CN109708001A - A kind of fuel gas sled of safe and reliable low energy consumption - Google Patents

A kind of fuel gas sled of safe and reliable low energy consumption Download PDF

Info

Publication number
CN109708001A
CN109708001A CN201910033807.8A CN201910033807A CN109708001A CN 109708001 A CN109708001 A CN 109708001A CN 201910033807 A CN201910033807 A CN 201910033807A CN 109708001 A CN109708001 A CN 109708001A
Authority
CN
China
Prior art keywords
gas
safety valve
air inlet
energy consumption
safe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910033807.8A
Other languages
Chinese (zh)
Other versions
CN109708001B (en
Inventor
张飞飞
潘良
奚勤
施汉龙
李建军
胡石磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI FIORENTINI GAS EQUIPMENT CO Ltd
Original Assignee
SHANGHAI FIORENTINI GAS EQUIPMENT CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI FIORENTINI GAS EQUIPMENT CO Ltd filed Critical SHANGHAI FIORENTINI GAS EQUIPMENT CO Ltd
Priority to CN201910033807.8A priority Critical patent/CN109708001B/en
Publication of CN109708001A publication Critical patent/CN109708001A/en
Application granted granted Critical
Publication of CN109708001B publication Critical patent/CN109708001B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Separation By Low-Temperature Treatments (AREA)

Abstract

The present invention provides a kind of fuel gas sled of safe and reliable low energy consumption, including a compressor air inlet level-one pressure regulation unit, a regeneration gas air admission unit, a gas-liquid separation and heating unit and a second voltage regulation end-filtration and metering units;The compressor air inlet level-one pressure regulation unit connects the gas-liquid separation and heating unit with the regeneration gas air admission unit, and the gas-liquid separation and heating unit connect the second voltage regulation end-filtration and metering units;The exhaust outlet of a compressor air inlet level-one pressure regulation unit connection at least compressor;The purge gass exhaust outlet of the regeneration gas air admission unit connection at least molecular sieve of a dehydrating tower.A kind of fuel gas of safe and reliable low energy consumption of the invention is prized, and has the advantages that safe and reliable, low energy consumption.

Description

A kind of fuel gas sled of safe and reliable low energy consumption
Technical field
The present invention relates to gas transmission and distribution and application fields more particularly to a kind of fuel gas of safe and reliable low energy consumption to prize.
Background technique
The major function of compressor station is gas pressurized to improve the conveying capacity of pipeline.Current natural gas transmission and distribution situation is come It sees, many compressor stations have all selected combustion drive compressor, and compressor runs the consumption mainly by natural gas to support, so needing to set The fuel gas for setting a kind of safe and reliable low energy consumption is prized to depressurize to natural gas sled to natural gas, then will be natural after decompression Air lift supplies compressor and uses.The case where cooling will cause due to natural gas decompression, while in order to be also needed to compressor combustion gas The relatively high temperature of turbine improves efficiency of combustion, needs to increase heating link.General compressor station operating cost accounts for natural gas transportation 50% or so of the total running cost of pipeline, it is urgently to be resolved that reduction compressor station energy consumption cost just becomes Long-distance Transmission Pipeline system Matter of utmost importance.Therefore right letter shoot line is always transported in a kind of design of the fuel gas of safe and reliable low energy consumption of compressor station sled process flow Working cost has a great impact.
In a kind of technical flow design of the fuel gas sled of safe and reliable low energy consumption of traditional compressor station, usual compressor station is used Fuel gas should meet requirement of the gas turbine to makings, pressure and flow, and fuel gas gas source is generally single source of the gas, be separated by filtration Gas is taken on device downstream header and bypass line of more standing, carrys out temperature degree generally all at 10 DEG C or so;Pass through heating device temperature in future Degree is promoted, and is first heated and is cooled down in pressure regulation, final to guarantee temperature required for gas turbine, needs to consume in this process Big energy is heated.
In a kind of technical flow design of the fuel gas sled of safe and reliable low energy consumption of traditional compressor station, usual voltage-regulating system Form generally use safety cut-off valve+monitoring pressure regulator valve+work pressure regulator valve, general setting two-way, master is worked as on main road and spare road Main road monitoring pressure regulator valve replaces work when road pressure regulator valve breaks down, if main road monitoring pressure regulator valve also breaks down, main road Self-operated safety valve stop valve can cut off upstream and carry out gas, automatically switch to spare road, the same main road of spare operation order, when spare When the stop valve cutting on road, the gas supply at whole station stops, and then will affect the operation of gas turbine and entire compressor station, causes Biggish economic loss.
In a kind of technical flow design of the fuel gas sled of safe and reliable low energy consumption of traditional compressor station, the safety of general export Valve is when safety cut-off valve breaks down, when being unable to normal cutoff, to carry out superelevation as last one of safety guard The protection of pressure.The setting of safety valve generally is all the way, without spare road;When safety valve need third party demarcate during, system without Safety valve, can not safeguards system safety.
In a kind of technical flow design of the fuel gas sled of safe and reliable low energy consumption of traditional compressor station, container nitrogen and steaming The blowdown of vapour purge system is that the blowdown with station is summarized.When general operation, after emptying of stopping the supple of gas or steam, with residual air blowdown, row Cleaning purging is carried out with the steam of blow valve port injection high temperature after dirt, carries out displaced air with nitrogen after purging, then with naturally Gas displacement nitrogen;There are different medium sewage draining exits uniformly to summarize for this design, and the medium of different design conditions is at work It is possible that occurring mutually going here and there, safe hidden danger is generated.
In a kind of technical flow design of the fuel gas sled of safe and reliable low energy consumption of traditional compressor station, the temperature of heater Collection point is after heater, before pressure regulation.According to the temperature drop that the pressure drop of pressure regulator valve generates, retrodict required for calculating pressure regulation valve inlet Temperature, the maximum temperature heated required for often considering according to most severe harsh operating condition in calculating process passes through temperature Degree detection instrument detection temperature is either with or without the temperature for being heated to design and wanting.This set not can guarantee final entire sled block Outlet temperature, outlet temperature can due to media components and operating parameter change and fluctuate, such as work as the practical ratio of inlet pressure When lower, the entire outlet temperature for prizing block can be excessively high, and biggish energy consumption is caused to waste.
Summary of the invention
In view of the deficiency of the prior art, the present invention provides a kind of fuel gas sled of safe and reliable low energy consumption, has Securely and reliably, the advantages of low energy consumption.
To achieve the goals above, the present invention provides a kind of fuel gas sled of safe and reliable low energy consumption, including a compressor Air inlet level-one pressure regulation unit, a regeneration gas air admission unit, a gas-liquid separation and heating unit and a second voltage regulation end-filtration and Metering units;The compressor air inlet level-one pressure regulation unit connects the gas-liquid separation and heating with the regeneration gas air admission unit Unit, the gas-liquid separation and heating unit connect the second voltage regulation end-filtration and metering units;The compressor air inlet The exhaust outlet of a level-one pressure regulation unit connection at least compressor;The molecule of a regeneration gas air admission unit connection at least dehydrating tower The purge gass exhaust outlet of sieve.
Preferably, the compressor air inlet level-one pressure regulation unit include one first air inlet branch road, one first electric heating mechanism, One first pressure regulating mechanism and one first safety valve system;The air inlet of first air inlet branch road, first electric heating Mechanism and the first pressure regulating mechanism are set in turn in first air inlet branch road, and first safety valve system is connected to The first air inlet branch between one gas exhaust piping and the first pressure regulating mechanism and the gas-liquid separation and heating unit Between road;The first pressure regulating mechanism includes two first pressure regulation branch pipes, is distinguished successively on each first pressure regulation branch pipe One first monitoring pressure regulator valve and one first work pressure regulator valve, the first monitoring pressure regulator valve and the first work pressure regulation are installed Valve is separately connected the first pressure detection device being set on a total inlet pipe;First safety valve system includes two first Safety valve branch, each first safety valve branch road are equipped with one first full flow safety valve and multiple first control valves.
Preferably, first safety valve system further includes the mechanical device of one first automatic switchover, and described first cuts automatically It changes mechanical device and connects first control valve.
Preferably, first electric heating mechanism includes one first electrical heating controller, one first electric heater, one first Temperature detector and a second temperature detector;First electric heater is installed in first air inlet branch road, and described One temperature detector is set in first air inlet branch road of the output end of first electric heater;The second temperature inspection Device is surveyed to be set in first air inlet branch road between the first pressure regulating mechanism and first safety valve system;Institute It states the first electrical heating controller and connects first electric heater, first temperature detector and second temperature detection Device.
Preferably, the gas-liquid separation and heating unit include: one first gas-liquid separator, one second electric heating mechanism and One second safety valve system;The air intake of first gas-liquid separator connects the total inlet pipe, the second electric heating machine Structure is connected between the second voltage regulation end-filtration and metering units and one first gas outlet of first gas-liquid separator; Second safety valve system is connected between the gas exhaust piping and one second gas outlet of first gas-liquid separator.
Preferably, second safety valve system includes that two second safety valve branches and one second automatically switch mechanical dress It sets, each second safety valve branch road is equipped with multiple second control valves;Described second automatically switches mechanical device connection Second control valve.
Preferably, the second voltage regulation end-filtration and metering units include two second pressure regulation branch pipes, two second gas-liquids point From device, a third safety valve system and an output pipe;The second pressure regulation branch pipe is connected to the gas-liquid separation and heating is single It is first between the output pipe;Two second gas-liquid separators are respectively arranged on the second pressure regulation branch pipe;It is described Third safety valve system is connected between the gas exhaust piping and the output pipe.
Preferably, one second monitoring pressure regulator valve is sequentially installed on the second pressure regulation branch pipe respectively and one second work is adjusted Pressure valve, and it is described second monitoring pressure regulator valve and it is described second work pressure regulator valve be located at second gas-liquid separator air intake and Between the gas-liquid separation and heating unit;The two second monitoring pressure regulator valves, which are separately connected, to be set on the output pipe One second pressure detection device;The third safety valve system includes that two third safety valve branches and a third automatically switch machinery Device, each third safety valve branch road are equipped with one second full flow safety valve and multiple third control valves;Described Three, which automatically switch mechanical device, connects the third control valve.
Preferably, second electric heating mechanism includes one second electrical heating controller, one second electric heater, a third Temperature detector and one the 4th temperature detector;Second electric heater connects described the first of first gas-liquid separator Gas outlet;The third temperature detector connects the output end of second electric heater;The 4th temperature detector setting On the output pipe between the second pressure regulation branch pipe and the third safety valve system;Second electric heating control Device connects second electric heater, the third temperature detector and the 4th temperature detector.
The present invention due to use above technical scheme, make it have it is following the utility model has the advantages that
By the use of compressor air inlet level-one pressure regulation unit and regeneration gas air admission unit, it can be achieved that respectively that temperature is higher Compressor come gas and dehydrating tower molecular sieve purge gass as the first gas source and the second gas source, can be greatly reduced plus The power of hot equipment reduces energy consumption, considerably reduces running cost.First monitoring pressure regulator valve, the first work pressure regulator valve and the The cooperation of one full flow safety valve and the second monitoring pressure regulator valve, the second work pressure regulator valve and the second full flow safety valve are matched Close, it can be achieved that when operating normally the first work pressure regulator valve and the second work pressure regulator valve operation, the first work pressure regulator valve and/or the The first monitoring pressure regulator valve and the second monitoring pressure regulator valve replace corresponding first work pressure regulator valve and the when two work pressure regulator valve failures The work of two work pressure regulator valves, and when the first monitoring pressure regulator valve and the second monitoring pressure regulator valve break down, the first full flow peace Full valve and the second full flow safety valve discharge extra gas, still ensure the supply of the gas in downstream at this time, can be true Downstream is protected not stop the supple of gas or steam.Meanwhile to be all made of double branches double for first safety valve system, the second safety valve system and third safety valve system The structure of full flow safety valve, and be each configured with the first automatic switchover machinery device, second automatically switch mechanical device and the Three automatically switch mechanical device, have a full flow safety valve can be normal when to can guarantee safety valve calibration and maintenance Operation, it is ensured that the duration of the operation of system and safety.First temperature detector is set to the output end of the first electric heater Outlet pressure regulator valve after, final downstream user may be monitored and need temperature, as control signal control the first electric heater work Make;Simultaneously in order to avoid the failure of the first temperature detector, the first temperature after causing the first electric heater and pressure regulator valve is examined The temperature for surveying the pipeline between device is excessively high, is more than design temperature, original third temperature is retained after the second electric heater, before pressure regulation Detector is spent as additional safety guard, it is ensured that the security reliability of system, while it being able to achieve biggish reduction energy consumption, The operating cost of whole system is reduced, it is with higher economical.
Detailed description of the invention
Fig. 1 is a kind of general structure schematic diagram of the fuel gas sled of safe and reliable low energy consumption of the embodiment of the present invention;
Fig. 2 is the structural representation of compressor air inlet the level-one pressure regulation unit and regeneration gas air admission unit of the embodiment of the present invention Figure;
Fig. 3 is the gas-liquid separation of the embodiment of the present invention and the structural schematic diagram of heating unit;
Fig. 4 is the second voltage regulation end-filtration of the embodiment of the present invention and the structural schematic diagram of metering units.
Specific embodiment
Below according to attached FIG. 1 to FIG. 4, presently preferred embodiments of the present invention is provided, and is described in detail, is enabled more preferable geographical Solve function of the invention, feature.
Referring to Fig. 1, a kind of fuel gas of safe and reliable low energy consumption of the embodiment of the present invention is prized, including a compressor air inlet Level-one pressure regulation unit 1, a regeneration gas air admission unit 2, a gas-liquid separation and heating unit 3 and a second voltage regulation end-filtration and meter Measure unit 4;Compressor air inlet level-one pressure regulation unit 1 and regeneration gas air admission unit 2 connect gas-liquid separation and heating unit 3, gas-liquid Separation and heating unit 3 connect second voltage regulation end-filtration and metering units 4;Compressor air inlet level-one pressure regulation unit 1 is connected to The exhaust outlet of a few compressor;The purge gass exhaust outlet of the connection of the regeneration gas air admission unit 2 at least molecular sieve of a dehydrating tower.
By the use of compressor air inlet level-one pressure regulation unit 1 and regeneration gas air admission unit 2, it can be achieved that respectively by temperature compared with High compressor carrys out the purge gass of the molecular sieve of gas and dehydrating tower as the first gas source and the second gas source, can be greatly reduced The power of heating equipment reduces energy consumption, considerably reduces running cost.
Fig. 1 and Fig. 2 are please referred to, compressor air inlet level-one pressure regulation unit 1 includes that one first air inlet branch road, 11, one first electricity adds Heat engine structure 12, a first pressure regulating mechanism 13 and one first safety valve system 14;The air inlet of first air inlet branch road 11, first Electric heating mechanism 12 and first pressure regulating mechanism 13 are set in turn in the first air inlet branch road 11, the connection of the first safety valve system 14 The first air inlet branch road 11 between a gas exhaust piping 5 and first pressure regulating mechanism 13 and gas-liquid separation and heating unit 3 it Between;First pressure regulating mechanism 13 includes two first pressure regulation branch pipes 131, is successively installed respectively on every one first pressure regulation branch pipe 131 There are one first monitoring pressure regulator valve B4 and one first work pressure regulator valve B5, the first monitoring pressure regulator valve B4 and pressure regulator valve B5 points of the first work The first pressure detection device E2 not being connected on a total inlet pipe 15;First safety valve system 14 includes two first peaces Full valve branch 141 is equipped with one first full flow safety valve C6 and multiple first control valves on every one first safety valve branch 141 C4。
First safety valve system 14 further includes the mechanical device SP1 of one first automatic switchover, and first automatically switches mechanical device SP1 the first control valve of connection C4.
First electric heating mechanism 12 includes one first electrical heating controller A61, one first electric heater A6, one first temperature Detector A62 and a second temperature detector C 2;First electric heater A6 is installed in the first air inlet branch road 11, the inspection of the first temperature It surveys in the first air inlet branch road 11 of the output end that device A62 is set to the first electric heater A6;Second temperature detector C 2 is set to In the first air inlet branch road 11 between first pressure regulating mechanism 13 and the first safety valve system 14;First electrical heating controller A61 the first electric heater of connection A6, the first temperature detector A62 and second temperature detector C 2.
Regeneration gas air admission unit 2 includes one second air inlet branch road 21 and the multiple instrument instrument for being installed on the second air inlet branch road 21 Device.
Fig. 1, Fig. 3 and Fig. 4 are please referred to, gas-liquid separation and heating unit 3 include: one first gas-liquid separator E7, one second Electric heating mechanism 31 and one second safety valve system 32;The air intake connection total inlet pipe 15 of first gas-liquid separator E7, second Electric heating mechanism 31 is connected to second voltage regulation end-filtration and metering units 4 and one first gas outlet of the first gas-liquid separator E7 Between;Second safety valve system 32 is connected between gas exhaust piping 5 and one second gas outlet of the first gas-liquid separator E7.
Second safety valve system 32 includes that two second safety valve branches 321 and one second automatically switch mechanical device SP2, often Multiple second control valve C are installed on one second safety valve branch 321;Second, which automatically switches machinery device SP2 connection second, controls Valve C processed.
Second electric heating mechanism 31 includes one second electrical heating controller F51, one second electric heater F5, a third temperature Detector F52 and one the 4th temperature detector H16;The first outlet of second electric heater F5 the first gas-liquid separator of connection E7 Mouthful;The output end of third temperature detector F52 the second electric heater of connection F5;4th temperature detector H16 is set to the second tune It presses on the output pipe 43 between branch pipe 41 and third safety valve system 42;Second the second electricity of electrical heating controller F51 connection adds Hot device F5, third temperature detector F52 and the 4th temperature detector H16.
Second voltage regulation end-filtration and metering units 4 include two second pressure regulation branch pipes 41, two second gas-liquid separator H9, one Third safety valve system 42 and an output pipe 43;Second pressure regulation branch pipe 41 is connected to gas-liquid separation and heating unit 3 and output Between pipeline 43;Two second gas-liquid separator H9 are respectively arranged on one second pressure regulation branch pipe 41;Third safety valve system 42 connects It is connected between gas exhaust piping 5 and output pipe 43.
One second monitoring pressure regulator valve H4 and one second work pressure regulator valve H6 are sequentially installed on second pressure regulation branch pipe 41 respectively, And second monitoring pressure regulator valve H4 and the second work pressure regulator valve H6 be located at the air intake of the second gas-liquid separator H9 and gas-liquid separation and Between heating unit 3;Two second monitoring pressure regulator valve H4 are separately connected the second pressure detection dress being set on output pipe 43 Set H14;Third safety valve system 42 includes two third safety valve branches 421, is equipped with one on each third safety valve branch 421 Second full flow safety valve H29 and multiple third control valve FB.
Third safety valve system 42 further includes that a third automatically switches mechanical device SP3, and third automatically switches mechanical device SP3 connection third control valve FB.
First gas-liquid separator E7 and the second gas-liquid separator H9 respectively includes one first sewage draining exit 33 and one second blowdown Mouth 34, the second sewage draining exit 34 connect a blowdown general pipeline 6.
FIG. 1 to FIG. 4, a kind of fuel gas sled of safe and reliable low energy consumption of the embodiment of the present invention are please referred to, the first monitoring is adjusted Pressure valve B4, the cooperation of the first work pressure regulator valve B5 and the first full flow safety valve C6 and the second monitoring pressure regulator valve H4, the second work Make the cooperation of pressure regulator valve H6 and the second full flow safety valve H29, it can be achieved that when operating normally the first work pressure regulator valve B5 and the First monitoring pressure regulator valve when two work pressure regulator valve H6 operations, the first work pressure regulator valve B5 and/or the second work pressure regulator valve H6 failure The monitoring of B4 and second pressure regulator valve H4 replaces the work of corresponding first work pressure regulator valve B5 and the second work pressure regulator valve H6, and when the When one monitoring pressure regulator valve B4 and the second monitoring pressure regulator valve H4 break down, the first full flow safety valve C6 and the second full flow safety Valve H29 discharges extra gas, still ensures the supply of the gas in downstream at this time, it can be ensured that do not stop the supple of gas or steam in downstream.
Meanwhile first safety valve system 14, the second safety valve system 32 and third safety valve system 42 are all made of double branches It enjoys a double blessing the structure of flow safety valve, and is each configured with the first automatic switchover machinery device SP1, second automatically switches mechanical device SP2 and third automatically switch mechanical device SP3, have a full flow safety valve when to can guarantee safety valve calibration and maintenance It can normally run, it is ensured that the duration of the operation of system and safety.
First gas-liquid separator E7 and the second gas-liquid separator H9 respectively includes one first sewage draining exit 33 and one second blowdown Mouthfuls 34, the second sewage draining exit 34 connect the structure of a blowdown general pipeline 6, it can be achieved that container nitrogen and steam purge system blowdown and field The blowdown stood separately summarizes, and avoids the abnormal mutually string of medium at work under different operating conditions, further increases The safety of system.
It, may monitoring after first temperature detector A62 is set to the outlet pressure regulator valve of the output end of the first electric heater A6 Final downstream user needs temperature, and the work of the first electric heater A6 is controlled as control signal;Simultaneously in order to avoid the first temperature It spends detector A62 to break down, the pipeline between the first temperature detector A62 after causing the first electric heater A6 and pressure regulator valve Temperature it is excessively high, be more than design temperature retain original third temperature detector F52 before pressure regulation after the second electric heater F5 As additional safety guard, it is ensured that the security reliability of system, while it being able to achieve biggish reduction energy consumption, it reduces entire The operating cost of system, it is with higher economical.
A kind of fuel gas of safe and reliable low energy consumption of the embodiment of the present invention is prized, and upstream of combustion turbine, Mei Geyi can be placed in The fuel gas sled of the safe and reliable low energy consumption of kind is corresponded with each with gas unit.
The present invention has been described in detail with reference to the accompanying drawings, those skilled in the art can be according to upper It states and bright many variations example is made to the present invention.Thus, certain details in embodiment should not constitute limitation of the invention, this Invention will be using the range that the appended claims define as protection scope of the present invention.

Claims (9)

1. a kind of fuel gas of safe and reliable low energy consumption is prized, which is characterized in that including a compressor air inlet level-one pressure regulation unit, one Regeneration gas air admission unit, a gas-liquid separation and heating unit and a second voltage regulation end-filtration and metering units;The compressor Air inlet level-one pressure regulation unit connects the gas-liquid separation and heating unit with the regeneration gas air admission unit, the gas-liquid separation and Heating unit connects the second voltage regulation end-filtration and metering units;The compressor air inlet level-one pressure regulation unit connection is at least The exhaust outlet of one compressor;The purge gass exhaust outlet of the regeneration gas air admission unit connection at least molecular sieve of a dehydrating tower.
2. a kind of fuel gas of safe and reliable low energy consumption according to claim 1 is prized, which is characterized in that the compressor into Gas level-one pressure regulation unit includes one first air inlet branch road, one first electric heating mechanism, a first pressure regulating mechanism and one first Safety valve system;The air inlet of first air inlet branch road, first electric heating mechanism and the first pressure regulating mechanism It is set in turn in first air inlet branch road, first safety valve system is connected to a gas exhaust piping and the first pressure tune It saves between first air inlet branch road between mechanism and the gas-liquid separation and heating unit;The first pressure regulating mechanism Including two first pressure regulation branch pipes, one first monitoring pressure regulator valve and one the are sequentially installed on each first pressure regulation branch pipe respectively One work pressure regulator valve, the first monitoring pressure regulator valve and the first work pressure regulator valve are separately connected and are set on a total inlet pipe A first pressure detection device;First safety valve system includes two first safety valve branches, each first safety Valve branch road is equipped with one first full flow safety valve and multiple first control valves.
3. a kind of fuel gas of safe and reliable low energy consumption according to claim 2 is prized, which is characterized in that first safety Valve system further includes the mechanical device of one first automatic switchover, and described first, which automatically switches mechanical device connection described first, controls Valve.
4. a kind of fuel gas of safe and reliable low energy consumption according to claim 3 is prized, which is characterized in that first electricity adds Heat engine structure includes one first electrical heating controller, one first electric heater, one first temperature detector and second temperature detection Device;First electric heater is installed in first air inlet branch road, and first temperature detector is set to described first In first air inlet branch road of the output end of electric heater;The second temperature detector is set to the first pressure and adjusts In first air inlet branch road between mechanism and first safety valve system;Described in the first electrical heating controller connection First electric heater, first temperature detector and the second temperature detector.
5. a kind of fuel gas of safe and reliable low energy consumption according to claim 4 is prized, which is characterized in that the gas-liquid separation And heating unit includes: one first gas-liquid separator, one second electric heating mechanism and one second safety valve system;First gas The air intake of liquid/gas separator connects the total inlet pipe, and second electric heating mechanism is connected to the second voltage regulation end-filtration And between metering units and one first gas outlet of first gas-liquid separator;Second safety valve system is connected to described Between gas exhaust piping and one second gas outlet of first gas-liquid separator.
6. a kind of fuel gas of safe and reliable low energy consumption according to claim 5 is prized, which is characterized in that second safety Valve system includes two second safety valve branches and one second automatically switches mechanical device, and each second safety valve branch road is pacified Equipped with multiple second control valves;Described second, which automatically switches mechanical device, connects second control valve.
7. a kind of fuel gas of safe and reliable low energy consumption according to claim 5 or 6 is prized, which is characterized in that the second level Pressure regulation end-filtration and metering units include two second pressure regulation branch pipes, two second gas-liquid separators, a third safety valve system and One output pipe;The second pressure regulation branch pipe is connected between the gas-liquid separation and heating unit and the output pipe;Two Second gas-liquid separator is respectively arranged on the second pressure regulation branch pipe;The third safety valve system is connected to described Between gas exhaust piping and the output pipe.
8. a kind of fuel gas of safe and reliable low energy consumption according to claim 7 is prized, which is characterized in that second pressure regulation Be sequentially installed with respectively on branch pipe one second monitoring pressure regulator valve and one second work pressure regulator valve, and it is described second monitoring pressure regulator valve and The second work pressure regulator valve is located between the air intake and the gas-liquid separation and heating unit of second gas-liquid separator; The two second monitoring pressure regulator valves are separately connected the second pressure detection device being set on the output pipe;The third Safety valve system includes that two third safety valve branches and a third automatically switch mechanical device, each third safety valve branch On one second full flow safety valve and multiple third control valves are installed;The third automatically switches mechanical device connection described the Three control valves.
9. a kind of fuel gas of safe and reliable low energy consumption according to claim 8 is prized, which is characterized in that second electricity adds Heat engine structure includes one second electrical heating controller, one second electric heater, a third temperature detector and one the 4th temperature detection Device;Second electric heater connects first gas outlet of first gas-liquid separator;The third temperature detector Connect the output end of second electric heater;4th temperature detector is set to the second pressure regulation branch pipe and described the On the output pipe between three safety valve systems;Second electrical heating controller connects second electric heater, institute State third temperature detector and the 4th temperature detector.
CN201910033807.8A 2019-01-15 2019-01-15 Safe and reliable fuel gas sled of low energy consumption Active CN109708001B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910033807.8A CN109708001B (en) 2019-01-15 2019-01-15 Safe and reliable fuel gas sled of low energy consumption

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910033807.8A CN109708001B (en) 2019-01-15 2019-01-15 Safe and reliable fuel gas sled of low energy consumption

Publications (2)

Publication Number Publication Date
CN109708001A true CN109708001A (en) 2019-05-03
CN109708001B CN109708001B (en) 2023-12-05

Family

ID=66261348

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910033807.8A Active CN109708001B (en) 2019-01-15 2019-01-15 Safe and reliable fuel gas sled of low energy consumption

Country Status (1)

Country Link
CN (1) CN109708001B (en)

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2684119Y (en) * 2004-03-17 2005-03-09 唐德中 High efficiency energy saving consumption reducing machine
CN201057357Y (en) * 2007-05-30 2008-05-07 天津市华迈燃气技术发展有限公司 Mobile liquefied natural gas gasifying and supplying plant
CN102606880A (en) * 2012-04-11 2012-07-25 重庆巨创计量设备股份有限公司 Urban emergency LNG (liquefied natural gas) supply system
CN103160353A (en) * 2013-03-29 2013-06-19 四川金科深冷设备工程有限公司 Miniature skid-mounted natural gas recovery system
CN203656576U (en) * 2013-11-22 2014-06-18 山东科瑞油气工艺设备有限公司 Pressure regulating and metering platform for fuel gas
CN104654018A (en) * 2015-02-28 2015-05-27 四川宏达石油天然气工程有限公司 Pressure-regulating and metering pry for liquefied natural gas device
CN105154159A (en) * 2015-09-23 2015-12-16 天津市振津石油天然气工程有限公司 Small-size movable type skid-mounted device and method for recycling CNG from well head gas
US20160290563A1 (en) * 2015-04-02 2016-10-06 David A. Diggins System and Method for Unloading Compressed Natural Gas
CN206093516U (en) * 2016-10-10 2017-04-12 北京京诚泽宇能源环保工程技术有限公司 Gas storage and distribution pressure regulating system
CN206279176U (en) * 2016-06-30 2017-06-27 王永锋 A kind of integrated equipment of natural gas filtering, pressure regulation, metering and waste gas recovery
CN206329917U (en) * 2016-12-06 2017-07-14 新兴能源装备股份有限公司 Double gas circuit pry regulators
US20180003342A1 (en) * 2016-06-29 2018-01-04 Thomas Kunkel All-in-One Skid Assembly
CN108980614A (en) * 2018-08-20 2018-12-11 克拉玛依市富城天然气有限责任公司 Integrated natural gas processing system is recycled in a kind of formation testing, gas testing

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2684119Y (en) * 2004-03-17 2005-03-09 唐德中 High efficiency energy saving consumption reducing machine
CN201057357Y (en) * 2007-05-30 2008-05-07 天津市华迈燃气技术发展有限公司 Mobile liquefied natural gas gasifying and supplying plant
CN102606880A (en) * 2012-04-11 2012-07-25 重庆巨创计量设备股份有限公司 Urban emergency LNG (liquefied natural gas) supply system
CN103160353A (en) * 2013-03-29 2013-06-19 四川金科深冷设备工程有限公司 Miniature skid-mounted natural gas recovery system
CN203656576U (en) * 2013-11-22 2014-06-18 山东科瑞油气工艺设备有限公司 Pressure regulating and metering platform for fuel gas
CN104654018A (en) * 2015-02-28 2015-05-27 四川宏达石油天然气工程有限公司 Pressure-regulating and metering pry for liquefied natural gas device
US20160290563A1 (en) * 2015-04-02 2016-10-06 David A. Diggins System and Method for Unloading Compressed Natural Gas
CN105154159A (en) * 2015-09-23 2015-12-16 天津市振津石油天然气工程有限公司 Small-size movable type skid-mounted device and method for recycling CNG from well head gas
US20180003342A1 (en) * 2016-06-29 2018-01-04 Thomas Kunkel All-in-One Skid Assembly
CN206279176U (en) * 2016-06-30 2017-06-27 王永锋 A kind of integrated equipment of natural gas filtering, pressure regulation, metering and waste gas recovery
CN206093516U (en) * 2016-10-10 2017-04-12 北京京诚泽宇能源环保工程技术有限公司 Gas storage and distribution pressure regulating system
CN206329917U (en) * 2016-12-06 2017-07-14 新兴能源装备股份有限公司 Double gas circuit pry regulators
CN108980614A (en) * 2018-08-20 2018-12-11 克拉玛依市富城天然气有限责任公司 Integrated natural gas processing system is recycled in a kind of formation testing, gas testing

Also Published As

Publication number Publication date
CN109708001B (en) 2023-12-05

Similar Documents

Publication Publication Date Title
CN111350595A (en) Control system of shale gas supply device at wellhead of micro gas turbine generator
CN110346511B (en) On-line detection and treatment process for synthesis gas leakage
CN113982758B (en) Gas supply system, gas supply method, and equipment equipped with turbine engine
CN110410676A (en) A kind of unattended intelligent oil-gas mixing conveying system
CN113803638A (en) Intelligent generator hydrogen cooling system and control method
RU78896U1 (en) UNIT OF FUEL GAS PREPARATION UNIT
CN208475300U (en) A kind of gas-driven generator group low-pressure heater draining system
CN114810251B (en) Division Kuang Shun control starting control system and method for gas-steam combined cycle unit
CN209484284U (en) Fuel gas sled
CN109708001A (en) A kind of fuel gas sled of safe and reliable low energy consumption
CN212031995U (en) Flash evaporation gas recovery integrated device
CN108533964A (en) A kind of more gas source feed systems and its air supply method
CN219526556U (en) BGL gasifier nitrogen gas feed system
CN220379449U (en) Natural gas pressure regulating station system
CN104132326B (en) A kind of CFB boiler emergency water compensating system without emergency water compensating case
CN207702118U (en) A kind of emergent feeder of liquefied natural gas
CN113958873B (en) Method for replacing sealing nitrogen supply system of Sorption combustion drive compressor unit
WO2013157989A1 (en) System of leakage drains for a main circulating pump assembly
CN208652139U (en) Full-automatic gas shield dam fills row's control device
CN109442382B (en) Water supply system of gas power generation boiler
CN112880919A (en) Method and device for detecting pipe side leakage of high-pressure heater of steam turbine system
CN113324256A (en) Flare gas recovery system for offshore oil production platform
RU2157717C2 (en) Plant for trapping of hydrocarbon vapors
CN214840753U (en) Two or many thermal power generating unit condensate water contact systems
CN214141664U (en) Black water flash system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant