. Deep Foundation Pit Excavation as described in claim 1 vertically takes indigenous equipment, it is characterised in that: first upper roller is located at lower rolling Right above sub, haulage chain uplifted side is vertical.
3. Deep Foundation Pit Excavation as described in claim 1 vertically takes indigenous equipment, it is characterised in that: be equipped with one layer of flexible spout in hopper Bag, hopper are taken off around flexible pocket when first upper roller with the earthwork of taking-up together, flexible spout when hopper bypasses lower roller Bag is close to hopper under the pressure of the earthwork.
4. Deep Foundation Pit Excavation as described in claim 1 vertically takes indigenous equipment, it is characterised in that: positive stop strip is equipped with above chute, Hopper around Open Side Down the overturning of hopper when first upper roller until be limited item limit, when hopper is limited item limit, material Hopper opening is not overturn downward and excessively.
5. Deep Foundation Pit Excavation as described in claim 1 vertically takes indigenous equipment, it is characterised in that: frame can be with the intensification of foundation pit And downward spreading, haulage chain can with moving down for lower roller when frame spreading spreading.
6. Deep Foundation Pit Excavation as described in claim 1 vertically takes indigenous equipment, it is characterised in that: hopper includes by front and back both sides The stocking space that the rectangular slab of trapezoidal plate and the right and left surrounds and the liner plate positioned at the ipsilateral both sides in stocking space outside, liner plate Edge is hinged with haulage chain.
CN201910022571.8A 2019-01-09 2019-01-09 Deep Foundation Pit Excavation vertically takes indigenous equipment Pending CN109720781A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910022571.8A CN109720781A (en) 2019-01-09 2019-01-09 Deep Foundation Pit Excavation vertically takes indigenous equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910022571.8A CN109720781A (en) 2019-01-09 2019-01-09 Deep Foundation Pit Excavation vertically takes indigenous equipment

Publications (1)

Publication Number Publication Date
CN109720781A true CN109720781A (en) 2019-05-07

Family

ID=66299682

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910022571.8A Pending CN109720781A (en) 2019-01-09 2019-01-09 Deep Foundation Pit Excavation vertically takes indigenous equipment

Country Status (1)

Country Link
CN (1) CN109720781A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997174A (en) * 2020-09-30 2020-11-27 福建省清嵩环保科技有限公司 Integration sewage promotes pump station
CN113089676A (en) * 2021-03-23 2021-07-09 中国建筑一局(集团)有限公司 Rapid unearthing system for ultra-deep foundation pit
CN113602828A (en) * 2021-10-09 2021-11-05 徐州永凯新型材料科技有限公司 Building foundation ditch earthwork conveyer
CN115108251A (en) * 2021-03-19 2022-09-27 徐州中矿科光机电新技术有限公司 Follow-up compensation chain conveyor

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1068382A (en) * 1991-07-10 1993-01-27 北辰工业株式会社 In order to form the excavator of diaphragm wall body
CN203938097U (en) * 2014-05-08 2014-11-12 江苏韦欧机械有限公司 A kind of vertical dewatering bucket elevator
CN105780837A (en) * 2016-04-29 2016-07-20 石家庄铁道大学 Continuous excavation method and device for underground continuous wall
CN106276056A (en) * 2016-08-30 2017-01-04 上海市基础工程集团有限公司 Multi-segmental combination type earthwork perpendicular lifting apparatus
CN106315118A (en) * 2016-08-30 2017-01-11 上海市基础工程集团有限公司 Single chain type earthwork vertical lifting device
CN209582709U (en) * 2019-01-09 2019-11-05 中建三局集团有限公司 Deep Foundation Pit Excavation vertically takes indigenous equipment

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1068382A (en) * 1991-07-10 1993-01-27 北辰工业株式会社 In order to form the excavator of diaphragm wall body
CN203938097U (en) * 2014-05-08 2014-11-12 江苏韦欧机械有限公司 A kind of vertical dewatering bucket elevator
CN105780837A (en) * 2016-04-29 2016-07-20 石家庄铁道大学 Continuous excavation method and device for underground continuous wall
CN106276056A (en) * 2016-08-30 2017-01-04 上海市基础工程集团有限公司 Multi-segmental combination type earthwork perpendicular lifting apparatus
CN106315118A (en) * 2016-08-30 2017-01-11 上海市基础工程集团有限公司 Single chain type earthwork vertical lifting device
CN209582709U (en) * 2019-01-09 2019-11-05 中建三局集团有限公司 Deep Foundation Pit Excavation vertically takes indigenous equipment

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997174A (en) * 2020-09-30 2020-11-27 福建省清嵩环保科技有限公司 Integration sewage promotes pump station
CN115108251A (en) * 2021-03-19 2022-09-27 徐州中矿科光机电新技术有限公司 Follow-up compensation chain conveyor
CN115108251B (en) * 2021-03-19 2024-03-22 徐州中矿科光机电新技术有限公司 Follow-up compensation chain conveyor
CN113089676A (en) * 2021-03-23 2021-07-09 中国建筑一局(集团)有限公司 Rapid unearthing system for ultra-deep foundation pit
CN113602828A (en) * 2021-10-09 2021-11-05 徐州永凯新型材料科技有限公司 Building foundation ditch earthwork conveyer

Similar Documents

Publication Publication Date Title
CN109720781A (en) Deep Foundation Pit Excavation vertically takes indigenous equipment
CN202187764U (en) Integrally moving type mining and dressing unit in sand mine
CN106276056B (en) Multi-segmental combined type earthwork perpendicular lifting apparatus
CN207063013U (en) Excavator with agitator tank
CN106315118A (en) Single chain type earthwork vertical lifting device
CN114396087B (en) Dust fall anti-drop large-scale backhoe hydraulic excavator based on reaction force
CN209582709U (en) Deep Foundation Pit Excavation vertically takes indigenous equipment
CN105155605A (en) Amphibious shovel loader
CN204940393U (en) A kind of amphibious shovel loader
CN113152547B (en) Rapid foundation pit excavation equipment and excavation method
CN109056879A (en) A kind of riverway sludge cleaning plant and construction method
CN110629822B (en) Construction site sludge removal equipment and construction site drainage groove dredging method
CN210363991U (en) Subway construction soil device
CN216225399U (en) Anti-blocking vibrating screen coal separator
CN114483174A (en) Integrated method for storing, breaking and transporting gangue in driving roadway
CN214693079U (en) Earth handling device is used in excavation of dam foundation ditch
CN215718952U (en) Mining pneumatic tunnel repairing machine
CN113089676A (en) Rapid unearthing system for ultra-deep foundation pit
CN207634080U (en) A kind of tunnel excavation construction equipment
CN110439613A (en) A kind of coal working face tunnel filling spoil side dumping method
CN215927402U (en) Slag raking machine for underground excavation subway rapid construction
CN214778805U (en) Automatic sand and stone material conveying device for flood fighting and emergency rescue
CN210713022U (en) Auxiliary device of building site silt clear away equipment
CN210102963U (en) Excavation type loader for coal mine
CN211113649U (en) Reverse construction method construction device suitable for south Asia region high-rise underground water sand bed condition

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190507