CN109685301A - Method for managing resource, device, equipment and readable storage medium storing program for executing - Google Patents
Method for managing resource, device, equipment and readable storage medium storing program for executing Download PDFInfo
- Publication number
- CN109685301A CN109685301A CN201810952421.2A CN201810952421A CN109685301A CN 109685301 A CN109685301 A CN 109685301A CN 201810952421 A CN201810952421 A CN 201810952421A CN 109685301 A CN109685301 A CN 109685301A
- Authority
- CN
- China
- Prior art keywords
- project
- working hour
- item
- personnel
- hour module
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063112—Skill-based matching of a person or a group to a task
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063118—Staff planning in a project environment
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Educational Administration (AREA)
- Operations Research (AREA)
- Development Economics (AREA)
- Marketing (AREA)
- Game Theory and Decision Science (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of method for managing resource, device, equipment and readable storage medium storing program for executing, the described method includes: obtaining the item attribute information and project duration of the destination item from the configuration file of destination item when the project personnel for detecting destination item distribute instruction;The corresponding working hour module collection of the project duration is obtained, for each of set working hour module, executes step: item label processing is carried out to the working hour module based on the item attribute information;The personnel's attribute for obtaining the project personnel prestored carries out counterpart personnel's tag processes to the working hour module based on personnel's attribute;The corresponding item label and People Tab are matched, the working hour module of successful match is obtained, the project task for carrying out respective item personnel to the working hour module of successful match distributes, wherein project task is associated with the item label of the working hour module of successful match.During the present invention solves off-the-shelf item personnel assignment, the more technical problem of human and material resources waste.
Description
Technical field
The present invention relates to field of communication technology more particularly to a kind of method for managing resource, device, equipment and readable storage mediums
Matter.
Background technique
Enterprise generally requires the multiple projects of exploitation, thus, how to be reasonably allocation of items appropriate personnel, is each enterprise
Industry need solve the problems, such as, and currently, most of enterprise is all the artificial distribution for carrying out project personnel, and manually carry out project people
The distribution of member, needs to distribute the costly mental and physical efforts of personnel, this will cause the waste of human and material resources.
Summary of the invention
The main purpose of the present invention is to provide a kind of method for managing resource, device, equipment and readable storage medium storing program for executing, it is intended to
The technical issues of solving the artificial distribution for carrying out project personnel, will cause the waste of human and material resources.
To achieve the above object, the present invention provides a kind of method for managing resource, and the method for managing resource includes:
When the project personnel for detecting destination item distribute instruction, the mesh is obtained from the configuration file of destination item
The item attribute information and project duration of mark project;
The corresponding working hour module collection of the project duration is obtained, for each of working hour module collection working hour
Module executes following steps:
Item label processing is carried out to the working hour module based on the item attribute information;
The personnel's attribute for obtaining the project personnel prestored carries out corresponding people to the working hour module based on personnel's attribute
Member's tag processes;
Match the corresponding item label of the working hour module and People Tab, obtain the working hour module of successful match, to
The project task distribution of respective item personnel is carried out with successful working hour module, wherein the project task is matched into described
The item label of the working hour module of function is associated with.
Optionally, the corresponding item label of the matching working hour module and People Tab, obtain the work of successful match
When module, the project task allocation step for carrying out respective item personnel to the working hour module of successful match includes:
The corresponding item label of the working hour module and People Tab are matched, and judges the corresponding project of the working hour module
Label whether there is multiple matched People Tabs;
When there are when multiple matched People Tabs, obtain the mesh prestored for the corresponding item label of the working hour module
The project important level of mark project;
Project important level based on the destination item chooses target person from multiple matched People Tabs
Label, and obtain the successful working hour module of Corresponding matching;
Using the corresponding target person of the target person label as the project personnel of the successful working hour module of Corresponding matching,
And the destination item personnel are carried out with the distribution of respective item task.
Optionally, the project important level based on the destination item, from multiple matched People Tabs
Target person label is chosen, and obtains the successful working hour module step of Corresponding matching and includes:
Each matched People Tab is parsed, to obtain the length of service of corresponding project personnel, wherein personnel's mark
The length of service information of corresponding project personnel is carried in label;
Each matched People Tab is sorted from large to small based on each length of service, obtains the first sequence;
When the project important level of the destination item is higher than the first predetermined level, arrangement the is chosen from the first sequence
One People Tab obtains the successful working hour module of Corresponding matching as target person label.
Optionally, the project important level based on the destination item, from multiple matched People Tabs
Target person label is chosen, and obtaining the successful working hour module step of Corresponding matching includes: to obtain each matched personnel's mark
Sign length of service and the work scoring of corresponding project personnel;
The length of service for obtaining each project personnel respectively and work scoring are in target person label selection operation
Shared weight proportion;
Based on each weight proportion, and the corresponding project personnel the length of service and the work comment
Point, the matching score value of each matched People Tab is calculated;
The personnel that each matched People Tab is sorted from large to small based on each matching score value, obtain second row
Sequence;
When the project important level of the destination item is higher than the second predetermined level, the row of selection from second sequence
The People Tab of column first obtains the successful working hour module of Corresponding matching as target person label.
Optionally, the item attribute information includes project stage information, item classification information;
Carrying out item label processing step to the working hour module based on the item attribute information includes:
It obtains and the project stage based on the destination item obtains working hour module progress divided stages processing
The phase tag of the working hour module;
After obtaining phase tag, the working hour module is carried out at tag along sort according to preset term developing way type
Reason, to obtain the project development direction label of the working hour module.
Optionally, the corresponding item label of the matching working hour module and People Tab, obtain the work of successful match
When module step further include:
Obtain the project stage subtab in item label and the job sharing attribute subtab in People Tab;
Judge whether the corresponding project stage subtab of the working hour module and job sharing attribute subtab are consistent, when one
When cause, the successful working hour module of Corresponding matching is obtained, wherein the project stage subtab and the job sharing attribute mark
The label composition rule of label is identical.
Optionally, the corresponding item label of the matching working hour module and People Tab, obtain the work of successful match
When module, the working hour module of successful match is carried out include: after the project task allocation step of respective item personnel
Obtain carried out project task distribution project personnel communication account, the communication account include telephone number,
Wechat, nail nail and email address;
Communication account based on project personnel, by the corresponding notice of the project task of distribution to project personnel.
The present invention also provides a kind of resource management apparatus, the resource management apparatus includes:
First obtains module, when for instructing in the project personnel's distribution for detecting destination item, from matching for destination item
Set the item attribute information and project duration that the destination item is obtained in file;
Second obtains module, for obtaining the corresponding working hour module collection of the project duration, for the working hour module
Each of set working hour module, the resource management apparatus further include:
Third obtains module, for obtaining personnel's attribute of the project personnel prestored, based on personnel's attribute to described
Working hour module carries out counterpart personnel's tag processes;
Matching module obtains successful match for matching the corresponding item label of the working hour module and People Tab
Working hour module, the project task for carrying out respective item personnel to the working hour module of successful match distribute, wherein the project task
It is associated with the item label of the working hour module of the successful match.
Optionally, the matching module includes:
Matching unit for matching the corresponding item label of the working hour module and People Tab, and judges the working hour
The corresponding item label of module whether there is multiple matched People Tabs;
First acquisition unit, for there are multiple matched People Tabs when the corresponding item label of the working hour module
When, obtain the project important level of the destination item prestored;
Selection unit, for the project important level based on the destination item, from multiple matched People Tabs
Middle selection target person label, and obtain the successful working hour module of Corresponding matching;
Allocation unit, for using the corresponding target person of the target person label as the successful working hour mould of Corresponding matching
The project personnel of block, and the destination item personnel are carried out with the distribution of respective item task.
Optionally, the selection unit includes:
Parsing subunit, for parsing each matched People Tab, to obtain the length of service of corresponding project personnel,
Wherein, the length of service information of corresponding project personnel is carried in the People Tab;
First sorting subunit, for sorting from large to small each matched personnel's mark based on each length of service
Label, obtain the first sequence;
First choose subelement, for when the project important level of the destination item be higher than the first predetermined level when, from
The People Tab of arrangement first is chosen in first sequence as target person label, and obtains the successful working hour mould of Corresponding matching.
Optionally, the selection unit further include:
First obtain subelement, corresponded to for obtaining each matched People Tab project personnel length of service, with
And work scoring;
Second obtains subelement, and the length of service and work scoring for obtaining each project personnel respectively are in target
Shared weight proportion in People Tab's selection operation;
Computation subunit, for being based on each weight proportion, and the length of service of the corresponding project personnel
And the work scoring, the matching score value of each matched People Tab is calculated;
Second sorting subunit, for sorting from large to small each matched People Tab based on each matching score value
Personnel, obtain the second sequence;
Second choose subelement, for when the project important level of the destination item be higher than the second predetermined level when, from
The People Tab of arrangement first is chosen in second sequence as target person label, and obtains Corresponding matching successful working hour
Module.
Optionally, the item attribute information includes project stage information, item classification information;
Described second, which obtains module, includes:
Second acquisition unit carries out the working hour module for obtaining and the project stage based on the destination item
Divided stages processing, obtains the phase tag of the working hour module;
Taxon, for after obtaining phase tag, according to preset term developing way type to the working hour module
Tag along sort processing is carried out, to obtain the project development direction label of the working hour module.
Optionally, the matching module includes:
Third acquiring unit, for obtaining the project stage subtab in item label and the work in People Tab
Packet attributes subtab;
Judging unit, for judging the corresponding project stage subtab of the working hour module and job sharing attribute subtab
It is whether consistent, when consistent, obtain the successful working hour module of Corresponding matching, wherein the project stage subtab and the work
The label composition rule for making packet attributes subtab is identical.
Optionally, the source control device further include:
4th obtains module, for obtaining the communication account for having carried out the project personnel of project task distribution, the communication
Account includes telephone number, wechat, nail nail and email address;
Notification module gives the corresponding notice of the project task of distribution to project people for the communication account based on project personnel
Member.
In addition, to achieve the above object, the present invention also provides a kind of asset management device, the asset management device packet
It includes: memory, processor, communication bus and the resource manager being stored on the memory,
The communication bus is for realizing the communication connection between processor and memory;
The processor is for executing the resource manager, to perform the steps of
When the project personnel for detecting destination item distribute instruction, the mesh is obtained from the configuration file of destination item
The item attribute information and project duration of mark project;
The corresponding working hour module collection of the project duration is obtained, for each of working hour module collection working hour
Module executes following steps:
Item label processing is carried out to the working hour module based on the item attribute information;
The personnel's attribute for obtaining the project personnel prestored carries out corresponding people to the working hour module based on personnel's attribute
Member's tag processes;
Match the corresponding item label of the working hour module and People Tab, obtain the working hour module of successful match, to
The project task distribution of respective item personnel is carried out with successful working hour module, wherein the project task is matched into described
The item label of the working hour module of function is associated with.
Optionally, the corresponding item label of the matching working hour module and People Tab, obtain the work of successful match
When module, the project task allocation step for carrying out respective item personnel to the working hour module of successful match includes:
The corresponding item label of the working hour module and People Tab are matched, and judges the corresponding project of the working hour module
Label whether there is multiple matched People Tabs;
When there are when multiple matched People Tabs, obtain the mesh prestored for the corresponding item label of the working hour module
The project important level of mark project;
Project important level based on the destination item chooses target person from multiple matched People Tabs
Label, and obtain the successful working hour module of Corresponding matching;
Using the corresponding target person of the target person label as the project personnel of the successful working hour module of Corresponding matching,
And the destination item personnel are carried out with the distribution of respective item task.
Optionally, the project important level based on the destination item, from multiple matched People Tabs
Target person label is chosen, and obtains the successful working hour module step of Corresponding matching and includes:
Each matched People Tab is parsed, to obtain the length of service of corresponding project personnel, wherein personnel's mark
The length of service information of corresponding project personnel is carried in label;
Each matched People Tab is sorted from large to small based on each length of service, obtains the first sequence;
When the project important level of the destination item is higher than the first predetermined level, arrangement the is chosen from the first sequence
One People Tab obtains the successful working hour module of Corresponding matching as target person label.
Optionally, the project important level based on the destination item, from multiple matched People Tabs
Target person label is chosen, and obtaining the successful working hour module step of Corresponding matching includes: to obtain each matched personnel's mark
Sign length of service and the work scoring of corresponding project personnel;
The length of service for obtaining each project personnel respectively and work scoring are in target person label selection operation
Shared weight proportion;
Based on each weight proportion, and the corresponding project personnel the length of service and the work comment
Point, the matching score value of each matched People Tab is calculated;
The personnel that each matched People Tab is sorted from large to small based on each matching score value, obtain second row
Sequence;
When the project important level of the destination item is higher than the second predetermined level, the row of selection from second sequence
The People Tab of column first obtains the successful working hour module of Corresponding matching as target person label.
Optionally, the item attribute information includes project stage information, item classification information;
Carrying out item label processing step to the working hour module based on the item attribute information includes:
It obtains and the project stage based on the destination item obtains working hour module progress divided stages processing
The phase tag of the working hour module;
After obtaining phase tag, the working hour module is carried out at tag along sort according to preset term developing way type
Reason, to obtain the project development direction label of the working hour module.
Optionally, the corresponding item label of the matching working hour module and People Tab, obtain the work of successful match
When module step further include:
Obtain the project stage subtab in item label and the job sharing attribute subtab in People Tab;
Judge whether the corresponding project stage subtab of the working hour module and job sharing attribute subtab are consistent, when one
When cause, the successful working hour module of Corresponding matching is obtained, wherein the project stage subtab and the job sharing attribute mark
The label composition rule of label is identical.
Optionally, the corresponding item label of the matching working hour module and People Tab, obtain the work of successful match
When module, the working hour module of successful match is carried out include: after the project task allocation step of respective item personnel
Obtain carried out project task distribution project personnel communication account, the communication account include telephone number,
Wechat, nail nail and email address;
Communication account based on project personnel, by the corresponding notice of the project task of distribution to project personnel.
In addition, to achieve the above object, the present invention also provides a kind of readable storage medium storing program for executing, the readable storage medium storing program for executing storage
Have one perhaps more than one program the one or more programs can be held by one or more than one processor
Row is to be used for:
When the project personnel for detecting destination item distribute instruction, the mesh is obtained from the configuration file of destination item
The item attribute information and project duration of mark project;
The corresponding working hour module collection of the project duration is obtained, for each of working hour module collection working hour
Module executes following steps:
Item label processing is carried out to the working hour module based on the item attribute information;
The personnel's attribute for obtaining the project personnel prestored carries out corresponding people to the working hour module based on personnel's attribute
Member's tag processes;
Match the corresponding item label of the working hour module and People Tab, obtain the working hour module of successful match, to
The project task distribution of respective item personnel is carried out with successful working hour module, wherein the project task is matched into described
The item label of the working hour module of function is associated with.
When the present invention in the project personnel's distribution for detecting destination item by instructing, from the configuration file of destination item
Obtain the item attribute information and project duration of the destination item;The corresponding working hour module collection of the project duration is obtained,
For each of working hour module collection working hour module, following steps are executed: based on the item attribute information to institute
It states working hour module and carries out item label processing;The personnel's attribute for obtaining the project personnel prestored, based on personnel's attribute to institute
It states working hour module and carries out counterpart personnel's tag processes;The corresponding item label of the working hour module and People Tab are matched, is obtained
The working hour module of successful match, the project task for carrying out respective item personnel to the working hour module of successful match distribute, wherein institute
Project task is stated to be associated with the item label of the working hour module of the successful match.It in this application, is no longer manually to project
The distribution of project personnel is carried out, but automates and realizes personnel assignment, that is, is based on working hour module, item label and People Tab,
Realize the automatic distribution of project personnel, entire personnel assignment process is full-automatic, during avoiding manually carrying out personnel assignment
The work such as information identification, information matches, personnel's classification, rapid and simple realization project personnel distribution, avoid human and material resources
Waste, thus, present application addresses the distribution for manually carrying out project personnel in the prior art, will cause the wave of human and material resources
The technical issues of taking.
Detailed description of the invention
Fig. 1 is the flow diagram of method for managing resource first embodiment of the present invention;
Fig. 2 is the flow diagram of method for managing resource second embodiment of the present invention;
Fig. 3 is the device structure schematic diagram for the hardware running environment that present invention method is related to.
The embodiments will be further described with reference to the accompanying drawings for the realization, the function and the advantages of the object of the present invention.
Specific embodiment
It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not intended to limit the present invention.
The present invention provides a kind of method for managing resource, in the first embodiment of method for managing resource of the present invention, referring to figure
1, the method for managing resource includes:
Step S10 is obtained from the configuration file of destination item when the project personnel for detecting destination item distribute instruction
Take the item attribute information and project duration of the destination item;
Step S20 obtains the corresponding working hour module collection of the project duration, for every in the working hour module collection
One working hour module executes step:
Step S30 carries out item label processing to the working hour module based on the item attribute information;
Step S40 obtains personnel's attribute of the project personnel prestored, based on personnel's attribute to the working hour module into
Row counterpart personnel's tag processes;
Step S50 matches the corresponding item label of each working hour module and People Tab, obtains the work of successful match
When module, the project task for carrying out respective item personnel to the working hour module of successful match distributes, wherein the project task with
The item label of the working hour module of the successful match is associated with.
Specific step is as follows:
Step S10 is obtained from the configuration file of destination item when the project personnel for detecting destination item distribute instruction
Take the item attribute information and project duration of the destination item;
It should be noted that in the present embodiment, method for managing resource is applied to resource management system, in resource management system
In system, there are personal information repository, in the personal information repository, it is stored with personnel's attribute letter of each project personnel
Breath, wherein personnel's attribute information includes length of service, work item or the content of project personnel, job sharing, work establishment
Etc. information, for example, be stored in personal information repository a project personnel corresponding length of service such as 3 years, work item or
Content is WEB front-end exploitation, and job sharing is development group, work establishment to there is establishment, and work grading system is middle rank etc..Its
In, it specifically can be the job sharing according to locating for project personnel in personal information repository and each project personnel divided
Class storage.
In resource management system, project personnel's distribution function can be realized, specifically, batch operation personnel can provide
The personnel assignment function interface of management system triggers the item of destination item by touching or clicking allocation of items icon mode
Mesh personnel assignment instruction, when obtaining the item attribute information of the destination item from the configuration file of destination item with project
It is long, finally to realize the personnel assignment of destination item, before the project personnel of triggering destination item distribute instruction, have been introduced into
The destination item for needing allocated items personnel is each file such as mesh for having imported the destination item for needing allocated items personnel
The information such as project profile are marked, thus, when the project personnel for detecting destination item distribute instruction, it can realize and obtain
The configuration file of destination item obtains the destination item after obtaining configuration file from the configuration file of destination item
Item attribute information and project duration, wherein item attribute information includes project name, Item version, project task validity
Section, classification of the items mark etc., wherein project task validity section includes the validity section of each project segmentation task,
For example, project task includes system development, test, deployment design, goes into operation and evaluate equal segments task, thus, project task has
Effect property section includes the segmentation validity section of system development, test, deployment design, evaluation equal segments task of going into operation, wherein
In the present embodiment, classification of the items mark includes project development direction signs, as project has backstage developing way, client exploitation side
To etc..Other than it can obtain the item attribute information of destination item from configuration file, the project of destination item can also be obtained
Duration, wherein the project duration refers to estimated completion target item object time.
Step S20 obtains the corresponding working hour module collection of the project duration, for every in the working hour module collection
One working hour module executes following steps:
After obtaining project duration, the corresponding working hour module collection of the project duration is obtained, is acquisition project duration
Corresponding each working hour module, wherein can be that unit distributes working hour module according to hour, as project duration was if 1 month
30 days, daily 8 hours, then the corresponding working hour number of modules of project duration was 240, wherein each working hour module carries attribute
I.e. natural quality has: date, initial time, terminal time, time span etc..It is illustrated to specific embodiment, working hour
Module is corresponding to be can be from 9 points to 2018 10 points of mornings of on May 24, of morning on May 24th, 2018, and time span is 1 hour,
The working hour module is the corresponding working hour module of destination item, and destination item includes multiple working hour modules, institute
The time span for stating each working hour module can be with not just 1 hour.
Step S30 carries out item label processing to the working hour module based on the item attribute information;
After obtaining working hour module collection, for each of working hour module collection working hour module, executes: being based on
The item attribute information carries out item label processing to the working hour module, carries out each item label to the working hour module
Processing is referred to the working hour module add items attribute tags, is that can identify to working hour module addition machine
Item attribute label.
Wherein, the item attribute information includes project stage information, item classification information;
Carrying out item label processing step to the working hour module based on the item attribute information includes:
Step S21, acquisition and the project stage based on the destination item, the working hour module is carried out at divided stages
Reason, obtains the phase tag of the working hour module;
After obtaining needing each working hour module of add items label, each project working hour module is segmented
Processing, if project working hour module is 150, the time corresponds to the system development stage near 70 preceding working hour modules, and the time is slightly
30 forward working hour modules correspond to test phase, and 30 working hour modules of the time after are deployment design phase, time
20 working hour modules after are to go into operation to comment audit phase etc., can be right to distinguish the working hour module after each divided stages
Each working hour module corresponding label first is added different subtabs, such as by the corresponding mark of system development stage corresponding working hour module
Label first corresponding addition K subtab, adds C subtab for the corresponding working hour module of test phase, will dispose the design phase pair
The working hour module addition B subtab answered, comments the corresponding working hour module of audit phase to add T subtab operation, obtains each work
When module each stage subtab after.It should be noted that may be used also after carrying out divided stages processing to each working hour module
It is handled with carrying out further sub-stage division to each working hour module after divided stages, as the system development stage can be segmented
For demand analysis sub-stage, software design sub-stage, program coding sub-stage etc., each sub-stage corresponds to working hour module
Second bit identification of label, as demand analysis sub-stage, software design sub-stage, program coding sub-stage correspond to working hour module mark
The subtab of label is x, s and m, thus system development stage corresponding comprehensive label can be divided into Kx, Ks and Km etc..Exist
In the present embodiment, obtains and the project stage based on the destination item obtains working hour module progress divided stages processing
To the phase tag of the working hour module.
Step S22 divides the working hour module according to preset term developing way type after obtaining phase tag
Class tag processes, to obtain the project development direction label of the working hour module.
After obtaining each phase tag, contingency table is carried out to the working hour module according to preset term developing way type
Label processing specifically, carries out detailed programs classification to working hour module to obtain the project development direction label of the working hour module
The processing of classification subtab, detailed programs classification subtab is in the label third position of working hour module, classification of the items mark
Label include project development direction subtab, and if project has backstage developing way, the backstage exploitation subtab is #, client is opened
Originating party is to the client developing way subtab is % etc., is carrying out detailed programs classification to each working hour module
Classify after subtab processing, each item label of each working hour module can be obtained, as certain working hour module is
2018051209Kx#, wherein 2018051209 start for working hour module start time information i.e. 09 point of May 12 in 2018,
Kx is the demand analysis sub-stage in the system development stage, and it is backstage exploitation mark that #, which identifies the project,.
Step S40 obtains personnel's attribute of the project personnel prestored, based on personnel's attribute to the working hour module into
Row counterpart personnel's tag processes;
Obtain personnel's attribute of the project personnel prestored, wherein the project personnel prestored refer to storing in personal information
Each project personnel in library, in addition, the project personnel prestored may also refer to correspond to certain in personal information repository
It is corresponding each in the sub- repository of certain in the project personnel or personal information repository of one subsidiary or group internal
Project personnel, wherein personal information repository is classified according to floor or place subsidiary etc. where project personnel, is obtained
Each sub- repository, further, each project personnel prestored can also be the project personnel in triggering destination item
Distribution instruction before, manually choose for importing each project personnel, after the project personnel prestored, obtain it is described pre-
Personnel's attribute of each project personnel deposited specifically obtains the job sharing attribute of each project personnel, action attribute
Deng after obtaining the job sharing attribute of project personnel, based on personnel's attribute to working hour module progress counterpart personnel
Tag processes accordingly add the label of personnel's attribute of all project personnel prestored to working hour module, if a certain purpose
Project personnel share 4, then the label addition for carrying out 4 People Tabs to certain any working hour module of the project is handled,
According to the job sharing attribute of project personnel, action attribute etc., wherein there are structures in the item label and People Tab
At the identical subtab of rule, if the job sharing attribute of 4 project personnel is system development group, action
Attribute is respectively demand analysis, software design, program coding, program coding, then 4 project personnel counterpart personnel's subtab
Respectively Kx#, Ks#, Km# and Km# etc., K indicate project personnel's job sharing attribute be system development group, and x, s, m with
And m indicates that project personnel's action is demand analysis, software design, program coding, program coding, i.e., the described expression project people
The label of member's action is identical as the item label sub-stage division corresponding composition rule of label, and # indicates that the project is to correspond to
Backstage developing way, then it is described after the label addition processing for carrying out 4 People Tabs to any working hour module of the project
Any working hour module has 4 People Tabs: 2018051209Kx#, 2018051209Ks#, 2018051209Km#,
2018051209Km# label, wherein 2018051209 open for working hour module start time information i.e. 09 point of May 12 in 2018
Begin, it should be noted that People Tab can also include the length of service information and work score information etc. of project personnel, such as
People Tab can be 2018051209Kx#58, wherein 5 have 5 years lengths of service for the project personnel, are described in 8 expressions
Project personnel's scoring is 8 points.
Step S50 matches the corresponding item label of the working hour module and People Tab, obtains the working hour mould of successful match
Block, the project task for carrying out respective item personnel to the working hour module of successful match distribute, wherein the project task with it is described
The item label of the working hour module of successful match is associated with.
Match the corresponding item label of the working hour module and People Tab, obtain the working hour module of successful match, to
The project task distribution of respective item personnel is carried out with successful working hour module, wherein the project task is matched into described
The item label of the working hour module of function is associated with.If certain working hour module item label is 2018051209Kx#, corresponding each personnel's mark
Label are 2018051209Kx#, 2018051209Ks#, 2018051209Km#, 2018051209Km#, then to the working hour module
For, there are a People Tab 2018051209Kx# to match with item attribute label, that is, 2018051209Kx#, the working hour
Module is the working hour module of successful match, and the project task for carrying out respective item personnel to the working hour module of successful match distributes,
The 2018051209Kx# corresponded into project task distribute to 2018051209Kx# and correspond to project personnel, i.e., project task with
The item label of the working hour module of the successful match is associated with.
Specifically, described to match the corresponding item label of each working hour module and People Tab, obtain successful match
Working hour module step further include:
Step S41 obtains the project stage subtab in item label and job sharing attribute in People Tab
Label;
In the present embodiment, it is the matching for quickly carrying out each working hour module corresponding item label and People Tab, obtains
It takes and obtains the project stage subtab in item label and the job sharing attribute subtab in People Tab.
Step S42 judges whether are the corresponding project stage subtab of the working hour module and job sharing attribute subtab
Unanimously, when consistent, the successful working hour module of Corresponding matching is obtained, wherein the project stage subtab and the work point
The label composition rule of group attribute subtab is identical.
After obtaining project stage subtab and job sharing attribute subtab, the corresponding item of a certain working hour module is judged
Whether mesh stage subtab and job sharing attribute subtab are consistent or identical, and when identical, it is successful to obtain Corresponding matching
Working hour module, wherein the project stage subtab is identical as the label composition rule of job sharing attribute subtab.
When the present invention in the project personnel's distribution for detecting destination item by instructing, from the configuration file of destination item
Obtain the item attribute information and project duration of the destination item;The corresponding working hour module collection of the project duration is obtained,
For each of working hour module collection working hour module, following steps are executed: based on the item attribute information to institute
It states working hour module and carries out item label processing;The personnel's attribute for obtaining the project personnel prestored, based on personnel's attribute to institute
It states working hour module and carries out counterpart personnel's tag processes;The corresponding item label of the working hour module and People Tab are matched, is obtained
The working hour module of successful match, the project task for carrying out respective item personnel to the working hour module of successful match distribute, wherein institute
Project task is stated to be associated with the item label of the working hour module of the successful match.It in this application, is no longer manually to project
The distribution of project personnel is carried out, but automates and realizes personnel assignment, that is, is based on working hour module, item label and People Tab,
Realize the automatic distribution of project personnel, entire personnel assignment process is full-automatic, during avoiding manually carrying out personnel assignment
The work such as information identification, information matches, personnel's classification, rapid and simple realization project personnel distribution, avoid human and material resources
Waste, thus, present application addresses the distribution for manually carrying out project personnel in the prior art, will cause the wave of human and material resources
The technical issues of taking.
Further, the present invention provides another embodiment of method for managing resource, in the described embodiment, the matching institute
The corresponding item label of each working hour module and People Tab are stated, the working hour module of successful match is obtained, to the work of successful match
When module carry out respective item personnel project task allocation step include:
Step S43 matches the corresponding item label of the working hour module and People Tab, and judges the working hour module pair
The item label answered whether there is multiple matched People Tabs;
In the present embodiment, it is understood that there may be the case where multiple project personnel can be handled project details,
I.e. there may be multiple matched People Tabs for the corresponding item label of working hour module, such as: certain working hour module item label is
2018051209Km#, corresponding each People Tab are 2018051209Kx#, 2018051209Ks#, 2018051209Km#,
2018051209Km# etc., wherein then for the working hour module, exist at least two People Tab 2018051209Km# with
Item attribute label, that is, 2018051209Km# matching.
Step S44, when the corresponding item label of the working hour module is there are when multiple matched People Tabs, acquisition is prestored
The destination item project important level;
There are when multiple matched People Tabs, obtain the target prestored for the corresponding item label of each working hour module
The project important level of project, wherein project grade is information entrained by each project, or is obtaining matching for destination item
When setting file, the project important level of destination item can be obtained, the project grade includes extremely important, important, inferior heavy
The grades such as want, be common, is inessential.
Step S45, the project important level based on the destination item are chosen from multiple matched People Tabs
Target person label, and obtain the successful working hour module of Corresponding matching;
Specifically, the project important level based on the destination item, from multiple matched People Tabs
Target person label is chosen, and obtains the successful working hour module step of Corresponding matching and includes:
Step A1 parses each matched People Tab, to obtain the length of service of corresponding project personnel, wherein institute
State the length of service information that corresponding project personnel are carried in People Tab;
Due to may include the length of service information of project personnel in People Tab, thus after obtaining People Tab, solution
The matched People Tab is analysed, to obtain the length of service of each matched project personnel.
Step A2 sorts from large to small each matched People Tab based on each length of service, obtains first row
Sequence;
Each matched People Tab is sorted from large to small based on each length of service, obtains the first sequence, such as work
Before 5 years project personnel's counterpart personnel's labels of work come work 3 years project personnel's counterpart personnel's labels.
Step A3 is selected from the first sequence when the project important level of the destination item is higher than the first predetermined level
It takes the People Tab of arrangement first as target person label, and obtains the successful working hour mould of Corresponding matching.
When the project important level of the destination item is higher than the first predetermined level, such as work as the project of the destination item
When important level is higher than common grade (the first predetermined level), the People Tab of arrangement first is chosen from the first sequence as mesh
People Tab is marked, and obtains the successful working hour module of Corresponding matching.Be since destination item is critically important, thus, for quickly or
The completion destination item task of person's high quality, thus, it chooses working year limit for length and chooses working experience project personnel abundant, into
The processing of row destination item task, and obtain the successful working hour module of Corresponding matching.
Further, there are project personnel's length of service is few, but task completes the high situation of quality, thus, it is accurate
Choose the project personnel for completing destination item, the project important level based on the destination item, from multiple matchings
People Tab in choose target person label, and obtain the successful working hour module step of Corresponding matching further include:
Step B1 obtains length of service and work scoring that each matched People Tab corresponds to project personnel;
In the present embodiment, length of service and the work scoring of project personnel is comprehensively considered, accurately to choose project people
Member.
Step B2, the length of service and work scoring for obtaining each project personnel respectively are chosen in target person label
Shared weight proportion in operation;
After obtaining each matched People Tab and corresponding to length of service and the work scoring of each project personnel, obtain
The length of service is taken and the scoring weight proportion shared in target person label selection operation that works, such as the weight of length of service
Ratio is 40%, and the weight proportion for the scoring that works is 60%.
Step B3, is based on each weight proportion, and length of service of the corresponding project personnel and described
Work scoring, is calculated the matching score value of each matched People Tab;
After obtaining weight proportion, it is based on each weight proportion, and the working year of the corresponding project personnel
Limit and work scoring, are calculated the matching score value of each matched People Tab, and such as project personnel corresponding
It can be 7,8 etc. with score value.
Step B4 is sorted from large to small the personnel of each matched People Tab based on each matching score value, obtained
Second sequence;
The personnel that each matched People Tab is sorted from large to small based on each matching score value, obtain second row
Sequence, in the second sequence, score value is high stands out for matching.
Step B5, when the project important level of the destination item is higher than the second predetermined level, from second sequence
The middle People Tab for choosing arrangement first obtains the successful working hour module of Corresponding matching as target person label.
When the project important level of the destination item is higher than the second predetermined level, the row of selection from second sequence
The People Tab of column first obtains the successful working hour module of Corresponding matching as target person label.Such as when the target item
When purpose project important level is higher than important level (the second predetermined level), personnel's mark of arrangement first is chosen from the second sequence
Label are used as target person label, and obtain the successful working hour module of Corresponding matching.It should be noted that there are multiple arrangements the
When one People Tab, the corresponding project personnel of People Tab of the multiple arrangement first are notified, for the project personnel
Oneself choose whether the corresponding project task of alignment processing.
In the present embodiment, by parsing each matched People Tab, to obtain the working year of corresponding project personnel
Limit, wherein the length of service information of corresponding project personnel is carried in the People Tab;Based on each length of service from greatly to
Small each matched People Tab of sequence, obtains the first sequence;When the project important level of the destination item is higher than first
When predetermined level, the People Tab of arrangement first is chosen from the first sequence as target person label, and obtain Corresponding matching
Successful working hour mould.Working experience project personnel abundant are chosen since working year limit for length can be chosen in the present embodiment,
The processing of destination item task is carried out, thus improves project treatment effeciency.
Further, the present invention provides another embodiment of method for managing resource, in the described embodiment, the matching institute
The corresponding item label of each working hour module and People Tab are stated, the working hour module of successful match is obtained, to the work of successful match
When module carry out respective item personnel project task allocation step after include:
Step S50, obtains the communication account for having carried out the project personnel of project task distribution, and the communication account includes electricity
Talk about number, wechat, nail nail and email address;
In the present embodiment, after the working hour module to successful match carries out the project task distribution of respective item personnel,
People Tab based on project personnel obtains the project personnel's for having carried out project task distribution from personal information repository
Account is communicated, the communication account includes telephone number, wechat, nail nail and email address etc.
Step S60, the communication account based on project personnel, by the corresponding notice of the project task of distribution to project personnel.
After obtaining the communication account of project personnel, by short message, wechat, the forms such as nail and mail are followed closely by project task
Corresponding notice is to project personnel, so that project personnel obtain waiting task to be treated in time.
In the present embodiment, the communication account of the project personnel of project task distribution, the communication have been carried out by obtaining
Account includes telephone number, wechat, nail nail and email address;Communication account based on project personnel appoints the project of distribution
The corresponding notice of business is to project personnel.Since project personnel can be allowed to obtain waiting task to be treated in time.Thus, it is promoted
Project treatment effeciency.
Referring to Fig. 3, Fig. 3 is the device structure schematic diagram for the hardware running environment that the embodiment of the present invention is related to.
Asset management device of the embodiment of the present invention can be PC, be also possible to smart phone, tablet computer, e-book reading
Device, MP3 (Moving Picture Experts Group Audio Layer III, dynamic image expert's compression standard audio
Level 3) player, MP4 (Moving Picture Experts Group Audio Layer IV, dynamic image expert compression
Standard audio level 3) terminal devices such as player, portable computer.
As shown in figure 3, the asset management device may include: processor 1001, such as CPU, memory 1005, communication is always
Line 1002.Wherein, communication bus 1002 is for realizing the connection communication between processor 1001 and memory 1005.Memory
1005 can be high speed RAM memory, be also possible to stable memory (non-volatile memory), such as disk is deposited
Reservoir.Memory 1005 optionally can also be the storage equipment independently of aforementioned processor 1001.
Optionally, which can also include target user interface, network interface, camera, RF (Radio
Frequency, radio frequency) circuit, sensor, voicefrequency circuit, WiFi module etc..Target user interface may include display screen
(Display), input unit such as keyboard (Keyboard), optional target user interface can also include that the wired of standard connects
Mouth, wireless interface.Network interface optionally may include standard wireline interface and wireless interface (such as WI-FI interface).
It will be understood by those skilled in the art that asset management device structure shown in Fig. 3 is not constituted to resource management
The restriction of equipment may include perhaps combining certain components or different component cloth than illustrating more or fewer components
It sets.
As shown in figure 3, as may include that operating system, network are logical in a kind of memory 1005 of computer storage medium
Believe module and resource manager.Operating system is to manage and control the program of asset management device hardware and software resource,
The operation of support resource management program and other softwares and/or program.Network communication module is for realizing in memory 1005
Communication between each component in portion, and communicated between hardware and softwares other in asset management device.
In asset management device shown in Fig. 3, processor 1001 is for executing the resource pipe stored in memory 1005
The step of managing program, realizing method for managing resource described in any of the above embodiments.
Asset management device specific embodiment of the present invention and each embodiment of above-mentioned method for managing resource are essentially identical, herein
It repeats no more.
The present invention also provides a kind of resource management apparatus, the resource management apparatus includes:
First obtains module, when for instructing in the project personnel's distribution for detecting destination item, from matching for destination item
Set the item attribute information and project duration that the destination item is obtained in file;
Second obtains module, for obtaining the corresponding working hour module collection of the project duration, for the working hour module
Each of set working hour module, the resource management apparatus further include:
Third obtains module, for obtaining personnel's attribute of the project personnel prestored, based on personnel's attribute to described
Working hour module carries out counterpart personnel's tag processes;
Matching module obtains successful match for matching the corresponding item label of the working hour module and People Tab
Working hour module, the project task for carrying out respective item personnel to the working hour module of successful match distribute, wherein the project task
It is associated with the item label of the working hour module of the successful match.
Resource management apparatus specific embodiment of the present invention and each embodiment of above-mentioned method for managing resource are essentially identical, herein
It repeats no more.
The present invention provides a kind of readable storage medium storing program for executing, the readable storage medium storing program for executing is stored with one or more than one journey
Sequence, the one or more programs can also be executed by one or more than one processor for realizing above-mentioned
The step of method for managing resource described in one.
Readable storage medium storing program for executing specific embodiment of the present invention and each embodiment of above-mentioned method for managing resource are essentially identical, herein
It repeats no more.
The above is only a preferred embodiment of the present invention, is not intended to limit the scope of the invention, all to utilize this hair
Equivalent structure or equivalent flow shift made by bright specification and accompanying drawing content is applied directly or indirectly in other relevant skills
Art field similarly includes in patent process range of the invention.
Claims (10)
1. a kind of method for managing resource, which is characterized in that the method for managing resource includes:
When the project personnel for detecting destination item distribute instruction, the target item is obtained from the configuration file of destination item
Purpose item attribute information and project duration;
The corresponding working hour module collection of the project duration is obtained, for each of working hour module collection working hour mould
Block executes following steps:
Item label processing is carried out to the working hour module based on the item attribute information;
The personnel's attribute for obtaining the project personnel prestored carries out counterpart personnel's mark to the working hour module based on personnel's attribute
Label processing;
Match the corresponding item label of the working hour module and People Tab, obtain the working hour module of successful match, to matching at
The working hour module of function carries out the project task distribution of respective item personnel, wherein the project task and the successful match
The item label of working hour module is associated with.
2. method for managing resource as described in claim 1, which is characterized in that described to match the corresponding project of the working hour module
Label and People Tab obtain the working hour module of successful match, carry out respective item personnel's to the working hour module of successful match
Project task allocation step includes:
The corresponding item label of the working hour module and People Tab are matched, and judges the corresponding item label of the working hour module
With the presence or absence of multiple matched People Tabs;
When there are when multiple matched People Tabs, obtain the target item prestored for the corresponding item label of the working hour module
Purpose project important level;
Project important level based on the destination item chooses target person mark from multiple matched People Tabs
Label, and obtain the successful working hour module of Corresponding matching;
Using the corresponding target person of the target person label as the project personnel of the successful working hour module of Corresponding matching, and it is right
The destination item personnel carry out the distribution of respective item task.
3. method for managing resource as claimed in claim 2, which is characterized in that
The project important level based on the destination item chooses target person from multiple matched People Tabs
Label, and obtain the successful working hour module step of Corresponding matching and include:
Each matched People Tab is parsed, to obtain the length of service of corresponding project personnel, wherein in the People Tab
Carry the length of service information of corresponding project personnel;
Each matched People Tab is sorted from large to small based on each length of service, obtains the first sequence;
When the project important level of the destination item is higher than the first predetermined level, arrangement first is chosen from the first sequence
People Tab obtains the successful working hour module of Corresponding matching as target person label.
4. method for managing resource as claimed in claim 2, which is characterized in that the project based on the destination item is important
Grade chooses target person label from multiple matched People Tabs, and obtains the successful working hour module of Corresponding matching
Step includes: length of service and the work scoring for obtaining each matched People Tab and corresponding to project personnel;
Length of service and the work scoring for obtaining each project personnel respectively are shared in target person label selection operation
Weight proportion;
Based on the length of service and the work scoring of each weight proportion, and the corresponding project personnel, meter
Calculation obtains the matching score value of each matched People Tab;
The personnel that each matched People Tab is sorted from large to small based on each matching score value, obtain the second sequence;
When the project important level of the destination item is higher than the second predetermined level, arrangement the is chosen from second sequence
One People Tab obtains the successful working hour module of Corresponding matching as target person label.
5. method for managing resource as described in claim 1, which is characterized in that the item attribute information includes project stage letter
Breath, item classification information;
Carrying out item label processing step to the working hour module based on the item attribute information includes:
It obtains and the project stage based on the destination item obtains described working hour module progress divided stages processing
The phase tag of working hour module;
After obtaining phase tag, tag along sort processing is carried out to the working hour module according to preset term developing way type,
To obtain the project development direction label of the working hour module.
6. method for managing resource as described in claim 1, which is characterized in that described to match the corresponding project of the working hour module
Label and People Tab obtain the working hour module step of successful match further include:
Obtain the project stage subtab in item label and the job sharing attribute subtab in People Tab;
Judge whether the corresponding project stage subtab of the working hour module and job sharing attribute subtab are consistent, when consistent
When, obtain the successful working hour module of Corresponding matching, wherein the project stage subtab and the job sharing attribute subtab
Label composition rule it is identical.
7. method for managing resource as claimed in any one of claims 1 to 6, which is characterized in that the matching working hour module pair
The item label answered and People Tab obtain the working hour module of successful match, carry out corresponding entry to the working hour module of successful match
Include: after the project task allocation step of mesh personnel
Obtain carried out project task distribution project personnel communication account, the communication account include telephone number, wechat,
Nail nail and email address;
Communication account based on project personnel, by the corresponding notice of the project task of distribution to project personnel.
8. a kind of resource management apparatus, which is characterized in that the resource management apparatus includes:
First obtains module, for when the project personnel for detecting destination item distribute instruction, the configuration from destination item to be literary
The item attribute information and project duration of the destination item are obtained in part;
Second obtains module, for obtaining the corresponding working hour module collection of the project duration, for the working hour module collection
Each of working hour module, the resource management apparatus further include:
Third obtains module, for obtaining personnel's attribute of the project personnel prestored, based on personnel's attribute to the working hour
Module carries out counterpart personnel's tag processes;
Matching module obtains the working hour of successful match for matching the corresponding item label of the working hour module and People Tab
Module, the project task for carrying out respective item personnel to the working hour module of successful match distribute, wherein the project task and institute
State the item label association of the working hour module of successful match.
9. a kind of asset management device, which is characterized in that the asset management device includes: memory, processor, communication bus
And it is stored in the resource manager on the memory,
The communication bus is for realizing the communication connection between processor and memory;
The processor is for executing the resource manager, to realize the resource as described in any one of claims 1 to 7
The step of management method.
10. a kind of readable storage medium storing program for executing, which is characterized in that resource manager is stored on the readable storage medium storing program for executing, it is described
It realizes when resource manager is executed by processor such as the step of method for managing resource of any of claims 1-7.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810952421.2A CN109685301A (en) | 2018-08-21 | 2018-08-21 | Method for managing resource, device, equipment and readable storage medium storing program for executing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810952421.2A CN109685301A (en) | 2018-08-21 | 2018-08-21 | Method for managing resource, device, equipment and readable storage medium storing program for executing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109685301A true CN109685301A (en) | 2019-04-26 |
Family
ID=66184441
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810952421.2A Pending CN109685301A (en) | 2018-08-21 | 2018-08-21 | Method for managing resource, device, equipment and readable storage medium storing program for executing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109685301A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110428133A (en) * | 2019-06-27 | 2019-11-08 | 平安科技(深圳)有限公司 | Personnel's packet control process, device, computer equipment and storage medium |
CN111062580A (en) * | 2019-11-26 | 2020-04-24 | 北京云测信息技术有限公司 | Matching method of staff and target project and electronic equipment |
CN112766719A (en) * | 2021-01-18 | 2021-05-07 | 中国工商银行股份有限公司 | Task allocation method and device |
CN112907210A (en) * | 2021-03-02 | 2021-06-04 | 岭东核电有限公司 | Execution work order distribution method, execution work order distribution device, computer equipment and storage medium |
CN113256108A (en) * | 2021-05-24 | 2021-08-13 | 平安普惠企业管理有限公司 | Human resource allocation method, device, electronic equipment and storage medium |
CN113487159A (en) * | 2021-06-30 | 2021-10-08 | 武汉空心科技有限公司 | Task demand statistical induction system and method based on labels |
CN114219309A (en) * | 2021-12-16 | 2022-03-22 | 中国建设银行股份有限公司 | Project evaluation method, device and equipment and computer storage medium |
CN115952444A (en) * | 2023-03-10 | 2023-04-11 | 潍坊市平安消防工程有限公司 | Intelligent detection method and system for building fire-fighting facilities |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006344015A (en) * | 2005-06-09 | 2006-12-21 | Hitachi Information Systems Ltd | Inquiry item management system and inquiry item management program |
US20100115523A1 (en) * | 2008-10-30 | 2010-05-06 | International Business Machines Corporation | Method and apparatus for allocating tasks and resources for a project lifecycle |
CN104700190A (en) * | 2014-09-17 | 2015-06-10 | 国家电网公司 | Method and device for matching item and professionals |
US20170124157A1 (en) * | 2015-11-04 | 2017-05-04 | International Business Machines Corporation | Providing Search Result Content Tailored to Stage of Project and User Proficiency and Role on Given Topic |
WO2017130446A1 (en) * | 2016-01-29 | 2017-08-03 | 日揮株式会社 | Project management device, project management system, project management method and program |
CN107527163A (en) * | 2017-09-30 | 2017-12-29 | 新奥(中国)燃气投资有限公司 | A kind of project implementation method and device |
-
2018
- 2018-08-21 CN CN201810952421.2A patent/CN109685301A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006344015A (en) * | 2005-06-09 | 2006-12-21 | Hitachi Information Systems Ltd | Inquiry item management system and inquiry item management program |
US20100115523A1 (en) * | 2008-10-30 | 2010-05-06 | International Business Machines Corporation | Method and apparatus for allocating tasks and resources for a project lifecycle |
CN104700190A (en) * | 2014-09-17 | 2015-06-10 | 国家电网公司 | Method and device for matching item and professionals |
US20170124157A1 (en) * | 2015-11-04 | 2017-05-04 | International Business Machines Corporation | Providing Search Result Content Tailored to Stage of Project and User Proficiency and Role on Given Topic |
WO2017130446A1 (en) * | 2016-01-29 | 2017-08-03 | 日揮株式会社 | Project management device, project management system, project management method and program |
CN107527163A (en) * | 2017-09-30 | 2017-12-29 | 新奥(中国)燃气投资有限公司 | A kind of project implementation method and device |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110428133A (en) * | 2019-06-27 | 2019-11-08 | 平安科技(深圳)有限公司 | Personnel's packet control process, device, computer equipment and storage medium |
CN111062580A (en) * | 2019-11-26 | 2020-04-24 | 北京云测信息技术有限公司 | Matching method of staff and target project and electronic equipment |
CN111062580B (en) * | 2019-11-26 | 2023-05-23 | 北京云测信息技术有限公司 | Matching method of staff and target item and electronic equipment |
CN112766719A (en) * | 2021-01-18 | 2021-05-07 | 中国工商银行股份有限公司 | Task allocation method and device |
CN112907210A (en) * | 2021-03-02 | 2021-06-04 | 岭东核电有限公司 | Execution work order distribution method, execution work order distribution device, computer equipment and storage medium |
CN112907210B (en) * | 2021-03-02 | 2024-05-21 | 岭东核电有限公司 | Method, device, computer equipment and storage medium for distributing execution worksheet |
CN113256108A (en) * | 2021-05-24 | 2021-08-13 | 平安普惠企业管理有限公司 | Human resource allocation method, device, electronic equipment and storage medium |
CN113487159A (en) * | 2021-06-30 | 2021-10-08 | 武汉空心科技有限公司 | Task demand statistical induction system and method based on labels |
CN114219309A (en) * | 2021-12-16 | 2022-03-22 | 中国建设银行股份有限公司 | Project evaluation method, device and equipment and computer storage medium |
CN115952444A (en) * | 2023-03-10 | 2023-04-11 | 潍坊市平安消防工程有限公司 | Intelligent detection method and system for building fire-fighting facilities |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109685301A (en) | Method for managing resource, device, equipment and readable storage medium storing program for executing | |
CN112541745A (en) | User behavior data analysis method and device, electronic equipment and readable storage medium | |
CN111324786B (en) | Method and device for processing consultation problem information | |
CN113220563B (en) | Test case generation method, system, storage medium and computer equipment | |
CN107301179A (en) | The method and apparatus of data base read-write separation | |
CN115002200A (en) | User portrait based message pushing method, device, equipment and storage medium | |
Mairiza et al. | Towards a Catalogue of Conflicts Among Non-functional Requirements. | |
CN111666298A (en) | Method and device for detecting user service class based on flink, and computer equipment | |
CN113268665A (en) | Information recommendation method, device and equipment based on random forest and storage medium | |
CN107480188B (en) | Audit service data processing method and computer equipment | |
CN112527664A (en) | Method and device for generating test case, electronic equipment and storage medium | |
CN112529100A (en) | Training method and device for multi-classification model, electronic equipment and storage medium | |
CN112631884A (en) | Pressure measurement method and device based on data synchronization, computer equipment and storage medium | |
CN114880368A (en) | Data query method and device, electronic equipment and readable storage medium | |
CN113313211A (en) | Text classification method and device, electronic equipment and storage medium | |
CN116820714A (en) | Scheduling method, device, equipment and storage medium of computing equipment | |
Ponelis et al. | A descriptive framework of business intelligence derived from definitions by academics, practitioners and vendors | |
CN110619541A (en) | Application program management method and device, computer equipment and storage medium | |
CN107045452A (en) | Dispatching method of virtual machine and device | |
CN114691782A (en) | Database table increment synchronization method and device and storage medium | |
CN114896164A (en) | Interface optimization method and device, electronic equipment and storage medium | |
CN114282078A (en) | Project data processing method and device, electronic equipment and storage medium | |
CN112132597A (en) | Data processing method, device, equipment and storage medium | |
CN110471752A (en) | Task executing method, device, electronic equipment and computer readable storage medium | |
CN114723280A (en) | Task object allocation method and device, electronic equipment and readable storage medium |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |