CN109707446A - Tunnel center gutter template component, gutter structure and its construction method - Google Patents
Tunnel center gutter template component, gutter structure and its construction method Download PDFInfo
- Publication number
- CN109707446A CN109707446A CN201910092230.8A CN201910092230A CN109707446A CN 109707446 A CN109707446 A CN 109707446A CN 201910092230 A CN201910092230 A CN 201910092230A CN 109707446 A CN109707446 A CN 109707446A
- Authority
- CN
- China
- Prior art keywords
- gutter
- space
- tunnel
- template
- principal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 53
- 238000005266 casting Methods 0.000 claims abstract description 36
- 239000000758 substrate Substances 0.000 claims abstract description 31
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 12
- 230000015572 biosynthetic process Effects 0.000 claims description 9
- 238000000926 separation method Methods 0.000 claims 1
- 239000000463 material Substances 0.000 abstract description 9
- 238000000034 method Methods 0.000 description 6
- 229910000831 Steel Inorganic materials 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 230000007812 deficiency Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000009833 condensation Methods 0.000 description 1
- 230000005494 condensation Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 230000008676 import Effects 0.000 description 1
- 230000008595 infiltration Effects 0.000 description 1
- 238000001764 infiltration Methods 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000003643 water by type Substances 0.000 description 1
- 238000004078 waterproofing Methods 0.000 description 1
Abstract
The present invention relates to a kind of tunnel center gutter template component, gutter structure and its construction methods, it include: that the exterior sheathing being placed in tunnel substrate casting space to form gutter construction space to pour, and is formed by the side spaces that gutter construction space includes principal space and is connected with principal space;The inner template being placed in the principal space separates principal space and side spaces by the inner template, in pouring to form main structure in principal space, gutter is formed inside the main structure, which can pour to form permeable structure;And it is placed in the preset diversion pipe in main body casting space, to form the drainage hole of connection permeable structure and gutter.Bill of materials one is poured present invention efficiently solves gutter and gutter interface is easy the problem of leaking, so that part made of the different materials of gutter has different performances, the water of interface leakage is imported in gutter by permeable structure, meets the tunnel drainage requirement of complex condition.
Description
Technical field
The present invention relates to constructing tunnel field, refer in particular to a kind of tunnel center gutter template component, gutter structure and its
Construction method.
Background technique
Since Tunnel Engineering is built in subterranean strata mostly, entire tunnel structure be likely to be at underground water encirclement it
In, and underground water is all-pervasive, often because each link such as deficiency, design and construction for early period address explore work less than
Position causes tunnel waterproof and water drainage system to generate defect, and so as to cause tunnel, there is a phenomenon where percolating waters, and percolating water has become shadow
One of the main problem for ringing highway in China tunnel is an important factor for influencing vcehicular tunnel normal operation and service life.
Whole tunnel is longitudinally run through in vcehicular tunnel center gutter, be whole tunnel catchment, the key link of drainage system,
Infiltration except tunnel structure in stratum, it is blind by transverse drainage by the catchmenting of circle draining blind pipe, the convergence of longitudinal drainage pipe
Pipe is final to import center gutter, and is discharged into drainage system outside tunnel by center gutter.
Current gutter mostly uses greatly a template pouring molding, and this method can only use a kind of material to gutter
Ditch body is poured, so that the performance that gutter has is more single, and when transverse drainage blind pipe is drained to center gutter,
Interface might have leakage, and currently used technology is to carry out water-proofing treatment in interface, but the durability degree of waterproof construction is not
Height, what the water leaked after waterproof construction failure can not be successfully is discharged into Central drain.
Summary of the invention
It is an object of the invention to overcome the deficiencies of existing technologies, a kind of tunnel center gutter template component, row are provided
Ditch structure and its construction method solve the problems, such as that gutter interface is easy leakage, to arrange using the method for placement layer by layer
The ditch body in ditch is made of two kinds of different materials, so that part made of the different materials of gutter has different performances, is met
The tunnel drainage requirement of complex condition, promotes integral construction efficiency, and meet the high construction requirement of short time limit, quality.
Realizing the technical solution of above-mentioned purpose is:
The present invention provides tunnel center gutter template components, comprising:
The exterior sheathing being placed in tunnel substrate casting space, two sides are equipped with side portion structure, by the exterior sheathing in tunnel base
Gutter construction space is formed on plate, and the gutter construction space of the formation includes principal space and is connected with the principal space
Logical side spaces;
The inner template being placed in principal space, the inner template separate principal space and side spaces, and in principal space
It forms main body casting space to form main structure to pour, forms gutter inside the main structure, which can pour
Form permeable structure;And
It is placed in the preset diversion pipe of in main body casting space and respective sides space setting, the preset diversion pipe and inner template
Connection, by the preset diversion pipe in the drainage hole for forming connection permeable structure and gutter in main structure.
The present invention uses tunnel center gutter template component pair, pours sky by the way that exterior sheathing is first placed in tunnel substrate
In and poured so that gutter identical with an exterior sheathing profile construction space is formed on tunnel inverted arch, and then at this
Inner template is placed in the construction space of gutter with the principal space and side spaces of compartment drainage ditch construction space, thus in main body
Main body casting space is formed in space, by the preset diversion pipe in position in main body casting space respective sides space and to main body
Casting space is poured, to obtain the main structure that side has drainage hole, and then counter-lateral quadrents space pour and shape
At permeable structure, drainage hole is connected to permeable structure and main structure, and the method using placement layer by layer is to making gutter difference material
Part made of expecting has different performances, and transverse drain ditch and the water of the interface leakage in center gutter flow into center draining
It is imported in the gutter of center in the permeable structure of ditch two sides and by drainage hole, to solve the problems, such as that gutter interface leaks.
Tunnel center of the present invention gutter template component further improvement lies in that, which includes two be oppositely arranged
A first block piece and drawknot are connected between two the first block pieces and spaced first screw rod, by adjusting the first screw rod
Length to change the distance between two first block pieces.
Tunnel center of the present invention gutter template component further improvement lies in that, which includes:
The first transverse slat being placed in tunnel substrate casting space;
It is vertically connected at the starting stave of end of first transverse slat far from another first block piece, the starting stave and first
The corresponding end of bar is fixedly connected;
It is fixedly arranged on first enclosing of the starting stave far from another first block piece side, the section of first enclosing is at right angles terraced
The upper plane of shape, first enclosing is concordant with the top of starting stave;And
It is fixedly arranged on first hanging ring of the starting stave far from the first transverse slat end.
Tunnel center of the present invention gutter template component further improvement lies in that, which includes two be oppositely arranged
A second stopper and drawknot are connected between two second stoppers and spaced second screw rod, by adjusting the second screw rod
Length to change the distance between two second stoppers.
Tunnel center of the present invention gutter template component further improvement lies in that, which includes:
The second transverse slat being placed in the construction space of gutter;
It is vertically connected at the second riser of end of second transverse slat far from another second stopper, second riser and second
The corresponding end of bar is fixedly connected;
It is fixedly arranged at the top of the second riser and is located at second enclosing of second riser far from another second stopper side, this second
The rectangular in cross-section of enclosing, the width of second enclosing are greater than the thickness of the second riser;And
It is fixedly arranged on the second hanging ring of end of second riser far from the second transverse slat.
The present invention provides the gutter structures that a kind of tunnel center gutter template component is formed, comprising:
On tunnel substrate and it is formed in the main structure in principal space, which is in " Qian " font, and interior
Portion is formed with gutter;
Positioned at main structure two sides and it is formed in the permeable structure in side spaces, the permeable structure is in a rectangular trapezoid, and
The upper plane length of the permeable structure is greater than lower plane length;
Drainage hole set on main structure side, the drainage hole are connected to permeable structure and gutter;And
The cover board being covered on gutter.
Tunnel center of the present invention gutter template component formed gutter structure further improvement lies in that, main structure
Part at the top of two sidewalls close to gutter to lower recess and forms the support face placed for cover board, and the support face and main body knot
The distance between structure top side wall is equal to the thickness of cover board;
Road structure is equipped on permeable structure, and the top of the road structure is concordant with the top of main structure, it should
The thickness of road structure is equal to the thickness of cover board.
Tunnel center of the present invention gutter template component formed gutter structure further improvement lies in that, the permeable knot
Structure is formed by sand-free coarse porous concrete concreting, which is formed by C20 concreting, which is mixed by C25 element
Solidifying soil pours.
The present invention provides a kind of construction methods of tunnel center gutter template component, include the following steps:
S11., exterior sheathing is provided, exterior sheathing is placed in tunnel substrate casting space and tunnel substrate casting space is carried out
It pours to form tunnel substrate, and is formed with the gutter construction space to match with exterior sheathing, the draining on the tunnel substrate
Ditch construction space includes principal space and the side spaces that are connected with principal space;
S12. exterior sheathing is removed, and is put into frame body in principal space, is erect between the side spaces and principal space
Demarcation plate is to separate side spaces and principal space, and the demarcation plate is connected close to the side of principal space with one end of diversion pipe
It connects;
S13., inner template is provided, inner template is placed on frame body, and the other end of the side of the inner template and diversion pipe
It offsets, and in formation main body casting space in principal space and is poured to form main structure, the inside of the main structure
Gutter is formed, and the main structure side corresponds to the drainage hole of position formation the communicated drainage ditch and side spaces of diversion pipe;
S14. demarcation plate and diversion pipe are removed from side spaces, so counter-lateral quadrents space poured it is permeable to be formed
Structure, and inner template is removed.
The construction method of tunnel center of the present invention gutter template component further improvement lies in that, the main structure two sides
Part at the top of wall close to gutter to lower recess and forms the support face placed for cover board, and cover board is placed on support face;
The laying depth road structure identical with cover sheet thickness on permeable structure, and the top of the road structure and main body
The top of structure is concordant.
Detailed description of the invention
Fig. 1 is the gutter part of tunnel center of the present invention gutter template component, gutter structure and its construction method
Structural schematic diagram.
Fig. 2 is the exterior sheathing part of tunnel center of the present invention gutter template component, gutter structure and its construction method
Front view.
Fig. 3 is the exterior sheathing part of tunnel center of the present invention gutter template component, gutter structure and its construction method
Top view.
Fig. 4 is the inner template part of tunnel center of the present invention gutter template component, gutter structure and its construction method
Front view.
Fig. 5 is the inner template part of tunnel center of the present invention gutter template component, gutter structure and its construction method
Top view.
Fig. 6 is that the gutter of tunnel center of the present invention gutter template component, gutter structure and its construction method is constructed
Space segment structural schematic diagram.
Fig. 7 is the process for using figure of tunnel center of the present invention gutter template component, gutter structure and its construction method.
Specific embodiment
The present invention will be further explained below with reference to the attached drawings and specific examples.
Refering to fig. 1, the present invention provides a kind of tunnel center gutter template components, by the way that exterior sheathing is first placed in tunnel
It in road substrate casting space and is poured, so that it is empty to form a gutter construction identical with exterior sheathing profile on tunnel inverted arch
Between, and then inner template is placed in the gutter construction space with the principal space of compartment drainage ditch construction space and side sky
Between, so that main body casting space is formed in principal space, it is preset by the position in main body casting space respective sides space
Diversion pipe simultaneously pours main body casting space, to obtain the main structure that side has drainage hole, and then counter-lateral quadrents are empty
Between poured and formed permeable structure, drainage hole is connected to permeable structure and main structure, and the method using placement layer by layer is to making
Obtaining part made of the different materials of gutter has different performances, transverse drain ditch and the interface leakage in center gutter
Water is flowed into the permeable structure of center gutter two sides and is imported in the gutter of center by drainage hole, to solve gutter interface
The problem of place's leakage.Tunnel center of the present invention gutter template component is illustrated with reference to the accompanying drawing.
Refering to fig. 1, Fig. 1 is the row of tunnel center of the present invention gutter template component, gutter structure and its construction method
The structural schematic diagram of ditch part.Below with reference to Fig. 1, tunnel center of the present invention gutter template component is illustrated.
As shown in figures 1 to 6, tunnel center of the present invention gutter template component, comprising:
The exterior sheathing 11 being placed in tunnel substrate casting space, two sides are equipped with side portion structure, by the exterior sheathing 11 in tunnel
Gutter construction space 211 is formed on road substrate, and the gutter construction space 211 being formed by includes 2111 He of principal space
The side spaces 2112 being connected with principal space 2111;
The inner template 12 being placed in principal space 2111, the inner template 12 separate principal space 2111 and side spaces
2112, and main structure 2113 is formed to pour in forming main body casting space in principal space 2111, the main structure 2113
Inside forms gutter 212, which can pour to form permeable structure 2116;And
Be placed in the preset diversion pipe that in main body casting space and respective sides space 2112 is arranged, the preset diversion pipe with it is interior
Template 12 connects, by preset diversion pipe in the row for forming connection permeable structure 2116 and gutter 212 in main structure 2113
Water hole 2114.
As a better embodiment of the invention, as shown in connection with fig. 2, which includes be oppositely arranged two the
One block piece 111 and drawknot are connected to the first screw rod 112 between two the first block pieces 111, by adjusting the first screw rod 112
Length is to change the distance between two first block pieces 111.
Further, as shown in connection with fig. 3, which includes:
The first transverse slat 1111 being placed in tunnel substrate casting space;
It is vertically connected at the starting stave 1112 of end of first transverse slat 1111 far from another first block piece 111;And
It is fixedly arranged on first enclosing 1113 of the starting stave 1112 far from another first block piece, 111 side, first enclosing
1113 section is in a rectangular trapezoid, and the upper plane length of first enclosing 1113 is greater than the lower plane length of the first enclosing 1113,
And first enclosing 1113 upper plane it is concordant with the top of starting stave 1112.
Specifically, the end of first screw rod 112 be fixedly connected on two opposite the first block pieces 111 respectively it is first perpendicular
On plate 1112, which is spaced along the first block piece 111 is arranged, and the starting stave 1112 is far from the first transverse slat 1111
End is additionally provided with the first hanging ring 1114.
Preferably, first block piece 111 is made using angle steel and channel steel.
As another better embodiment of the invention, as shown in connection with fig. 4, which includes two be oppositely arranged
Second stopper 121 and drawknot are connected to the second screw rod 122 between two second stoppers 121, by adjusting the second screw rod 122
Length to change the distance between two second stoppers 121.
Further, as shown in connection with fig. 5, which includes:
The second transverse slat 1211 being placed in gutter construction space 211;
It is vertically connected at the second riser 1212 of end of second transverse slat 1211 far from another second stopper 121;And
It is fixedly arranged on 1212 top of the second riser and is located at second of the second riser 1212 far from another 121 side of second stopper
Enclosing 1213, the rectangular in cross-section of second enclosing 1213, and the width of second enclosing 1213 are greater than the second riser 1212
Thickness.
Specifically, the end of second screw rod 122 be fixedly connected on two second stoppers 121 being oppositely arranged it is second perpendicular
Plate 1212, which is spaced along second stopper 121 is arranged, end of second riser 1212 far from the second transverse slat 1211
Portion is additionally provided with the second hanging ring 1214.
Preferably, the second stopper 121 is made of angle steel and channel steel.
As shown in Figure 1, the gutter structure that tunnel center of the present invention gutter template component is formed, comprising:
In tunnel inverted arch and the main structure 2113 that is formed in principal space 2111, the main structure 2113 are in
" Qian " font, and inside is formed with gutter 212;
Positioned at 2113 two sides of main structure and the permeable structure 2116 that is formed in side spaces 2112, the permeable knot
Structure 2116 is in a rectangular trapezoid, and the upper plane length of the permeable structure 2116 is greater than lower plane length;
Drainage hole 2114 in main structure 2113, the drainage hole 2114 are connected to permeable structure 2116 and gutter
212;And
The cover board 213 being covered on gutter 212.
As a better embodiment of the invention, as shown in connection with fig. 1, close to row at the top of 2113 two sidewalls of main structure
The part in ditch 212 is to lower recess and forms the support face placed for cover board 213, and the support face and 2113 side wall of main structure
The distance between top is equal to the thickness of cover board 213;
Road structure 2115, and the top of the road structure 2115 and main structure are equipped on the permeable structure 2116
2113 top is concordant, and the thickness of the road structure 2115 is equal to the thickness of cover board 213.
Specifically, the permeable structure 2116 is formed by sand-free coarse porous concrete concreting, road structure 2115 is by C20 concrete
It pours, which is poured by C25 plain concrete.
A specific embodiment of the invention is as follows:
Exterior sheathing 11 is placed on the center line of tunnel substrate casting space, and exterior sheathing 11 is poured, so that tunnel
Gutter identical with 11 cross sectional shape of exterior sheathing construction space 211 is formed on the inverted arch in road;
The length of the first screw rod 112 is adjusted to reduce opposite the distance between two the first block pieces 111, thus by external mold
Plate 11 in gutter construction space 211 by taking out;
After the condensation of gutter construction space 211, in gutter, 211 inside bottom of construction space is put into frame body, the frame body
Height be equal to 211 bottom of 212 bottom of gutter and gutter construction space between designed distance, inner template 12 is placed in
On the frame body, and side spaces 2112 close to principal space 2111 position place demarcation plate with separate principal space 2111 with
Side spaces 2112, concrete flows into side spaces 2112 when preventing from pouring inner template;
The demarcation plate is fixedly welded with pvc pipe close to the side of inner template 12, which, which dips down, is tiltedly fixed on template
On;
The casting concrete into the main body casting space between demarcation plate, gutter construction space 211 and inner template 12, with
It forms main structure 2113 and forms gutter 212 identical with 12 shape of inner template, and main body inside main structure 2113
There are the drainage holes 2114 tilted down that pvc pipe is formed in structure 2113, and it is opposite to reduce to adjust the length of the second screw rod 122
The distance between two second stoppers 121, thus by inner template 12 by being taken out in gutter 212, and by demarcation plate from side
It is taken out in space 2112, related extraction pvc pipe;
In label height on the side wall of side spaces 2112, and counter-lateral quadrents space 2112 pours the height to the label with shape
At permeable structure, so that there are identical as 213 thickness of cover board and for formation road structure 2115 on the top of side spaces 2112
Space, can be used end-enclosed during pouring permeable structure 2116 and the rod piece to match with drainage hole 2114 is plugged in
To avoid the clogging drainage hole 2114 of material for pouring side spaces 2112 in drainage hole 2114;
Pavement concrete is poured within this space and forms road structure 2115, completes pouring to entire center gutter 21
It builds, finally the upper cover plate 213;
Underground water is delivered at center gutter 21 by transverse drain ditch, and transverse drain ditch is connected with center gutter 21
The case where position connect is likely to occur leak, the water flow of leakage flow into the sand-free coarse porous concrete concrete in side spaces 2112, in turn
It is imported in center gutter 21 by drainage hole 2114.
As shown in fig. 7, the construction method of tunnel center of the present invention gutter template component, includes the following steps:
It executes step S11. and exterior sheathing 11 is provided, exterior sheathing 11 is placed on the center line of tunnel substrate casting space,
Tunnel substrate casting space is poured to form tunnel substrate, and is formed on the tunnel substrate and matches with exterior sheathing 11
Gutter construction space 211, which includes principal space 2111 and being connected with principal space 2111
Side spaces 2112;Then step S12 is executed
It executes step S12. and removes exterior sheathing 11, and be put into frame body in the principal space 2111, in side spaces 2112
Demarcation plate is erect between principal space 2111 to separate side spaces 2112 and principal space 2111, and the demarcation plate is close to main
The side in body space 2111 is connected with one end of diversion pipe;Then step S13 is executed
Execute step S13. provide inner template 12, inner template 12 is placed on frame body, and the side of the inner template 12 with
The other end of diversion pipe offsets, and in formation main body casting space in principal space 2111 and is poured to form main structure
2113, the inside of the main structure 2113 forms gutter 212, and 2113 side of main structure corresponds to the position shape of diversion pipe
At the drainage hole 2114 of communicated drainage ditch 212 and side spaces 2112;Then step S14 is executed
Execute step S14. demarcation plate and diversion pipe are removed from side spaces 2112, and then counter-lateral quadrents space 2112 into
Row is poured to form permeable structure 2116, and inner template 12 is removed.
Further, the part at the top of 2113 two sidewalls of main structure close to gutter 212 to lower recess and forms confession
The support face that cover board 213 is placed, cover board 213 is placed on the support face;
The laying depth road structure 2115 identical with 213 thickness of cover board on permeable structure 2116, and the road structure
2115 top is concordant with the top of main structure 2113.
Concrete construction method of the invention is as follows:
Exterior sheathing 11 is placed in tunnel substrate casting space by the first hanging ring 1114 hung on exterior sheathing 11
On heart line, to the tunnel, substrate casting space is poured, and is formed with forming the center of tunnel substrate and the tunnel substrate
Gutter construction space 211, the gutter construction space 211 have in rectangle principal space 2111 and with the first enclosing 1113
The side spaces 2112 to match;
Frame body is placed in the bottom of principal space 2111, and erects demarcation plate on the lower plane of side spaces 2112, it should
Demarcation plate is welded with several diversion pipes tilted down close to the side of main structure 2111;
Inner template 12 is placed on frame body by the second hanging ring 1214 hung in inner template 12, and the side of inner template 12
Wall offsets with diversion pipe, to form main body casting space, pours to main body casting space, to form the master for being in " Qian " font
Body structure 2113, and the side of main structure 2113 has the drainage hole 2114 tilted down;
Diversion pipe on demarcation plate and demarcation plate is extracted out from side spaces 2112,2112 make absolute altitude in side spaces
So that absolute altitude is equal to the thickness of cover board 213 to the distance of tunnel substrate, side spaces 2112 are poured to absolute altitude using seepy material
Position removes inner template 12 after forming permeable structure 2116, in 212 upper cover upper cover plate 213 of gutter;
Inner template 12 can also be first removed, is filled in using the closed rod piece to match with diversion pipe from 212 side of gutter
Enter in drainage hole 2114, and then counter-lateral quadrents space 2112 is poured to elevation location, is formed rod piece after permeable structure 2116 from row
212 side of ditch is taken out, in 212 upper cover upper cover plate 213 of gutter;
Road structure 2115 is laid on permeable structure 2116, so that road structure 2115 is concordant with cover board 213, completion pair
Center gutter 21 pours.
The present invention has been described in detail with reference to the accompanying drawings, those skilled in the art can be according to upper
It states and bright many variations example is made to the present invention.Thus, certain details in embodiment should not constitute limitation of the invention, this
Invention will be using the range that the appended claims define as protection scope of the present invention.
Claims (10)
1. a kind of tunnel center gutter template component characterized by comprising
The exterior sheathing being placed in tunnel substrate casting space, two sides are equipped with side portion structure, by the exterior sheathing in tunnel substrate
Upper formation gutter construction space, and be formed by gutter construction space and include principal space and be connected with principal space
Side spaces;
The inner template being placed in the principal space, the inner template separation principal space and the side spaces, and in
Main body casting space is formed in the principal space to form main structure to pour, and gutter is formed inside the main structure,
The side spaces can pour to form permeable structure;And
Be placed in the main body casting space and the preset diversion pipe of the corresponding side spaces setting, the preset diversion pipe with
The inner template connection is connected to the permeable structure and the row in formation in the main structure by the preset diversion pipe
The drainage hole in ditch.
2. tunnel center as described in claim 1 gutter template component, which is characterized in that the exterior sheathing includes opposite sets
Two the first block pieces and drawknot set are connected between two first block pieces and spaced first screw rod, pass through tune
The length of first screw rod is saved to change the distance between two described first block pieces.
3. tunnel center as claimed in claim 2 gutter template component, which is characterized in that first block piece includes:
The first transverse slat being placed in the tunnel substrate casting space;
Be vertically connected at the starting stave of end of first transverse slat far from another first block piece, the starting stave with it is described
The corresponding end of first screw rod is fixedly connected;
It is fixedly arranged on first enclosing of the starting stave far from another first block piece side, the section of first enclosing is rectangular
Trapezoidal, the upper plane length of first enclosing is greater than the lower plane length of first enclosing, and first enclosing is upper
Plane is concordant with the top of the starting stave;And
It is fixedly arranged on first hanging ring of the starting stave far from first transverse slat end.
4. tunnel center as described in claim 1 gutter template component, which is characterized in that the inner template includes opposite sets
Two second stoppers and drawknot set are connected between two second stoppers and spaced second screw rod, pass through tune
The length of second screw rod is saved to change the distance between two described second stoppers.
5. tunnel center as claimed in claim 4 gutter template component, which is characterized in that the second stopper includes:
The second transverse slat being placed in the gutter construction space;
Be vertically connected at the second riser of the end of second transverse slat far from another second stopper, second riser with it is described
The corresponding end of second screw rod is fixedly connected;
It is fixedly arranged at the top of second riser and is located at second enclosing of second riser far from another second stopper side, institute
The rectangular in cross-section of the second enclosing is stated, the width of second enclosing is greater than the thickness of second riser;And
It is fixedly arranged on the second hanging ring of end of second riser far from second transverse slat.
6. a kind of gutter structure formed using tunnel center as described in claim 1 gutter template component, feature
It is, comprising:
On the tunnel substrate and the main structure that is formed in the principal space, the main structure are in " Qian " word
Shape, and inside is formed with gutter;
Positioned at the main structure two sides and the permeable structure that is formed in the side spaces, the permeable structure is at right angles terraced
Shape, and the upper plane length of the permeable structure is greater than lower plane length;
Drainage hole set on the main structure side, the drainage hole are connected to the permeable structure and the gutter;And
The cover board being covered on the gutter.
7. the gutter structure that tunnel center as claimed in claim 6 gutter template component is formed, which is characterized in that
Part at the top of the main structure two sidewalls close to the gutter to lower recess and is formed for cover board placement
Support face, and the distance between the support face and the main structure top side wall are equal to the thickness of the cover board;
Road structure, and the top horizontal at the top of the road structure and the main structure are equipped on the permeable structure
Together, the thickness of the road structure is equal to the thickness of the cover board.
8. the gutter structure that tunnel center as claimed in claim 7 gutter template component is formed, which is characterized in that described
Permeable structure is formed by sand-free coarse porous concrete concreting, and the road structure is formed by C20 concreting, the main body knot
Structure is poured by C25 plain concrete.
9. a kind of construction method of tunnel center as described in claim 1 gutter template component, which is characterized in that including such as
Lower step:
S11., exterior sheathing is provided, the exterior sheathing is placed on tunnel substrate casting space and sky is poured to the tunnel substrate
Between poured to form tunnel substrate, and be formed with the gutter to match with the exterior sheathing on the tunnel substrate and construct
Space, the gutter construction space include principal space and the side spaces that are connected with principal space;
S12. the exterior sheathing is removed, and is put into frame body in the principal space, it is empty in the side spaces and the main body
Between between erect demarcation plate to separate the side spaces and the principal space, and the demarcation plate is close to the principal space
Side be connected with one end of the diversion pipe;
S13., inner template is provided, the inner template is placed on the frame body, and the side of the inner template and the water conservancy diversion
The other end of pipe offsets, and in formation main body casting space in the principal space and is poured to form main structure, institute
The inside for stating main structure forms gutter, and the main structure side corresponds to described in the position formation connection of the diversion pipe
The drainage hole in gutter and the side spaces;
S14. the demarcation plate and the diversion pipe are removed from the side spaces, so counter-lateral quadrents space poured with
Permeable structure is formed, and the inner template is removed.
10. the construction method of tunnel center as claimed in claim 9 gutter template component, which is characterized in that the main body
Part at the top of structure two sidewalls close to the gutter to lower recess and forms the support face placed for cover board, by the cover board
It is placed on the support face;
The laying depth road structure identical with the cover sheet thickness on the permeable structure, and the top of the road structure
It is concordant with the top of the main structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910092230.8A CN109707446A (en) | 2019-01-30 | 2019-01-30 | Tunnel center gutter template component, gutter structure and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910092230.8A CN109707446A (en) | 2019-01-30 | 2019-01-30 | Tunnel center gutter template component, gutter structure and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109707446A true CN109707446A (en) | 2019-05-03 |
Family
ID=66263326
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910092230.8A Pending CN109707446A (en) | 2019-01-30 | 2019-01-30 | Tunnel center gutter template component, gutter structure and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109707446A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110214752A (en) * | 2019-07-23 | 2019-09-10 | 公保 | A kind of ecological, environmental protective protection against rodents animal cave |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101392544A (en) * | 2007-09-19 | 2009-03-25 | 北京泰宁科创科技有限公司 | Gap catchment infiltration type drainage ditch |
US20150125215A1 (en) * | 2011-06-21 | 2015-05-07 | Stabinor As | Method for constructing a tunnel course, and structural element for use by the method |
CN205529791U (en) * | 2016-04-13 | 2016-08-31 | 重庆华宇园林有限公司 | Concrete ecological garden road permeates water |
CN207278299U (en) * | 2017-08-10 | 2018-04-27 | 中交一公局第三工程有限公司 | A kind of ditch template |
CN207526507U (en) * | 2017-12-08 | 2018-06-22 | 中铁二局集团有限公司 | A kind of mobile formwork for being used to pour into a mould tunnel Central drain |
CN108301440A (en) * | 2018-03-29 | 2018-07-20 | 沈阳建筑大学 | With waterproof, the underground pipe gallery construction method of drain function |
CN209654079U (en) * | 2019-01-30 | 2019-11-19 | 中国建筑第八工程局有限公司 | Tunnel center gutter template component and its gutter structure of formation |
-
2019
- 2019-01-30 CN CN201910092230.8A patent/CN109707446A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101392544A (en) * | 2007-09-19 | 2009-03-25 | 北京泰宁科创科技有限公司 | Gap catchment infiltration type drainage ditch |
US20150125215A1 (en) * | 2011-06-21 | 2015-05-07 | Stabinor As | Method for constructing a tunnel course, and structural element for use by the method |
CN205529791U (en) * | 2016-04-13 | 2016-08-31 | 重庆华宇园林有限公司 | Concrete ecological garden road permeates water |
CN207278299U (en) * | 2017-08-10 | 2018-04-27 | 中交一公局第三工程有限公司 | A kind of ditch template |
CN207526507U (en) * | 2017-12-08 | 2018-06-22 | 中铁二局集团有限公司 | A kind of mobile formwork for being used to pour into a mould tunnel Central drain |
CN108301440A (en) * | 2018-03-29 | 2018-07-20 | 沈阳建筑大学 | With waterproof, the underground pipe gallery construction method of drain function |
CN209654079U (en) * | 2019-01-30 | 2019-11-19 | 中国建筑第八工程局有限公司 | Tunnel center gutter template component and its gutter structure of formation |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110214752A (en) * | 2019-07-23 | 2019-09-10 | 公保 | A kind of ecological, environmental protective protection against rodents animal cave |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207512745U (en) | A kind of caisson device and its foundation pit structure | |
CN206408655U (en) | The top plate sidewall structure of covered back-digging construction | |
CN105350581A (en) | Advanced sealing structure for basement top slab settlement post-cast strips | |
CN104652495B (en) | Internal support of foundation pit column and base plate node waterproof construction technology | |
CN105970994A (en) | Pouring jacket cofferdam pile cap structure and construction method | |
CN104358275B (en) | Darker elevator shaft or collecting well construction method | |
CN109707446A (en) | Tunnel center gutter template component, gutter structure and its construction method | |
CN209654079U (en) | Tunnel center gutter template component and its gutter structure of formation | |
CN215106098U (en) | Prefabricated post connection structure | |
CN207327274U (en) | A kind of water channel engineering system | |
CN105756100A (en) | Basement post-pouring belt system and making method thereof | |
CN210596882U (en) | Pedestrian road | |
CN106400838B (en) | A kind of city integrated Pipe rack of prefabricated assembled concrete and construction method | |
CN208363508U (en) | The underground space can white-out infiltration ground structure | |
CN107190781A (en) | Horizontal joint waterproofing construction method is set up in large space basement roof post-cast strip | |
CN203247838U (en) | Fully-buried basement side wall post-pouring belt advance water stop formwork | |
CN107447779B (en) | A kind of assembling structure of concrete stacked plate type piping lane | |
CN109083176A (en) | A kind of design has the local Yield rainfall relation system of auxiliary slip casting function | |
CN210887323U (en) | Connect and build engineering underground structure construction joint watertight fittings | |
CN212454452U (en) | Multifunctional observation hole for controlling concrete pouring of tunnel secondary lining vault | |
CN110424439B (en) | Prefabricated ceramsite concrete hollow slab shaping tire membrane and construction method thereof | |
CN203756235U (en) | Lateral drainage device of tunnel | |
CN107152111A (en) | The lenticular plain concrete construction of guide wall technique used between many boiled water rooms | |
CN208604973U (en) | A kind of underground space ground pavement infiltration white-out structure | |
CN214401732U (en) | Novel water drainage hole |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |