CN109670796A CN201811626411.6A CN201811626411A CN109670796A CN 109670796 A CN109670796 A CN 109670796A CN 201811626411 A CN201811626411 A CN 201811626411A CN 109670796 A CN109670796 A CN 109670796A
Authority
CN
China
Prior art keywords
engineering
project
data
metadata
entry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811626411.6A
Other languages
Chinese (zh)
Other versions
CN109670796B (en
Inventor
李月阳
尹利洁
张雷
乔胜利
赵刚
张建全
刘志强
阚生雷
刘文彬
万家和
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Urban Construction Exploration and Surveying Design Research Institute Co Ltd
Original Assignee
Beijing Urban Construction Exploration and Surveying Design Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Urban Construction Exploration and Surveying Design Research Institute Co Ltd filed Critical Beijing Urban Construction Exploration and Surveying Design Research Institute Co Ltd
Priority to CN201811626411.6A priority Critical patent/CN109670796B/en
Publication of CN109670796A publication Critical patent/CN109670796A/en
Application granted granted Critical
Publication of CN109670796B publication Critical patent/CN109670796B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a kind of Engineering documents Management method and system, by obtaining the operation requests information to the engineering data information imported in advance, required metadata sources are determined from the metadatabase pre-established, and call engineering data data in metadata sources, engineering data data are converted into corresponding project entity, corresponding relationship again based on the project entity and engineering project entry that pre-establish, it identifies project engineering project entry corresponding to each project entity in entity, the finally metadata type according to corresponding to operation information, keyword and engineering project entry execute corresponding operating, determine the operating result of respective operations information.By the way that engineering data is carried out entry in advance, when subsequent user carries out corresponding operating to the engineering data, the purpose of efficient acquisition needed for operating result quick based on the engineering data after entry is realized.

Description

Engineering documents Management method and system
Technical field
The present invention relates to data management technical field more particularly to a kind of Engineering documents Management method and system.
Background technique
It is becoming increasingly popular currently, taking subway trip, so more and more countries and cities start to pay attention to subway Construction, for subway from the data such as a large amount of drawings that can be generated and data of constructing are planned for, the preservation of these data and access are also more aobvious It obtains important.It in existing subway engineering data management method, is saved and inquires for a basic unit with whole data.
In the prior art, whole data may include the prospecting, design, construction, environment and of project according to classification of the items Tripartite's monitoring etc..Further, prospecting is divided into elementary exploration, in detail prospecting etc.;Design is divided into safety exit structure chart, enters and leaves Mouth structure plan view, air channel structure plan view etc.;Construction be divided into vertical shaft monitoring point be general layout, construction shaft monitoring scheme, Design of Construction Organization etc.;Environment is divided into survey report etc.;Third party monitoring can be divided into section third party monitoring scheme, vertical shaft Tripartite's monitoring scheme etc..
It can be seen from the above, the scheme using the prior art can only find whole data, can not quickly obtain more Detailed information.
Summary of the invention
In view of this, the embodiment of the invention provides a kind of Engineering documents Management method and system, more quick with realization, The purpose of particulars in effective acquisition engineering data.
To achieve the above object, the embodiment of the present invention provides the following technical solutions:
A kind of Engineering documents Management method, comprising:
The operation requests information to the engineering data information imported in advance is obtained, the operation requests information includes key Word, Engineering Speciality classification, and it is used to indicate the operation information that user carries out the engineering data information imported in advance, The keyword includes at least engineering name;
Determine first number corresponding to the Engineering Speciality corresponding metadata type of classification and the operation requests information According to type;
Based on the corresponding metadata type of Engineering Speciality classification, and the metadatabase pre-established, institute is determined The corresponding metadata sources of Engineering Speciality classification are stated, the metadatabase pre-established includes the engineering money imported in advance Expect metadata sources corresponding to information;
The engineering data data in the metadata sources are called, it is real that the engineering data data are converted to corresponding project Body;
Based on the corresponding relationship of the project entity and engineering project entry that pre-establish, determine each in the project entity Engineering project entry corresponding to the project entity;
Phase is executed according to metadata type corresponding to the operation information, the keyword and the engineering project entry It should operate, determine the operating result of the corresponding operation information.
Preferably, the process of the metadatabase pre-established includes:
Engineering data information to be imported is obtained and analyzed, Engineering Speciality classification and the classification of engineering entry, the work are obtained Journey professional classification includes each project entity for constituting engineering project data, and the engineering entry classification includes being based on the engineering The engineering project entry that classification of the items determines;
Establish the one-to-one relationship of each project entity Yu the engineering project entry;
It determines metadata type corresponding to each project entity, each project entity is converted to corresponding each From the engineering data data of the metadata type;
Engineering data data based on the metadata type and the corresponding metadata type, are established described to be imported Metadata sources corresponding to engineering data information;
Metadatabase is established according to the metadata sources got.
Preferably, the metadata type corresponding based on Engineering Speciality classification, and the metadatabase pre-established, Determine the corresponding metadata sources of the Engineering Speciality classification, comprising:
If the corresponding metadata type of the Engineering Speciality classification is any node in engineering project, acquisition is pre-established Metadatabase in correspond to the metadata sources of the node;
Determine that the metadata sources are the corresponding metadata sources of Engineering Speciality classification.
Preferably, if metadata type corresponding to the operation information is data query metadata, the keyword packet Include engineering name, item entry and project entity, the metadata type according to corresponding to the operation information, the key Word and the engineering project entry execute corresponding operating, determine the operating result of the corresponding operation information, comprising:
Based on data query metadata corresponding to the operation information and the engineering name and item in the keyword The engineering project entry of the corresponding keyword of mesh entry inquiry;
It inquires and determines real with the consistent project of project entity in the keyword in the engineering project entry Body is operating result.
Preferably, if metadata type corresponding to the operation information is data download metadata, the keyword packet Include engineering name, item entry and project entity, the metadata type according to corresponding to the operation information, the key Word and the engineering project entry execute corresponding operating, determine the operating result of the corresponding operation information, comprising:
Based on data download metadata corresponding to the operation information and the engineering name and item in the keyword The engineering project entry of the corresponding keyword of mesh entry inquiry;
Inquire in the engineering project entry with the consistent project entity of project entity in the keyword;
It calls the project entity and downloads.
Preferably, further includes:
The log behavior record data in preset time period are obtained, the log behavior record data are led for recording user Enter engineering data information or for behavioral data corresponding to corresponding operating performed by the engineering data information imported in advance;
The log behavior record data are analyzed, determine that number of operations is greater than the engineering of preset value in the preset time period Data.
A kind of project consultant firm, comprising:
Module is obtained, for obtaining the operation requests information to the engineering data information imported in advance, the operation requests Information includes keyword, Engineering Speciality classification, and be used to indicate user to the engineering data information institute imported in advance into Capable operation information, the keyword include at least engineering name;
Determination type module, for determining that the Engineering Speciality corresponding metadata type of classification and the operation are asked Seek metadata type corresponding to information;
Data source determining module for the metadata type corresponding based on Engineering Speciality classification, and is built in advance Vertical metadatabase, determines the corresponding metadata sources of the Engineering Speciality classification, and the metadatabase pre-established includes Metadata sources corresponding to the engineering data information imported in advance;
Calling module, for calling the engineering data data in the metadata sources, by the engineering data data conversion For corresponding project entity;
Entry determining module is determined for the corresponding relationship based on the project entity and engineering project entry that pre-establish Engineering project entry corresponding to each project entity in the project entity;
Operation module, for the metadata type according to corresponding to the operation information, the keyword and the engineering Item entry executes corresponding operating, determines the operating result of the corresponding operation information.
Preferably, further includes:
Analysis module obtains Engineering Speciality classification and engineering item for obtaining and analyzing engineering data information to be imported Mesh classification, the Engineering Speciality classification includes each project entity for constituting engineering project data, the engineering entry classification packet Include the engineering project entry determining based on engineering project classification;
First establishes module, and the one-to-one correspondence for establishing each project entity and the engineering project entry closes System;
Conversion module, it is for determining metadata type corresponding to each project entity, each project is real Body is converted to the engineering data data of the corresponding respectively metadata type;
Second establishes module, for the engineering data number based on the metadata type and the corresponding metadata type According to establishing metadata sources corresponding to the engineering data information to be imported;
Third establishes module, for establishing metadatabase according to the metadata sources got.
Preferably, the data source determining module, if the metadata category corresponding specifically for Engineering Speciality classification Type is any node in engineering project, obtains the metadata sources for corresponding to the node in the metadatabase pre-established, determines institute Stating metadata sources is the corresponding metadata sources of Engineering Speciality classification.
Preferably, the operation module, if being looked into specifically for metadata type corresponding to the operation information for data Metadata is ask, the keyword includes engineering name, item entry and project entity, based on number corresponding to the operation information According to the engineering project of engineering name and the corresponding keyword of item entry inquiry in query metadata and the keyword Entry inquires and is with the consistent project entity of project entity in the keyword in the determining engineering project entry Operating result;
Alternatively, the operation module, specifically for based on data download metadata corresponding to the operation information, and The engineering project entry of engineering name and the corresponding keyword of item entry inquiry in the keyword, inquires the engineering With the consistent project entity of project entity in the keyword in item entry, calls the project entity and download.
Based on a kind of Engineering documents Management method and system that the embodiments of the present invention provide, the Engineering documents Management side Method determines institute by obtaining the operation requests information to the engineering data information imported in advance from the metadatabase pre-established The metadata sources needed, and the engineering data data in metadata sources are called, the engineering data data are converted into corresponding item Mesh entity, then the corresponding relationship based on the project entity and engineering project entry that pre-establish determine every in the project entity Engineering project entry corresponding to one project entity, the finally metadata type according to corresponding to the operation information, institute It states keyword and the engineering project entry executes corresponding operating, determine the operating result of the corresponding operation information.By pre- Engineering data is first subjected to entry, when subsequent user carries out corresponding operating to the engineering data, is realized based on after entry Engineering data it is quick, it is efficient obtain needed for operating result purpose.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this The embodiment of invention for those of ordinary skill in the art without creative efforts, can also basis The attached drawing of offer obtains other attached drawings.
Fig. 1 is a kind of flow diagram of Engineering documents Management method disclosed by the embodiments of the present invention;
Fig. 2 is a kind of structural schematic diagram of item entry disclosed by the embodiments of the present invention;
Fig. 3 a is a kind of flow diagram for pre-establishing metadatabase disclosed by the embodiments of the present invention;
Fig. 3 b is a kind of hierarchical structure schematic diagram of engineering project data disclosed by the embodiments of the present invention;
Fig. 4 is a kind of flow diagram for executing inquiry operation disclosed by the embodiments of the present invention;
Fig. 5 is a kind of flow diagram for executing down operation disclosed by the embodiments of the present invention;
Fig. 6 is a kind of analysis flow chart diagram of log recording data disclosed by the embodiments of the present invention;
Fig. 7 is a kind of structural schematic diagram of project consultant firm disclosed by the embodiments of the present invention;
Fig. 8 is the structural schematic diagram of another project consultant firm disclosed by the embodiments of the present invention;
Fig. 9 is the structural schematic diagram of another project consultant firm disclosed by the embodiments of the present invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
In this application, the terms "include", "comprise" or any other variant thereof is intended to cover non-exclusive inclusion, So that the process, method, article or equipment for including a series of elements not only includes those elements, but also including not having The other element being expressly recited, or further include for elements inherent to such a process, method, article, or device.Do not having There is the element limited in the case where more limiting by sentence "including a ...", it is not excluded that in the mistake including the element There is also other identical elements in journey, method, article or equipment.
It can be seen from background technology that user is based on Engineering documents Management method disclosed in the prior art, is only capable of getting engineering Whole data belonging to project, and the more content of details is directed in engineering project, as in entire Project Life Cycle Any node can not then directly acquire, it is also necessary to which user voluntarily searches in the whole data.Thus user is influenced to search The efficiency and impression of data.
Therefore, the embodiment of the invention discloses a kind of Engineering documents Management methods, by pre-establishing metadatabase, are leading Engineering data is carried out entry when entering engineering data information can be based in order to which subsequent user is when searching corresponding data Engineering data entry directly finds required project entity.Specific implementation is described in detail by following embodiment.
Metadata is defined as describing the data of data and its environment, is an attribute.In the embodiment of the present invention to first number According to being defined in advance.Specifically, in embodiments of the present invention, metadata includes data service metadata, technology metadata, operation member Data etc..Wherein, data service metadata mainly includes the metadata of each node related information in project construction whole life cycle Definition, node refer to prospecting, design, construction and third party monitoring etc.;Technology metadata mainly includes user class metadata, data visit Ask that metadata, program constitute metadata etc.;Operation metadata mainly includes data load/more new metadata, the first number of data output Metadata, data query metadata etc. are constituted according to, program.
Engineering documents Management disclosed by the embodiments of the present invention is based primarily upon the data of subway construction, it is not limited to subway The data of construction.
As shown in Figure 1, be a kind of flow diagram of Engineering documents Management method disclosed by the embodiments of the present invention, it is main to wrap Include following steps.
Step S101: the operation requests information to the engineering data information imported in advance is obtained.
In step s101, operation requests information includes keyword, Engineering Speciality classification, and is used to indicate user to institute State the operation information that the engineering data information imported in advance is carried out.
The keyword includes at least engineering name.
Optionally, which can be any keyword in instruction engineering data information main title or subhead, For example, the principal mark of engineering data information is entitled " Beijing Metro construction data ", wherein " Beijing Metro " can be used as keyword. Include in the subhead of " Beijing Metro construction data " " No. six lines of Beijing Metro build data ", " Foundation of Beijing Metro Line 5 construction money Material " etc., wherein " No. six lines of Beijing Metro " can be used as keyword.In the subhead of " No. six lines of Beijing Metro build data " Including " data is built at the southern station the Bai Shiqiao western station-Che Gongzhuan ", " data is built at North Sea northern station-Nanluoguxiang station " etc., wherein similar In " southern station the Bai Shiqiao western station-Che Gongzhuan ", printed words can be used as keyword.
Engineering Speciality classification refers to each node of composition whole life cycle during Engineering Project Construction.Such as: it should Engineering Speciality classification includes the nodes such as prospecting, design, construction, environment, third party monitoring.
In the concrete realization, it can also further be divided.Such as: prospecting can be divided into elementary exploration, survey in detail It examines.Design can be divided into safety exit structure chart, port structure plan view, air channel structure plan view etc..Construction can be with Being divided into vertical shaft monitoring point is general layout, construction shaft monitoring scheme, Design of Construction Organization etc..Environment can be divided into survey report Deng.Third party monitoring can be divided into section third party monitoring scheme, vertical shaft third party monitoring scheme.
The operation information includes the operations such as inquiry, downloading, downloading and storage.The embodiment of the present invention is not limited in the above public affairs The operation opened can also include other operations, such as modification operation.
Step S102: determine that the Engineering Speciality is classified corresponding to corresponding metadata type and the operation information Metadata type.
In step s 102, the attribute of Engineering Speciality classification and the attribute of operation information, the first number of the attribute are extracted respectively It is indicated according to type.
Such as, Engineering Speciality is classified are as follows: prospecting.Referring to the content disclosed above in relation to metadata, prospecting is used as engineering project In a node, corresponding metadata type be data service metadata.
If operation information are as follows: inquiry.Referring to the content of related metadata disclosed above, this operation attribute category is inquired In operation metadata, specific corresponding to metadata type be data query metadata.
Step S103: based on the corresponding metadata type of Engineering Speciality classification, and the metadata pre-established Library determines the corresponding metadata sources of the Engineering Speciality classification.
In step s 103, if metadata type corresponding to Engineering Speciality classification is any section in engineering project Point obtains the metadata sources that the node is corresponded in the metadatabase pre-established, determines that the metadata sources are the engineering Metadata sources corresponding to professional classification.
In the concrete realization, the metadatabase pre-established involved in step S103 includes described importing in advance Metadata sources corresponding to engineering data information.The metadata sources include engineering project data information and each data information institute Corresponding item entry.
The structure of the item entry is as shown in Figure 2.Wherein, 200 refer to engineering project essential information, and 201 refer to geologic information letter Breath, 202 finger ring border parameter information messages, 203 refer to design and construction data information, and 204 refer to monitoring materials information.Fig. 2 is only for example Illustrate, during specifically establishing item entry, involved engineering project data is related with concrete engineering project data.
Step S104: calling the engineering data data in the metadata sources, and the engineering data data are converted to pair The project entity answered.
In step S104, metadata sources corresponding to the engineering data information based on above-mentioned determination call the metadata The engineering data data of the engineering data information are corresponded in source.It should be noted that can not directly be stored in metadata sources Corresponding data information, such as project entity.Storage is engineering data data corresponding to engineering data information.
Step S105: the corresponding relationship based on the project entity and engineering project entry that pre-establish determines the project Engineering project entry corresponding to each project entity in entity.
In step s105, on the basis of the engineering data data of calling, based on the project entity and work pre-established The corresponding relationship of journey item entry calls engineering project entry corresponding to each project entity from engineering data data.
Step S106: according to metadata type corresponding to the operation information, the keyword and the engineering project Entry executes corresponding operating, determines the operating result of the corresponding operation information.
During executing step S106, based on above-mentioned metadata sources determining layer by layer, engineering project entry and project Entity, the metadata type according to corresponding to operation information, the keyword and engineering project entry execute corresponding operating.If operation For inquiry, then each project entity of the engineering project item of corresponding keyword now, or the project entity of corresponding keyword are inquired. If operation is downloading, each project entity of the engineering project item of corresponding keyword now, or the tool of corresponding keyword are downloaded The project entity of body.
Engineering documents Management method disclosed by the embodiments of the present invention, by obtaining to the engineering data information imported in advance Operation requests information determines required metadata sources from the metadatabase pre-established, and calls the engineering in metadata sources The engineering data data are converted to corresponding project entity by data, then based on the project entity and work pre-established The corresponding relationship of journey item entry determines engineering project entry corresponding to each project entity in the project entity, Finally the metadata type according to corresponding to the operation information, the keyword and the engineering project entry execute corresponding behaviour Make, determines the operating result of the corresponding operation information.By the way that engineering data is carried out entry in advance, in subsequent user to this When engineering data carries out corresponding operating, efficient acquisition needed for operation knot quick based on the engineering data after entry is realized The purpose of fruit.
In the concrete realization, the related metadatabase pre-established is the first number established according to engineering data information According to library.The process specifically pre-established is as shown in Figure 3a, includes the following steps:
Step S301: obtaining and analyzes engineering data information to be imported, obtains Engineering Speciality classification and engineering entry point Class.
In step S301, the essential characteristic of engineering data information to be imported is analyzed.It as shown in table 1, is this A prospecting data essential characteristic shown in inventive embodiments.It as shown in table 2, is the design data base shown in the embodiment of the present invention Eigen.It as shown in table 3, is construction information essential characteristic disclosed by the embodiments of the present invention.As shown in table 4, real for the present invention Apply a third party monitoring data essential characteristic disclosed in example.
Table 1: the station-line of tunneling-Beijing ten (lotus flower bridge station-lotus flower bridge station) reconnoitres data essential characteristic
Table 2: the station-line of tunneling-Beijing ten (lotus flower bridge station-lotus flower bridge station) design data essential characteristic
Table 3: the station-line of tunneling-Beijing ten (lotus flower bridge station-lotus flower bridge station) construction information essential characteristic
4 stations of the table-tunneling-line of Beijing ten (lotus flower bridge station-lotus flower bridge station) third party monitoring data essential characteristic
The above-mentioned analysis carried out based on essential characteristic is mainly the analysis of essential characteristic level, for determining that it is included Engineering Speciality classification, material form, the data content stored and engineering entry classification.
According to the division of level, Engineering Speciality classification includes engineering project data, and engineering project data includes constituting engineering Each project entity of project data.Project entity refers generally to the entities such as cover, catalogue, text, figure, the table of engineering data.
The classification of engineering entry includes the engineering project entry determining based on engineering project classification.According to drawing for level Point, engineering entry classification can divide are as follows:
It as shown in Figure 3b, is the hierarchical structure of a specific engineering project data.Wherein, professional classification and entry point Class is first layer A1.
Professional classification is continued to divide, second layer A2 is engineering project data.Engineering project data is continued to divide, third Layer A3 is project entity layer, specifically includes that cover, catalogue, chapters and sections, customized entry, illustration and table etc..Wherein, chapters and sections and from Definition entries can continue to divide.Chapters and sections continue to be divided into the 4th layer of A4, including illustration and table.Customized entry continues to be divided into Four layers of A4, including illustration and table.
Entry classification is continued to divide, second layer A2 is entry subitem.Entry subitem is continued to divide, third time A3 is work Journey item entry.
The hierarchical structure of engineering project data is only for example above.Other Engineering project data can refer to above-mentioned Mode is divided, can also be more careful.As long as meeting according to distinguishing hierarchy.
Step S302: the one-to-one relationship of each project entity Yu the engineering project entry is established.
In step s 302, based on the disclosed distinguishing hierarchy in above-mentioned steps S301, it is each for executing step S302 One-to-one relationship is established between project entity and specific engineering project entry.Ensure engineering project data entry Afterwards, corresponding operating can be carried out to the project entity of determining engineering project item now.
For example, it is desired to inquire an illustration.Engineering project entry belonging to the illustration can be first determined, then in the engineering item Mesh item is inquired now.By establishing one-to-one close between above-mentioned each project entity and specific engineering project entry System, can faster when executing corresponding operating to each project entity, and efficiency is also higher.
Step S303: determining metadata type corresponding to each project entity, and each project entity is turned It is changed to the engineering data data of the corresponding respectively metadata type.
It is an attribute because metadata is defined as the data of description data and its environment in step S303, and item Mesh entity is the data content in specific engineering data, when which needs to be stored in metadatabase, needs to carry out Conversion, that is, the engineering data data of corresponding metadata type are converted to, it can just be stored.It is thus necessary to determine that should Metadata type corresponding to project entity.
In the concrete realization, metadata type corresponding to project entity includes document associated metadata, the related member of chart Data, geology associated metadata etc..
Step S304: the engineering data data based on the metadata type and the corresponding metadata type establish institute State metadata sources corresponding to engineering data information to be imported.
In step s 304, it obtains and executes each project entity determined by above-mentioned steps S302 and the engineering project item Purpose one-to-one relationship, and the engineering data data that step S303 is determined are executed, establish engineering data information to be imported Corresponding metadata sources.The metadata sources include a variety of corresponding relationships.
Step S305: metadatabase is established according to the metadata sources got.
In step S305, using metadata sources corresponding to engineering data information to be imported obtained above as first number According to a part of data in library, database needed for project consultant firm disclosed in the embodiment of the present invention is established, also It is metadatabase.
It should be noted that after initial metadatabase establishes, if user needs to increase newly new engineering data letter Breath establishes newly-increased engineering data information still using the execution step of the above-mentioned metadata sources for establishing the engineering data information Metadata sources.
In the concrete realization, the tool according to performed by different operation information and keyword of step S106 shown in Fig. 1 Gymnastics is made different.It is illustrated below:
If metadata type corresponding to the operation information is data query metadata, the keyword includes engineering name Title, item entry and project entity, then the specific implementation process of step S106 is as shown in Figure 4, comprising:
Step S401: based on data query metadata corresponding to the operation information and the work in the keyword The engineering project entry of journey title and the corresponding keyword of item entry inquiry;
Step S402: inquiring and determine in the engineering project entry with the consistent institute of project entity in the keyword Stating project entity is operating result.
If metadata type corresponding to the operation information is data download metadata, the keyword includes engineering name Title, item entry and project entity, then the specific implementation process of step S106 is as shown in Figure 5, comprising:
Step S501: based on data download metadata corresponding to the operation information and the work in the keyword The engineering project entry of journey title and the corresponding keyword of item entry inquiry;
Step S502: inquire in the engineering project entry with the consistent project of project entity in the keyword Entity;
Step S503: it calls the project entity and downloads.
It is above-mentioned as imported executing based on Engineering documents Management method disclosed in the embodiments of the present invention, inquiry and under Corresponding behavior record data can be generated during the concrete operations such as load, are stored in a manner of log.For log lines Analysis for record data to the operation of user, it may be determined that the common or required at present engineering data of present period user Information.Based on this, corresponding engineering data information can be carried out perfect.The analytic process of specific log recording data, such as Shown in Fig. 6, mainly include the following steps:
Step S601: the log behavior record data in preset time period are obtained.
In step s 601, the log behavior record data import engineering data information or for pre- for recording user Behavioral data corresponding to corresponding operating performed by the engineering data information first imported.
The preset time is set by the user, and the log behavior record number in the set period of time can be obtained according to setting time According to.
Step S602: analyzing the log behavior record data, determines that number of operations is greater than pre- in the preset time period If the engineering data of value.
In step S602, in such a way that number of operations in preset time period is greater than preset value, determine in the period The engineering data that user often operates.
The embodiment of the present invention is not limited in the mode for the engineering data that user in the determining period often operates This optionally can also then be considered common engineering data more than default counting by the way of counting.
The embodiment of the present invention analyzes log behavior record data by above-mentioned, can instruct user or data management people Member carries out the determining common engineering data information of present period perfect.
Based on Engineering documents Management method disclosed in the embodiments of the present invention, also correspondence of the embodiment of the present invention discloses one Kind project consultant firm, is described in detail especially by following embodiment.
As shown in fig. 7, being a kind of structural schematic diagram of project consultant firm disclosed by the embodiments of the present invention, the engineering Data supervision system, which specifically includes that, obtains module 701, determination type module 702, data source determining module 703, calling module 704, entry determining module 705 and operation module 706.
Module 701 is obtained, for obtaining the operation requests information to the engineering data information imported in advance, the operation is asked Seeking information includes keyword, Engineering Speciality classification, and is used to indicate user to the engineering data information institute imported in advance The operation information of progress, the keyword include at least engineering name.
Determination type module 702, for determining the Engineering Speciality corresponding metadata type of classification and the operation Metadata type corresponding to solicited message.
Data source determining module 703, for the metadata type corresponding based on Engineering Speciality classification, and in advance The metadatabase of foundation determines the corresponding metadata sources of the Engineering Speciality classification, the metadatabase packet pre-established Include metadata sources corresponding to the engineering data information imported in advance.
In the concrete realization, the data source determining module 703, if corresponding specifically for Engineering Speciality classification Metadata type is any node in engineering project, obtains the metadata that the node is corresponded in the metadatabase pre-established Source determines that the metadata sources are the corresponding metadata sources of Engineering Speciality classification.
Calling module 704 turns the engineering data data for calling the engineering data data in the metadata sources It is changed to corresponding project entity.
Entry determining module 705, for the corresponding relationship based on the project entity and engineering project entry that pre-establish, really Engineering project entry corresponding to each project entity in the fixed project entity.
Operation module 706, for the metadata type according to corresponding to the operation information, the keyword and the work Journey item entry executes corresponding operating, determines the operating result of the corresponding operation information.
In the concrete realization, optionally, the operation module 706, if specifically for member corresponding to the operation information Data type is data query metadata, and the keyword includes engineering name, item entry and project entity, is based on the behaviour Make described in data query metadata corresponding to information and the engineering name in the keyword and item entry inquiry correspondence The engineering project entry of keyword is inquired and is determined consistent with the project entity in the keyword in the engineering project entry The project entity be operating result.
Optionally, the operation module 706, specifically for downloading first number based on data corresponding to the operation information According to and the keyword in engineering name and the corresponding keyword of item entry inquiry engineering project entry, inquiry With the consistent project entity of project entity in the keyword in the engineering project entry, the project entity is called And it downloads.
In conjunction with Fig. 7, as shown in figure 8, project consultant firm disclosed by the embodiments of the present invention 700 further includes default unit 707。
The default unit 707, comprising:
Analysis module obtains Engineering Speciality classification and engineering item for obtaining and analyzing engineering data information to be imported Mesh classification, the Engineering Speciality classification includes each project entity for constituting engineering project data, the engineering entry classification packet Include the engineering project entry determining based on engineering project classification.
First establishes module, and the one-to-one correspondence for establishing each project entity and the engineering project entry closes System.
Conversion module, it is for determining metadata type corresponding to each project entity, each project is real Body is converted to the engineering data data of the corresponding respectively metadata type.
Second establishes module, for the engineering data number based on the metadata type and the corresponding metadata type According to establishing metadata sources corresponding to the engineering data information to be imported.
Third establishes module, for establishing metadatabase according to the metadata sources got.
In conjunction with Fig. 7, as shown in figure 9, project consultant firm disclosed by the embodiments of the present invention 700 further includes log analysis Module 708.
Log analysis module 708, comprising:
Module is obtained, for obtaining the log behavior record data in preset time period.
Analysis module determines that number of operations is big in the preset time period for analyzing the log behavior record data In the engineering data of preset value.
In conclusion Engineering documents Management method and system disclosed by the embodiments of the present invention, are imported by obtaining to preparatory Engineering data information operation requests information, required metadata sources are determined from the metadatabase pre-established, and call The engineering data data are converted to corresponding project entity, then are based on building in advance by the engineering data data in metadata sources The corresponding relationship of vertical project entity and engineering project entry, determines in the project entity corresponding to each project entity Engineering project entry, the finally metadata type according to corresponding to the operation information, the keyword and the engineering item Mesh entry executes corresponding operating, determines the operating result of the corresponding operation information.By the way that engineering data is carried out entry in advance Change, when subsequent user carries out corresponding operating to the engineering data, realization is quick based on the engineering data after entry, efficiently The purpose of operating result needed for obtaining.
All the embodiments in this specification are described in a progressive manner, same and similar portion between each embodiment Dividing may refer to each other, and each embodiment focuses on the differences from other embodiments.Especially for system or For system embodiment, since it is substantially similar to the method embodiment, so describing fairly simple, related place is referring to method The part of embodiment illustrates.System and system embodiment described above is only schematical, wherein the conduct The unit of separate part description may or may not be physically separated, component shown as a unit can be or Person may not be physical unit, it can and it is in one place, or may be distributed over multiple network units.It can root According to actual need that some or all of the modules therein is selected to achieve the purpose of the solution of this embodiment.Ordinary skill Personnel can understand and implement without creative efforts.
Professional further appreciates that, unit described in conjunction with the examples disclosed in the embodiments of the present disclosure And algorithm steps, can be realized with electronic hardware, computer software, or a combination of the two, in order to clearly demonstrate hardware and The interchangeability of software generally describes each exemplary composition and step according to function in the above description.These Function is implemented in hardware or software actually, the specific application and design constraint depending on technical solution.Profession Technical staff can use different methods to achieve the described function each specific application, but this realization is not answered Think beyond the scope of this invention.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.

Claims (10)

1. a kind of Engineering documents Management method characterized by comprising
The operation requests information to the engineering data information imported in advance is obtained, the operation requests information includes keyword, work Journey professional classification, and it is used to indicate the operation information that user carries out the engineering data information imported in advance, it is described Keyword includes at least engineering name;
Determine metadata category corresponding to the Engineering Speciality corresponding metadata type of classification and the operation requests information Type;
Based on the corresponding metadata type of Engineering Speciality classification, and the metadatabase pre-established, the work is determined Metadata sources corresponding to journey professional classification, the metadatabase pre-established include the engineering data letter imported in advance The corresponding metadata sources of breath;
The engineering data data in the metadata sources are called, the engineering data data are converted into corresponding project entity;
Based on the corresponding relationship of the project entity and engineering project entry that pre-establish, determine each described in the project entity Engineering project entry corresponding to project entity;
Corresponding behaviour is executed according to metadata type corresponding to the operation information, the keyword and the engineering project entry Make, determines the operating result of the corresponding operation information.
2. the method according to claim 1, wherein the process of the metadatabase pre-established includes:
Engineering data information to be imported is obtained and analyzed, Engineering Speciality classification and the classification of engineering entry are obtained, the engineering is special Industry classification includes each project entity for constituting engineering project data, and the engineering entry classification includes being based on the engineering project The determining engineering project entry of classification;
Establish the one-to-one relationship of each project entity Yu the engineering project entry;
It determines metadata type corresponding to each project entity, each project entity is converted into corresponding respective institute State the engineering data data of metadata type;
Engineering data data based on the metadata type and the corresponding metadata type, establish the engineering to be imported Metadata sources corresponding to data information;
Metadatabase is established according to the metadata sources got.
3. the method according to claim 1, wherein the metadata category corresponding based on Engineering Speciality classification Type, and the metadatabase pre-established determine the corresponding metadata sources of the Engineering Speciality classification, comprising:
If the corresponding metadata type of the Engineering Speciality classification is any node in engineering project, the member pre-established is obtained The metadata sources of the node are corresponded in database;
Determine that the metadata sources are the corresponding metadata sources of Engineering Speciality classification.
4. method according to any one of claim 1-3, which is characterized in that if first number corresponding to the operation information It is data query metadata according to type, the keyword includes engineering name, item entry and project entity, described according to Metadata type corresponding to operation information, the keyword and the engineering project entry execute corresponding operating, determine and correspond to The operating result of the operation information, comprising:
Based on data query metadata corresponding to the operation information and the engineering name in the keyword and project item The engineering project entry of the corresponding keyword of mesh inquiry;
It inquires and determines in the engineering project entry and be with the consistent project entity of project entity in the keyword Operating result.
5. method according to any one of claim 1-3, which is characterized in that if first number corresponding to the operation information It is data download metadata according to type, the keyword includes engineering name, item entry and project entity, described according to Metadata type corresponding to operation information, the keyword and the engineering project entry execute corresponding operating, determine and correspond to The operating result of the operation information, comprising:
Based on data download metadata corresponding to the operation information and the engineering name in the keyword and project item The engineering project entry of the corresponding keyword of mesh inquiry;
Inquire in the engineering project entry with the consistent project entity of project entity in the keyword;
It calls the project entity and downloads.
6. method according to any one of claim 1-3, which is characterized in that further include:
The log behavior record data in preset time period are obtained, the log behavior record data import work for recording user Journey data information or for behavioral data corresponding to corresponding operating performed by the engineering data information imported in advance;
The log behavior record data are analyzed, the engineering for determining that number of operations is greater than preset value in the preset time period provides Material.
7. a kind of project consultant firm characterized by comprising
Module is obtained, for obtaining the operation requests information to the engineering data information imported in advance, the operation requests information Classify including keyword, Engineering Speciality, and be used to indicate what user carried out the engineering data information imported in advance Operation information, the keyword include at least engineering name;
Determination type module, for determining the Engineering Speciality corresponding metadata type of classification and operation requests letter The corresponding metadata type of breath;
Data source determining module, for the metadata type corresponding based on Engineering Speciality classification, and pre-establish Metadatabase determines the corresponding metadata sources of the Engineering Speciality classification, and the metadatabase pre-established includes described Metadata sources corresponding to the engineering data information imported in advance;
Calling module is converted to the engineering data data pair for calling the engineering data data in the metadata sources The project entity answered;
Entry determining module, for the corresponding relationship based on the project entity that pre-establishes and engineering project entry, determine described in Engineering project entry corresponding to each project entity in project entity;
Operation module, for the metadata type according to corresponding to the operation information, the keyword and the engineering project Entry executes corresponding operating, determines the operating result of the corresponding operation information.
8. system according to claim 7, which is characterized in that further include:
Analysis module obtains Engineering Speciality classification and engineering entry point for obtaining and analyzing engineering data information to be imported Class, the Engineering Speciality classification includes each project entity for constituting engineering project data, and the engineering entry classification includes base In the determining engineering project entry of engineering project classification;
First establishes module, for establishing the one-to-one relationship of each project entity Yu the engineering project entry;
Conversion module turns each project entity for determining metadata type corresponding to each project entity It is changed to the engineering data data of the corresponding respectively metadata type;
Second establishes module, for the engineering data data based on the metadata type and the corresponding metadata type, builds Found metadata sources corresponding to the engineering data information to be imported;
Third establishes module, for establishing metadatabase according to the metadata sources got.
9. system according to claim 7, which is characterized in that
The data source determining module, if being engineering project specifically for the corresponding metadata type of Engineering Speciality classification Middle any node obtains the metadata sources that the node is corresponded in the metadatabase pre-established, determines that the metadata sources are The corresponding metadata sources of the Engineering Speciality classification.
10. the system according to any one of claim 7-9, which is characterized in that
The operation module, if being data query metadata, institute specifically for metadata type corresponding to the operation information Stating keyword includes engineering name, item entry and project entity, based on data query member number corresponding to the operation information According to and the keyword in engineering name and the corresponding keyword of item entry inquiry engineering project entry, inquiry And determining in the engineering project entry with the consistent project entity of project entity in the keyword is operating result;
Alternatively, the operation module, specifically for based on data download metadata corresponding to the operation information and described The engineering project entry of engineering name and the corresponding keyword of item entry inquiry in keyword, inquires the engineering project With the consistent project entity of project entity in the keyword in entry, calls the project entity and download.
CN201811626411.6A 2018-12-28 2018-12-28 Engineering data management method and system Active CN109670796B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811626411.6A CN109670796B (en) 2018-12-28 2018-12-28 Engineering data management method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811626411.6A CN109670796B (en) 2018-12-28 2018-12-28 Engineering data management method and system

Publications (2)

Publication Number Publication Date
CN109670796A true CN109670796A (en) 2019-04-23
CN109670796B CN109670796B (en) 2023-03-14

Family

ID=66147473

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811626411.6A Active CN109670796B (en) 2018-12-28 2018-12-28 Engineering data management method and system

Country Status (1)

Country Link
CN (1) CN109670796B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118071304A (en) * 2024-04-17 2024-05-24 广联达科技股份有限公司 Engineering project data management method, device, equipment and readable storage medium

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101196900A (en) * 2007-12-27 2008-06-11 中国移动通信集团湖北有限公司 Information searching method based on metadata
CN104881751A (en) * 2015-06-04 2015-09-02 北京建工土木工程有限公司 System and method for construction material management based on building information model
CN107193859A (en) * 2017-03-29 2017-09-22 广州地铁设计研究院有限公司 A kind of data management method and data supervision system
CN107423886A (en) * 2017-06-29 2017-12-01 中国建筑局(集团)有限公司 Engineering data synchronous management system and method based on tracking table
CN108121825A (en) * 2018-01-15 2018-06-05 霍亮 Topographic data manages system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101196900A (en) * 2007-12-27 2008-06-11 中国移动通信集团湖北有限公司 Information searching method based on metadata
CN104881751A (en) * 2015-06-04 2015-09-02 北京建工土木工程有限公司 System and method for construction material management based on building information model
CN107193859A (en) * 2017-03-29 2017-09-22 广州地铁设计研究院有限公司 A kind of data management method and data supervision system
CN107423886A (en) * 2017-06-29 2017-12-01 中国建筑局(集团)有限公司 Engineering data synchronous management system and method based on tracking table
CN108121825A (en) * 2018-01-15 2018-06-05 霍亮 Topographic data manages system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
解丽等: "测绘生产资料管理系统的设计与实现", 《地理信息世界》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118071304A (en) * 2024-04-17 2024-05-24 广联达科技股份有限公司 Engineering project data management method, device, equipment and readable storage medium

Also Published As

Publication number Publication date
CN109670796B (en) 2023-03-14

Similar Documents

Publication Publication Date Title
CN104854583B (en) Search result rank and presentation
CN106126521B (en) The social account method for digging and server of target object
CN103699689B (en) Method and device for establishing event repository
CN107766511A (en) Intelligent answer method, terminal and storage medium
US20100030768A1 (en) Classifying documents using implicit feedback and query patterns
CN105468605A (en) Entity information map generation method and device
CN104246757B (en) Predictive service access
CN102346747A (en) Method for searching parameters in data model
Yudelson et al. Towards user modeling meta-ontology
CN109710739A (en) A kind of information processing method and device, storage medium
WO2014127500A1 (en) Natural language processing based search
CN110399470A (en) Conversation message processing
CN104246756A (en) A system and method for providing a prediction for controlling a system
CN108875090A (en) A kind of song recommendations method, apparatus and storage medium
CN105338154A (en) Method, device and terminal for contact person ordering
CN103150409B (en) Method and system for recommending user search word
CN102508971A (en) Method for establishing product function model in concept design stage
US11928083B2 (en) Determining collaboration recommendations from file path information
CN107832385A (en) Picture processing method and device and electronic equipment
CN113742496A (en) Power knowledge learning system and method based on heterogeneous resource fusion
CN108875032A (en) Area type determines method and device
CN109670796A (en) Engineering documents Management method and system
CN110516185A (en) Method and device for processing dynamic website
CN106843822A (en) One kind performs code generating method and equipment
JP2004102818A (en) Retrieval support method and retrieval support device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant