CN109703925A - A kind of pulverized fuel ash cement material pot blows bl bridge layer and method - Google Patents

A kind of pulverized fuel ash cement material pot blows bl bridge layer and method Download PDF

Info

Publication number
CN109703925A
CN109703925A CN201811611645.3A CN201811611645A CN109703925A CN 109703925 A CN109703925 A CN 109703925A CN 201811611645 A CN201811611645 A CN 201811611645A CN 109703925 A CN109703925 A CN 109703925A
Authority
CN
China
Prior art keywords
control valve
blows
cement
cement bin
auger
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811611645.3A
Other languages
Chinese (zh)
Inventor
谌德强
周兵
陈春生
谈建平
赵复林
陈强
秦杰
侯海林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
404 Co Ltd China National Nuclear Corp
Original Assignee
404 Co Ltd China National Nuclear Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 404 Co Ltd China National Nuclear Corp filed Critical 404 Co Ltd China National Nuclear Corp
Priority to CN201811611645.3A priority Critical patent/CN109703925A/en
Publication of CN109703925A publication Critical patent/CN109703925A/en
Pending legal-status Critical Current

Links

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

A kind of pulverized fuel ash cement material pot blows bl bridge layer, including air accumulator, and air accumulator is separately connected control valve A and control valve B, blows bridge formation A in control valve A connection cement bin A, blows bridge formation B in control valve B connection cement bin B;And cement bin A passes through outlet valve A with cement bin B respectively and connect auger with outlet valve B, lower section is equipped with nucleon and claims flowmeter, and between auger connection stirred tank.

Description

A kind of pulverized fuel ash cement material pot blows bl bridge layer and method
Technical field
The invention belongs to intermediate level liquid waste Cemetation process fields, and in particular to a kind of pulverized fuel ash cement object Batch can blows bl bridge layer and method.
Background technique
Intermediate level liquid waste Cemetation engineering waste liquid flow and solid stream amount are wherein vital two Control parameter.Evaluation solidify one of fine or not standard of weight --- and the ratio of mud is exactly waste liquid flow and consolidates stream amount (or waste liquid Cumulative amount and expect cumulative amount admittedly) the ratio between.In solid stream amount control system, Gu the quality of stream amount control system, directly reflects Whether it is capable of the operation of continuous-stable to solid material flow system, is also related to whether solid stream amount controls in given value, while It is related to the ratio of mud whether control system controlled level reaches control.In casting operational process in the past, admittedly expect flowed fluctuation Larger (up to 8%), post operation personnel, which will ceaselessly operate, blows bridge formation pressure sky, controls its pressure, in operation, Sometimes pressure open very stream amount does not always reach requirement admittedly greatly, pressure very little and solid stream amount is very big, is difficult to realize sometimes Compared with stability contorting, or even process control needs are not achieved.Therefore urgently process flow is simple in exploration one, and application cost is low, effect The high treatment process of rate is to realize the problems such as adjusting to solid stream amount.
Summary of the invention
It is an object of the invention to: a kind of pulverized fuel ash cement material pot blows bl bridge layer, and it is solid to solve large volume pouring cement Change material flow control admittedly 3% hereinafter, to improve the stability of solid stream amount.
Technical scheme is as follows: a kind of pulverized fuel ash cement material pot blows bl bridge layer, including air accumulator, air accumulator It is separately connected control valve A and control valve B, blows bridge formation A in control valve A connection cement bin A, in control valve B connection cement bin B Blow bridge formation B;And cement bin A passes through outlet valve A with cement bin B respectively and connect auger with outlet valve B, lower section is equipped with nucleon and claims Flowmeter, and between auger connection stirred tank.
The auger is L-type.
A kind of method that pulverized fuel ash cement material pot blows bl bridge layer, comprising the following steps:
S1: opening control valve A, control valve B, opens outlet valve A, outlet valve B, starts auger;Air accumulator is supplied;
S2: the flow that nucleon claims flowmeter is adjusted;
S3: cement bin A, cement bin B pressure are adjusted by control valve A, control valve B;
S4: cement bin A, after the cement in cement bin B is blown bridge formation, blows bridge formation B purging, through outlet valve A, outlet valve B and Auger is transported between stirred tank;
In the S2, the flow for adjusting nucleon flowmeter is referred to as 11T/h~14T/h.
Cement bin A, cement bin B pressure are adjusted in 0.4kPa~15kPa by control valve A, control valve B.
Remarkable result of the invention is: reducing influence of the pressure to cement bin blanking, solution is exactly to replace two It is a to blow bridge formation, to avoid bridging in cement bin and clogging, admittedly material flow control is 3% hereinafter, improving solid stream amount Stability, this work have been resolved.
Detailed description of the invention
Fig. 1 is that pulverized fuel ash cement material pot of the present invention blows bl bridge layer schematic diagram;
Fig. 2 blows bl bridge layer for pulverized fuel ash cement material pot of the present invention and blows bridge formation schematic diagram;
In figure: blow bridge formation A1, cement bin A2, outlet valve A3, control valve A4, air accumulator 5, nucleon claim flowmeter 6, auger 7, 8 between stirred tank, control valve B9, blow bridge formation B10, cement bin B11, outlet valve B12
Specific embodiment
A kind of pulverized fuel ash cement material pot blows bl bridge layer, including air accumulator 5, air accumulator 5 be separately connected control valve A4 with Bridge formation A1 is blown in control valve B9, control valve A4 connection cement bin A2, blows bridge formation B10 in control valve B9 connection cement bin B11; And cement bin A2 passes through outlet valve A3 with cement bin B11 respectively and connect auger 7 with outlet valve B12, auger 7 is L-type, lower section peace Claim flowmeter 6 equipped with nucleon, and auger 7 is connected to 8 between stirred tank.
A kind of pulverized fuel ash cement material pot blows bridging method, comprising the following steps:
S1: opening control valve A4, control valve B9, opens outlet valve A3, outlet valve B12, starts auger 7;Air accumulator 5 carries out Gas supply;
S2: the flow for adjusting nucleon flowmeter 6 is referred to as 11T/h~14T/h;
S3: cement bin A2, cement bin B11 pressure are adjusted in 0.4kPa~15kPa by control valve A4, control valve B9;
S4: cement bin A2, after the cement in cement bin B11 is blown bridge formation 1, blows bridge formation B10 purging, through outlet valve A3, go out Material valve B12 and auger 7 are transported to 8 between stirred tank;
Bridge formation, which is blown, by operation wall built-up or blocking warehouse occurs to avoid storehouse inner wall, it is unstable so as to cause cement bin blanking Existing phase, eliminate original blows influence of the bl bridge layer to warehouse blanking, material is at the uniform velocity to auger ash conveying cement.

Claims (5)

1. a kind of pulverized fuel ash cement material pot blows bl bridge layer, it is characterised in that: including air accumulator (5), air accumulator (5) connects respectively Control valve A (4) and control valve B (9) are connect, blowing bridge formation A (1) in control valve A (4) connection cement bin A (2), control valve B (9) is even Bridge formation B (10) are blown in water receiving hopper dredger B (11);And cement bin A (2) and cement bin B (11) by outlet valve A (3) and go out respectively Expect valve B (12) connection auger (7), lower section is equipped with nucleon and claims flowmeter (6), and between auger (7) connection stirred tank (8).
2. a kind of pulverized fuel ash cement material pot according to claim 1 blows bl bridge layer, it is characterised in that: the auger It (7) is L-type.
3. a kind of method for applying a kind of pulverized fuel ash cement material pot as claimed in claim 2 to blow bl bridge layer, feature exist In: the following steps are included:
S1: opening control valve A (4), control valve B (9), opens outlet valve A (3), outlet valve B (12), starts auger (7);Gas storage Tank (5) is supplied;
S2: the flow that nucleon claims flowmeter (6) is adjusted;
S3: cement bin A (2), cement bin B (11) pressure are adjusted by control valve A (4), control valve B (9);
S4: cement bin A (2), after the cement in cement bin B (11) is blown bridge formation (1), blows bridge formation B (10) purging, through outlet valve A (3), outlet valve B (12) and auger (7) are transported between stirred tank (8).
4. a kind of pulverized fuel ash cement material pot according to claim 3 blows bridging method, it is characterised in that: in the S2, The flow for adjusting nucleon flowmeter (6) is referred to as 11T/h~14T/h.
5. a kind of pulverized fuel ash cement material pot according to claim 3 blows bridging method, it is characterised in that: pass through control valve A (4), control valve B (9) adjust cement bin A (2), cement bin B (11) pressure in 0.4kPa~15kPa.
CN201811611645.3A 2018-12-27 2018-12-27 A kind of pulverized fuel ash cement material pot blows bl bridge layer and method Pending CN109703925A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811611645.3A CN109703925A (en) 2018-12-27 2018-12-27 A kind of pulverized fuel ash cement material pot blows bl bridge layer and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811611645.3A CN109703925A (en) 2018-12-27 2018-12-27 A kind of pulverized fuel ash cement material pot blows bl bridge layer and method

Publications (1)

Publication Number Publication Date
CN109703925A true CN109703925A (en) 2019-05-03

Family

ID=66257771

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811611645.3A Pending CN109703925A (en) 2018-12-27 2018-12-27 A kind of pulverized fuel ash cement material pot blows bl bridge layer and method

Country Status (1)

Country Link
CN (1) CN109703925A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110759097A (en) * 2019-11-14 2020-02-07 上海电气集团股份有限公司 Feeding system for fly ash washing
CN111115034A (en) * 2020-01-14 2020-05-08 煤科院节能技术有限公司 Anti-blocking powder bin fluidizing device

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1909219B2 (en) * 1969-02-24 1978-03-02 Fendt, Wolfgang, Dr., 8032 Graefelfing Pneumatic device for discharging products from bulk material containers
JPS5488558A (en) * 1977-12-22 1979-07-13 Ebara Corp Method of eliminating bridge in stock material supplying device
CN2296868Y (en) * 1997-05-06 1998-11-11 长春市商品混凝土供应公司 Steel structure equipment for storing and supplying bulk cement
CN201056395Y (en) * 2007-06-13 2008-05-07 中国石油天然气股份有限公司 Powdery material blanking fluidizer
CN201808842U (en) * 2010-09-14 2011-04-27 新会双水发电(B厂)有限公司 Coal bucket coal injection device
CN203268733U (en) * 2013-04-15 2013-11-06 郑州东方科技耐火材料有限公司 Discharge device of blending bin
CN203268734U (en) * 2013-04-15 2013-11-06 郑州东方科技耐火材料有限公司 Conveying device used for material discharging of stock bin
CN205499894U (en) * 2016-03-30 2016-08-24 博广热能股份有限公司 Buggy storehouse layering multiple spot fluidizer

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1909219B2 (en) * 1969-02-24 1978-03-02 Fendt, Wolfgang, Dr., 8032 Graefelfing Pneumatic device for discharging products from bulk material containers
JPS5488558A (en) * 1977-12-22 1979-07-13 Ebara Corp Method of eliminating bridge in stock material supplying device
CN2296868Y (en) * 1997-05-06 1998-11-11 长春市商品混凝土供应公司 Steel structure equipment for storing and supplying bulk cement
CN201056395Y (en) * 2007-06-13 2008-05-07 中国石油天然气股份有限公司 Powdery material blanking fluidizer
CN201808842U (en) * 2010-09-14 2011-04-27 新会双水发电(B厂)有限公司 Coal bucket coal injection device
CN203268733U (en) * 2013-04-15 2013-11-06 郑州东方科技耐火材料有限公司 Discharge device of blending bin
CN203268734U (en) * 2013-04-15 2013-11-06 郑州东方科技耐火材料有限公司 Conveying device used for material discharging of stock bin
CN205499894U (en) * 2016-03-30 2016-08-24 博广热能股份有限公司 Buggy storehouse layering multiple spot fluidizer

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110759097A (en) * 2019-11-14 2020-02-07 上海电气集团股份有限公司 Feeding system for fly ash washing
CN110759097B (en) * 2019-11-14 2021-07-23 上海电气集团股份有限公司 Feeding system for fly ash washing
CN111115034A (en) * 2020-01-14 2020-05-08 煤科院节能技术有限公司 Anti-blocking powder bin fluidizing device

Similar Documents

Publication Publication Date Title
CN108993761B (en) Coordination control method based on dense medium suspension density and liquid level
CN108993762B (en) Density and liquid level control device for dense medium coal separation and coordination control method
CN103350037B (en) Overflow particle size control method for cyclone
CN109703925A (en) A kind of pulverized fuel ash cement material pot blows bl bridge layer and method
US20080212397A1 (en) Method and Apparatus to Optimize the Mixing Process
CN106964483A (en) A kind of unpressurized feeding dense medium cyclone coal separation process autocontrol method and system
CN103100242B (en) Canal formula concentrator
CN104487715B (en) The method for operating multiphase pump and its equipment
CN204699815U (en) A kind of mine tailing discharge mechanism of separation of coarse slime machine
CN101974860B (en) Method for medium-consistency refining and pumping
CN201706199U (en) Residual pulp pneumatic automatic conveying device
CN110360165B (en) Method and device for designing two-stage jet pump
JP2018526199A (en) Hydrodynamic removal of high density material from slurry.
US4089563A (en) Apparatus for pneumatic conveyance of pulverulent or granular materials
CN204502590U (en) Vertical gas-liquid separation device
CN110469363B (en) Vertical sand silo sand discharging device capable of discharging materials continuously and stably
CN104043522B (en) High-gradient vertical ring magnet separator liquid level automatic control device
CN104848036A (en) System for continuously decompressing high pressure fluid containing solid particles
CN206666159U (en) A kind of cyclone separator of straight tube water flowing out structure
CN207246792U (en) Produce the feed system of water
CN101852334B (en) Pneumatic and automatic conveying device for residual slurry
CN208018556U (en) A kind of carclazyte quantitatively adds control system carclazyte addition mechanism
RU2445171C2 (en) Method of automatic control over hydraulic cyclone
US20110235460A1 (en) Method and apparatus to optimize the mixing process
CN215854012U (en) Powdery material blanking control system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190503