CN109711567A - Service work safety measure Automatic generation of information method and system - Google Patents

Service work safety measure Automatic generation of information method and system Download PDF

Info

Publication number
CN109711567A
CN109711567A CN201811534519.2A CN201811534519A CN109711567A CN 109711567 A CN109711567 A CN 109711567A CN 201811534519 A CN201811534519 A CN 201811534519A CN 109711567 A CN109711567 A CN 109711567A
Authority
CN
China
Prior art keywords
equipment
disjunction
information
safety measure
grounding apparatus
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811534519.2A
Other languages
Chinese (zh)
Inventor
修洪江
褚兆勇
张哲�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuhai Unitech Power Technology Co Ltd
Original Assignee
Zhuhai Unitech Power Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuhai Unitech Power Technology Co Ltd filed Critical Zhuhai Unitech Power Technology Co Ltd
Priority to CN201811534519.2A priority Critical patent/CN109711567A/en
Publication of CN109711567A publication Critical patent/CN109711567A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of service work safety measure Automatic generation of information method and systems.Wherein, this method comprises: S1 obtains Awaiting Overhaul equipment;Determining first grounding apparatus with Awaiting Overhaul equipment with electric connecting relation of S2, wherein the first grounding apparatus is used to provide grounding safety guarantee for service work region;The determining first disjunction equipment with the first grounding apparatus with electric connecting relation of S3, wherein the first disjunction equipment is electrically disconnected for ensuring service work region and other regions or electrical isolation;S4 output safety Action Message, wherein safety measure information includes the status information of the first grounding apparatus and the first grounding apparatus or/and the status information of the first disjunction equipment and the first disjunction equipment.The present invention solves the technical issues of cannot be automatically generated safety measure.

Description

Service work safety measure Automatic generation of information method and system
Technical field
The present invention relates to security fields, in particular to a kind of service work safety measure Automatic generation of information method And system.
Background technique
In the plant stand/substation in the fields such as power grid, power generation and industrial and mining enterprises, before overhaul of the equipments operation, basis is needed The bills such as " electric power safety working regulation " authorized strength work ticket, grid switching operation bill, dangerous point prevention and control measure ticket, and according to careful Bill after core passes through provides safe to work such as scene execution equipment grid switching operation, safety measure deployment for overhaul of the equipments Working environment.
With the arrival of information age, various measure bills have stepped into graphical, electronization, the work of procedure more Operation mode, but the content in measure bill still needs through hand filling, selects by hand in multiple options, in graphic elements In the manual types such as click one by one and generate, the workload for generating Cui Shi bill is still larger and be easy to omit during filling in Measure content.
In addition, being required according to electric power safety, during safety measure deployment, certain action-items are that have stringent sequence to want It asks, but existing safety measure generates system and lacks and do not have this function.
It is above-mentioned cannot be automatically generated safety measure information aiming at the problem that, currently no effective solution has been proposed.
Summary of the invention
The embodiment of the invention provides a kind of service work safety measure Automatic generation of information method and systems, at least to solve The technical issues of certainly cannot be automatically generated safety measure.
According to an aspect of an embodiment of the present invention, a kind of method for obtaining safety measure information is provided, comprising: S1 is obtained Take Awaiting Overhaul equipment;Determining first grounding apparatus with the Awaiting Overhaul equipment with electric connecting relation of S2, wherein described the One grounding apparatus is used to provide grounding safety guarantee for service work region;S3 is determining to be had electrically with first grounding apparatus First disjunction equipment of connection relationship, wherein the first disjunction equipment is for ensuring the service work region and other areas Domain electrically disconnects or electrical isolation;S4 output safety Action Message, wherein the safety measure information includes first ground connection The state of the status information or/and the first disjunction equipment and the first disjunction equipment of equipment and first grounding apparatus Information.
Further, obtain safety measure information method further include: S21 using the Awaiting Overhaul equipment as starting point, with every Amorph equipment is boundary, searches the grounding apparatus with the possible electrically conducting of the Awaiting Overhaul equipment, and be determined as described first and connect Ground equipment;S31 is using first grounding apparatus as starting point, using disjunction equipment as boundary, searches and the first grounding apparatus electricity The disjunction equipment that gas is directly connected to, and it is determined as the first disjunction equipment;S41 exports the safety measure information, wherein institute Stating safety measure information includes: the state of first grounding apparatus to be all set to the information of coincidence and/or by described The state of one disjunction equipment is all set to the information of quartile.
Further, obtain the method for safety measure information further include: according to the first disjunction equipment, search with it is described First disjunction equipment carries out the first disjunction equipment and the second disjunction equipment with the second disjunction equipment of electrical separation Merge, is determined as third disjunction equipment;The first disjunction equipment in the safety measure information is replaced with into the third Disjunction equipment.
Further, after S4 output safety Action Message, the method also includes: S51 is according to the safety measure Information generates the work ticket of the Awaiting Overhaul equipment.
Further, after S4 output safety Action Message, the method also includes: S521 is according to first ground connection The status information of the status information of equipment and the first disjunction equipment, determines operation information, wherein the operation information is used for Indicate that first grounding apparatus and the operation of the first disjunction equipment execute sequence;S522 is raw according to the operation information At the operation order of the Awaiting Overhaul equipment.
Further, after S4 output safety Action Message, the method also includes: S531 determines the safety measure The corresponding dangerous point information of information;S532 generates the pre- prevention and control in dangerous point of the Awaiting Overhaul equipment according to the dangerous point information Measure list processed.
Further, after S4 output safety Action Message, the method also includes: S54 is according to the safety measure Information determines the security identifier of the maintenance mark and safety measure equipment of the Awaiting Overhaul equipment, wherein the safety measure is set It is standby to include at least first grounding apparatus and the first disjunction equipment;According to the maintenance mark and the security identifier, Show the Awaiting Overhaul equipment and the safety measure equipment.
According to another aspect of an embodiment of the present invention, a kind of service work safety measure Automatic generation of information system is additionally provided System, comprising: Awaiting Overhaul equipment;Detection device, for obtaining Awaiting Overhaul equipment;Determination has with the Awaiting Overhaul equipment electrically to be connected Connect the first grounding apparatus and the first disjunction equipment of relationship, and output safety Action Message;Wherein, first grounding apparatus is used In providing grounding safety guarantee for service work region, the first disjunction equipment is for ensuring the service work region and its Its region electrically disconnects or electrical isolation, and the safety measure information includes that first grounding apparatus and first ground connection set The status information of standby status information or/and the first disjunction equipment and the first disjunction equipment.
Further, the detection device is also used to using the Awaiting Overhaul equipment as starting point, using isolated state equipment as side The grounding apparatus with the possible electrically conducting of the Awaiting Overhaul equipment is searched, and is determined as first grounding apparatus in boundary;With described First grounding apparatus is starting point, using disjunction equipment as boundary, searches the disjunction being electrically directly connected to first grounding apparatus Equipment, and it is determined as the first disjunction equipment;And export the safety measure information;Wherein, the safety measure packet It includes: the state of first grounding apparatus being all set to the information of coincidence and/or by the state of the first disjunction equipment It is all set to the information of quartile.
Further, the detection device is also used to according to the first disjunction equipment, and lookup is set with first disjunction Standby the second disjunction equipment with electrical separation, the first disjunction equipment and the second disjunction equipment are merged, and are determined For third disjunction equipment;The first disjunction equipment in the safety measure information is replaced with into the third disjunction equipment.
In embodiments of the present invention, Awaiting Overhaul equipment is the equipment for needing to overhaul, before treating repair apparatus and being overhauled, Awaiting Overhaul equipment is obtained, determining first grounding apparatus with Awaiting Overhaul equipment with electric appliance connection relationship is set by the first ground connection Standby to provide grounding safety guarantee for the service work region of Awaiting Overhaul equipment, then determining with grounding apparatus there is electric appliance to connect pass First disjunction equipment of system, service work region is ensured by the first disjunction equipment and other regions electrically disconnect or electrically every From;After determining the first grounding apparatus and the first disjunction equipment, the safety measure information of Awaiting Overhaul equipment is exported, the safety is passed through Action Message indicates the status information of the first grounding apparatus and the first grounding apparatus;Or first disjunction equipment and the first disjunction equipment Status information or the first grounding apparatus and the first grounding apparatus status information and the first disjunction equipment and the first disjunction equipment Status information, to realize technical effect that is more acurrate, more fully being automatically generated to repair apparatus safety measure, And then solves the technical issues of cannot be automatically generated safety measure information.
Detailed description of the invention
The drawings described herein are used to provide a further understanding of the present invention, constitutes part of this application, this hair Bright illustrative embodiments and their description are used to explain the present invention, and are not constituted improper limitations of the present invention.In the accompanying drawings:
Fig. 1 is a kind of flow chart one of method for obtaining safety measure information according to an embodiment of the present invention;
Fig. 2 is a kind of flowchart 2 of method for obtaining safety measure information according to an embodiment of the present invention;
Fig. 3 is a kind of schematic diagram of the electric connecting relation of Awaiting Overhaul equipment according to an embodiment of the present invention;
Fig. 4 is a kind of flow chart 3 of method for obtaining safety measure information according to an embodiment of the present invention;
Fig. 5 is the schematic diagram that a kind of intelligence according to an embodiment of the present invention generates safety measure method;
Fig. 6 is a kind of schematic diagram for generating grid switching operation bill according to an embodiment of the present invention;
Fig. 7 is the schematic diagram of a kind of pair of line segregation overhaul of the equipments according to an embodiment of the present invention;
Fig. 8 is the schematic diagram of a kind of pair of busbar overhaul according to an embodiment of the present invention;
Fig. 9 is the schematic diagram of a kind of pair of bus bar side disconnecting link overhaul according to an embodiment of the present invention;
Figure 10 is the schematic diagram of a kind of pair of main transformer maintenance according to an embodiment of the present invention;
Figure 11 is a kind of schematic diagram of system for obtaining safety measure information according to an embodiment of the present invention;
Figure 12 is a kind of schematic diagram of detection device according to an embodiment of the present invention;
Figure 13 is a kind of schematic diagram of detection device according to an embodiment of the present invention;
Figure 14 is a kind of schematic diagram of system for obtaining safety measure information according to an embodiment of the present invention;
Figure 15 is a kind of schematic diagram of system for obtaining safety measure information according to an embodiment of the present invention;
Figure 16 is a kind of schematic diagram of system for obtaining safety measure information according to an embodiment of the present invention.
Specific embodiment
In order to enable those skilled in the art to better understand the solution of the present invention, below in conjunction in the embodiment of the present invention Attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is only The embodiment of a part of the invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill people The model that the present invention protects all should belong in member's every other embodiment obtained without making creative work It encloses.
It should be noted that description and claims of this specification and term " first " in above-mentioned attached drawing, " Two " etc. be to be used to distinguish similar objects, without being used to describe a particular order or precedence order.It should be understood that using in this way Data be interchangeable under appropriate circumstances, so as to the embodiment of the present invention described herein can in addition to illustrating herein or Sequence other than those of description is implemented.In addition, term " includes " and " having " and their any deformation, it is intended that cover Cover it is non-exclusive include, for example, the process, method, system, product or equipment for containing a series of steps or units are not necessarily limited to Step or unit those of is clearly listed, but may include be not clearly listed or for these process, methods, product Or other step or units that equipment is intrinsic.
According to embodiments of the present invention, a kind of embodiment of the method for obtaining safety measure information is provided, it should be noted that Step shown in the flowchart of the accompanying drawings can execute in a computer system such as a set of computer executable instructions, and It, in some cases, can be to be different from sequence execution institute herein and although logical order is shown in flow charts The step of showing or describing.
Fig. 1 is a kind of flow chart one of method for obtaining safety measure information according to an embodiment of the present invention, such as Fig. 1 institute Show, this method comprises the following steps:
S1 obtains Awaiting Overhaul equipment;
Determining first grounding apparatus with Awaiting Overhaul equipment with electric connecting relation of S2, wherein the first grounding apparatus is used In providing grounding safety guarantee for service work region;
The determining first disjunction equipment with the first grounding apparatus with electric connecting relation of S3, wherein the first disjunction equipment For ensuring service work region and other regions electrically disconnect or electrical isolation;
S4 output safety Action Message, wherein safety measure information includes the first grounding apparatus and the first grounding apparatus The status information of status information or/and the first disjunction equipment and the first disjunction equipment.
In embodiments of the present invention, Awaiting Overhaul equipment is the equipment for needing to overhaul, before treating repair apparatus and being overhauled, Awaiting Overhaul equipment is obtained, determining first grounding apparatus with Awaiting Overhaul equipment with electric appliance connection relationship is set by the first ground connection Standby to provide grounding safety guarantee for the service work region of Awaiting Overhaul equipment, then determining with grounding apparatus there is electric appliance to connect pass First disjunction equipment of system, service work region is ensured by the first disjunction equipment and other regions electrically disconnect or electrically every From;After determining the first grounding apparatus and the first disjunction equipment, the safety measure information of Awaiting Overhaul equipment is exported, the safety is passed through Action Message indicates the status information of the first grounding apparatus and the first grounding apparatus;Or first disjunction equipment and the first disjunction equipment Status information, to realize technical effect that is more acurrate, more fully being automatically generated to repair apparatus safety measure, And then solves the technical issues of cannot be automatically generated safety measure information.
It should be noted that causing electric loop to be not turned on since the equipment such as breaker are in quartile in electric loop Situation, it is referred to as electrical to disconnect.
It should be noted that being caused electrically in electric loop since the equipment such as disconnecting switch, isolation trolley are in quartile Circuit is not turned on and the situation with obvious cut-off point, referred to as electrical isolation.
Optionally, grounding apparatus includes: grounding switch and ground line;Disjunction equipment includes: disconnecting link, disconnecting switch and open circuit Device, there are electrical wiring relationships between Awaiting Overhaul equipment, grounding apparatus and disjunction equipment.
Optionally, during treating repair apparatus and being overhauled, staff is needed to carry out the region of inspection operation As service work region, with Awaiting Overhaul equipment there are in the region of electric connecting relation, the region in addition to service work is For other regions.In order to guarantee that the safety of service work carries out, therefore, to assure that service work region will not be charged, so needs are The incoming call side of Awaiting Overhaul equipment provides grounding safety guarantee.
Optionally, the safety measure information of output can be setting including at least one grounding apparatus and disjunction equipment Standby set, which may include: the status information of the first grounding apparatus and the first grounding apparatus;It can be the first disjunction equipment And first disjunction equipment status information;Can also be the first grounding apparatus and the first grounding apparatus status information and first point The status information of disconnected equipment and the first disjunction equipment.
Fig. 2 is a kind of flowchart 2 of method for obtaining safety measure information according to an embodiment of the present invention, such as Fig. 2 institute Show, this method comprises the following steps:
S21 is using Awaiting Overhaul equipment as starting point, and using isolated state equipment as boundary, searching may electrically conducting with Awaiting Overhaul equipment Grounding apparatus, and be determined as the first grounding apparatus;
S31 is using the first grounding apparatus as starting point, and using disjunction equipment as boundary, lookup electrically directly connects with the first grounding apparatus The disjunction equipment connect, and it is determined as the first disjunction equipment;
S41 output safety Action Message, wherein safety measure information includes: all to set the state of the first grounding apparatus It is set to the information of coincidence and/or the state of the first disjunction equipment is all set to the information of quartile.
The above embodiment of the present invention, using Awaiting Overhaul equipment as starting point, is set in Awaiting Overhaul equipment region with isolated state Standby is boundary, traverses each electrical equipment between Awaiting Overhaul equipment and isolated state equipment, lookup exists with Awaiting Overhaul equipment may The grounding apparatus of electrically conducting is as grounding apparatus, then using the first grounding apparatus as starting point, using disjunction equipment as boundary, and traversal Each electrical equipment between first grounding apparatus and disjunction equipment, there are electrical direct connection relationals with the first grounding apparatus for lookup Disjunction equipment be the first disjunction equipment, then output safety Action Message treats maintenance by safety measure information expression In the case that equipment is overhauled, it sets the first grounding apparatus to the information of coincidence, and set the first disjunction equipment to The information of quartile.
It should be noted that during treating repair apparatus and being overhauled, in order to treat the check man of repair apparatus Make region and grounding safety guarantee is provided, needs to set coincidence state for the first grounding apparatus;In order to ensure service work region It is electrically disconnected with other regions or electrical isolation, needs to set the first disjunction equipment to coincidence state, and then the safety exported Action Message is to set the first grounding apparatus to the information of coincidence, and set the first disjunction equipment to the information of coincidence At least one of.
It should be noted that isolated state equipment refers to keeping apart with obvious physics cut-off point when in quartile state The equipment such as pass, isolation trolley.
It should be noted that in electric loop, except disconnecting switch, the isolation trolley etc. that occur quartile on electrical path are set Think electrically to be not turned on when standby, remaining situation thinks possible electrically conducting, for example occurs no matter breaker (divides in electrical path Close) or all kinds of transformers or all kinds of capacitors etc., thinking may electrically conducting.
It should be noted that in electric loop, in the electrical connection path between equipment and equipment there is no breaker, The disjunctions equipment such as disconnecting switch, car switch, is considered as electrically is directly connected at this time.
Fig. 3 is a kind of schematic diagram of the electric connecting relation of Awaiting Overhaul equipment according to an embodiment of the present invention, such as Fig. 3 institute Show, comprising: grounding switch (JDDZ), ground line (JDX), disconnecting switch (GLKG), trolley (XC) and breaker (DLQ), wherein Grounding switch (JDDZ) includes: JG1-JDDZ1, JG1-JDDZ2, JG1-JDDZ3, JG2-JDDZ1, JG2-JDDZ2 and JG4- JDDZ1;Ground line (JDX) include: JG1-JDX1, JG1-JDX2, JG1-JDX3, MX1-JDX1, MX1-JDX2, MX2-JDX1, MX2-JDX2, ZB-JDX1 and ZB-JDX2;Disconnecting switch (GLKG) include: JG1-GLKG1, JG1-GLKG2, JG2-GLKG1 and JG2-GLKG2;Trolley (XC) includes: JG3-XC;Breaker (DLQ) includes: JG1-DLQ, JG2-DLQ, JG3DLQ and JG4- DLQ。
Optionally, it is based on electric connecting relation shown in Fig. 3, determines that the rule of grounding apparatus describes according to Awaiting Overhaul equipment It is as follows: with Awaiting Overhaul equipment (ZB) for starting point, successively to traverse and each electrically set along the electric connecting relation of each side of Awaiting Overhaul equipment It is standby, determine that the grounding switch (JDDZ) and ground line (JDX) in traverse path are grounding apparatus, and traversing disconnecting switch (GLKG) and until the isolated states equipment such as trolley (XC) or natural breakpoint.
Optionally, from starting point between target point (i.e. traversal terminal), the grounding switch (JDDZ) of appearance is grounded (JDX) the first grounding apparatus determined needed for being.
Optionally, it is based on electric connecting relation shown in Fig. 3, the rule description of disjunction equipment is determined such as according to grounding apparatus Under: it is traversed since any one grounding apparatus to electrical connection, until traversing disconnecting switch (GLKG) and trolley (XC) etc. Until isolated state equipment or natural breakpoint bit.Wherein, what is occurred in disconnecting switch (GLKG) and trolley (XC) and traverse path is disconnected Road device (DLQ) is the first disjunction equipment.
It should be noted that disjunction equipment includes at least the first disjunction equipment and the second disjunction equipment, wherein the first disjunction Equipment and the second disjunction equipment are the disjunction equipment in same electrical separation.
Optionally, to cooperate above-mentioned disconnecting switch, trolley to change state, with the disconnecting switch in electrical separation, breaker It also is the second disjunction equipment.
Optionally, disjunction equipment further includes third disjunction equipment, can indicate to be in same electricity by third disjunction equipment The first disjunction equipment and the second disjunction equipment in gas interval.
Fig. 4 is a kind of flow chart 3 of method for obtaining safety measure information according to an embodiment of the present invention, such as Fig. 4 institute Show, this method comprises the following steps:
S311 searches the second disjunction equipment with the first disjunction equipment with electrical separation according to the first disjunction equipment, by the One disjunction equipment is merged with the second disjunction equipment, is determined as third disjunction equipment;
The first disjunction equipment in safety measure information is replaced with third disjunction equipment by S411.
The above embodiment of the present invention can search after determining the first disjunction equipment and be in same with the first disjunction equipment Second disjunction equipment of electrical separation, then the first disjunction equipment and the second disjunction equipment are merged, obtain third disjunction Then the first disjunction equipment in safety measure information is replaced with third point end equipment by equipment.
It should be noted that electrical separation refers to a complete circuit, containing breaker, disconnecting switch, mutual inductor, take shelter from the thunder Device etc., all electric units with perfect in shape and function are known as an electrical separation.
Optionally, it is based on electric connecting relation shown in Fig. 3, the rule description of safety measure is determined such as according to disjunction equipment Under: after determining disjunction equipment, all disjunction equipment and grounding apparatus then form electrical primary in Awaiting Overhaul equipment safety measure Cluster tool.It should be noted that including at least the first disjunction equipment, the second disjunction based on the disjunction equipment that Fig. 3 is obtained herein Equipment and third disjunction equipment.
Optionally, it by secondary device preset in data memory module and primary equipment dependence, can obtain Obtain the set of secondary device.
As a kind of optional embodiment, after S4 output safety Action Message, method further include: S51 is according to safety Action Message generates the work ticket of Awaiting Overhaul equipment.
The above embodiment of the present invention can be preparatory according to safety measure information solicitation after output safety Action Message The work ticket template of setting, to generate the work ticket of Awaiting Overhaul equipment.
As a kind of optional embodiment, after S4 output safety Action Message, method further include: S521 is according to first The status information of the status information of grounding apparatus and the first disjunction equipment, determines operation information, wherein operation information is for indicating The operation of first grounding apparatus and the first disjunction equipment executes sequence;S522 generates the behaviour of Awaiting Overhaul equipment according to operation information Make ticket.
The above embodiment of the present invention can also be according to the state of the first grounding apparatus after output safety Action Message The status information of information and the first disjunction equipment determines that the operation for indicating the first grounding apparatus and the first disjunction equipment executes The operation information of sequence, then according to operation information and the preset operation order template of safety measure information solicitation, thus raw At the operation order of Awaiting Overhaul equipment.
As a kind of optional embodiment, after S4 output safety Action Message, method further include: S531 determines safety The corresponding dangerous point information of Action Message;S532 according to dangerous point information, arrange by the dangerous point prevention and control for generating Awaiting Overhaul equipment Shi Dan.
The above embodiment of the present invention is analyzed by the Action Message of Awaiting Overhaul equipment, can be determined and be set to Awaiting Overhaul It is standby overhauled during, in fact it could happen that dangerous point, obtain the dangerous point information of Awaiting Overhaul equipment, believed according to the dangerous point Breath can fill in preset dangerous point Control Measure single mode plate, and the dangerous point prevention and control for obtaining Awaiting Overhaul equipment are arranged Shi Dan.
As a kind of optional embodiment, after S4 output safety Action Message, method further include: S54 is according to safety Action Message determines the security identifier of the maintenance mark and safety measure equipment of Awaiting Overhaul equipment, wherein safety measure equipment is extremely It less include the first grounding apparatus and the first disjunction equipment;According to maintenance mark and security identifier, Awaiting Overhaul equipment and safety are shown Measure equipment.
The above embodiment of the present invention, safety measure equipment include the first grounding apparatus and the first disjunction equipment, safety measure The facility information of equipment then includes the facility information of the first grounding apparatus and the facility information of the first disjunction equipment, to be checked determining After the safety measure information for repairing equipment, the corresponding maintenance mark of Awaiting Overhaul equipment and peace can be determined according to safety measure information Then the security identifier of full measure equipment shows Awaiting Overhaul equipment and safety measure equipment according to maintenance mark and security identifier, To realize that treating repair apparatus and safety measure equipment carries out differentiation and show, improves Awaiting Overhaul equipment and safety measure equipment Resolution.
The present invention also provides a kind of preferred embodiment, the preferred embodiment provides a kind of intelligently raw by repair apparatus At the system and implementation method of safety measure.
Fig. 5 is the schematic diagram that a kind of intelligence according to an embodiment of the present invention generates safety measure method, as shown in figure 5, choosing Awaiting Overhaul equipment is selected, according to Awaiting Overhaul equipment, generates the safety measure for meeting service work requirement, it is then raw according to safety measure At work ticket, grid switching operation bill (i.e. operation order) and dangerous point Control Measure list.
It should be noted that Awaiting Overhaul equipment include: breaker, disconnecting link, grounding switch, bus, route outlet, main transformer, The equipment such as PT, capacitor.
It should be noted that safety measure includes: grounding requirement, off device requirement, secondary device requirement, safety measure Isolated operation requirement, the requirement of multi-scheme processing mode, equipment operation during deployment, wherein grounding requirement includes: closure ground connection Disconnecting link, connection ground line;Off device requires to include: cut-off breaker and disconnecting link (trolley);Secondary device requires to include: It needs that the secondary device carried out operation and overhaul of the equipments needs is cooperated to carry out when off device operation and ground connection operation secondary Equipment operation;Multi-scheme processing mode includes: the measures for carrying into execution a plan in the presence of difference, and intelligence generates various schemes combinations, Row major grade of going forward side by side sequence is convenient for artificial selection, such as: grounding scheme;Equipment operation requires can be such as " grid switching operation process " original Then.
It should be noted that generating work ticket includes: to generate the breaker that need to be pulled open, disconnecting switch;The ground connection that need to be closed Equipment.
It should be noted that generating grid switching operation bill includes: according to the current state of breaker, disconnecting switch, intelligence is raw At grid switching operation sequence.
It should be noted that generating dangerous point Control Measure list includes: type, the safety measure according to repair apparatus The factors such as the risk situation that may relate to when deployment, intelligence generate dangerous point Control Measure list.
According to that above embodiment of the present invention, one or a set of Awaiting Overhaul equipment can be clicked in system graphical interfaces, Determining can be according to the constraint item of operation order between current device state, the connecting relation of equipment, equipment after Awaiting Overhaul equipment Part etc. generates the strategy for meeting the requirement of service work safety measure by modes such as intellectual analysis, calculating, judgements, and determines peace The service works deployment secures such as work ticket, operation order, dangerous point Control Measure list are automatically generated on the basis of full measure to arrange Apply required bill.
Optionally, it after determining Awaiting Overhaul equipment, first by the wiring relationship of each electrical equipment, identifies, retrieve and connect Ground equipment, then the state of grounding apparatus and wiring relation recognition, retrieve and disconnect required for meeting Awaiting Overhaul equipment ground The disconnecting switch that breaker and needs pull open, operation when finally being executed according to overhaul of the equipments and safety measure, identifies danger Danger point and the required Control Measure taken.
It should be noted that treating the most basic requirement that repair apparatus is overhauled is: each incoming call side of Awaiting Overhaul equipment, It must satisfy reliable ground, system identifies according to this principle and retrieve grounding apparatus when meeting overhaul of the equipments.
Optionally, grounding apparatus can be grounding switch, be also possible to temporary grounding point (or ground line), for the same side There is grounding switch, have temporary grounding point again, then system automatically generated meets the different schemes overhauled and respectively flank ground, and carries out excellent First grade sequence, easy access staff selection.
Such as: scheme 1 is grounded using grounding switch mode is closed;Scheme 2 is grounded using temporary ground wire mode is hung.
Optionally, the requirement for meeting grounding apparatus ground connection makes the breaker of each side of grounding apparatus, disconnecting switch must be disconnected Open state is identified according to this principle and retrieves when meeting grounding apparatus ground connection, the breaker that needs to operate, disconnecting switch.
Optionally, breaker, disconnecting switch need to be equipped with corresponding two before its operation, after operation when executing operation Secondary device operation, system, which is identified and retrieved according to this principle, meets breaker, disconnecting switch when executing operation, needs to hold Capable secondary device action-item.
Optionally, when pending equipment is executed maintenance and operated to safety measure equipment, according to " Risk Pre-control Management system " it requires, it need to differentiate and identify the dangerous point being involved in, and must adopt in operation process to these risk factors Corresponding Control Measure is taken to be coped with.
It, can be according to the shape of safety measure equipment after the safety measure equipment for meeting service work requirement is identified Connection relationship between state, safety measure equipment, by safety measure equipment operation to the state for meeting service work requirement.
Optionally, the state of safety measure equipment generally divides, closes 2 kinds of states, and in maintenance, grounding apparatus needs are being closed Position, breaker, disconnecting switch need to be in quartiles.
Optionally, the mode of connection between safety measure equipment, defined complete to plant stand/substation equipment modeling initial stage At.
Optionally, safety measure equipment is operated, in addition to the state and safety measure equipment with safety measure equipment Between connection relationship have outside the Pass, operation order is also related with pre-set rule condition.According to pre-set Safety measure equipment is ranked up by rule condition according to fool proof sequence automatically.
Optionally, pre-set rule condition includes: five anti-primitive rules, grid switching operation service condition, rear point of electricity The requirement such as source disconnecting switch and other specific conditions.
It should be noted that five anti-primitive rules include: to prevent mistake point, falsely close circuit breaker;It prevents on-load from drawing, close isolation Switch or handcart contact;Prevent band cable address (conjunction) ground line (grounding switch);Prevent line with ground (grounding switch) from closing breaker (disconnecting switch);Prevent mistakenly entering charged chamber.
It should be noted that grid switching operation service condition includes: first point load side isolation switch
Optionally, after determining safety measure, work ticket, grid switching operation can be automatically generated with establishing criteria note form The bills such as ticket, dangerous point precautionary measures control ticket.
Optionally, the generation of work ticket can fill corresponding action according to work ticket format module automatically, for It is selected and is confirmed in the presence of the measure that difference carries into execution a plan, after the completion of selection, what intelligent decision entirety measure carried into execution a plan fills Divide property and necessity.
Optionally, after the generation of grid switching operation bill (i.e. operation order) then confirms according to operation order format module, work ticket Scheme and grid switching operation sequence generate grid switching operation bill.Furthermore it is possible to require configuration grid switching operation bill according to the different of user Generation, such as: breaker is individually created whether grid switching operation bill, whether by interval to generate grid switching operation bill, grounding apparatus independent Generate grid switching operation bill etc..
Optionally, the generation of dangerous point Control Measure ticket is then according to dangerous point Control Measure ticket format module, And the scheme after work ticket confirmation, according to the corresponding content of spreadsheet autocomplete.
Fig. 6 is a kind of schematic diagram for generating grid switching operation bill according to an embodiment of the present invention, as shown in fig. 6, judgement open circuit Whether the state of device is in coincidence, if breaker is in coincidence, the sequence of operation of generation are as follows: 1, separated breaker;2, separately negative He Cedaozha;3, source side disconnecting link is separated;4, grounding apparatus is closed;5, the isolating closing lock sequence of operation is generated as needed.
Optionally, if breaker is not in coincidence, whether detection and isolation switch is in coincidence, closes if disconnecting switch is in Position, the sequence of operation of generation are as follows: 1, separated load side disconnecting link;2, source side disconnecting link is separated;3, grounding apparatus is closed;4, according to need Generate the isolating closing lock sequence of operation.
Optionally, if disconnecting switch is in quartile, the sequence of operation of generation are as follows: 1, conjunction grounding apparatus;2, raw as needed At the isolating closing lock sequence of operation.
Fig. 7 is the schematic diagram of a kind of pair of line segregation overhaul of the equipments according to an embodiment of the present invention, as shown in fig. 7, comprises: Breaker 201 is overhauled and disconnecting link 2013 is overhauled.
Optionally, include: to the maintenance of breaker 201
1, clicking breaker 201 is Awaiting Overhaul equipment.
2, determine that meeting the grounding apparatus of maintenance condition includes: 20129,20139,201-1d, 201-2d and 201-3d.
3, determine that the disconnecting link, the breaker that meet and be grounded and need to disconnect include: 2011,2012,2013 and 201.
4, according to grounding apparatus, different grounding schemes is generated, such as: 20129,20139 ground connection;201-1d,201-3d;Or 201-2d, 201-3d etc., and sort.
5, grid switching operation bill is generated according to the safety measure equipment after determining grounding scheme.
For example, the state of disconnecting link 2011 and 2013 is " conjunction ", then formation sequence if the state of breaker 201 is " conjunction " are as follows: Pull open 201 breakers;Pull open disconnecting link 2013;Pull open disconnecting link 2011;Close grounding switch 20129;Close grounding switch 20139.
6, secondary device, check item, the operation for confirming item, are inserted in corresponding one by the incidence relation with primary equipment Secondary device operation front and back.
Optionally, include: to the maintenance of disconnecting link 2013
1, clicking disconnecting link 2013 is Awaiting Overhaul equipment.
2, determine that meeting the grounding apparatus of maintenance includes: 2019,20139,201-3d, 201-4d and 201-5d.
3, it determines and meets disconnecting link, breaker that ground connection need to disconnect: 2011,2012,2013 and 201.
4, according to grounding apparatus, different grounding schemes is generated, such as: 2019,20139 ground connection;Or 201-1d, 201-3d; Or 201-2d, 201-3d etc., and sort.
5, grid switching operation bill is generated according to the safety measure equipment after determining grounding scheme.
For example, if the state " conjunction " of breaker 201, the state " conjunction " of disconnecting link 2011 and 2013;Then formation sequence are as follows: pull open 201 breakers;Pull open disconnecting link 2013;Pull open disconnecting link 2011;Close grounding switch 2019;Close grounding switch 20139.
6, secondary device, check item, the operation for confirming item, are inserted in corresponding one by the incidence relation with primary equipment Secondary device operation front and back.
Fig. 8 is the schematic diagram of a kind of pair of busbar overhaul according to an embodiment of the present invention, as shown in Figure 8, comprising:
1, clicking bus 110kVI is Awaiting Overhaul equipment.
2, determine that meeting the grounding apparatus of maintenance includes: 110IM-1d and 110IM-2d.
3, determine meet ground connection disconnecting link, the breaker that need to disconnect include: 1121,190,1101,1111,1001 and 112, 110、111、100。
4, according to grounding apparatus, grounding scheme is generated, such as: 110IM-1d, 110IM-2d.
5, grid switching operation bill is generated according to the safety measure equipment after determining grounding scheme.
For example, the state of breaker 111 and 100 is " dividing " if the state of breaker 112 and 110 is " conjunction ";And disconnecting link 1121,1122,1101 and 1102 state is " to close, the state of disconnecting link 190,1111,1112,1001 and 1002 is " dividing ";Then give birth to At sequence are as follows: pull open 112 breakers;Pull open disconnecting link 1122;Pull open disconnecting link 1121;Pull open breaker 110;Pull open disconnecting link 1102; Pull open disconnecting link 1101;Load onto ground line 110IM-1d;Load onto ground line 110IM-2d.
6, secondary device, check item, the operation for confirming item, are inserted in corresponding one by the incidence relation with primary equipment Secondary device operation front and back.
Fig. 9 is the schematic diagram of a kind of pair of bus bar side disconnecting link overhaul according to an embodiment of the present invention, as shown in Figure 9, comprising:
1, clicking disconnecting link 1121 is Awaiting Overhaul equipment.
It should be noted that choosing the disconnecting link phase any one or more in the disconnecting link 190,1101,1111 and 1001 of bus bar side Together.
2, determine that meeting the grounding apparatus of maintenance includes: 110IM-1d, 110IM-2d and 112-1d.
3, determine meet ground connection disconnecting link, the breaker that need to disconnect include: 1121,190,1101,1111,1001 and 112, 110、111、100。
4, according to grounding apparatus, grounding scheme is generated, such as: 110IM-1d, 112-1d ground connection or 112-1d, 110IM-2d Ground connection.
5, grid switching operation bill is generated according to the safety measure equipment after determining grounding scheme.
For example, the state of breaker 111 and 100 is " dividing " if the state of breaker 112 and 110 is " conjunction ";Disconnecting link 1121,1122,1101 and 1102 state is " conjunction ", and the state of disconnecting link 190,1111,1112,1001 and 1002 is " dividing ", then Formation sequence are as follows: pull open breaker 112;Pull open disconnecting link 1122;Pull open disconnecting link 1121;Pull open breaker 110;Pull open disconnecting link 1102;Pull open disconnecting link 1101;Load onto ground line 110IM-1d;Load onto ground line 112-1d.
6, secondary device, check item, the operation for confirming item, are inserted in corresponding one by the incidence relation with primary equipment Secondary device operation front and back.
Figure 10 is the schematic diagram of a kind of pair of main transformer maintenance according to an embodiment of the present invention, as shown in Figure 10, comprising:
1, clicking main transformer 2# is Awaiting Overhaul equipment.
2, determine that meeting the grounding apparatus of maintenance includes: 1ZB-1d, 1ZB-2d and 1ZB-3d.
3, it determines and meets disconnecting link, breaker that ground connection need to disconnect: 1201,1202,360XC, 602XC and 120,360,602.
4, according to grounding apparatus, grounding scheme is generated, such as: 1ZB-1d, 1ZB-2d, 1ZB-3d.
5, grid switching operation bill is generated according to the safety measure equipment after determining grounding scheme.
For example, if the state of breaker 120,360 and 602 is " to close;Disconnecting link/trolley 1201,1202,360XC, 602XC State is " to close;Then formation sequence are as follows: pull open breaker 602;Trolley 602 is drawn to maintenance position;Pull open breaker 360;It will be small Vehicle 360 is drawn to maintenance position;Pull open breaker 120;Pull open disconnecting link 1201;Pull open disconnecting link 1202;Load onto ground line 1ZB-1d;Dress Upper ground line 1ZB-2d;Load onto ground line 1ZB-3d.
6, secondary device, check item, the operation for confirming item, are inserted in corresponding one by the incidence relation with primary equipment Secondary device operation front and back.
Figure 11 is a kind of schematic diagram of system for obtaining safety measure information according to an embodiment of the present invention, such as Figure 11 institute Show, comprising: Awaiting Overhaul equipment 1101;Detection device 1103, for obtaining Awaiting Overhaul equipment;It is determining that there is electricity with Awaiting Overhaul equipment First grounding apparatus of gas connection relationship and the first disjunction equipment, and output safety Action Message;Wherein, the first grounding apparatus is used In providing grounding safety guarantee for service work region, the first disjunction equipment is for ensuring service work region and other regions electricity Gas disconnects or electrical isolation, and safety measure information includes the status information or/and the of the first grounding apparatus and the first grounding apparatus The status information of one disjunction equipment and the first disjunction equipment.
In embodiments of the present invention, Awaiting Overhaul equipment is the equipment for needing to overhaul, before treating repair apparatus and being overhauled, Awaiting Overhaul equipment is obtained, determining first grounding apparatus with Awaiting Overhaul equipment with electric appliance connection relationship is set by the first ground connection Standby to provide grounding safety guarantee for the service work region of Awaiting Overhaul equipment, then determining with grounding apparatus there is electric appliance to connect pass First disjunction equipment of system, service work region is ensured by the first disjunction equipment and other regions electrically disconnect or electrically every From;After determining the first grounding apparatus and the first disjunction equipment, the safety measure information of Awaiting Overhaul equipment is exported, the safety is passed through Action Message indicates the status information of the first grounding apparatus and the first grounding apparatus;Or first disjunction equipment and the first disjunction equipment Status information or the first grounding apparatus and the first grounding apparatus status information and the first disjunction equipment and the first disjunction equipment Status information, to realize technical effect that is more acurrate, more fully being automatically generated to repair apparatus safety measure, And then solves the technical issues of cannot be automatically generated safety measure information.
As a kind of optional embodiment, detection device is also used to using Awaiting Overhaul equipment as starting point, is with isolated state equipment The grounding apparatus with the possible electrically conducting of Awaiting Overhaul equipment is searched, and is determined as the first grounding apparatus in boundary;It is set with the first ground connection Standby is starting point, using disjunction equipment as boundary, searches the disjunction equipment being electrically directly connected to the first grounding apparatus, and is determined as the One disjunction equipment;And output safety Action Message;Wherein, safety measure information includes: that the state of the first grounding apparatus is whole It is set as the information of coincidence and/or the state of the first disjunction equipment is all set to the information of quartile.
As a kind of optional embodiment, detection device is also used to according to the first disjunction equipment, and lookup is set with the first disjunction Standby the second disjunction equipment with electrical separation, the first disjunction equipment and the second disjunction equipment are merged, and are determined as third point Disconnected equipment;The first disjunction equipment in safety measure information is replaced with into third disjunction equipment.
Figure 12 is a kind of schematic diagram of detection device according to an embodiment of the present invention, as shown in figure 12, comprising: obtains module 1201, computing module 1203, output module 1204, memory module 1205, wherein obtain module for obtaining by Awaiting Overhaul equipment Or the Awaiting Overhaul equipment of user's input;Computing module, for determining the first grounding apparatus according to Awaiting Overhaul equipment, and according to first Grounding apparatus determines the first disjunction equipment, and the peace of Awaiting Overhaul equipment is then determined according to the first grounding apparatus and the first disjunction equipment Full Action Message;Output module, for exporting the safety measure information of Awaiting Overhaul equipment;Memory module is compiled for storing equipment Number, title, type, communication, electric connecting relation, equipment and equipment room the facility informations such as dependence, as Awaiting Overhaul equipment, First grounding apparatus and the first disjunction equipment.
Optionally, computing module obtains Awaiting Overhaul equipment by obtaining module, can be from depositing then according to Awaiting Overhaul equipment Store up the dependence between number, title, type, remote signalling, electric connecting relation, equipment and the equipment of inquiring Awaiting Overhaul equipment in module Etc. information, computing module can determine grounding apparatus and the first disjunction equipment after obtaining Awaiting Overhaul equipment, and then determination is to be checked The safety measure information of equipment is repaired, and safety measure information is exported by output module.
Figure 13 is a kind of schematic diagram of detection device according to an embodiment of the present invention, and as shown in figure 13, detection device also wraps Rule module 1302 is included, is stored for determining the first rule searching of the first grounding apparatus, for determining the first disjunction equipment Second rule searching and rule for determining safety measure information.
Optionally, rule module: can pre-define the rule that the first grounding apparatus is determined from Awaiting Overhaul equipment, from first Grounding apparatus determines the rule of the first disjunction equipment, determines safety measure information from the first grounding apparatus, the first disjunction equipment Rule.
During determining the safety measure information of Awaiting Overhaul equipment, computing module can read the rule in rule module Then information can determine the first grounding apparatus according to Rule Information according to Awaiting Overhaul equipment, determine the according to the first grounding apparatus One disjunction equipment, and then safety measure information is determined according to the first disjunction equipment.
Optionally, computing module can search device numbering, title, class from memory module after obtaining Awaiting Overhaul equipment Type, remote signalling, electric connecting relation information etc., read Rule Information from rule module, can be with after the processing by transporting module Determine the corresponding safety measure information of Awaiting Overhaul equipment.
Figure 14 is a kind of schematic diagram of system for obtaining safety measure information according to an embodiment of the present invention, such as Figure 14 institute Show, detection device, is also used to determine the peace of the maintenance mark and safety measure equipment of Awaiting Overhaul equipment according to safety measure information Full mark, wherein safety measure equipment includes the first grounding apparatus and the first disjunction equipment;System further include: display terminal 142, it is connected with detection device, for showing Awaiting Overhaul equipment and safety measure equipment according to maintenance mark and security identifier.
Optionally, display terminal may include: display, smart phone, PAD etc..
The above embodiment of the present invention, repair apparatus are connected with display terminal 122, pass through 2D graphical display circle by display terminal Face and 3D graphic display interface treat repair apparatus, safety measure equipment carries out differentiation and shows.
Optionally, in 2D graphic display interface, Awaiting Overhaul equipment, safety can be distinguished by way of colour-difference alienation Measure equipment and other equipment, such as: Awaiting Overhaul equipment can show that the equipment that safety measure is included can be aobvious with blue with yellow Show, with currently practical status display color, (running equipment is red to other equipment, outaged equipment is green, stand-by equipment is ash Color).
Optionally, in 2D graphic display interface, Awaiting Overhaul equipment, safety can be distinguished by way of figure layer differentiation Measure equipment, other equipment, such as: clicking Awaiting Overhaul mechanical floor, all Awaiting Overhaul equipment light tones are shown or visual, remaining equipment Gray is not visible;When clicking safety measure mechanical floor, effect is identical.
Optionally, in 2D graphic display interface, can by way of Graphics overlay differentiation, distinguish Awaiting Overhaul equipment, Safety measure equipment, other equipment, such as: Awaiting Overhaul equipment, the icon of superposition selection thereon, or the icon similar to maintenance mark The icon similar to quiescing is then superimposed Deng, safety measure equipment.
Optionally, it in 3D graphic display interface, based on the threedimensional model of Awaiting Overhaul equipment, is arrived with Awaiting Overhaul equipment Safety measure equipment is boundary, forms the three-dimensional space that a yellow line sketches the contours, and using whole region as check man Make region.
As a kind of optional embodiment, system further include: transmission device is connected with detection device, for arranging safety It applies information and is transmitted to operating terminal;Operating terminal, for generating operational order according to safety measure information, wherein operational order For controlling the operation that unblocks of lockset.
Figure 15 is a kind of schematic diagram of system for obtaining safety measure information according to an embodiment of the present invention, such as Figure 15 institute Show, further includes: transmission device 1501, operating terminal 1503, lockset 1505 etc., detection device can convert safety measure information Operating terminal is transmitted to by transmission device as operational order, and by operational order, by operating terminal according to operational order pair Intelligent lock carries out the operation that unblocks.
Optionally, operating terminal can be computer key, be also possible to the combination of smart phone/PAD and unlocking device.
Figure 16 is a kind of schematic diagram of system for obtaining safety measure information according to an embodiment of the present invention, such as Figure 16 institute Show, further includes: ticket module 1602 is connected with detection device, for generating the work of Awaiting Overhaul equipment according to safety measure information Make ticket, operation order and dangerous point Control Measure list.
As a kind of optional embodiment, ticket module includes: work single module, for according to safety measure information, life At work ticket;Operation order module, for generating operation order according to safety measure information and operation information, wherein operation information by Repair apparatus determines that, for indicating that the operation of the first grounding apparatus and the first disjunction equipment executes sequence, Awaiting Overhaul equipment is also used According to the status information of the first grounding apparatus and the status information of the first disjunction equipment, operation information is determined;Dangerous point is pre- Anti- control measure single module generates danger for obtaining the corresponding dangerous point information of safety measure information, and according to dangerous point information Danger point Control Measure list.
Optionally, safety measure information can be used as work ticket, dangerous point is prevented and the tickets systems such as control measure ticket, operation order The input data source of system or module can carry out information exchange, file by text mode between ticket module and repair apparatus Name can be * .xml, * .json etc..
It should be noted that safety measure information of the repair apparatus to ticket module transfer, not only comprising generating operation order Required equipment item, such as the first disjunction equipment, the first grounding apparatus also include the first disjunction equipment, the first grounding apparatus Operation execute sequence.
Optionally, safety measure information can be passed through preset format mould in workpiece ticket module by work ticket module Plate automatically generates as work ticket needed for user job.
Optionally, safety measure information can be passed through format mould preset in operation order module by operation order module In the operation order that plate is automatically generated as operation order needed for user job, and generated except safety measure equipment needed for operation with It outside, further include that the operation of safety measure equipment executes sequence, wherein safety measure equipment is arranged according to necessary sequence is operated Column.
Optionally, safety measure information can be passed through dangerous point precautionary measures single mode by dangerous point precautionary measures single module Preset format module in block automatically generates as precautionary measures list in dangerous point needed for user job.
The serial number of the above embodiments of the invention is only for description, does not represent the advantages or disadvantages of the embodiments.
In the above embodiment of the invention, it all emphasizes particularly on different fields to the description of each embodiment, does not have in some embodiment The part of detailed description, reference can be made to the related descriptions of other embodiments.
In several embodiments provided herein, it should be understood that disclosed technology contents can pass through others Mode is realized.Wherein, the apparatus embodiments described above are merely exemplary, such as the division of the unit, Ke Yiwei A kind of logical function partition, there may be another division manner in actual implementation, for example, multiple units or components can combine or Person is desirably integrated into another system, or some features can be ignored or not executed.Another point, shown or discussed is mutual Between coupling, direct-coupling or communication connection can be through some interfaces, the INDIRECT COUPLING or communication link of unit or module It connects, can be electrical or other forms.
The unit as illustrated by the separation member may or may not be physically separated, aobvious as unit The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple On unit.It can some or all of the units may be selected to achieve the purpose of the solution of this embodiment according to the actual needs.
It, can also be in addition, the functional units in various embodiments of the present invention may be integrated into one processing unit It is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated list Member both can take the form of hardware realization, can also realize in the form of software functional units.
If the integrated unit is realized in the form of SFU software functional unit and sells or use as independent product When, it can store in a computer readable storage medium.Based on this understanding, technical solution of the present invention is substantially The all or part of the part that contributes to existing technology or the technical solution can be in the form of software products in other words It embodies, which is stored in a storage medium, including some instructions are used so that a computer Equipment (can for personal computer, server or network equipment etc.) execute each embodiment the method for the present invention whole or Part steps.And storage medium above-mentioned includes: that USB flash disk, read-only memory (ROM, Read-Only Memory), arbitrary access are deposited Reservoir (RAM, Random Access Memory), mobile hard disk, magnetic or disk etc. be various to can store program code Medium.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (10)

1. a kind of service work safety measure Automatic generation of information method characterized by comprising
S1 obtains Awaiting Overhaul equipment;
Determining first grounding apparatus with the Awaiting Overhaul equipment with electric connecting relation of S2, wherein first ground connection sets It is ready for use on and provides grounding safety guarantee for service work region;
The determining first disjunction equipment with first grounding apparatus with electric connecting relation of S3, wherein first disjunction Equipment is for ensuring the service work region and other regions electrically disconnect or electrical isolation;
S4 output safety Action Message, wherein the safety measure information includes that first grounding apparatus and described first connect The status information of the status information of ground equipment or/and the first disjunction equipment and the first disjunction equipment.
2. the method according to claim 1, wherein further include:
S21 is using the Awaiting Overhaul equipment as starting point, and using isolated state equipment as boundary, searching may be electrical with the Awaiting Overhaul equipment The grounding apparatus of conducting, and it is determined as first grounding apparatus;
S31 is using first grounding apparatus as starting point, using disjunction equipment as boundary, searches electrically straight with first grounding apparatus The disjunction equipment connect in succession, and it is determined as the first disjunction equipment;
S41 exports the safety measure information, wherein the safety measure information includes: by the shape of first grounding apparatus State is all set to the information of coincidence and/or the state of the first disjunction equipment is all set to the information of quartile.
3. according to the method described in claim 2, it is characterized by further comprising:
S311 searches the second disjunction equipment with the first disjunction equipment with electrical separation according to the first disjunction equipment, The first disjunction equipment and the second disjunction equipment are merged, third disjunction equipment is determined as;
The first disjunction equipment in the safety measure information is replaced with the third disjunction equipment by S411.
4. the method according to claim 1, wherein the method is also after S4 output safety Action Message Include:
S51 generates the work ticket of the Awaiting Overhaul equipment according to the safety measure information.
5. the method according to claim 1, wherein the method is also after S4 output safety Action Message Include:
S521 determines operation letter according to the status information of first grounding apparatus and the status information of the first disjunction equipment Breath, wherein the operation information is for indicating that first grounding apparatus and the operation of the first disjunction equipment execute sequence;
S522 generates the operation order of the Awaiting Overhaul equipment according to the operation information.
6. the method according to claim 1, wherein the method is also after S4 output safety Action Message Include:
S531 determines the corresponding dangerous point information of the safety measure information;
S532 generates the dangerous point Control Measure list of the Awaiting Overhaul equipment according to the dangerous point information.
7. the method according to claim 1, wherein the method is also after S4 output safety Action Message Include:
S54 determines the safety of the maintenance mark and safety measure equipment of the Awaiting Overhaul equipment according to the safety measure information Mark, wherein the safety measure equipment includes at least first grounding apparatus and the first disjunction equipment;
According to maintenance mark and the security identifier, the Awaiting Overhaul equipment and the safety measure equipment are shown.
8. a kind of service work safety measure Automatic generation of information system characterized by comprising
Awaiting Overhaul equipment;
Detection device, for obtaining Awaiting Overhaul equipment;It is determining to have the first of electric connecting relation to connect with the Awaiting Overhaul equipment Ground equipment and the first disjunction equipment, and output safety Action Message;
Wherein, first grounding apparatus is used to provide grounding safety guarantee, the first disjunction equipment for service work region For ensuring that the service work region and other regions electrically disconnect or electrical isolation, the safety measure information include described The status information or/and the first disjunction equipment of first grounding apparatus and first grounding apparatus and first disjunction are set Standby status information.
9. system according to claim 8, which is characterized in that the detection device is also used to the Awaiting Overhaul equipment The grounding apparatus with the possible electrically conducting of the Awaiting Overhaul equipment is searched, and be determined as using isolated state equipment as boundary for starting point First grounding apparatus;Using first grounding apparatus as starting point, using disjunction equipment as boundary, search and first ground connection The disjunction equipment that equipment is electrically directly connected to, and it is determined as the first disjunction equipment;And export the safety measure information;Its In, the safety measure information includes: the state of first grounding apparatus to be all set to the information of coincidence and/or by institute The state for stating the first disjunction equipment is all set to the information of quartile.
10. system according to claim 9, which is characterized in that the detection device is also used to according to first disjunction Equipment, search with the first disjunction equipment with electrical separation the second disjunction equipment, by the first disjunction equipment with it is described Second disjunction equipment merges, and is determined as third disjunction equipment;First disjunction in the safety measure information is set It is standby to replace with the third disjunction equipment.
CN201811534519.2A 2018-12-14 2018-12-14 Service work safety measure Automatic generation of information method and system Pending CN109711567A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811534519.2A CN109711567A (en) 2018-12-14 2018-12-14 Service work safety measure Automatic generation of information method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811534519.2A CN109711567A (en) 2018-12-14 2018-12-14 Service work safety measure Automatic generation of information method and system

Publications (1)

Publication Number Publication Date
CN109711567A true CN109711567A (en) 2019-05-03

Family

ID=66256542

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811534519.2A Pending CN109711567A (en) 2018-12-14 2018-12-14 Service work safety measure Automatic generation of information method and system

Country Status (1)

Country Link
CN (1) CN109711567A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111652389A (en) * 2020-05-28 2020-09-11 广东电网有限责任公司 Distribution network primary equipment grounding maintenance layout method, device, equipment and medium
CN111680802A (en) * 2020-06-01 2020-09-18 广东电网有限责任公司 Work ticket detection method, device, equipment and storage medium
CN113673718A (en) * 2021-08-23 2021-11-19 珠海优特电力科技股份有限公司 Method and device for managing and controlling field operation safety measure execution process and storage medium
CN114220068A (en) * 2021-11-08 2022-03-22 珠海优特电力科技股份有限公司 Method, device, equipment, medium and product for determining on-off state of disconnecting link
CN115146879A (en) * 2022-09-05 2022-10-04 国网山西省电力公司超高压变电分公司 Optimization method for safety measure arrangement path of transformer substation relay protection room
WO2023098375A1 (en) * 2021-12-01 2023-06-08 珠海优特电力科技股份有限公司 Operation sheet processing method and device, storage medium, and electronic device
CN116596505A (en) * 2023-04-21 2023-08-15 国网江苏省电力有限公司南京供电分公司 Substation safety measure generation method based on multiple databases

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070168488A1 (en) * 2004-04-30 2007-07-19 Mekiki Creates Co., Ltd. Working information processing system, device, method, and computer program
CN104965437A (en) * 2015-07-03 2015-10-07 国家电网公司 Intelligent operation order generation method
CN106159759A (en) * 2016-07-13 2016-11-23 国网四川省电力公司电力科学研究院 A kind of method automatically generating secondary system of intelligent substation maintenance safety measure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070168488A1 (en) * 2004-04-30 2007-07-19 Mekiki Creates Co., Ltd. Working information processing system, device, method, and computer program
CN104965437A (en) * 2015-07-03 2015-10-07 国家电网公司 Intelligent operation order generation method
CN106159759A (en) * 2016-07-13 2016-11-23 国网四川省电力公司电力科学研究院 A kind of method automatically generating secondary system of intelligent substation maintenance safety measure

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111652389A (en) * 2020-05-28 2020-09-11 广东电网有限责任公司 Distribution network primary equipment grounding maintenance layout method, device, equipment and medium
CN111652389B (en) * 2020-05-28 2024-02-27 广东电网有限责任公司 Distribution network primary equipment grounding overhaul layout method, device, equipment and medium
CN111680802A (en) * 2020-06-01 2020-09-18 广东电网有限责任公司 Work ticket detection method, device, equipment and storage medium
CN111680802B (en) * 2020-06-01 2023-09-08 广东电网有限责任公司 Method, device, equipment and storage medium for detecting work ticket
CN113673718A (en) * 2021-08-23 2021-11-19 珠海优特电力科技股份有限公司 Method and device for managing and controlling field operation safety measure execution process and storage medium
CN113673718B (en) * 2021-08-23 2024-03-15 珠海优特电力科技股份有限公司 Method and device for controlling site operation safety measure execution process and storage medium
CN114220068A (en) * 2021-11-08 2022-03-22 珠海优特电力科技股份有限公司 Method, device, equipment, medium and product for determining on-off state of disconnecting link
CN114220068B (en) * 2021-11-08 2023-09-01 珠海优特电力科技股份有限公司 Method, device, equipment, medium and product for determining disconnecting link switching state
WO2023098375A1 (en) * 2021-12-01 2023-06-08 珠海优特电力科技股份有限公司 Operation sheet processing method and device, storage medium, and electronic device
GB2619167A (en) * 2021-12-01 2023-11-29 Zhuhai Unitech Power Tech Co Operation sheet processing method and device, storage medium, and electronic device
CN115146879A (en) * 2022-09-05 2022-10-04 国网山西省电力公司超高压变电分公司 Optimization method for safety measure arrangement path of transformer substation relay protection room
CN116596505A (en) * 2023-04-21 2023-08-15 国网江苏省电力有限公司南京供电分公司 Substation safety measure generation method based on multiple databases

Similar Documents

Publication Publication Date Title
CN109711567A (en) Service work safety measure Automatic generation of information method and system
CN108549650B (en) Intelligent substation anti-misoperation lockout logic rule source end configuration method and system
CN109634243A (en) A kind of scheduler program operating system based on intelligent robot
CN103903075B (en) Protection device constant value automatic management method based on fuzzy matching
CN107846011A (en) A kind of distribution network failure restoration methods based on main distribution Collaborative Control
CN106021203B (en) Intelligent substation anti-misoperation lockout logic graphical expression method
CN105245001B (en) A kind of event driven substation accident intelligent alarm treating method and apparatus
CN101901492A (en) Automatic generating method of electric network station wiring diagram
CN105379135B (en) The system and method diagnosed automatically in real time in power network
CN106296467B (en) A method of generating operation order
Kimura et al. Development of an expert system for estimating fault section in control center based on protective system simulation
CN104778632A (en) Intelligent decision making aiding method and system for transfer power supply
CN102957203A (en) Electrical equipment anti-misoperation method, device and system
CN106505532A (en) A kind of intelligent distributed FA fault handling methods based on main website standby
CN104331777A (en) Error-preventing management system for county level power grid dispatching operation
CN104881737A (en) Control figure billing system
CN108631298A (en) A kind of unit style distribution network restoration strategy-generating method based on load balancing distribution
Su et al. Performance evaluation of multiagent systems for navy shipboard power system restoration
CN104407577A (en) Intelligent check anti-maloperation method based on real-time trend
CN105719102A (en) Intelligentized power grid accident plan processing method
CN106292499A (en) The safe related function method and device of secondary equipment of intelligent converting station O&M operation object
CN105226642B (en) A kind of power distribution network service restoration method under transformer station's full cut-off accident
CN101510076A (en) Method for auto-generating safety describing statement of electronic operation order
CN110704700B (en) One-key sequence control equipment state intelligent simulation method based on expert knowledge rule base
CN113471865A (en) Topological analysis-based power grid anti-misoperation electrical principle judgment method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190503